3 - 1 © 2011 Pearson Education, Inc. publishing as Prentice Hall 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e PowerPoint slides by Jeff Heyl

Post on 21-Dec-2015

217 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall

33 Project ManagementProject Management

PowerPoint presentation to accompany Heizer and Render Operations Management, 10e Principles of Operations Management, 8e

PowerPoint slides by Jeff Heyl

Page 2: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 2© 2011 Pearson Education, Inc. publishing as Prentice Hall

Examples of Projects

Building Construction

Research Project

Page 3: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 3© 2011 Pearson Education, Inc. publishing as Prentice Hall

Management of Projects

1. Planning - goal setting, defining the project, team organization

2. Scheduling - relates people, money, and supplies to specific activities and activities to each other

3. Controlling - monitors resources, costs, quality, and budgets; revises plans and shifts resources to meet time and cost demands

Page 4: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 4© 2011 Pearson Education, Inc. publishing as Prentice Hall

PlanningObjectivesResourcesWork break-down

structureOrganization

SchedulingProject activitiesStart & end timesNetwork

ControllingMonitor, compare, revise, action

Project Management Activities

Page 5: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 5© 2011 Pearson Education, Inc. publishing as Prentice Hall

Project Planning, Scheduling, and Controlling

Figure 3.1

Before Start of project Duringproject Timeline project

Page 6: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 6© 2011 Pearson Education, Inc. publishing as Prentice Hall

Project Planning, Scheduling, and Controlling

Figure 3.1

Before Start of project Duringproject Timeline project

Page 7: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 7© 2011 Pearson Education, Inc. publishing as Prentice Hall

Project Planning, Scheduling, and Controlling

Figure 3.1

Before Start of project Duringproject Timeline project

Page 8: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 8© 2011 Pearson Education, Inc. publishing as Prentice Hall

Project Planning, Scheduling, and Controlling

Figure 3.1

Before Start of project Duringproject Timeline project

Page 9: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 9© 2011 Pearson Education, Inc. publishing as Prentice Hall

Project Planning, Scheduling, and Controlling

Figure 3.1

Before Start of project Duringproject Timeline project

BudgetsDelayed activities reportSlack activities report

Time/cost estimatesBudgetsEngineering diagramsCash flow chartsMaterial availability details

CPM/PERTGantt chartsMilestone chartsCash flow schedules

Page 10: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 10© 2011 Pearson Education, Inc. publishing as Prentice Hall

Gantt chart Critical Path Method

(CPM) Program Evaluation

and Review Technique (PERT)

Project Management Techniques

Page 11: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 11© 2011 Pearson Education, Inc. publishing as Prentice Hall

A Simple Gantt Chart

TimeJ F M A M J J A S

Design

Prototype

Test

Revise

Production

Page 12: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 12© 2011 Pearson Education, Inc. publishing as Prentice Hall

Service For a Delta Jet

Figure 3.4

Passengers

Baggage

Fueling

Cargo and mail

Galley servicing

Lavatory servicingDrinking water

Cabin cleaning

Cargo and mail

Flight services

Operating crewBaggagePassengers

DeplaningBaggage claimContainer offloadPumpingEngine injection waterContainer offloadMain cabin doorAft cabin doorAft, center, forwardLoadingFirst-class sectionEconomy sectionContainer/bulk loadingGalley/cabin checkReceive passengersAircraft checkLoadingBoarding

0 10 20 30 40Time, Minutes

Page 13: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 13© 2011 Pearson Education, Inc. publishing as Prentice Hall

Project Control Reports Detailed cost breakdowns for each task Total program labor curves Cost distribution tables Functional cost and hour summaries Raw materials and expenditure forecasts Variance reports Time analysis reports Work status reports

Page 14: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 14© 2011 Pearson Education, Inc. publishing as Prentice Hall

Network techniques Developed in 1950’s

CPM by DuPont for chemical plants (1957) PERT by Booz, Allen & Hamilton with the

U.S. Navy, for Polaris missile (1958)

Consider precedence relationships and interdependencies

Each uses a different estimate of activity times

PERT and CPM

Page 15: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 15© 2011 Pearson Education, Inc. publishing as Prentice Hall

Six Steps PERT & CPM

1. Define the project and prepare the work breakdown structure

2. Develop relationships among the activities - decide which activities must precede and which must follow others

3. Draw the network connecting all of the activities

Page 16: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 16© 2011 Pearson Education, Inc. publishing as Prentice Hall

Six Steps PERT & CPM

4. Assign time and/or cost estimates to each activity

5. Compute the longest time path through the network – this is called the critical path

6. Use the network to help plan, schedule, monitor, and control the project

Page 17: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 17© 2011 Pearson Education, Inc. publishing as Prentice Hall

1. When will the entire project be completed?

2. What are the critical activities or tasks in the project?

3. Which are the noncritical activities?

4. What is the probability the project will be completed by a specific date?

Questions PERT & CPM Can Answer

Page 18: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 18© 2011 Pearson Education, Inc. publishing as Prentice Hall

5. Is the project on schedule, behind schedule, or ahead of schedule?

6. Is the money spent equal to, less than, or greater than the budget?

7. Are there enough resources available to finish the project on time?

8. If the project must be finished in a shorter time, what is the way to accomplish this at least cost?

Questions PERT & CPM Can Answer

Page 19: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 19© 2011 Pearson Education, Inc. publishing as Prentice Hall

A Comparison of AON and AOA Network ConventionsActivity on Activity Activity onNode (AON) Meaning Arrow (AOA)

A comes before B, which comes before C.

(a) A B CBA C

A and B must both be completed before C can start.

(b)

A

CC

B

A

B

B and C cannot begin until A is completed.

(c)

B

A

CA

B

CFigure 3.5

Page 20: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 20© 2011 Pearson Education, Inc. publishing as Prentice Hall

AON Example

Activity DescriptionImmediate

Predecessors

A Build internal components —

B Modify roof and floor —

C Construct collection stack A

D Pour concrete and install frame A, B

E Build high-temperature burner C

F Install pollution control system C

G Install air pollution device D, E

H Inspect and test F, G

Milwaukee Paper Manufacturing'sActivities and Predecessors

Table 3.1

Page 21: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 21© 2011 Pearson Education, Inc. publishing as Prentice Hall

AON Network for Milwaukee Paper

A

Start

BStart Activity

Activity A(Build Internal Components)

Activity B(Modify Roof and Floor)

Figure 3.6

Page 22: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 22© 2011 Pearson Education, Inc. publishing as Prentice Hall

AON Network for Milwaukee Paper

Figure 3.7

C

D

A

Start

B

Activity A Precedes Activity C

Activities A and B Precede Activity D

Page 23: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 23© 2011 Pearson Education, Inc. publishing as Prentice Hall

AON Network for Milwaukee Paper

G

E

F

H

CA

Start

DB

Arrows Show Precedence Relationships Figure 3.8

Page 24: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 24© 2011 Pearson Education, Inc. publishing as Prentice Hall

Determining the Project Schedule

Perform a Critical Path Analysis The critical path is the longest path

through the network The critical path is the shortest time in

which the project can be completed Any delay in critical path activities

delays the project Critical path activities have no slack

time

Page 25: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 25© 2011 Pearson Education, Inc. publishing as Prentice Hall

Determining the Project Schedule

Perform a Critical Path Analysis

Table 3.2

Activity Description Time (weeks)A Build internal components 2B Modify roof and floor 3C Construct collection stack 2D Pour concrete and install frame 4E Build high-temperature burner 4F Install pollution control system 3G Install air pollution device 5H Inspect and test 2

Total Time (weeks) 25

Page 26: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 26© 2011 Pearson Education, Inc. publishing as Prentice Hall

Determining the Project Schedule

Perform a Critical Path Analysis

Table 3.2

Activity Description Time (weeks)A Build internal components 2B Modify roof and floor 3C Construct collection stack 2D Pour concrete and install frame 4E Build high-temperature burner 4F Install pollution control system 3G Install air pollution device 5H Inspect and test 2

Total Time (weeks) 25

Earliest start (ES) = earliest time at which an activity can start, assuming all predecessors have been completed

Earliest finish (EF) = earliest time at which an activity can be finished

Latest start (LS) = latest time at which an activity can start so as to not delay the completion time of the entire project

Latest finish (LF) = latest time by which an activity has to be finished so as to not delay the completion time of the entire project

Page 27: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 27© 2011 Pearson Education, Inc. publishing as Prentice Hall

Determining the Project Schedule

Perform a Critical Path Analysis

Figure 3.10

A

Activity Name or Symbol

Earliest Start ES

Earliest FinishEF

Latest Start

LS Latest Finish

LF

Activity Duration

2

Page 28: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 28© 2011 Pearson Education, Inc. publishing as Prentice Hall

Forward Pass

Begin at starting event and work forward

Earliest Start Time Rule:

If an activity has only a single immediate predecessor, its ES equals the EF of the predecessor

If an activity has multiple immediate predecessors, its ES is the maximum of all the EF values of its predecessors

ES = Max {EF of all immediate predecessors}

Page 29: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 29© 2011 Pearson Education, Inc. publishing as Prentice Hall

Forward Pass

Begin at starting event and work forward

Earliest Finish Time Rule:

The earliest finish time (EF) of an activity is the sum of its earliest start time (ES) and its activity time

EF = ES + Activity time

Page 30: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 30© 2011 Pearson Education, Inc. publishing as Prentice Hall

ES/EF Network for Milwaukee Paper

Start

0

0

ES

0

EF = ES + Activity time

Page 31: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 31© 2011 Pearson Education, Inc. publishing as Prentice Hall

ES/EF Network for Milwaukee Paper

Start0

0

0

A

2

2

EF of A = ES of A + 2

0

ESof A

Page 32: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 32© 2011 Pearson Education, Inc. publishing as Prentice Hall

B

3

ES/EF Network for Milwaukee Paper

Start0

0

0

A

2

20

3

EF of B = ES of B + 3

0

ESof B

Page 33: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 33© 2011 Pearson Education, Inc. publishing as Prentice Hall

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

Page 34: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 34© 2011 Pearson Education, Inc. publishing as Prentice Hall

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

D

4

73= Max (2, 3)

Page 35: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 35© 2011 Pearson Education, Inc. publishing as Prentice Hall

D

4

3 7

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

Page 36: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 36© 2011 Pearson Education, Inc. publishing as Prentice Hall

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

D

4

3 7

C

2

2 4

ES/EF Network for Milwaukee Paper

B

3

0 3

Start0

0

0

A

2

20

Figure 3.11

Page 37: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 37© 2011 Pearson Education, Inc. publishing as Prentice Hall

Backward Pass

Begin with the last event and work backwards

Latest Finish Time Rule:

If an activity is an immediate predecessor for just a single activity, its LF equals the LS of the activity that immediately follows it

If an activity is an immediate predecessor to more than one activity, its LF is the minimum of all LS values of all activities that immediately follow it

LF = Min {LS of all immediate following activities}

Page 38: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 38© 2011 Pearson Education, Inc. publishing as Prentice Hall

Backward Pass

Begin with the last event and work backwards

Latest Start Time Rule:

The latest start time (LS) of an activity is the difference of its latest finish time (LF) and its activity time

LS = LF – Activity time

Page 39: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 39© 2011 Pearson Education, Inc. publishing as Prentice Hall

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

LF = EF of Project

1513

LS = LF – Activity time

Page 40: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 40© 2011 Pearson Education, Inc. publishing as Prentice Hall

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

LF = Min(LS of following activity)

10 13

Page 41: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 41© 2011 Pearson Education, Inc. publishing as Prentice Hall

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

10 13

8 13

4 8

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

LF = Min(4, 10)

42

Page 42: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 42© 2011 Pearson Education, Inc. publishing as Prentice Hall

LS/LF Times for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

10 13

8 13

4 8

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

42

84

20

41

00

Page 43: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 43© 2011 Pearson Education, Inc. publishing as Prentice Hall

Computing Slack Time

After computing the ES, EF, LS, and LF times for all activities, compute the slack or free time for each activity

Slack is the length of time an activity can be delayed without delaying the entire project

Slack = LS – ES or Slack = LF – EF

Page 44: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 44© 2011 Pearson Education, Inc. publishing as Prentice Hall

Computing Slack Time

Table 3.3

Earliest Earliest Latest Latest OnStart Finish Start Finish Slack Critical

Activity ES EF LS LF LS – ES Path

A 0 2 0 2 0 YesB 0 3 1 4 1 NoC 2 4 2 4 0 YesD 3 7 4 8 1 NoE 4 8 4 8 0 YesF 4 7 10 13 6 NoG 8 13 8 13 0 YesH 13 15 13 15 0 Yes

Page 45: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 45© 2011 Pearson Education, Inc. publishing as Prentice Hall

Critical Path for Milwaukee Paper

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

10 13

8 13

4 8

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

42

84

20

41

00

Page 46: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 46© 2011 Pearson Education, Inc. publishing as Prentice Hall

ES – EF Gantt Chartfor Milwaukee Paper

A Build internal components

B Modify roof and floor

C Construct collection stack

D Pour concrete and install frame

E Build high-temperature burner

F Install pollution control system

G Install air pollution device

H Inspect and test

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Page 47: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 47© 2011 Pearson Education, Inc. publishing as Prentice Hall

LS – LF Gantt Chartfor Milwaukee Paper

A Build internal components

B Modify roof and floor

C Construct collection stack

D Pour concrete and install frame

E Build high-temperature burner

F Install pollution control system

G Install air pollution device

H Inspect and test

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

Page 48: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 48© 2011 Pearson Education, Inc. publishing as Prentice Hall

CPM assumes we know a fixed time estimate for each activity and there is no variability in activity times

PERT uses a probability distribution for activity times to allow for variability

Variability in Activity Times

Page 49: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 49© 2011 Pearson Education, Inc. publishing as Prentice Hall

Three time estimates are required Optimistic time (a) – if everything

goes according to plan Pessimistic time (b) – assuming very

unfavorable conditions Most likely time (m) – most realistic

estimate

Variability in Activity Times

Page 50: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 50© 2011 Pearson Education, Inc. publishing as Prentice Hall

Estimate follows beta distribution

Variability in Activity Times

Expected time:

Variance of times: t = (a + 4m + b)/6

v = [(b – a)/6]2

Page 51: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 51© 2011 Pearson Education, Inc. publishing as Prentice Hall

Estimate follows beta distribution

Variability in Activity Times

Expected time:

Variance of times: t = (a + 4m + b)/6

v = [(b − a)/6]2Probability of 1 in 100 of > b occurring

Probability of 1 in 100 of < a occurring

Pro

bab

ility

Optimistic Time (a)

Most Likely Time (m)

Pessimistic Time (b)

Activity Time

Figure 3.12

Page 52: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 52© 2011 Pearson Education, Inc. publishing as Prentice Hall

Computing Variance

Table 3.4

Most ExpectedOptimistic Likely Pessimistic Time Variance

Activity a m b t = (a + 4m + b)/6 [(b – a)/6]2

A 1 2 3 2 .11B 2 3 4 3 .11C 1 2 3 2 .11D 2 4 6 4 .44E 1 4 7 4 1.00F 1 2 9 3 1.78G 3 4 11 5 1.78H 1 2 3 2 .11

Page 53: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 53© 2011 Pearson Education, Inc. publishing as Prentice Hall

Probability of Project Completion

Project variance is computed by summing the variances of critical activities

s2 = Project variance

= (variances of activities on critical path)

p

Page 54: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 54© 2011 Pearson Education, Inc. publishing as Prentice Hall

Probability of Project Completion

Project variance is computed by summing the variances of critical activitiesProject variance

s2 = .11 + .11 + 1.00 + 1.78 + .11 = 3.11

Project standard deviation

sp = Project variance

= 3.11 = 1.76 weeks

p

Page 55: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 55© 2011 Pearson Education, Inc. publishing as Prentice Hall

Probability of Project Completion

PERT makes two more assumptions:

Total project completion times follow a normal probability distribution

Activity times are statistically independent

Page 56: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 56© 2011 Pearson Education, Inc. publishing as Prentice Hall

Probability of Project Completion

Standard deviation = 1.76 weeks

15 Weeks

(Expected Completion Time)Figure 3.13

Page 57: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 57© 2011 Pearson Education, Inc. publishing as Prentice Hall

Probability of Project Completion

What is the probability this project can be completed on or before the 16 week deadline?

Z = – /sp

= (16 wks – 15 wks)/1.76

= 0.57

due expected datedate of completion

Where Z is the number of standard deviations the due date or target date lies from the mean or expected date

Page 58: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 58© 2011 Pearson Education, Inc. publishing as Prentice Hall

Probability of Project Completion

What is the probability this project can be completed on or before the 16 week deadline?

Z = − /sp

= (16 wks − 15 wks)/1.76

= 0.57

due expected datedate of completion

Where Z is the number of standard deviations the due date or target date lies from the mean or expected date

.00 .01 .07 .08

.1 .50000 .50399 .52790 .53188

.2 .53983 .54380 .56749 .57142

.5 .69146 .69497 .71566 .71904

.6 .72575 .72907 .74857 .75175

From Appendix I

Page 59: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 59© 2011 Pearson Education, Inc. publishing as Prentice Hall

Probability of Project Completion

Time

Probability(T ≤ 16 weeks)is 71.57%

Figure 3.14

0.57 Standard deviations

15 16Weeks Weeks

Page 60: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 60© 2011 Pearson Education, Inc. publishing as Prentice Hall

Determining Project Completion Time

Probability of 0.01

Z

Figure 3.15

From Appendix I

Probability of 0.99

2.33 Standard deviations

0 2.33

Page 61: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 61© 2011 Pearson Education, Inc. publishing as Prentice Hall

Variability of Completion Time for Noncritical Paths

Variability of times for activities on noncritical paths must be considered when finding the probability of finishing in a specified time

Variation in noncritical activity may cause change in critical path

Page 62: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 62© 2011 Pearson Education, Inc. publishing as Prentice Hall

What Project Management Has Provided So Far

1. The project’s expected completion time is 15 weeks

2. There is a 71.57% chance the equipment will be in place by the 16 week deadline

3. Five activities (A, C, E, G, and H) are on the critical path

4. Three activities (B, D, F) are not on the critical path and have slack time

5. A detailed schedule is available

Page 63: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 63© 2011 Pearson Education, Inc. publishing as Prentice Hall

Trade-Offs and Project Crashing

The project is behind schedule The completion time has been

moved forward

It is not uncommon to face the following situations:

Shortening the duration of the project is called project crashing

Page 64: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 64© 2011 Pearson Education, Inc. publishing as Prentice Hall

Factors to Consider When Crashing a Project

The amount by which an activity is crashed is, in fact, permissible

Taken together, the shortened activity durations will enable us to finish the project by the due date

The total cost of crashing is as small as possible

Page 65: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 65© 2011 Pearson Education, Inc. publishing as Prentice Hall

Steps in Project Crashing

1. Compute the crash cost per time period. If crash costs are linear over time:

Crash costper period =

(Crash cost – Normal cost)

(Normal time – Crash time)

2. Using current activity times, find the critical path and identify the critical activities

Page 66: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 66© 2011 Pearson Education, Inc. publishing as Prentice Hall

Steps in Project Crashing3. If there is only one critical path, then

select the activity on this critical path that (a) can still be crashed, and (b) has the smallest crash cost per period. If there is more than one critical path, then select one activity from each critical path such that (a) each selected activity can still be crashed, and (b) the total crash cost of all selected activities is the smallest. Note that the same activity may be common to more than one critical path.

Page 67: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 67© 2011 Pearson Education, Inc. publishing as Prentice Hall

Steps in Project Crashing

4. Update all activity times. If the desired due date has been reached, stop. If not, return to Step 2.

Page 68: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 68© 2011 Pearson Education, Inc. publishing as Prentice Hall

Crashing The Project

Table 3.5

Time (Wks) Cost ($)Crash Cost Critical

Activity Normal Crash Normal Crash Per Wk ($) Path?

A 2 1 22,000 22,750 750 YesB 3 1 30,000 34,000 2,000 NoC 2 1 26,000 27,000 1,000 YesD 4 2 48,000 49,000 1,000 NoE 4 2 56,000 58,000 1,000 YesF 3 2 30,000 30,500 500 NoG 5 2 80,000 84,500 1,500 YesH 2 1 16,000 19,000 3,000 Yes

Page 69: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 69© 2011 Pearson Education, Inc. publishing as Prentice Hall

Crash and Normal Times and Costs for Activity B

| | |1 2 3 Time (Weeks)

$34,000 —

$33,000 —

$32,000 —

$31,000 —

$30,000 —

Activity Cost

Crash

Normal

Crash Time Normal Time

Crash Cost

Normal Cost

Crash Cost/Wk = Crash Cost – Normal CostNormal Time – Crash Time

=$34,000 – $30,000

3 – 1

= = $2,000/Wk$4,0002 Wks

Figure 3.16

Page 70: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 70© 2011 Pearson Education, Inc. publishing as Prentice Hall

Critical Path and Slack Times for Milwaukee Paper

Figure 3.17

E

4

F

3

G

5

H

2

4 8 13 15

4

8 13

7

13 15

10 13

8 13

4 8

D

4

3 7

C

2

2 4

B

3

0 3

Start0

0

0

A

2

20

42

84

20

41

00

Slack = 1 Slack = 1

Slack = 0 Slack = 6

Slack = 0

Slack = 0

Slack = 0

Slack = 0

Page 71: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 71© 2011 Pearson Education, Inc. publishing as Prentice Hall

Advantages of PERT/CPM

1. Especially useful when scheduling and controlling large projects

2. Straightforward concept and not mathematically complex

3. Graphical networks help highlight relationships among project activities

4. Critical path and slack time analyses help pinpoint activities that need to be closely watched

Page 72: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 72© 2011 Pearson Education, Inc. publishing as Prentice Hall

Advantages of PERT/CPM

5. Project documentation and graphics point out who is responsible for various activities

6. Applicable to a wide variety of projects7. Useful in monitoring not only schedules

but costs as well

Page 73: 3 - 1© 2011 Pearson Education, Inc. publishing as Prentice Hall 3 3 Project Management PowerPoint presentation to accompany Heizer and Render Operations

3 - 73© 2011 Pearson Education, Inc. publishing as Prentice Hall

1. Project activities have to be clearly defined, independent, and stable in their relationships

2. Precedence relationships must be specified and networked together

3. Time estimates tend to be subjective and are subject to fudging by managers

4. There is an inherent danger of too much emphasis being placed on the longest, or critical, path

Limitations of PERT/CPM