3 he relaxation below 1 k
DESCRIPTION
3 He Relaxation below 1 K. Jacob Yoder UIUC October 6 th , 2006. Outline. Goals Proposed method of measurement Status / To do. Goals. Measure relaxation time of 3 He on dTPB coated acrylic at temperatures between 0.3 K and 1.0 K - PowerPoint PPT PresentationTRANSCRIPT
3He Relaxation below 1 K
Jacob Yoder
UIUC
October 6th, 2006
Outline
• Goals
• Proposed method of measurement
• Status / To do
Goals
• Measure relaxation time of 3He on dTPB coated acrylic at temperatures between 0.3 K and 1.0 K
• Measure relaxation time of 3He in the presence of other materials
Proposed method
• Polarized 3He produced by MEOP
• Double cell: 3He polarized at room temp, T1 measured in cold cell
Manifold
RT pumping cell
Cold Cell
V1
V2
3He cycling
1) V1 open V2 open;
Evacuate cells
2) V1 open V2 closed;
Fill with 3He
3) V1 closed V2 closed;
Pump 3He
4) V1 closed V2 open;3He pulled into cold cell as pressure equalizes
5) V1 closed V2 closed;
Measure T1
Repeat
Manifold
RT pumping cell
Cold Cell
V1
V2
Status as of last meeting
• Cryostat reached 0.3 K unloaded
• Magnet built • ~ 1h relaxation
time seen in valve-less pyrex cells
Cool down with dummy cell
• Glass dummy cell cooled to ~1 K
• Anchors did not uniformly cool the cell
• Anchors will need to cover large fraction of the glass surface area
Magnet and NMR setup in place
• Magnet placed around cryostat
• Laser, valve-less double cell, coils put in place
Polarization measured in “cold” cell
• FID amplitude in the cold cell 3.3 V in old location, 2.1 V in cryostat
• T1 of 2500 s before, now T1 ~ 100 s
• T2 in each cell dropped by approximately ½
• Losses are likely due to nearby magnetic materials, which need to be moved away
Relationship between gradients and Relaxation times
mg/cm 12
120
2
242
GsT
Gl
DT
mG/cm 70 1001
2
20
1
GsTDG
BT
Mismatch between implied gradients likely due to highly localized gradient. Wilson seal or ball valve probably the culprit.
Nearby Magnetic Materials
Wilson SealBall Valve
Valve/O-Ring issues• Contamination of the MEOP discharge
– Contamination becomes problematic approximately 2 weeks after filling. This is much longer than the expected fill measurement cycle
• Depolarization of 3He as it passes through the valve– The valve did not reduce the polarization in the “cold”
cell in RT test
• “Real” valved double cell built
To Do• Reduce background gradients by removing
magnetic materials and possibly relocating cryostat +redo room temp test (2 wks)
• Put fill/pumpout manifold in place and test (3 wks)
• Relaxation measurement with pure 3He gas in pyrex cell below 1 K (3 wks)
• 4He wall coating? (2 wks)• Construct/borrow dTPB (?) coated cell and
perform relaxation measurement at working temperature (8-12 wks)
• Test other materials
Costs (to be assumed by Illinois)
• Upgrades to manifold -$500• Glassware -$1000• Materials for new cells 4X -$1200• LHe for tests (6 tests, 250 l/test) -$5265• Contingency (20%) -$1600• Total -$9600