3-5 great scotland yard, westminster ~ construction management plan 2012

Upload: fuzzywoodperson

Post on 03-Apr-2018

220 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    1/43

    3-5 Great Scotland Yar

    Construction Management PlaDecember 20

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    2/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    Contents

    1.0 Introduction

    1.1 Proposed Development

    1.2 Site Layout

    2.0 Phase 1 Demolition - McGee Construction Management Statement

    1. Introduction

    2. Outline Demolition & Construction Method Statement

    3. Site Security & Access Control

    4. Pedestrian Access

    5. Vehicular Access

    6. Material Distribution7. Waste Management

    8. Good Neighbour / Managing Environmental Impacts

    3.0 Construction Phase

    3.01 Sub-structure and Basement

    3.02 Super-structure

    3.03 Facade

    3.04 General working Practices

    3.05 Access arrangements for vehicles servicing the site

    3.06 Tower Crane Operations

    3.07 Vehicle Cleaning

    3.08 Road Sweeping

    3.09 Pedestrian and Cyclist Safety

    3.10 Plant & Machinery

    3.11 Storage of Materials

    3.12 Working at Heights

    3.13 Formwork

    3.14 Parking

    3.15 Electrical Equipment/Supplies

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    3/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    3.16 Electricity Supply

    3.17 Electrical Appliances

    3.18 240V Energised Circuits, pre-completion

    3.19 Bus Stand Suspension

    3.20 Temporary Footway & Lane Closure:

    3.21 Proposed Hoarding & Security

    3.22 Westminster Highways Inspector

    3.23 Unauthorised Access

    3.24 Cleanliness

    3.25 Regulatory Requirements

    4.0 General

    4.01 Proposed Working Hours & Completion Date

    4.02 Public Consultation

    4.03 Local Stakeholders

    4.04 Considerate Constructors Scheme

    4.05 Site Impacts

    5.0 Site accommodation & Welfare

    6.0 Appendices

    A. Construction Phase Logistics Drawing

    B. McGee Construction Management Statement

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    4/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    1.0IntroductionThis is the Construction Management Plan for the demolition and construction activities located at 3-5

    Baker Street. This document reflects traffic priorities, shared access routes, temporary diversions and

    signage it will be implemented, regularly reviewed and revised if required. It will also describe the

    techniques, equipment and plant, used during the contract.

    The proposed scheme is the conversion of the unoccupied office buildings owned by The Crown Estate

    located at 3-5 Great Scotland Yard, London, WC1 into a 233-bedroom boutique economy hotel with

    restaurant, bar, meeting rooms and reception areas, and further hotel suite guestrooms in the adjoining 1

    Great Scotland Yard.

    The buildings are located on Great Scotland Yard, a street that links Whitehall and Northumberland

    Avenue, close to Trafalgar Square in central London. 3-5 Great Scotland Yard is a 1910 office building

    spread over 5 floors, built as the Central London Recruiting Office by the Office of Works. An atrium spaceand additional floor area were constructed within the original buildings courtyard in 1982 and it became

    the library for the Ministry of Defence until its relocation in 1999. 1 Great Scotland Yard is to the west of

    the building at 3-5. It is a Grade II listed building that stands set back from the street (following the line of

    an original terrace of dwellings). It is currently unoccupied having been in office use.

    This construction management plan seeks to outline the management of activities during the development

    period at 3-5 Great Scotland Yard and has been prepared in conjunction with advice from Westminster

    Council and Local Stakeholders. The project consists of demolition phase (approximately the first 6 months

    of the project) and a construction phase, the plan reflects this and incorporates the management plan as

    developed by the demolition Contractor

    1.1 Proposed Development

    The project is to refurbish, convert and extend the existing office buildings at 3-5 Great Scotland Yard,

    London WC1 into a 233-bedroom boutique economy hotel with further guestroom suites in the adjoining 1

    Great Scotland Yard.

    The project includes the strip out and demolition of the existing building at 3-5 Great Scotland Yard with

    retained facades. The building will be extended with two levels of basement and two levels above the

    existing roof level, and refitted internally with new core circulation, floors and lightwell. The Grade II listed

    building at 1 Great Scotland Yard will be refurbished and a link opened up between the adjacent buildings.

    The external facades are retained on the south elevation to Great Scotland Yard, the north elevation to

    Craigs Court and the east elevation to the lightwell against the police station. The north, south and east

    elevations will be extended upwards. The west elevation will be rebuilt. Two new stories will be added to

    the existing building height, including the top storey in a mansard roof with roof level plant and ecological

    features. The new elevations and lightwells are shown to coordinate with the materials and proportions of

    the existing building. The appearance will be in accordance with the Local Authority planning approval for

    3-5 and Listed Building Consent for 1 Great Scotland Yard.

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    5/43

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    6/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    3.02 Super-structure

    The basement and ground floors are to be constructed in reinforced concrete. The upper floor

    construction is currently a steel frame with consideration being given to a concrete frame. Again all loading

    and off-loading will be carried out by the tower cranes and the tower cranes will be serviced via the

    dedicated loading bay.

    3.03 Facade

    The greater percentage of the facade exists and is of brickwork construction, the main work on the

    elevations is general repair work, this work will be carried out from a scaffold erected inside the retention

    structure. Both the faade retention structure and scaffolding will be erected during the demolition works

    and will remain in place until the structural frame and faade works are complete.

    3.04 General working Practices

    A Traffic Marshall dressed in an orange hi visibility jacket and complete with 2 way radio wil

    escort all lorries in and out of site, particular care will be taken during reversing operations.

    Lorries will enter and leave the site via the loading bay located in the side street to the West ofthe property.

    Lorry wheels will be washed down on a hard standing area before leaving site, the hard core /

    concrete standing will be replaced as required so that wheel cleaning is kept to a minimum.

    Roadways will be Jet Washed regularly, should the need arise a road sweeper will be utilised to

    clean the exit to the site and surrounding Roads.

    If necessary to avoid congestion in Great Scotland Yard Lorries will be held in an off site location

    or holding area.

    To keep other contractors and visitors away from the demolition works a demolition exclusion

    zone will be formed separating it from the remainder of the site works by a Heras Fenced

    barrier at a distance in accordance with BS 6187:2000 Clause 13, carrying signs indicating thatdemolition work is being carried out within it.

    All walkways/ pavements will be kept clear of debris and/or material to prevent slips, trips and

    fall hazards.

    Warning signs will be displayed in prominent positions around the site and work area indicating

    CAUTION CONSTRUCTION SITE TRAFFIC.

    For the delivery of heavy plant, this will be coordinated with the local police via movement

    orders, the delivery of these are typically during quiet hours to avoid presenting disruption to

    local traffic.

    All vehicular traffic after leaving or entering the site will take due regard to all other road users

    and pedestrians. All drivers will be given a site specific induction on first arrival on site; this is to ensure that

    everyone understands the site traffic requirements and precaution to prevent injury.

    When lorries are reversing onto site they will be fitted with an audible alarm and be directed by

    a Banksman

    Site plant i.e. excavators, diggers etc, will only be driven by persons that are trained and

    competent with the appropriate qualifications.

    Prior to works starting all personnel will be given a site specific induction and orientation to the

    site, this will be conducted by the site manager who will advise personnel on any specific safety

    requirement that are required during the course of the project.

    Plant equipment will not be offloaded onto the public highway, it will be reversed on to site by abanksman and unloaded.

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    7/43

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    8/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    Egress from site

    Heavy plant and vehicles will not be allowed to park or build up on Whitehall or Northumberland Avenue.

    A professional logistic management company will be employed on site to manage the all deliveries and

    vehicle movements. The key member of the logistics team is the logistics manager, all vehicles will be

    booked in with the logistics manager prior to arrival on site and have times and dates agreed. The logistics

    personnel and Banksmen will direct the vehicle when arriving and leaving the site. Vehicles are not to be

    reversed in construction areas unless under the control of an authorised banks man. Only authorised

    personnel; i.e. plant operators, banks-men/slingers truck drivers will be allowed in areas of machine/plant

    activity. Due to the tight constraints within the site all vehicles will load unload within the zone to the

    South side of the property.

    3.06 Tower Crane Operations

    The tower crane(s) erected on the site will be managed by a dedicated team of Crane Supervisor,

    Banksmen, Drivers and relief Drivers. The cranes will be luffing Jib tower cranes to avoid oversailing issues.

    On the erection of a second crane both cranes will be fitted with anti-collision devices.

    3.07 Vehicle Cleaning

    Powered jet washes will be provided for wheel washing of all vehicles leaving the site to reduce the impact

    on the surrounding road network

    3.08 Road Sweeping

    Public Highways and other publicly accessible roads are to be kept clear of mud at all times. Vehicles

    leaving the construction site will be cleaned before joining the highway to minimize the spreading of mud

    and dust onto the surrounding roads. As a minimum road sweeping will be provided and shall be used on

    all public roads used by site traffic within 500m of the site entrances. Roads outside of this will be

    monitored and inspected and road sweeping will be undertaken where required. Highway cleaning

    operations will be undertaken in line with the Considerate Constructor Scheme.

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    9/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    3.09 Pedestrian and Cyclist Safety

    Construction traffic poses a potential risk to pedestrians and cyclists safety, particularly when entering and

    exiting the site. The safety of pedestrians and cyclists will be ensured by the use of banksmen during all

    periods of operation at the site. Professional banksmen will supervise all arrivals and departures of

    construction traffic. Traffic movements will be co-ordinated such that the arrival of vehicles is staggered to

    ensure that there is no overhang of vehicles

    All pedestrian personnel will enter and exit the site through a clearly signed and supervised security gate

    leading into No. 1 Great Scotalnd Yard where security and welfare facilities will be provided, there will also

    be a seperate Pedestrian Gate In Craigs Court. Pedestrians must sign in and out upon entering and leaving

    the site, no matter how many times they leave and re-enter the site each day. There will be a pedestrian

    emergency exit into Craigs Court.

    A safe walkway will provide safe access to the work area, keeping operatives away from plant/delivery

    operations as much as possible. This will be supervised rigorously by site management.

    Relevant signage will be erected and site personnel will be informed of the site traffic plan during

    induction. Sight lines, particularly those on the approach to the site entrance will be maintained

    unobstructed. Signage warning traffic of the construction site and heavy plant crossing will be erected on

    approaches to the site entrance/exit.

    3.10 Plant & Machinery

    The Company will ensure that all plant delivered to site is in good working order, in a safe condition, and

    that in relation to lifting appliances and tackle, has been thoroughly examined within the defined statutory

    period and has a current test certificate. Daily inspections will be recorded on a pro-forma record sheet

    and weekly inspections will be recorded in the PUWER and LOLER register for machines and lifting tackle.

    All excavators that lift structural sections and other items will be deemed to be lifting appliances for the

    purposes of statutory inspections.

    The site management team will be responsible for ensuring that when not in use each item of plant and

    equipment is suitably immobilised and secured so as to prevent unauthorised use or interference.

    All plant operatives must be competent, trained and be able to provide relevant qualifications for the item

    of plant they are operating. With regards to foreign plant operatives who do not have a U.K. recognised

    training certificate or skills card, McAleer and Rushe will contact CITB to arrange a competency assessment

    for that driver.

    All dumpers, excavators and cranes will have either a CCTV or convex mirror fitted for all round vision. Al

    excavators, used as lifting equipment, should be fitted with Check Valves and equipped with fire

    extinguishers and spill kits. Quick hitch pins and retaining clips will be used at all times.

    Telehandlers will have all protective screens intact prior to being used; this is due to the hydraulic boom

    being positioned in close proximity to the operators cab. If the screen is missing and the operator has any

    body parts outside of the cab then the boom could potentially dismember limbs.

    All lifting equipment used in lifting operations will be accompanied by appropriate Test certificates and

    undergo Thorough Examinations every 12 months. Lifting accessories such as chains/slings must be

    Thoroughly Examined every 6 months. Each item of lifting equipment put in place for the duration of the

    works must be appropriately tested and thoroughly examined prior to use.

    The records for all subcontractors plant on site will be handed in at the weekly safety review meeting.

    These will be filed and available for inspection. All records for plant owned or hired by McAleer and Rushe

    will be held on site and will be regularly updated by the Plant Department

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    10/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    3.11 Storage of Materials

    Materials will be stored within the designated areas as agreed. Hazardous materials will be securely stored

    to prevent access by unauthorised persons and other materials will be stored/stacked in a safe and secure

    manner.

    Continual monitoring of the site will be undertaken to control the amount of debris around the site. Goodhousekeeping practices will be adopted to control waste and ensure debris is disposed of appropriately.

    Contractors must ensure that the timing of waste collection must be so arranged to prevent nuisance,

    hazard or obstruction of the street for prolonged periods and be made at a reasonable hour. McAleer and

    Rushe will manage this locally and all contractors will be informed of these requirements.

    Material deliveries will be off loaded from within the site boundaries, stored and stacked safely. Vehicles

    will be guided by a banksman / signaller to the off-loading area and only authorised personnel e.g. slingers

    and telehandler operators, will have access to this area.

    Contractors will be advised to adopt appropriate control measures when decommissioning and removing

    unidentified pipes in low levels of the building due to the potential presence of flammable substances bothliquid and/or gaseous representing a hazard both to safety and to fire. McAleer and Rushe will bring this to

    the attention of the Demolition Subcontractors and ensure that these hazards are outlined within the

    RAMS for demolition.

    3.12 Working at Heights

    The Company will adopt a variety of safe working methods when working at height. The exact methods

    will be outlined in method statements produced by the site management team in consultation with the

    Project Manager.

    An appointed member of the site management team will ensure that weekly inspections are carried out on

    working platforms, i.e. scaffold, ladders, etc. Internal work at height will be achieved by means of mobile

    alloy towers, properly erected by PASMA trained scaffolders.

    3.13 Formwork

    Formwork will be designed by a competent designer who will issue the designs to the contractor and sign

    off ensuring that it is fit for purpose. Formwork will be erected by a competent contractor. All formwork

    erectors constructing and erecting table formwork for slabs, column boxes and shuttering for sheer walls,

    will be experienced operatives, informed by their supervisor of the safe system of work, particularly when

    working at height and will be adequately supervised at all times.

    McAleer and Rushe will adopt a stringent system of checking formwork procedures from method

    statements and risk assessments to sign off sheets. This will be carried out by the onsite management

    team in conjunction with the relevant subcontractor.

    All requisite paperwork in accordance with legislation will be submitted by the subcontractor at the weekly

    safety review meeting on a weekly basis.

    3.14 Parking

    No parking other than delivery or service vehicles will be permitted on site. No vehicles other than

    authorised site vehicles shall be permitted to access beyond the Site Office compound onto theconstruction Site.

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    11/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    Parking shall not be permitted on public roads where access or egress to buildings or houses will be

    affected. Statutory bodies plant / equipment shall be kept clear and accessible at all times e.g. fire

    hydrants. The parking in the immediate area is controlled by City of Westminster.

    McAleer and Rushe are aware of the parking restrictions in the area and their implication for short term

    parking for delivery of equipment etc. The area is well served by Public Transport.

    3.15 Electrical Equipment/Supplies

    All portable electrical appliances used on site will be powered with a 110v supply and will be

    inspected/tested in accordance with the requirements of the Electricity at Work Regulations.

    Temporary supplies will be installed and tested by a competent electrical contractor to the recognised

    standard. Site huts will be electrically inspected and tested approximately every twelve months.

    3.16 Electricity SupplyA generator or temporary mains supply will be available on site and transformers will be installed to

    provide a 110 volt supply for portable electrical appliances, generally on each floor. These transformers will

    be inspected by a competent person before first use and subsequently on a weekly basis to ensure

    electrical safety, the results of those inspections being recorded in the site office.

    Welfare facilities and offices will be provided with a safe 240V electricity supply, protected by RCD devices.

    3.17 Electrical Appliances

    Only 110-volt electric or battery powered tools will be used on site. All component parts will be colour

    coded yellow for easy identification. Special allowances may be made for the use of higher voltage

    appliances, but Residual Current Devices (RCDs) or other precautions must be in place before approval

    can be granted for their use. Portable electrical appliances will be inspected regularly; PAT (Portable

    Appliance Tested) every three months and certified that they comply with industry standards.

    Extension leads must be placed where they cannot be damaged or cause a tripping hazard. Damaged or

    defective equipment will be replaced or taken out of service until repairs have been carried out.

    3.18 240V Energised Circuits, pre-completion

    The electrical contractor will test and commission electrical installations as and when necessary. Onlycompetent, experienced electricians will carry out this work under the supervision of the electrical

    foreman or Contracts Manager. Prior to operations they will formulate Risk Assessments and Methodology

    specific to their works.

    The electrical contractor will liaise with McAleer & Rushes Site Manager when this operation is being

    carried out as systems will be energised. The electrical contractor will display warning signage in clearly

    visible locations in areas under test. Once testing is complete, systems will be de-energised and the lockout

    systems re-instated.

    As and when mains power supply is required, McAleer & Rushe Ltd. will issue a written request for the

    electrical contractor to energise the required installations. The sequence for energising floor levels will bepre-determined after discussions with interested parties.

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    12/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    Access to Switch Rooms will be restricted. Trades / operatives requiring entrance to this area must gain

    permission via a Permit to Work from the Site Manager in consultation with the electrical contractor prior

    to carrying out any work. A specific Risk Assessment for these works must be carried out and a safe system

    of work implemented.

    The electrical contractor will specify a key-holder who will open the door on production of the Permit to

    Work. They will only permit work to be carried out if they are satisfied that conditions are safe and that the

    Switch Board is locked out. Instruction from the electrical contractor must be complied with.

    Even though 240v power will be available, operatives working in energised areas will only use 110v electric

    tools powered from a transformer connected to the mains or suitable generator. Safe procedures will be

    communicated to contractors at the Site Safety Meeting and during a Tool Box Talk given by contractors

    to their operatives.

    3.19 Bus Stand Suspension

    As detailed in the site logistics plan the one way traffic order will require the suspension of the Bus Stand

    opposite the site.

    3.20 Temporary Footway & Lane Closure:

    To facilitate the demolition and construction of the building an external faade retention scheme is

    required this will be located on the footway and highway adjacent to the South boundary of the site. To

    facilitate this Great Scotland Yard will become a one way street and the lane and footway adjacent to the

    site will be closed, this will be carried out under a temporary traffic management order on Great Scotland

    Yard.

    The loading bay will also require a road closure of the side street on the West side of the site directly in

    front of No.1 Great Scotland Yard. Access for deliveries to the Public House and McDonalds will be

    maintained adjacent to the loading bay.

    It is expected that these arrangements will remain in place for the entire period of the demolition and

    construction works.

    3.21 Proposed Hoarding & Security

    The site will require the erection of a hoarding which will be constructed from plywood and will be 3.0m

    high, the final design for this will be agreed with Westminster. The layout of the proposed hoarding can be

    seen on the accompanying drawing in the appendices.

    The site will be guarded by a 24hr security guard and if appropriate CCTV cameras will be installed on the

    perimeter hoarding.

    The Security Guard will man the main access point, access to the site will be achieved by signing in through

    and electronic hand scanner.

    3.22 Westminster Highways Inspector

    Through discussions with Westminster it has been agreed that the project will pay for a dedicated

    highways inspector for the scheme. The highways inspector will ensure that the site is managed in line with

    the agreed traffic orders and that the site is maintained and managed to the required standards. Local

    Stakeholders will have access to the Highways inspector ensuring that any issues are dealt with

    immediately.

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    13/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    3.23 Unauthorised Access

    The Site Management Team will ensure that all fences, security and signs are checked on a regular basis.

    Everyone will remain vigilant for trespassers.

    3.24 Cleanliness

    Operatives will be advised to wash their hands at meal breaks and at the end of each shift. Information onleptospirosis and arsenic will be provided.

    3.25 Regulatory Requirements

    Standards

    The works shall be carried out, as far as is reasonably practicable, in compliance with the following

    standards:

    British Standard BS:5288 Noise Control on Construction and Open Sites, and

    The guidance contained in the BRE publication BRE Pollution Control Guide - Controlling particles, vapour

    and noise pollution from construction sites :

    Part 1 Pre project planning and effective management

    Part 2 Site preparation, demolition, earthworks and landscaping

    Part 3 Haulage routes, vehicles and plant

    Part 4 Materials handling, storage, stockpiles, spillage and disposal

    Part 5 Fabrication processes and internal and external finishes

    Statutory RequirementsThe relevant statutory requirements are listed below:

    Control of Pollution Act 1974

    Environmental Protection Act 1990

    Clean Air Act 1993

    Environmental Protection (Duty of Care) Regulations 1991

    Special Waste Regulations 1997

    Pollution Prevention Control Act 1999 Pollution Prevention and Control Regulations 2000

    The Control of Noise (Codes of Practice for Construction and Open Sites) (England) Order 2002

    Building Act 1984

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    14/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    To work on the project all sub-contractors are expected to have a working knowledge of all relevant Acts

    and Regulations (some of which are listed below) and so be able to promote, stimulate and encourage a

    high standard of health and safety during their work:

    Health and Safety at Work etc Act 1974 The Health and Safety (First Aid) Regulations 1981

    Construction (Head Protection) Regulations 1989

    Manual handling Operation Regulations 1992

    Workplace (Health, Safety and Welfare) Regulations 1992

    Construction (Design Management) Regulations 2007

    Personal Protective Equipment at Work Regulations 1992

    Reporting of Injuries, Diseases and Dangerous Occurrences (RIDDOR) Regulations 1995

    Construction (Health, Safety and Welfare) Regulations 1996

    Confined Spaces Regulations 1997

    The Provision and Use of Work Equipment Regulations 1998

    The Lifting Operations and Lifting Equipment Regulations 1998

    Health and Safety (Enforcing Authority) Regulations 1998

    Control of Substances Hazardous to Health (COSHH) Regulations 2002

    Management of Health and Safety at Work Regulations 1999

    Both of the above lists are not exhaustive.

    Health and Safety Guidance

    MAR shall maintain an updated copy of Construction Site Safety Safety Notes GE-700 (CITB Publication)

    and Successful Health & Safety Management (HSE Publication) which provides guidance on construction

    activities, use of plant and equipment and PPE, etc. This publication shall be readily referred to by the Site

    Manager as and when additional information is required in respect of associated activities (e.g. working

    with asbestos).

    Specific health and safety issues relating to the site shall be dealt with by the Construction Health and

    Safety Plan which shall be maintained throughout the project commencement and shall be updated as

    required.

    A Construction Health and Safety File shall be prepared and submitted upon the completion of the

    construction phase in accordance with the CDM Regulations 2007.

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    15/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    4.0 General

    4.01 Proposed Working Hours & Construction Period

    Access to site will be between the hours of 0800 and 1800hrs Monday to Friday and 0800 to 1300hrs on

    Saturday. No works are expected to take place on Sunday. The whole demolition and construction process

    is scheduled to be undertaken within a 107 week programme.4.02 Public Consultation

    Consultation has already taken place with local stakeholders.

    McAleer & Rushe will also keep the local stakeholders and public updated via the circulation of monthly

    newsletters. These newsletters will provide information relating to the site detailing, progress, programme

    for the next month and contact details in the event that they have any concerns or difficulties. During the

    construction phase information will be provided on a regular basis to all people living in the immediate

    vicinity of the site.

    4.03 Local Stakeholders

    There is in the immediate proximity, neighbouring buildings whose daily activities vary but could be

    impacted with the works. In particular, the neighbouring building occupied by the mounted police division

    and there is a need for consideration due to the presence of working horses in the direct vicinity of the

    works.

    Such provisions that will need to be catered for are:

    Welfare of the animals

    Consideration of the work sequences of the horses

    Timing for quiet works

    Consideration of vibration transfer through the mediums

    Entry and Exit times of the horses when on duty

    Horse Box space to the front

    Awareness of the workforce as to the requirement of the consideration for the horses

    To the west elevation there are two neighbouring buildings whose close proximity may have a bearing on

    the method of construction. They are both commercial and include a pub and McDonalds Fast Food

    restaurant. The access road does not contribute to either premises as a primary or a main pedestrian

    entrance to the businesses but the access road does provide for deliveries to both. It allows for the

    entrance to the cellar for the pub, and a rear door for the McDonalds restaurant. It is understood that the

    building directly opposite is the DECC and it is maintained that there will be no impact on them accessing

    their rear doors.

    4.04 Considerate Constructors Scheme (CCS)

    McAleer & Rushe will register the scheme with the CCS and it is within our own standards to target a score

    of between 34 and 36

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    16/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    4.05 Site Impacts

    Minimising Impacts on Local Environments

    Construction, by its very nature, has the potential to cause many negative environmental impacts upon the

    local environment. All neighbours will have concerns about the impact that construction works will have on

    their lives. It is fair to say that most peoples concerns will be regarding the cleanliness of the project andthe potential for noise that is associated with construction projects. It is, therefore, recommended that

    daily visual checks are carried out to determine if the site could be considered a nuisance. These checks

    should be recorded and rapidly dealt with, the following list, although not full and final - asks questions of

    the kinds of impacts that should be considered:

    Is the site and surrounding area tidy and free of visual intrusion?

    Are footpaths and roads kept clean and free of obstruction?

    If you were a local resident is there anything that would annoy you?

    Are measures being implemented to keep the air clean i.e. reduce dust?

    Are there areas close to the site at higher risk such as flora, fauna and water courses?

    Can noise be limited or eliminated?

    By understanding this concept each member of the construction workforce can help ensure that they are

    the first to identify areas that have the potential to cause concern to local residents and businesses.

    Monitoring Site Impacts

    As noted above construction activity has the potential to cause nuisance, or even harm, from

    environmental disturbance such as noise, vibration and dust. Such issues are often a cause for concern to

    the Local Authority, the projects neighbours and the public at large. Whilst mitigation measures can be

    adopted to minimise nuisance, it is also important to conduct environmental monitoring to measure site

    performance in relation to baseline data and to ensure agreed noise levels are not exceeded.

    Dust and Vibration

    Dust is often the most notable nuisance when it comes to negative construction impacts. Unlike noise and

    vibration dust remains long after the operation that caused it has ceased. In addition to its unsightliness

    dust can be damaging to health as well as detrimental to property. Given the location of the project it wil

    be necessary to adopt robust procedures for dealing with this issue. Dry spells during the summer months

    are the most likely times of year where dust can become a nuisance not least because of the lack of

    moisture to dampen down particles stopping them from becoming airborne. This will, therefore, require a

    monitoring and management regime to be employed by site staff. Where practicable it should be

    considered that any potentially dusty works are to be carried out during the most suitable weather

    conditions. Site management will be best placed to plan these works with due consideration for the localsurroundings but will also have a range of tools at their disposal for managing any dust generated.

    Minimising dust is the best way to avoid any issues arising and this can be done by simply employing a

    vigorous housekeeping regime that uses an absorbent sweeping compound such as Dusmo. The use of

    water, wet vacs, mechanical sweepers and vacuum cleaners may also be used as an effective way of

    keeping dust to a minimum.

    Vibration is to be monitored to demonstrate compliance. To aid this, a baseline survey is undertaken and

    used to measure all works to evaluate their impact.

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    17/43

    C o n s t r u c t i o n s M a n a g e m e n t P l a n 3 - 5 G r e a t S c o t l a n d Y a r d

    Managing Site Impacts

    Controls for day to day issues affecting the local environment will include:-

    Dust Suppression stand pipes with shower head hoses should be available around critical areas of the

    project. Hose heads shall be spring loaded to ensure that water cannot be left running whilst unattended.

    Maintaining road cleanliness Cleanliness of the site perimeter hoardings shall be cleaned regularly to help maintain the sites

    tidy image.

    Provisions for inclement weather grit bins shall be available and positioned at the site gate and be

    filled with salt grit which can then be used for the purpose of snow clearance and frost prevention /

    removal.

    Pest control the provision of adequate means into which canteen and office waste can be

    deposited will greatly reduce the possibility of attracting vermin but will not entirely negate the

    need for a suitable pest control regime.

    Spill kits spill kits for use on site in the event of a spillage shall be readily available. These kits

    should be located at areas of the project which post the most significant risk. In this instance we

    recommend that they be placed at the vehicle gate plus the nominated fuel storage zone and the

    main vehicle unloading are.

    5.0Site Accomodation & WelfareThe decision has been made to utilise No.1 Great Scotland Yard for the provision of site accommodation

    and welfare facilities. When the construction process is sufficiently advanced additional site

    accommodation will be provided within the new building structure.

    6.0 Appendices

    C. Construction Phase Logistics Drawing

    D. McGee Construction Management Statement

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    18/43

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    19/43

    Bus

    Stand

    Bus

    Stand

    Bus

    Stand

    METAL PLASTER

    INERT

    STOPGO

    Site

    Welfare

    Great ScotlandY

    Outline Logistic Plan

    Great Scotland Yard - Logistics Plan -Alandale Logistics Ltd

    40 Yard Skips

    Timber, Metals, Packaging, Inert Was

    Recycling Statistics

    It is anticipated that 90% of all waste

    produced will be recycled.

    Waste Monitoring

    'Smartwaste' is proposed to be used

    Project to monitor on recycling perce

    throughout the project.

    Traffic Management of

    all Construction Vehicles

    by fully trained and qualified

    CITB Traffic Officers

    Vehicle, fork-lift,

    tower crane and hoist

    bookings co-ordinated via

    Alandale's web-based

    Delivery Booking Manager

    Alandale Fire Point

    consisting of:

    1no. CO - 1no. Foam -

    1no Water - Alarm Systemand Fire PlanSignage

    2

    Alandales S2k SAccess Control Sy

    co-ordinate and m

    movements ente

    exiting site

    Alandales biomhand scanner pr

    heightened seand increased

    Driving Access

    Driving Egress

    Reversing Manoeuvre

    Great Scotland Yard

    NRSWA Trained Traffic Marshals to control third party traffic movementswhen construction vehicles arrive and depart utilising Stop/Go boards .Fire Point locations maintained and approved on a regular basis via a quality audit system.Loading bay facilities located adjacent to building.Waste Management team to collect full bins and replacing with empty bins to each level.Full time logistics manager to liaise with project management and site personnel .Central Waste Management Area allocated for a designated collection point .Decorated 3m high hoarding.Half height hoarding with mesh.Proposed location of scaffolding andmonoflex.Indicative location of luffing jib tower cranes.Gate to be used byUKPN.Pedestrian access gate.Fire escape exit.Existing bus stand to be removed.No access from Whitehall. Great Scotland Yard to be one way traffic.Proposed horse box parking area.Welfare and site accommodation located at No. 1 Great Scotland Yard.

    1.

    2.3.4.5.6.7.8.9.10.11.12.13.14.15.16.17.

    Legend

    2

    3

    5

    6

    7

    910

    11

    13

    17

    1

    4

    12

    16

    2

    7

    8

    10

    15

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    20/43

    Construction ManagementStatement

    Document Reference

    MGL-GSY-CMP01rev03

    Version

    Draft

    Prepared By

    Henry Hathaway

    Approved By

    Nicholas Taylor

    Date

    12-11-2012

    Project:Project: 3-5 Great Scotland Yard

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    21/43

    Contents1. INTRODUCTION 42. OUTLINEDEMOLITION&CONSTRUCTIONMETHODSTATEMENT 53. SITESECURITY&ACCESSCONTROL 64. PEDESTRIANACCESS 85. VEHICULARACCESS 96. MATERIALDISTRIBUTION 127. WASTEMANAGEMENT 128. GOODNEIGHBOUR/MANAGINGENVIRONMENTALIMPACTS 15

    APPENDICESAppendixA TrafficManagementPlanDrawingsAppendixB 24hourContactDetails

    Page235GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    22/43

    REVISIONRECORDVersion Date Page/SectionAffected Preparedby Approvedby01 28.11.12 All HH NT

    DISTRIBUTIONLISTVersion Date Recipient00 12.11.12 NiallCanning ProjectManager01 27.11.12 NiallCanning ProjectManager02 28.11.12 NiallCanning ProjectManager03 29.11.12 NiallCanning ProjectManager

    Page335GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    23/43

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    24/43

    Tothewestelevationtherearetwoneighboringbuildingswhosecloseproximitymayhaveabearingonthemethodofdeconstruction.TheyarebothcommercialandincludeapubandMcDonaldsFastFoodrestaurant.Theaccessroaddoesnotcontributetoeitherpremisesasaprimaryoramainpedestrianentrancetothebusinessesbuttheaccessroaddoesprovidefordeliveriestoboth.Itallowsfortheentrancetothecellarforthepub,andareardoorfortheMcDonaldsrestaurant.ItisunderstoodthatthebuildingdirectlyoppositeistheDECCanditismaintainedthattherewillbenoimpactonthemaccessingtheirreardoors.ThereisalsonoriskofthetemporarysiteaccommodationoverseeingthebuildingoccupiedbytheDECCastherewillbenocabinsonthegantryandthescaffoldwillbesheetedwithmonarflex.Refertoparagraph8.2foradescriptionofthemeasurestobeimplementedtoprotectthemountedPoliceDivision.

    2. OUTLINEDEMOLITION&CONSTRUCTIONMETHODSTATEMENT2.1 DemolitionPriortodemolitionoftheexistingbuilding,afullconditionsurveywillbeundertakenandagreedwiththerelevantappointedpartywallsurveyorsandlocalauthority. Theexistingservicesfeedingthesitewillbeidentifiedwiththestatutoryundertakersandterminatedattheboundaryofthesite.FollowingafullR&DAsbestosSurveyandanalysis,anyasbestosconfirmedaspresentwillberemovedbyalicensedandauthorisedasbestosremovalcontractor,havingcompletedtherequirednotificationtotheappropriateregulatorybodies.Withanyasbestosremovedandthenecessarycertificatesissued,demolitioncanproceed. Thedemolitionoftheexistingstructurewillrequireanexternalscaffoldtobeerectedtotheperimeterofthebuilding. ThescaffoldwillbefullysheetedwithhoardingatthelowerlevelandMonarflexabove. Thiswillprovideasealedenvelopetothesiteaffordingprotectiontothepublicandlimitingthedustemissionsfromthesiteduringthedemolitionprocess.Softstripwillbeundertakeninsequencewithanyasbestosremoval. Thiswillincludeinternalfinishes,partitioning,windowsetc. Allarisingswillbesortedforpotentialrecycling. Onceinternalareashavebeenstripped,theroofcoveringswillberemovedtoexposethestructuralroof. Withtheroofstructureremoved,theinternal wallswillbedemolishedtogroundslablevelusingmechanicalplantworkingfromtheexistingconcretegroundslab. Wherepossibletheexistingbrickswillbesalvagedandsortedforrecycling,theremainingmaterialwillberemovedfromthesite. Theremovaloftheinternalbrick/blockworkinfillpanelswillleavetheexteriorfacadesexposed. Careshallbetakentoretainongoingstructuralstability. Alltemporarysupportworkswillhavebeenagreedpriortoanydemolitionworkscommencingwiththeengineer.Thefaadeistoberetainedwiththeinternalelementsofthebuildingdemolishedtogroundfloorlevel,theexistingconcreteslabwillberemovedandcrushedtoformhardcoreforthenewfoundations.2.2 PilingHavingcompleteddemolitionandlevelledthesiteinpreparationforsubstructureworks,theboredpilingwillbeinstalledtoformtheperimeterofthenewbasementareas.ThepilingwillalsobeundertakentothesubstructureoftheproposedUKPNsubstation.

    Page535GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    25/43

    2.3 SubstructureThepilingwillrequiretemporaryproppingasthebulkexcavationproceedstothelowerlevelsaschemethat

    warrantsadetailedtemporaryworksdesign. Thelowergroundfloorwillbeexcavatedfromthewestofthesite,

    workingtowardsthesiteentranceinGreatScotlandYard.Itisexpectedthatalongsidethedemolitionthiswill

    posethe

    most

    frequent

    vehicle

    movements

    during

    the

    project.

    As

    excavation

    proceeds,

    the

    foundations

    can

    starttobeinstalled,againstartingattheeastextremityofthesiteandgraduallyworkingitswaytotheaccess

    roadentrance.

    2.4 Health&SafetyHealth&safetyisanintegralpartoftheplanningprocessforeachproject. Implementationofcomprehensive

    Health&SafetySystemandProceduresensureseveryfacetoftheconstructionprocessisplanned,managed

    andmonitored. Thisalsoensurescompliancewithstatutoryobligations.

    Designersandcontractorsengagedontheprojectwillbecompetentandadequatelyresourced. Thiswillbe

    achievedby:

    Interviewstoascertaincompliancewiththeirlegalduties

    Reviewofexistinghealth&safetypoliciesandprocedures

    Reviewoftheirhealth&safetyperformanceandsitevisits

    TheprincipalcontractorwillbetaskedwithproducingtheConstructionPhasePlanbasedonthecurrent

    informationandthepretenderplan. Theplanwillsetoutthearrangementsformanagingandmonitoringthe

    project. ContractorsengagedtocarryoutworksontheprojectwillbeissuedwiththisHealth&SafetyPlanso

    thattheycanintegratethismanagementphilosophyintotheirhealth&safetyplans. Theprojectteamwill

    implementtheplanassistedbyspecialisthealth&safetyadvisors.

    Allpersonswillbeencouragedtoexpresstheirviewsandconcernsabouthealth&safety. Thisisachievedbyhe

    formulationofvariousroutes. Theseinclude:

    ProjectHealth&Safetycommittees

    Safetyrepresentativesfromeachcontractor

    Toolboxtalksincludingafeedbackprocess

    Discussionandbriefingonmethodstatementsandriskassessments

    Anopendoorpolicywillbeemployedwherebyanyindividualscandiscusshealth&safetyissueswithany

    memberoftheprojectteam. Sitenoticeboards,toolboxtalksandpostersareusedtoconveyrelevant

    informationtopersonsontheproject.

    3. SITESECURITY&ACCESSCONTROL3.1 Introduction

    Page6

    35GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    26/43

    AllsecurityoperationsshallbeimplementedinaccordancewiththelatestBritishStandardsapplicabletothesecurityindustryieBS7858:2006andBS7499:2007andfullcompliancewiththePrivateSecurityIndustryAct2001.ThepresenceoftheMetropolitanPolice,governmentdepartments,residentialandcommercialpropertiesisrecognisedandthefollowingmeasureshavebeendevelopedwithalloftheneighbouringpropertiesinmind.3.2 GenerallyThegeneralsecurityofthesitefallsintothreemaincategories:a) Maintainingasecureperimeterb) Preventingunauthorisedaccessc) DeterringactsoftheftandvandalismThisprotectionisprovidedbyacombinationofphysicalandmannedsecurity.3.3 PhysicalSecurityPhysicalsecurityofthesitewillbeaffordedbytheerectionofperimeterhoardingandfencingerectedinaccordancewiththeCodeofGoodConstructionPracticeorasotherwiseagreedwithLondonBoroughofWestminster.Hoardingswillincorporateanumberoflockablegatestoeffectaccessandegressforbothpedestriansandvehicles. Vehiclegateswillbesupplementedbyraisingarmbarrierswhichofferamorepracticalsolutionduringtheworkingdaywhereasgateswillsecurethesiteperimeterduringsilenthours.Proposedgatesandbarriersareidentifiedonthelogisticsphasingplans. Furthermeasuresincludingalarmstoscaffolding(wheninstalledattheperimeterofthesite)andfloodlightingtosecuritysensitiveareasduringthehoursofdarknessmayalsobeconsidered. Suchenhancedsecuritymaybeofparticularbenefitduringthefitoutstageoftheproject.3.4 MannedSecurityThesiteshallbemannedbyacombinationofstaticandmobileguards. Access/egresspointsshallbemannedbystaticguardswhilstmobileguardsundertakingregularpatrolswillmonitorthephysicalperimetersecurityandrandomlychallengepersonnelonsitetoensuretheyholdavalidsecuritypassfortheproject.Additionalpersonnelmaybedeployedduringthelatterstagesoftheprojecttypicallywhenareasarenearingcompletionorwhenhighvaluefixtures,fittingsandequipmentarepresentonsite. Permittoaccessproceduresmayalsobeimplementedatsuchtimeandwillbemanagedbythesitesecurityteam.Tomaximiseefficiencythemobileguardsprovidereliefcoverforthestaticguardsandmayalsoundertakeadditionaltasksaspartoftheirregulardailyduties,mostcommonlyfiremarshalling. AlloperativesinvolvedwithsitesecuritymustmeettherequirementsofBritishStandard7858:2006(securityscreeningofindividualsemployedinasecurityenvironment).3.5 ThirdPartyLiaisonTheSecurityManagementwillidentifyandliaisewiththelocalCrimePreventionandReductionAdviserandensurethatagoodworkingrelationshipisimplemented. Furthermore,throughcloseliaisonwiththeowners/

    Page735GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    27/43

    occupiersofadjacentpropertiesandtheirsecurityifpresent,anysecurityconcernsheldbytheprojects

    neighbourswillbeadequatelyandeffectivelymanaged.

    4. PEDESTRIANACCESS4.1 IntroductionWhenconsideringpedestrianaccessthethreeprimaryissuestoconsiderare:

    a) Appropriatenessoflocationb) Maintainingsitesecurityc) Segregationofpedestrianandvehiculartraffic4.2 AppropriatenessofLocationPedestrian

    access

    points

    will

    be

    treated

    sympathetically

    to

    principal

    arrival

    routes,

    typically

    determined

    by

    primarypublictransportroutes. Theseaccesspointsshouldalsobeinreasonablycloseproximitytothesite

    welfareaccommodationwhichwillbeaccessibleviaasafe,PPEfree,greenroute. Asafurtherconsideration

    accesspointsshouldbelocatedsuchthatsitepersonnel,whenarrivingatorleavingthesite,donotcauseundue

    inconvenienceornuisancetoneighbouringpremisesortothegeneralpublicatlarge.

    4.3 MaintainingSiteSecurityInordertomaintainsitesecurityitisimportanttoprovidetheminimumpracticablenumberofpedestrian

    access/egresspoints. Inthisinstanceasingleaccesspointintotheprojectisproposed. Accessintothesitewill

    bemanagedtoensureonlyauthorisedpersonnelgainaccess. Theprimarycontrolpointwillbelocatedatthe

    designatedpedestrian

    access.

    This

    control

    point

    shall

    be

    permanently

    manned

    to

    process

    visitors

    and

    non

    inductedpersonnel.

    4.4 SecurityAccessControlItisproposedthatallpersonnel(management,operatives,visitorsetc)arrivingonsiteshouldimmediately

    reporttotheprojectsecurityreceptionwithintheprojectaccommodation. Allpersonnelenteringthesitewill

    berequiredtologinandoutofthesitethispoint,thisattendanceinformationbeingessentialshouldtherebe

    anemergencysiteevacuation.

    4.5 Pedestrian/VehicularSegregationRegulation36oftheConstruction(Designandmanagement)Regulations2007requiresthateveryconstruction

    siteshallbeorganisedinsuchawaythat,sofarasisreasonablypracticablepedestriansandvehiclescanmove

    safelyandwithoutriskstohealth. Againthereisparticularattentiontobepaidtothefactthatthehorsesofthe

    MetPolicearetransitedregularlyandinshortnoticeandabovetheimplementedstandardsconsiderationisto

    beshowntoliaiseinduetimeofprogressandintentionsoftheworks.Inshort,thisregulationrequiresthe

    provisionofsafe,effectiveandfunctionalpedestrianandvehiclesegregation. Itistherefore,proposed,that

    Page8

    35GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    28/43

    pedestriansandvehicleswill,whereverpracticable,notshareaccess/egresspointsorcirculationroutes.

    Therefore,wherevervehiclesandpedestriansarerequiredtoutiliseadjacentaccesssuitablephysical

    segregationshallbeinstalledtodemarcatesafepedestrianroutes.

    4.6 SiteLayoutPedestrianaccess/egresspointsandprimarycirculationroutesaredepictedonthesitelogisticsplan. Vehicles

    makingdeliveriestothesiteordemolitionmaterialwilltravelviathedesignatedroutes.

    OperativeswillattirethemselveswithappropriatePPEwithinthesitewelfarebeforeproceedingontosite.

    Whenpassingbetweenthewelfarecompoundandtheworkingsiteallpersonnelwillberequiredtopass

    throughasecuritycontrolpoint(fullheightturnstilesareproposed). Withinsite,pedestrianrouteswillbe

    delineated,segregatedfromvehicularconstructiontraffic. Theseshallbeclassifiedassitewalkwaysandthe

    wearingofPPEintheseareasshallbemandatory.

    4.7 TransportLinksThesewillbenoparkingavailableonsiteandlocalparkingfacilitiesarelimited. Itwill,therefore,be

    recommendedthatsitepersonneltraveltositeonpublictransport.Whilstnoscheduledbusservices

    immediatelypassthesite,numerousroutesservethesurroundingareawithregularservicesrunning

    throughouttheCity.

    5. VEHICULARACCESS5.1 IntroductionWhenconsideringvehicularaccessthefourprimaryissuestoconsiderare:

    a) Maintainingsitesecurityb) Segregationofpedestrianandvehiculartrafficc) Manoeuvringofvehiclesd) Deliverycoordinatione) MovementofPedestriansandNeighborsProposedsitedemolitionandconstructionworkstrafficroutesareillustratedinAppendixAofthisdocument.

    TherewillbeonevehicleentrancetothesitefromGreatScotlandYard.Forthedurationoftheworkstheflow

    oftrafficonGreatScotlandYardwillbecomeaonewayfromEasttoWest.Thiswillbecoveredundera

    TemporaryTrafficOrder(TTO)agreedandissuedbyTheLondonBoroughofWestminster. Accessgateswillbe

    providedforpedestrianandvehicularaccessintothesitewithclearsignagetomaintainthesafetyofthesite

    andthepublicsubjecttoagreementandapprovalfromTFLandWestminsterHighwaysDepartment

    representatives.Forthepurposesofloadingtherewillbenomorethanfourvehicleswaitingonthestreettobe

    Page9

    35GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    29/43

    loadedasshowninappendixA.Communicationistobethroughthedespatchcontrollertoeachvehicledriverviatwowayradiodirectingthemtoholdpositionifrequiredoutsideoftheborough.Loadingoperationswilltakeplaceduringthehoursof8amto6pm.TheexistingtwowaytrafficsystemonGreatScotlandYardwillbesubjectedtoatrafficorderthatwillimplementaneasttowestonewaysystem.Lorrieswillbereverseddownthesideaccessroadtoallowloadingandunloadingandallowlorriestobeloadedbyanexcavatorthatissituatedonagantry.Theaccessandegressofworkstrafficwillbecarefullymanagedtominimiseitsimpactuponthesurroundinghighwayandlocalneighbors. AccessandegressforconstructionvehiclesmayvaryaccordingtotheparticularstageofworksbutgenerallywillfollowthelogisticsplanattachedintheAppendixA. Deliverieswillbephasedandcontrolledonajustintimebasisallbeingclearlymarkedtoshowtheirdestination. Thiswillminimisetransportaroundthesiteandanyassociatednoise. Alltransportationto,fromandonsitewillbeonrubbertyrevehicles. AllvehicleswillbetakenintothemainbodyofthesiteunderescortbytheMGLormaincontractorappointedTrafficMarshallsandBanksmen.Alldemolitionmaterialwillbedepositedintocontainervehiclesusingskipssuspendedfromthetowercrane. Thedebriswillbethoroughlydampenedattheworkfacetoavoidanydustnuisanceduringtheloadingoperation. Shouldtheroadbeaffectedinanywaybyouractivities,cleaningmeasureswillbeimplementedimmediatelybyanattendantMGLoperative.Allplantandmaterialsaretobestoredwithintheconfinesofthehoarding.Anydeviationfromtheagreedlocaltrafficmanagementmeasuresforsiteaccess/egresswillbepreviouslyagreedwiththerelevantLondonBoroughofWestminsterandTransportforLondonhighwayauthoritiesandtheadjoiningownersbeforeimplementation.Therewillbenoprivatecarparkingallowedonsitealthoughsomesubcontractorworksvehiclesmayrequireparkingfacilitiesonsiteaspartoftheirworksbutspaceswillbelimited. TheMGLsitelabourforceandmanagementwillbeencouragedtousepublictransportandthesiteisveryclosetobothCharingCrosstubestationandCharingCrossmainlinestation.Therewillbenooperativesvehiclesparkedoutsideofthesite.

    5.2 MaintainingSiteSecurityInordertomaintainsitesecurityitisimportantthatvehiclegatesprovideaccesstovehiculartrafficonly.Pedestrianaccess willbeprohibitedatthesepoints. Vehicleaccessgates willbekeptclosed,openedonlytoreceiveordispersevehicles. Pedestrianbarriersareutilisedtomoreefficientlycontroltrafficaccess/egressduringtheworkingdaywhilstthegateswillbeclosedandlockedattheendoftheshifttosecurethesite.Vehicleaccessandegresspointsshouldalsobemannedduringsiteoperationalhours.5.3 Vehicular/PedestrianSegregationItisrecommendedthatvehiclesandpedestriansshould,whereverpracticable,notshareaccess/egressorcirculationroutes. Aspreviouslystatedin4.5constructionvehiclesshallenter/exitthesiteataseparate

    Page1035GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    30/43

    locationtopedestrians. Furthermore,protectedpedestrianrouteswillbeestablishedwithinthesitetoensure

    segregationfromvehiclesoutsideofthesite.

    5.4 ManoeuvringofVehicles

    Inordertopromotesafemanoeuvringinandaroundthesitereversingwillberestrictedtovehiclesreversing

    intothe

    access

    road

    under

    the

    direct

    supervision

    of

    traffic

    marshalls.

    Due

    consideration

    is

    given

    to,

    amongst

    others,thespacerequiredtocompletesuchmanoeuvres,theexclusionofpersonnelfromthisareaandthe

    supervision,directionandcontrolaffordedtothemanoeuvrebyasuitableexperiencedbanksman.

    5.5 VehicleArrivalandDispersal

    Allvehiclesshallapproachthesouthernpartofthesite,westbound,alongtheonewaytrafficsystemin

    accordancewiththeTemporaryTrafficOrder.Directedbyprominentsignageandcontrolledbyattendant

    banksmen,vehiclesshallenterandexitthesiteinaccordancewiththetrafficmanagementplan.Thiswill

    minimisethepotentialforcongestion.

    5.6 VehicleAccess&Egress

    AllvehiclesshallenterthesiteviaGreatScotlandYard.Uponreachingthesitevehiclesshallbemetbyavehicle

    gatemanwhowillcheckthedeliveryagainsthisrecordsbeforeassistingthevehiclewiththemanoeuvre

    requiredtoentersite. Giventhelimitedspacewithinthesiteboundarytherewillnotbesufficientspacetoturn

    vehiclesaround. Itwill,therefore,benecessaryforvehiclestoreverseintositefromthehammerheadjunction.

    Toensurethismanoeuvreisachievedwithmaximumefficiencyandinthesafestpossiblemannertheassistance

    ofatleastonevehiclebanksmanwillberequired. Twooperativeswillbeonhandtoassistinthismanoeuvre,

    oneateachendofthevehicle. Vehiclesshallexitthroughthissamegateandonceagainwillbeassistedbya

    vehiclebanksmanwhowillbeonhandtodispersevehicleswhenitissafetodosoasdescribedbelow.

    5.7 TrafficManagementOperatives

    Allvehicleentrancesandexitsshallbemannedbysecuritytrafficmarshalsresponsibleforreceivingand

    dispersingvehicles. Dutieswillincludecheckingthatvehiclesarriveinaccordancewiththeplanneddelivery

    schedules,advisingdriversofsiterules,issuingvehiclepassesanddirectingtotheappropriateoffloadingzone.

    Whenleaving,marshalswillcollectpasses,confirmthelegitimacyofanyplantormaterialsbeingremovedfrom

    siteandcheckvehiclescleanlinessbeforefinallydispersingbackontothepublichighway. Marshalswillalsobe

    responsiblefordirectingandbankingvehiclestoensurethatmanoeuvresareexecutedsafely,minimisingthe

    risktothegeneralpublic. Finally,marshalswillensurethatthesegatesareusedforvehiculartrafficonly,

    pedestriansseekingtogainentryorexitbeingdirectedtosecurityreception.

    5.8 DeliveryCoordinationofPlantandMaterials

    Siteaccess/egressforallmaterialsandwastewillrequire closecontrol. Thedevelopmentofascheduling

    systemwillprovideanefficientandeffectivemeansofcontrollingalldeliveries. Theimplementationofpre

    agreeddeliveryschedulesandprogrammeswillensurethatalldeliveriesarriveattherighttimewithmaterials

    beingefficientlydespatchedtothecorrectoffloadingandstoragezone. Deliveryschedulingshouldnotbe

    limitedtoreceivingmaterialdeliveriesonsitebutshouldbefullycoordinatewithallmaterialshandling

    Page11

    35GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    31/43

    equipmentwithinthesite(cranes/forklifts/hoistsetc). Dailydeliveryschedulesshouldbeprovidedatallgate

    posts/offloadingpointsandalsoforthecranecoordinator,hoistdrivers,forkliftdriversandanyothermaterials

    handlingequipmentoperators,allofwhomwillbeinconstantradiocommunicationwithoneanother.

    Successfulimplementationofdeliverymanagementregimesrequirescommitmentfromallpersonnelinvolved

    (trafficmarshals,hoistdrivers,materialshandlingequipmentoperators,securityetc). Regulardeliverymeetings

    betweenall

    trade

    contractors

    should

    be

    implemented

    to

    ensure

    that

    the

    delivery

    schedules

    are

    pre

    agreed

    with

    all.

    6. MATERIAL/PLANTDISTRIBUTIONANDSTORAGE6.1 Introduction

    Offloadingmaterialsclosetotheirfinallocationwherepracticable.

    Distributondirectlyfromoffloadtoworkface,justintimedeliveriestominimisestorageanddouble

    handling).

    Useofmaterialshandlingequipmenttotransportmaterialsaroundsiteandtoeachlevelwithinbuildings

    (minimisemanualhandling).

    Theaccessroadistobeusedforoffloadingsoasnottointerruptthemaintrafficflow.

    Materialsstorageistobewithinthehoardingconfinesandnotonthehighway.

    Thecraneistobeusedtoloadandunloadinasafemannerandwithintheremitofthecraneliftingplan.

    7. WASTEMANAGEMENT7.1 IntroductionWastemanagementcanbeconsideredunderthreebroadheadings:

    Collectionandtransportationfromtheworkface

    Removaloffsiteanddisposal

    Environmentalissues(segregation,recyclingetc)

    Aproposedsolutionfortheprojectisdetailedbelow. Itshouldbenotedthattheproposalrelatestogeneral

    buildersrubbishonly,structuraltradestypicallybeingresponsiblefortheirownwastewhereskipsandmuch

    awayvehicles

    will

    be

    used

    to

    collect

    spoils.

    7.2 CollectionandTransportationAsufficientnumberof240/660litrewheeledbinswillbedeliveredtositeanddistributedup/downtoand

    acrossallfloorsbythelogisticsoperatives.. Tradecontractorswillberequiredtodepositalltheirownrubbishin

    thesebins. Astradecontractorsfillthebins,logisticslabourwillbedeployedtoexchangefullbinsforempties,

    transportingfullbinstothegroundfloor. Fullbinswillbestoredinbinholdingareasatgroundlevelawaiting

    Page12

    35GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    32/43

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    33/43

    secondaryprocesstosortcollectedmixedwaste. Onsitesegregationreliesonthesupportofallsite

    managementtoensureunauthoriseduseofdedicatedcontainersforgeneralbuildersrubbishisprohibited.

    Loadsfoundtocontainover5%diversityaredeemedascontaminatedandsubjecttoincreasedtransportand

    handlingcostsofwastetransferstations.

    OffsiteSegregationMixedwastecollectedfromsitewillbesegregatedoffsideatalocalwastetransferstationwhereallmaterials

    willbeprocessedthroughaMRF(MaterialRecyclingFacility). Materialswillbehandpickedandsortedinto

    variouscategoriesreadyforonwardtransportationtorecyclingdepots. Materialsthataredeemedtobenon

    recyclablewillthenbesentthroughatrommeltobepulverisedandusedforfines,anymaterialsremainingfrom

    theprocesswillbesenttolandfill. Itisestimatedthatatleast80%ofwastegeneratedonconstructionprojects

    isrecyclable.

    ReclamationPerformanceTheprojectteamwillagreeatargetbenchmarkforwastereclamation(iewastedivertedfromlandfill). This

    targetwillbepublishedintheSiteWasteManagementPlan.Wastereclamationincludes:

    Reuseonsite

    Reuseonothersites

    Salvagedforreuse

    Returntosupplierviaatakebackscheme

    Collectedfromsitebyanapprovedlicensedwastemanagementcontractorwhoshallsegregate

    wastestreamsforrecycling,recoveryorreuse.

    Thetargetbenchmarkshallbeaminimumof75%byweightor65%byvolumeofnonhazardousconstruction

    waste.

    7.8 SiteWasteManagementPlanSWMPshavebeenbroughtintoforceinEnglandforallprojectsover250,000. Legislationdictatesthataplanis

    inexistencefromdesignstagethroughouttheprojectduration. Aprojectwastechampionwillbeappointedto

    ensureproceduresarekeptrelevantanduptodateandalsotoensurewastermaterialsleavingsiteare

    recordedforprojectbenchmarkingpurposes. Theclientshallappointawastechampiontoberesponsiblefor

    thedevelopmentoftheSiteWasteManagementPlanandsubsequentimplementationandcompliance. This

    maybetheprincipalcontractorbutanalternativeappointmentmaybemadetoensuredesignandpre

    constructionactivitiesareincorporated. TheSiteWasteManagementPlanshallincludethefollowing:

    Identificationofthewastechampion(thenominatedindividualresponsibleforimplementationoftheplan).

    Thetargetbenchmarkforresourceefficiency(theminimisationofwastegenerated)iem3ortonnesof

    wasteproducedper100m2. Thistargetwillbeagreedwiththeprojectteam.

    Thetargetbenchmark,byweightorvolume,forwastereclamation(iediversionfromlandfillthroughreuse,

    recyclingorrecovery). Thistargetwillbeagreedwiththeprojectteam.

    Page14

    35GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    34/43

    Proceduresandcommitmentsforminimisinghazardousandnonhazardouswastetoachieveorexceedthetargetbenchmark.

    Proceduresformonitoring,measuringandreportinghazardousandnonhazardouswastetoidentifyand

    recordthetypeandquantityofwasteproduced.

    Proceduresforsortingwastegeneratedintodefinedwastestreamsforsubsequentreuse,recyclingor

    recovery(either

    on

    site

    or

    off

    site

    at

    alicensed

    facility).

    Proceduresformonitoring,measuringandreportinghazardousandnonhazardouswastetoidentifyand

    recordwhereandhoweachwastestreamisdisposedandthequantityreclaimed.

    Proceduresforcommunicatingtheplantomanagementandoperativesincludingappropriatetargeted

    training.

    Areviewprocesstomonitorthesuccessoftheforegoingproceduresandpromotecontinuousimprovement

    duringtheprojectandforfutureprojects.

    7.9 DutyofCareAsawasteproducer,theclienthasadutytoensurethatanycontractorwhoremoveswastefromthesiteis

    registeredwiththeEnvironmentAgency. Theprincipalcontractorshallberequiredtoprovidedocumentary

    evidencethatallwastecarriersandwastebrokersemployedinconnectionwiththeprojectareappropriately

    licensed. Siterecordsincludingtransfernotesandconveyancenotesshallbecollectedandretained.

    7.10 EnvironmentTheprojectteamwillbecommittedtomaintainingthehighestenvironmentalstandardsanddemandthesame

    standardsthroughoutthesupplychain. Inconjunctionwiththelogisticsprovider,regularauditswillbe

    conductedorpreferredwastecarriers,transferstationsandlandfillsites. Theseauditsareintendedtoconfirm

    compliancewithlegislationandtoensureeveryeffortisbeingmadetomaximisetherecyclingofwaste

    generatedfromsite.

    Anyroadclosuresortrafficmanagementproposalswillbeplannedwellinadvanceandtherelevant

    documentationwillbeagreedwithWestminsterCouncil,TransportforLondonandtheMetropolitanTraffic

    Officersinadvanceincludingtimelyissueofassociatedmethodstatements,datesetc.

    Monthlynewsletterswillbeissuedtothelocalcommunityandneighboursandwillincludedetailsofany

    proposedmajortrafficmanagementchanges.

    8. GOODNEIGHBOUR/MANAGINGENVIRONMENTALIMPACTS8.1 IntroductionThedevelopmentwillbeprogressedwithdueandproperconsiderationgiventothesensitivenatureofadjacent

    occupiedpremises. Akeytoolinthesuccessfulmanagementoftheseconcernswillbetheestablishmentand

    visibleimplementationofarobustGoodNeighbourPolicy.

    8.2 MountedPoliceDivisionPage15

    35GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    35/43

    PreviouslyintheintroductionithasbeendescribedthatthemountedPoliceDivisionisincloseproximitytothe

    proposeddevelopmentandtheworksanddueconsiderationistobeshownthattheoccupiersofthebuilding

    arehorses.Therearenocurrentproposalstorehousethehorsesduringtheworksandthereforeitisnecessary

    toincorporatetheirpresenceintothemanagementoftheproject.

    Thewelfare

    of

    the

    animals

    is

    of

    primary

    importance

    and

    the

    impact

    that

    the

    works

    may

    have

    on

    them.

    The

    horsesareworkhorsesanditisnotedthatthestablesprovidearestareathatisimportantwhennotonduty.It

    isnotedthatthepolicehorsesworkingdaycommencesat6amandwhilethesiteworkinghoursarefrom8am

    andthatthehorsesareeventhorsesaswellashavingtobemadeavailableforemergenciesandmaynotreturn

    until1.30am.Therefore,whiletheremaybepatternstotheirworkingday,thecontractornotesthatsuch

    patternsarenottoberelieduponandinanygivenmomentanemergencymayarise.

    Typically,thecontractorisobligedtoretainthehoursofnoisyandnonnoisyworkandtothateffectthenon

    noisyworksaretobedeemedtoincludeclearingupandloadingmaterialanddebris.Mopachaverequested

    thatthetimebetween2pmand4pmistobereservedasanonnoisytimeeachday. Nonnoisyworkswill

    excludetheuseofanimpacthydraulicbreaker.Equallyso,inordertominimisethedirecttransferofvibration,

    itisproposedthatwherethetwoelevationsexistthatthehorsesarelocatedontheoppositesideofthe

    development,thecontractorproposestousereasonableattemptstodivorcethemainslabfromthewallthat

    wouldtransferthevibration.Cuttingofthestructurewillbeatpreagreedtimes.Thiscanbeundertakenwith

    smallertoolstominimisetheimpact.Wherepossibletheuseoftheimpacthydraulicbreakerwillberestricted

    whereithasbeendemonstratedthattheuseofahydraulicpulveriser(muncher)isasproductiveasthe

    proposedmethodofthehydraulicbreaker.

    Thereisarequirementthatthehorseswillleaveandenterthebuildingatvarioustimesandthetrafficmarshalls

    aretobegivenexplicitdirectionsthatvehiclesaretostopandgivewayandregardlessofthenatureofthework

    thatthehorsesundertakethatnohorns,shoutingorsuddennoisesaretobeallowedforontheroad.Therewill

    betimesthattheMOPAChorseboxwillberequiredtotransportthehorses.Aspaceistobereservedinfrontof

    the35GreatScotlandYardbuildingbetweenthefaaderetentionandthepoliceentrance.Iftherearea

    contractorsvehicleinthispositionthepolicevehicletakesprecedence.(SeeAppendixA)

    Whentheworkforcehasestablishedthemselvesatsite,arepresentativefromthepoliceforcewillbeinvitedto

    visitsiteandgiveapresentationtotheworkerstoensurethattheyareawareofthesensitivitiesofthehorses.

    Keytotheestablishmentofaworkingrapportwillbetheabilityforthesergeantorinspectortohaveadirect

    contactintheeventofanemergency.Thiswillbethesitemanager,insuchaneventthesitemanagerwilldirect

    thatallvehiclesaretoberemovedfromsiteassoonaspossibleandthetrafficmarshallsaretobekeytosucha

    process.Atrialofsuchaneventcanbeundertakenatthesametimeasafiredrill.

    Allscaffoldistobealarmed forsecurityandtobereviewedcontinuously.Owingtothefactthattherearelive

    animalsnexttothesitethealarmsaretobesilentandrespondtotheprivatesecuritycompanydirect.

    Page16

    35GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    36/43

    8.3 PublicHouseandMcDonaldsRestaurantOntheoppositeelevationtotheMountedPoliceDivision,itisnotedthattherewillbevehiclesarrivingto

    undertakedeliveriestothebusinessesofthepublichouseandtoMcDonaldsRestaurant.Itisnotedthatthat

    thereisthepotentialofdisruptionforthebusinessesdeliveries.TheContractoriscommittedtoallowingaccess

    toallow

    for

    the

    deliveries

    and

    to

    help

    in

    all

    instances.

    This

    will

    include

    close

    liaison

    with

    the

    managers

    of

    the

    respectivepremisesoftheirintendeddeliveriesandtocoordinatethecontractorsdeliveries.Thecontractor

    doesnotintendthateitherbusinesswillaltertheirscheduleorimpactontheefficiencyoftheirdeliveries.

    8.4 ConsiderateConstructorsScheme(CCS)TheprojectwillberequiredtoregisterwiththeConsiderateConstructorsSchemeandcomplywiththeirSite

    CodeofConsideratePracticewhichcommitscontractorstobeconsiderateandgoodneighboursaswellas

    clean,respectful,safe,environmentallyconscious,responsibleandaccountable. Theprincipalcontractorwillbe

    requiredtodemonstratetheircommitmentandcompliancewiththescheme,bothpriortoappointmentand

    throughoutconstruction. InordertomaximisetheBREEAMratingforthedevelopment,theprincipalcontractor

    willberequiredtocommittoattainingthemaximumpracticableCSSCodeofConstructionPracticescore.

    BREEAMcredits,inrespectofthisscheme,areawardedasfollows:

    o OnecreditACCSCodeofConstructionPracticescorebetween24.0and31.5.o TwocreditsACCSCodeofConstructionPracticescorebetween32.0and35.5.o ExemplaryLevelACCSCodeofConstructionPracticescoreof36.0ormore.TheprincipalcontractorwillbeexpectedtoattainaminimumCCSCodeofConstructionPracticescoreof32.0.

    8.5 MinimisingImpactsontheLocalEnvironmentConstruction,byitsverynature,hadthepotentialtocausemanynegativeenvironmentalimpactsuponthelocal

    environment. Allneighbourswillhaveconcernsabouttheimpactthatconstructionworkswillhaveontheir

    lives. Itisfairtosaythatmostpeoplesconcernswillberegardingthecleanlinessoftheprojectandthe

    potentialfornoisethatisassociatedwithconstructionprojects. Itis,therefore,recommendedthatdailyvisual

    andaudiochecksarecarriedouttodetermineifthesitecouldbeconsideredanuisance. Thesechecksshould

    berecordedandrapidlydealt withthefollowinglist,althoughnotfullandfinal asksquestionsofthekindsof

    impactsthatshouldbeconsidered:

    Isthesiteandsurroundingareatidyandfreeofvisualintrusion?

    Arefootpathsandroadskeptcleanandfreeofobstruction?

    Ifyouwerealocalresidentisthereanythingthatwouldannoyyou?

    Aremeasuresbeingimplementedtokeeptheaircleaniereducedust?

    Arethereareasclosetothesiteathigherrisksuchasflora,faunaandwatercourses?

    Cannoisebelimitedoreliminated?

    Page17

    35GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    37/43

    Byunderstandingthisconcepteachmemberoftheconstructionworkforcecanhelpensurethattheyarethe

    firsttoidentifyareasthathavethepotentialtocauseconcerntolocalresidentsandbusinesses.

    8.6 MonitoringSiteImpactsAsnotedaboveconstructionactivityhasthepotentialtocausenuisance,orevenharm,fromenvironmental

    disturbancesuch

    as

    noise,

    vibration

    and

    dust.

    Such

    issues

    are

    often

    acause

    for

    concern

    to

    the

    Local

    Authority,

    theprojectsneighboursandthepublicatlarge.Whilstmitigationmeasurescanbeadoptedtominimise

    nuisance,itisalsoimportanttoconductenvironmentalmonitoringtomeasuresiteperformanceinrelationto

    baselinedataandtoensureagreednoiselevelsarenotexceeded.

    8.7 DustandVibrationDustisoftenthemostnotablenuisancewhenitcomestonegativeconstructionimpacts. Unlikenoiseand

    vibrationdustremainslongaftertheoperationthatcausedithasceased. Inadditiontoitsunsightlinessdust

    canbedamagingtohealthaswellasdetrimentaltoproperty. Giventhelocationoftheprojectitwillbe

    necessarytoadoptrobustproceduresfordealingwiththisissue. Dryspellsduringthesummermonthsarethe

    mostlikelytimesofyearwheredustcanbecomeanuisancenotleastbecauseofthelackofmoisturetodampen

    downparticlesstoppingthemfrombecomingairborne. Thiswill,therefore,requireamonitoringand

    managementregimetobeemployedbysitestaff.Wherepracticableitshouldbeconsideredthatany

    potentiallydustyworksaretobetimestobecarriedoutduringthemostsuitableweatherconditions. Site

    managementwillbebestplacedtoplantheseworkswithdueconsiderationforthelocalsurroundingsbutwill

    alsohavearangeoftoolsattheirdisposalformanaginganydustgenerated.Minimising dustisthebestwayto

    avoidanyissuesarisingandthiscanbedonebysimplyemployingavigoroushousekeepingregimethatusesan

    absorbentsweepingcompoundsuchasDusmo. Theuseofwater,wetvacs,mechanicalsweepersandvacuum

    cleanersmayalsobeusedasaneffectivewayofkeepingdusttoaminimum.

    Vibrationistobemonitoredtodemonstratecompliance.Toaidthis,abaselinesurveyisundertakenandused

    tomeasureallworkstoevaluatetheirimpact.Toreducethevibrationthemethodwillbeevaluatedandwhere

    possibletheuseofhydraulicpulverisorswillbeused.Whereapplicabletheadjoiningstructureswillbedivorced

    priortothemaindemolitionoftheelement.

    8.8 ManagingSiteImpactsAconsiderateprincipalcontractorshouldhavearangeoftoolsandproceduresattheirdisposalinordertoreact

    toeverydayconditionsthatmayariseduringthecourseoftheproject. Thesubjectsoftrafficmanagementand

    wastemanagementaretackledseparatelyinearliersections. Controlsfordaytodayissuesaffectingthelocal

    environmentwillinclude:

    DustSuppressionstandpipeswithshowerheadhosesshouldbeavailablearoundcriticalareasofthe

    project. Hoseheadsshallbespringloadedtoensurethatwatercannotbeleftrunningwhilstunattended.

    Page18

    35GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    38/43

    Maintainingroadcleanlinessduringearlyworkstheuseofapressurewashertobeusedbygatemenshallbeconsideredtocleanvehiclewheelsuponexitfromsite. Avisitingroadsweepingserviceshouldalsobe

    consideredtohelpupkeepthesurroundingroads.

    Cleanlinessofthesiteperimeterhoardingsshallbecleanedregularlytohelpmaintainthesitestidy

    image. Thisshallbeachievedwithneighboursinmindandexecutedwithinacordonedareaduringoffpeak

    periodsby

    using

    asimple

    wipe

    down

    technique

    or,

    ifnecessary,

    using

    the

    aforementioned

    pressure

    washer.

    Provisionsforinclementweathergritbinsshallbeavailableandpositionedatthesitegateandbefilled

    withbrownsaltgritwhichcanthenbeusedforthepurposeofsnowclearanceandfrostpreparation.

    Pestcontroltheprovisionofadequatemeansintowhichcanteenandofficewastecanbedepositedwill

    greatlyreducethepossibilityofattractingverminbutwillnotentirelynegatetheneedforasuitablepest

    controlregime.

    Spillkitsspillkitsforuseonsiteintheeventofaspillageshallbereadilyavailable. Thesekitsshouldbe

    locatedatareasoftheprojectwhichpostthemostsignificantrisk. Inthisinstancewerecommendthatthey

    beplacedatthevehiclegateplusthenominatedfuelstoragezoneandthemainvehicleunloadingare.

    Outlinelogisticsphasingplanshavebeenpreparedtodemonstratepracticallogisticalsolutionsthroughoutthe

    constructioncycle.

    Thelogisticsphasingplansdepictthefollowing:

    Mainaccess/egressroutes

    Delivery /offloadingpoints

    Hoardingandfencinglayout,decoratedandmaintained.

    Page19

    35GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    39/43

    AppendixATrafficManagementPlanDrawings

    Page2035GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    40/43

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    41/43

    AppendixB24HourContactNumbers

    Page2135GreatScotlandYard ConstructionLogisticsPlan

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    42/43

  • 7/28/2019 3-5 Great Scotland Yard, Westminster ~ Construction Management Plan 2012

    43/43

    McGee Group Limited340-342 Athlon Road

    WembleyMiddlesexHA0 1BX

    T: +44 (0) 20 8998 1101