2nd qatar bim user day scheduling, qto and estimating technology

17
1 Dr. Racha Chahrour HOCHTIEF ViCon 2 nd Qatar BIM User Day “Technology is the key to success” BIM for Project Scheduling and Quantity Take-Off Dr. Racha Chahrour HOCHTIEF ViCon Qatar W.L.L. www.hochtief-vicon.com

Upload: bim-user-day

Post on 06-May-2015

248 views

Category:

Technology


2 download

DESCRIPTION

Speaker: Racha Chahrour– Hochtief ViCon -How are classic technologies being adopted? -Challenges – experience, software capabilities About the Qatar BIM User Day: Qatar University, HOCHTIEF ViCon and Teesside University proudly take the initiative to facilitate modern and innovative methods in the Gulf construction industry. The focus is Building Information Modeling (BIM), and our aim is to establish a knowledge platform with government, research and industry experts. The User Day aims to help people to share knowledge, discuss new technologies, and identify new potentials for BIM. More information: www.bimuserday.com Follow BUD on Twitter @bimuserday

TRANSCRIPT

Page 1: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

1 Dr. Racha Chahrour

HOCHTIEF ViCon

2nd Qatar BIM User Day “Technology is the key to success”

BIM for Project Scheduling and Quantity Take-Off Dr. Racha Chahrour HOCHTIEF ViCon Qatar W.L.L. www.hochtief-vicon.com

Page 2: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

2 Dr. Racha Chahrour

HOCHTIEF ViCon

Agenda

1. 4D Model Creation Strategy

2. 4D Scheduling Software

3. Quantity Take Off

4. Summary

Page 3: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

3 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Model Creation Strategy

Major Elements

3D Model

Schedule

4D Model

Page 4: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

4 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Editors

Program

Imp

ort

C

reate

4D

4D Scheduling Software

Available Software Systems

3D Model

Page 5: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

5 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Scheduling Software

Manual Linking in NavisWorks

Structured 3D Selection Sets

Schedule activities Links

Page 6: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

6 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Scheduling Software

Rule-based Linking in NavisWorks

Parameter based search sets

Linking rules

Parameter

Page 7: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

7 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Scheduling Software

Manual and Rule-based Linking in Synchro

Attributes 3D objects

Attribute scheduling tasks

Linking rules

Page 8: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

8 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Scheduling Software

State of the Art Functionalities of 4D Editors

• Import various 3D model formats

• Support major scheduling software

• Construction sequence animation

• Synchronisation of model and program data

• Rule-based activity linking

Visual Schedule

Analysis

Page 9: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

9 Dr. Racha Chahrour

HOCHTIEF ViCon

4D Scheduling Software

Limitations of 4D Editors

• Limited export of created 4D model

• Complex and time consuming linking process

• Focus on visual schedule analysis

• High efforts for 4D model updates

No Scheduling

Support

Page 10: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

10 Dr. Racha Chahrour

HOCHTIEF ViCon

Quantity Take Off

Model-based Quantities - Creation Strategy / Software

Filled BOQ with model-based Quantities

Specs 3D Model

Page 11: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

11 Dr. Racha Chahrour

HOCHTIEF ViCon

• Elements:

• Columns

• Walls

• Ceilings

• Beams

• Quantities with the corresponding structural elements

Quantity Take Off

Structural Elements

Page 12: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

12 Dr. Racha Chahrour

HOCHTIEF ViCon

• All openings like doors, windows, ceiling fretworks are subtracted -according to the QRM- of the corresponding structural elements

• If wall and beams intersect, the intersection area is subtracted of the wall

Quantity Take Off

Rules of Measurements

Page 13: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

13 Dr. Racha Chahrour

HOCHTIEF ViCon

• Walls, columns and ceilings may have different qualities. e.g. walls:

a. Drywalls

b. Blockwork

c. Concrete

• So different types of walls are displayed in different colours

a. c.

Quantity Take Off

Visualisation of Object Attributes

b.

Page 14: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

14 Dr. Racha Chahrour

HOCHTIEF ViCon

• Finishing works can be calculated over the rooms

• A room is bounded by vertical and horizontal structural elements

Quantity Take Off

Finishing Works

Page 15: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

15 Dr. Racha Chahrour

HOCHTIEF ViCon

• Full definition of model requirements at project start to ensure re-usage of 3D models

• Definition of the model structure considering construction joints

• Usage of appropriate agreed/standarised description for 3D model elements

• Implementation of rules of measurement to consider small openings

• Easy access to created data for all stakeholders

Quantity Take Off

Process Requirements

Page 16: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

16 Dr. Racha Chahrour

HOCHTIEF ViCon

Summary

• Latest technology is generally able to meet common project

requirements

• Rule-based schedule linking would improve performance

• Visualising the construction program improves project communication

among all stakeholders

• Data exchange is limited

• Quantity take off requires accurate, structured and qualified 3D

models

Page 17: 2nd Qatar BIM User Day  Scheduling, QTO and Estimating Technology

17 Dr. Racha Chahrour

HOCHTIEF ViCon

Dr. Racha Chahrour

BIM Manager

HOCHTIEF ViCon Qatar W.L.L.

www.hochtief-vicon.com

Thank you for your attention!