3 integration of asu in process of power generation final presentations/s2b … · linde...
TRANSCRIPT
Dr. Dimitri Goloubev, Dr. Alexander Alekseev
The Linde Group
3rd Oxyfuel Combustion Conference, Ponferrada, 10.09.2013
INTEGRATION OF ASU IN PROCESS OF POWER GENERATION
Linde Engineering
Linde AG Linde Engineering Division
Agenda
• Heat Integration between ASU and Oxyfuel Power PlantØWhat is meant by Heat Integration?
ØRealisation and Power Benefit
• Energy Management between ASU and Power Plant
ØWhat is meant by Energy Management?
ØEvaluation of different Concepts
ØSuitable Choice
• Discussion
Linde Engineering
Linde AG Linde Engineering Division
Heat Integration between ASU and Oxyfuel Power Plant
• Thermodynamic losses in the air compressor of ASU are still very high
Ø The isothermal compressor efficiency is around 75% (25% of consumed power is lost at compressor itself)
• The heat flow from the air compressor can be recovered at the power plant to reduce these losses
• The heat recovering must be maximised with minimisation of the compressor power consumption
Linde Engineering
Linde AG Linde Engineering Division
Heat Integration between ASU and Oxyfuel Power Plant
• Optimisation is possible Ø adiabatic compression at lower pressures doesn't lead to
significant power penalty due to saving the pressure loss in intercooler but allows to recover the heat at higher temperature level
Ø The power penalty can be totally avoided with use of an axial compressor stage at lower pressures
Linde Engineering
Linde AG Linde Engineering Division
Heat Integration between ASU and Oxyfuel Power Plant
Axial compressor with radial stage for MP Air Stream can be used
example picture
Linde Engineering
Linde AG Linde Engineering Division
Heat Integration between ASU and Oxyfuel Power PlantHeat Exchanger for "Heat Integration"
example picture for a small coil-wound HEX
Coil-Wound Heat Exchanger • Efficient cross-flow counter-current
principle
• Air flow as a shell side stream
• Coiled tubes in layers for Feed-Water
• Compactness
• High mechanical robustness
• Linde Technology (LNG Heat Exchangers)
The requirements for "Heat Integration"- heat exchanger are quite strict:
Ø Very large amount of Heat is to be transferred with small temperature difference (MTD=10-15 K or even less)
Ø Very small allowed pressure loss for the air stream (≤ 100 mbar)
Linde Engineering
Linde AG Linde Engineering Division
Heat Integration between ASU and Oxyfuel Power PlantCase study, Results
specific Oxygen Demand: 420 Nm3/MWh @ 1.3 bar(a)
Oxygen Purity: 96.3 %
specific ASU Power: 0,118 MW/MW electrical gross output
Example Power Plant*: W = 400 MW (gross electrical output)
ASU power*: P = 47,2 MW
Heat Integration Gain: approx. 4.15 MW (gross electrical output)
Additional CAPEX: < 1000 Euro/kW
Usual energy evaluation: > 3000 Euro/kW
* No Heat Integration, atm. pressure 1.013 bar(a), rel. humidity 65%, amb. air temperature 291.1 K
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power Plant MAIN IDEA
The main idea is• to liquefy the oxygen during the off- peak power phase (night time or sunny
day etc.) and store it in the LOX storage
• to supply the oxygen from the LOX storage during the peak power phase and to reduce the ASU load (the load of the ASU main air compressor)
Very Important• The overall energy efficiency for characteristic "day – night" cycle becomes
generally lower. There is no power saving from the thermodynamical point of view
• The idea here is, that the overall OPEX becomes lower too in case of certain difference in power prices (off-peak/peak power phases)
• CAPEX becomes higher due to additional hardware components required
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power PlantSCENARIO UNDER CONSIDERATION
• Base load operation during the first yearsØ ASU design for normal flexibility range (80%-105% for the main air
compressor and rectification columns in the Coldbox)
• Scenario for energy management (future operation mode)Ø Oxygen consumption during the day time (16h) is always 100%
Ø Different energy tariffs for the night /day time and lower power output and respectively oxygen consumption in the night time (8h)
Ø It is possible, that he power plant will be operated at min load in the night time. Hereby the electricity feeding into the grid can be even penalised (but can be used for oxygen liquefaction)
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power PlantDifferent concepts for energy management are possible
•Liquefaction of oxygen during the night and evaporation within the day time
Øsimple evaporation of liquid oxygen
Øevaporation of liquid oxygen in ASU
Øadvanced concept with cold compressor for evaporation of liquid oxygen in ASU
Øswapping the liquids in ASU (based on LINDE "VAROX" principle, widely used for steel mills since 1980s)
"Add-on" units are required
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power PlantSimple Evaporation of Liquid Oxygen
Ø No "cold integration" àmuch energy is wasted
Ø Low efficiency of energy storage (only around 27%)
Ø High liquefaction capacities are required for "night" operation to reach significant reduction of ASU power consumption during the day
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power PlantEvaporation of liquid oxygen in ASU
Ø The refrigeration in ASU is provided by LOX-Injection à "cold integration"
Ø Increased efficiency of energy storage (around 55%)
Ø The amount of LOX injected into ASU is limited by refrigeration demand
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power PlantCold compressors for evaporation of liquid oxygen in ASU
Why cold compressors?The amount of LOX injected into ASU is limited by refrigeration demand
Øonly 10% of ASU power consumption can be saved during the day time (for optimised process design)
ØThe use of cold compressors leads to an additional heat input at low temperature level and allows to evaporate significantly higher amounts of LOX in the ASU
How to use cold compressors in the ASU?•Functional implementation of cold compressor into ASU process cycle
Øprofit not only by the heat input at low temperatures, but also by lower power demand with compression at low temperatures
•Adapt the process cycle and make use of cold compressor also in operation without LOX-Injection à CAPEX reduction
Linde Engineering
Linde AG Linde Engineering Division
Triple Column ASU Process Cycle WITHOUT Cold CompressorLOX-Injection Mode
Subc
oole
r
LP C
olum
n
MP
Col
umn
Heat Exchanger
GO
X
PGAN
HP
Col
umn
Linde Engineering
Linde AG Linde Engineering Division
Triple Column ASU Process Cycle WITHOUT Cold CompressorLOX-Injection Mode
Subc
oole
r
LP C
olum
n
MP
Col
umn
Heat Exchanger
GO
X
PGAN
HP
Col
umn
Linde Engineering
Linde AG Linde Engineering Division
Double Column ASU Process Cycle WITH Cold CompressorLOX-Injection Mode
Subc
oole
r
LP C
olum
n
HP
Col
umn
Heat Exchanger
GO
X
PG
AN
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power PlantDouble Column ASU Process Cycle with Cold Compressor
• The cycle with Cold Compressor has around 1.5% lower "stand alone" -efficiency in normal operation case (without LOX-Injection), but however it is partially compensated by better Heat Integration with Power Plant
• Efficient "cold integration" due to direct influence on the rectification process
Ø operation of cold compressor at minimum load in normal operation case
Ø operation of cold compressor at maximum load in LOX-Injection case allows to shift the heat loads between both condensers leading to reduction of the outlet pressure of the main air compressor, what saves energy
• High efficiency of energy storage (around 65%)
• 20% of ASU power consumption can be saved during the day time
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power PlantVarious oxygen production with swapping the liquids in ASU
• Liquids swapping in the ASU depending on Night/Day operation
• Storing the oxygen molecules (separation energy) in the night for day GOX production with reduced air consumption
• Additional costs due to LIN Tank (but no Hot Gas Expander and Liquefier)
GOX Product
AIR
LOX
Main Air Compressor
„COLD“ TurbinePGAN-Turbine for „cold production“(always in operation)
G
LIN
Cold Box ASU
LIN into ASU(Night)
LIN to tank(Day)
LOX into ASU(Day)
LOX to tank(Night)
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power PlantVAROX with swapping the liquids in ASU
• Around 11-12% of ASU power consumption can be saved during the day time (16h) with 100% GOX production
• The amount of stored LOX in the night is limited due to ASU design made basically for normal operation
• The method allows to store the separation energy but not the energy of liquefacton. Therefore significant amount of LOX needs to be stored in the night and injected into the ASU during the day time to have an perceptible effect on power saving
• Energy storage efficiency is high (>90%)
0
20
40
60
80
100
120
0 20 40 60
Oxy
gen
prod
uctio
n, %
Opreation hours, h
Plant design
GOX
LOX to tank
LOX into ASU
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power PlantCONCEPT COMPARISON, OPEX
Data for following scenario:
Ø ASU design for normal flexibility range (80%-105% for the main air compressor and rectification columns in the Coldbox)
Ø Power plant at 100% load during the day time (16h) and at minimal load during the night (8h)
70
80
90
100
110
120
130
0 2 4 6 8 10 12
Ove
rall
OPE
X fo
r ASU
, %
Power price factor (day/night)
Without EnergyManagement
LOX evaporation
LOX Injection
Cold compressor
Varox
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power PlantCONCEPT COMPARISON
LOX evaporation LOX injection Cold Compressor Varox
ASU Power Consumption during the day time forproduction of 100% GOX(ASU design for 80%-105%)
83%* 90%* 81%* 89%*
LOX supply from storage during the day time for production of 100% GOX
20% 5,6% 9,5% 13,2%
Energy Storage Efficiency 27% 55% 65% >90%
ASU Process cycleOxygen LiquefierHot Gas ExpanderAdditional LIN storageCold Compressor
Triple columnYesNoNoNo
Triple columnYesYesNoNo
Double columnYesYesNoYes
Triple columnNoNoYesNo
Relaibility medium medium low high
* Numbers for power consumption during the highcost –power phase, not for overall OPEX!
Linde Engineering
Linde AG Linde Engineering Division
Energy Management between ASU and Power PlantSuitable choice
• The difference in oxygen consumption (day/night) is important for choosing the energy management concept
• VAROX concept can be very efficient in case of large day/night spread in oxygen consumption
• The concept with cold compressors is efficient in case of small day/night spread in oxygen consumption
• The presented concepts can be improved and the overall OPEX can be further reduced if the requirement for energy management is envisaged in the ASU design (multi compressor trains, adapted ASU coldbox design etc.)
Ø higher CAPEX!
• EFFECTIVE SOLUTIONS FOR ENERGY MANAGEMENT CAN BE REALISED
Ø IT IS ALL ABOUT THE COSTS AND RELAIBILITY
Linde Engineering
Many thanksfor your attention