    Three-step problem solving

    Step 3: Action planning and tracking

  • 7/28/2019 3 Step Problem Solving - Step 3

    2/27

    To be the world's best gold company by finding,

    acquiring, developing and producing quality

    reserves in a safe, profitable and socially

    responsible manner.

    Safety Vision

    Every person going home safe and healthy every day.

    Vision

  • 7/28/2019 3 Step Problem Solving - Step 3

    3/27

    Barrick Values

    Behave Like an OwnerWe accept accountability for our actions and results. We treat the Companys assets as our own. We areentrepreneurial and look for opportunities to grow our business. We act with integrity, operating within the

    letter and spirit of the law and Barricks Code of Business Conduct and Ethics.

    Act with a Sense of UrgencyWe are decisive, take initiative and make tough decisions when necessary. We set priorities and act on them.

    Be a Team PlayerWe work safely at all times. We respect our colleagues and those we interact with outside our organization. We

    listen to others for understanding and we ask for help. We build trust and celebrate our successes. We helpothers improve their effectiveness. We promote confidence and trust in each others capabilities.

    Continually ImproveWe are always committed to improvement. We build on good ideas, learn from our mistakes and challenge the

    status quo. We think outside of the box and have a desire to succeed and add value to our work.

    Deliver ResultsWe have a clear vision of where were going and the plan to get there. We focus our resources to achieve our

    objectives. We pay attention to detail and keep our commitments. We deliver results.

  • 7/28/2019 3 Step Problem Solving - Step 3

    4/27

    BOS 3-STEP PROBLEM SOLVING

    Diagnose

    opportunity/set goals

    Keyactivities

    Define the problem

    and assign team Conduct critical

    analyses to identify

    vital few issues

    Build draft value-

    driver tree and

    identify KPIs Communicate

    approach

    and Phase 1

    findings

    Diagnose

    opportunity/set goals

    Step 1

    Generate ideas for

    improvement Existing ideas

    Brainstorming

    Specific tools

    (e.g., lean)

    Stand-alone

    initiatives

    Prioritize ideas

    Action Go-do

    ideas

    Prepare case for

    ideas requiring

    approval

    Generate and

    evaluate ideas

    Step 2

    Plan

    implementation

    Prepare action

    plans Key activities/

    milestones

    Targets on top and

    front-line KPIs

    Set up target

    control sheets

    around KPIs

    Implement and

    review progress

    Actions

    Impact

    Step 3

  • 7/28/2019 3 Step Problem Solving - Step 3

    5/27

    TWO KEY ELEMENTS FOR SUCCESSFUL IMPLEMENTATION

    Comprehensive action plans Ongoing tracking process

    Build understanding and commitment

    among all relevant stakeholders

    Develop explicit plan with actions,

    accountabilities, and milestones Integrate approved ideas into a master

    plan

    Prioritize/sequence ideas to

    maximize cash flow given difficulty

    of implementation

    Reprioritize current activities

    No-escape process to make improvements happen

    A good idea is only goo d onc e implemented!

    +

    Institute process to track

    implementation progress

    Tracking of KPIs and actions

    on target control sheets Regular update meetings

    (integrated into ongoing

    management meetings)

  • 7/28/2019 3 Step Problem Solving - Step 3

    6/27

    COMPREHENSIVE ACTION PLANS 2 BASIC STEPS

    Ensure plans for each idea

    contain all required steps (e.g.,training, new standard operating

    procedures)

    Assign specific resources to

    subtasks

    Include specific start dates, end

    dates, and milestones Clearly depict dependencies

    among tasks

    Develop individual action plans Develop master plan for area

    Ensure high-impact, quick-

    payback ideas are scheduled asearly as possible

    Identify predetermined

    constraints (e.g., capital),

    commitments, and

    interdependencies across ideas

    establish the critical path

    Check load on key individuals

    required after the initial plan; revise

    plans as required

    Build consensus and commitment

    with key managers/stakeholders

    Step 1 Step 2

  • 7/28/2019 3 Step Problem Solving - Step 3

    7/27

    WHAT MAKES A GOOD MILESTONE

    Specific end product that signals real progress toward full implementation

    It will be obvious when the milestone has been reached

    Responsibilities for the milestone are clear

    Project leaders are responsible to achieve milestones on time

    Poor milestone Hold the meeting with MacPherson on ball charge

    Good Milestone

    Final consensus achieved on optimal ball charge at 12%

  • 7/28/2019 3 Step Problem Solving - Step 3

    8/27

    BUILDING THE MASTER PLAN

    Individual action plans

    Resource/timing plan Master area action plan

    Amount of time and

    resources required to

    implement each

    initiative

    Current area

    responsibilities

    Resources required

    to maintain daily

    operations

    Other area initiatives

    Assessment of resources

    required to achieve all area

    goals

    Plan to ensure access toresources

    Other areas of operation

    Better resource sharing

    Recruiting

    Prioritization of individual

    action plans

    Assess interdependencies of

    ideas

    Bring forward maximum

    impact of initiatives while

    respecting resource constraints

    Prioritized set of

    action plans

    Adequate

    resourcesassigned to

    achieve full

    implementation

    Agreement from

    all levels of

    management thatthe plan is

    feasible

    +

  • 7/28/2019 3 Step Problem Solving - Step 3

    9/27

    TWO KEY ELEMENTS FOR SUCCESSFUL IMPLEMENTATION

    Comprehensive action plans Ongoing tracking process

    Build understanding and commitment

    among all relevant stakeholders

    Develop explicit plan with actions,

    accountabilities, and milestones

    Integrate approved ideas into a master

    plan

    Prioritize/sequence ideas to

    maximize cash flow given difficulty

    of implementation

    Reprioritize current activities

    Institute process to track

    implementation progress

    Tracking of KPIs and actions on

    target control sheets

    Regular update meetings(integrated into ongoing

    management meetings)

    No-escape process to make improvements happen

    A good idea is only good on ce implemented!

    +

  • 7/28/2019 3 Step Problem Solving - Step 3

    10/27

    TP/hour OP costsAvailability

    SAG Power

    utilization

    Activities

    What Who When

    Cone power

    utilization

    Activities

    What Who When

    Retorque per

    changeover

    Activities

    What Who When

    Liner Cost/ton

    Activities

    What Who When

    Overall

    targets

    Front-line

    KPIs andTarget

    Control

    Sheets

    Unit KPIs

    ILLUSTRATIVE

    TARGET CONTROL SHEETS LINK ACTION PLANS

    AND EXPECTED RESULTS

    Regular

    performancereviews

    Corrective action

    Wet Mill #1 Tons per day

    Operating cost/ton

    Grind constraints

  • 7/28/2019 3 Step Problem Solving - Step 3

    11/27

    WHAT IS A TARGET CONTROL SHEET?

    TARGET CONTROL SHEETS track the

    overall impact of these projects against

    planned results specified in individual

    projects

    Graphical

    representation of KPI

    performance versus

    target over time

    List of all projects

    that affect KPI and

    progress against

    each

    ILLUSTRATIVE

    TARGET CONTROL SHEETSubject: Reduction of Equipment Downtime

    Responsible: John Miller Dept. Production 13 B Date: Nov. 26, 1998

    month week 1 2 3 4 5 6 7 8 9 10 11 12

    Plan 11 11 10.5 9.5 9.2 8.7 8.5 8.2 7.8 7.5 7 6.5

    Act. 11.8 11.5 10.0 9.0 8.9 8.3 8.0 7.9 7.7

    Activities

    1. Trai n operat ors and Pl an

    MA's on problem

    solving Act.

    2. Introduce changeover Plan

    reduction program

    Act.

    3. Change all old rol lers Plan

    and bearings at

    conveyors Act.

    4 . In troduce P revent ive P lan

    Maintenance Program

    Act.

    Plan

    Actual

    Unit:[ %of total

    runtime ]

    8

    7

    6

    10

    9

    11

    KPI:

    Downtime

  • 7/28/2019 3 Step Problem Solving - Step 3

    12/27

    EXAMPLE TARGET CONTROL SHEET FROM MEIKLE

    Subject: RTD-TRACK DOZER-BLADE AIR FILTER COST BETZE- POST CONTINUOUS IMPROVEMENT.

    Responsible: KEVIN R HUGHES Department: MINE MAINTENANCEUpdate: 5/30/2001

    Date Jan/2001 Feb/2001 Mar/2001 Apr/2001 May/2001 Jun/2001 Jul/2001 Aug/2001 Sep/2001 Oct/2001 Nov/2001 Dec/2001Plan 2100 2100 2100 950 950 950 950 950 950 950 950 950

    Act. 2100 2100 700 644 980 633 1104

    Activities

    Condition based Plan

    Maintenance of filter.Act

    Remove air filters from Plan

    PM kits. Act.

    Train Maint Techs. On Plan

    restriction gauges Act.

    Train Operators on Plan

    restriction gauges Act.

    Plan

    Characteristic:Dollar Spend

    Unit: Dollars eamonth

    Week Month

    1500

    2000

    1000

    500

    Actual

  • 7/28/2019 3 Step Problem Solving - Step 3

    13/27

    RIGOROUS PERFORMANCE REVIEWS

    TOOLS FOR MONTHLY REVIEWS

    TARGET CONTROL SHEETSubject: Reduction of Equipment Downtime

    Responsible: JohnMiller Dept. : Production13B Date: Nov. 26, 1998

    m on th w ee k 1 2 3 4 5 6 7 8 9 10 11 12

    Plan 11 11 10.5 9.5 9.2 8.7 8.5 8.2 7.8 7.5 7 6.5

    Act. 11.8 11.5 10.0 9.0 8.9 8.3 8.0 7.9 7.7

    Activities

    1 . T ra in o pe ra to rs a nd P la n

    MA's onproblemsolving Act.

    2. Introducechangeover Plan

    reductionprogramAct.

    3. Changeall o ldro llers Plan

    andbearings atconveyors Act.

    4. IntroducePreventive Plan

    MaintenanceProgramAct.

    5. Establishautonomous Plan

    work teams with owner-s hip for e qu ip me nt A ct .

    6. Focusedproblem solvingPlan

    tot acklespecificproblems Act.

    Plan

    Actual

    Unit:[ %oftotal

    runtime ]

    8

    7

    6

    10

    9

    11

    Characteristic:

    D

    owntime

    Bring background

    data for detailed

    discussion of

    problems

    Pareto equipment downtime

    2. Review actual

    performance vs. target.

    3. Review progress of

    planned projects.

    Understand delays in

    projects or lack of impact.

    Decide additional activities

    or adjust detailed action

    steps

    1. Bring updated TargetControl Sheet to the

    monthly review

    meeting

    ILLUSTRATIVE

  • 7/28/2019 3 Step Problem Solving - Step 3

    14/27

    KEY QUESTIONS FOR IMPLEMENTATION REVIEW MEETINGS

    1. Did we do what we said wed do?

    2. Are we getting the impact?

    3. What are we going to do about it?

    4. What else should we be doing to improve?

    TARGET CONTROL SHEETSubject: Reduction of Equipment Downtime

    Responsible: JohnMiller Dept. : Production13B Date: Nov. 26, 1998

    m on th w ee k 1 2 3 4 5 6 7 8 9 10 11 12

    Plan 11 11 10.5 9.5 9.2 8.7 8.5 8.2 7.8 7.5 7 6.5

    Act. 11.8 11.5 10.0 9.0 8.9 8.3 8.0 7.9 7.7

    Activities

    1 . T ra in o pe ra to rs a nd P la n

    MA's onproblem

    solving Act.

    2. Introducechangeover Plan

    reductionprogram

    Act.

    3. Changeall o ldrollers Plan

    andbearings at

    conveyors Act.

    4. IntroducePreventive Plan

    MaintenanceProgram

    Act.

    5. Establishautonomous Plan

    work teams withowner-

    s hi p fo r eq ui pm en t A ct .

    6. Focusedproblem solvingPlan

    totacklespecific

    problems Act.

    Plan

    Actual

    Unit:[ %oftotal

    runtime ]

    8

    7

    6

    10

    9

    11

    C

    haracteristic:

    Downtime

  • 7/28/2019 3 Step Problem Solving - Step 3

    15/27

  • 7/28/2019 3 Step Problem Solving - Step 3

    16/27

    TRACKING BEST PRACTICES

    This phase is critical, without impact the project will have been

    worse than simply a waste of time

    Tried that, didnt work syndrome tough to restart

    Work to create a culture of disciplineWe do what we

    commit to, and we raise issues early

    Best practice Common pitfalls

    Milestone tracking provides early

    warning system for possible delays,

    removal of barriers

    Meetings focused on identifying and

    solving implementation problems

    what are we going to do about it?

    Celebrate wins/successes

    Issues not discussed or addressed

    until project slippage has occurred

    Meetings focus on assigning blame

    May cause people to hide issues

    until they become crises Wins go uncelebrated, lose

    improvement momentum

  • 7/28/2019 3 Step Problem Solving - Step 3

    17/27

    TWO KEY ELEMENTS FOR SUCCESSFUL IMPLEMENTATION

    Action plans Ongoing tracking process

    Build understanding and commitment

    among all relevant stakeholders

    Develop explicit plan with actions,

    accountabilities, and milestones

    No-escape process to make improvements happen

    A good idea is on ly good once implemented!

    +

    Institute process to track

    implementation progress

    Tracking of KPIs and actions

    on target control sheets Weekly/bi-weekly team

    progress reviews

    Monthly update meetings to

    management

  • 7/28/2019 3 Step Problem Solving - Step 3

    18/27

    3a) WHAT IS AN ACTION PLAN???

    What it is What it does

    Visually displays what actions are

    going to happen and shows their

    interdependencies

    Answers the 3Ws what, who and

    when

    Shows all meetings, needed

    approvals, timelines, etc.

    Is easily updated

    Sets a provisional standard

    Ensures you have thought through

    everything that needs to happen

    Ensures accountability and clarity

  • 7/28/2019 3 Step Problem Solving - Step 3

    19/27

    WHAT MAKES A GOOD MILESTONE

    Specific end product that signals real progress toward fullimplementation

    It will be obvious when the milestone has been reached

    Responsibilities for the milestone are clear

    Project leaders are responsible to achieve milestones on time

    Poor milestone

    Hold the meeting with MacPherson on ball charge

    Good Milestone

    Final consensus achieved on optimal ball charge at 12%

  • 7/28/2019 3 Step Problem Solving - Step 3

    20/27

    3a) EXAMPLE IMPLEMENTATION PLAN

    What Who When

    07:00 08:0007:15 07:30 07:45

    Wake up Call service

    Take shower Me

    Shave Me

    Get dressed Me

    Brush hair Me

    Leave for work Me

    Make breakfast Tim Hortons

    Eat breakfast Me

    Arrive at work Me

    Walk to work Me

    Walk to breakfast Me

  • 7/28/2019 3 Step Problem Solving - Step 3

    21/27

    3a) ACTION PLANNING EXERCISE - BUYING A HOUSE

    Overview A couple is currently renting an apartment, but have

    decided to purchase their first home. They need an

    action plan from decision to move in.

    Exercise Please build the couples action plan and present in a

    GANTT chart format

  • 7/28/2019 3 Step Problem Solving - Step 3

    22/27

    TWO KEY ELEMENTS FOR SUCCESSFUL IMPLEMENTATION

    Ongoing Tracking Process

    Build understanding and commitment

    among all relevant stakeholders

    Develop explicit plan with actions,

    accountabilities, and milestones

    +

    Institute process to track

    implementation progress

    Tracking of KPIs and actions

    on target control sheets Weekly/bi-weekly team

    progress reviews

    Monthly update meetings to

    management

    Action Plans

    No-escape process to make improvements happen

    A good idea is on ly good once implemented!

  • 7/28/2019 3 Step Problem Solving - Step 3

    23/27

    TARGET CONTROL SHEETSubject: Reduction of Equipment Downtime

    Responsible: John Miller Dept. Production 13 B Date: Nov. 26, 1998

    month week 1 2 3 4 5 6 7 8 9 10 11 12

    Plan 11 11 10.5 9.5 9.2 8.7 8.5 8.2 7.8 7.5 7 6.5

    Act. 11.8 11.5 10.0 9.0 8.9 8.3 8.0 7.9 7.7

    Activities

    1. Trai n operat ors a nd P lan

    MA's on problem

    solving Act.

    2. Introduce changeover Plan

    reduction program

    Act.

    3. Change all old rol lers Plan

    and bearings at

    conveyors Act.

    4 . In troduce P revent ive P lan

    Maintenance Program

    Act.

    Plan

    Actual

    Unit:[ %of total

    runtime ]

    8

    7

    6

    10

    9

    11

    K

    PI:

    Dow

    ntime

    3b) WHAT IS A TARGET CONTROL SHEET?

    TARGET CONTROL SHEETS track the

    overall impact of these projects against

    planned results specified in individual

    projects

    Graphical

    representation of KPI

    performance versus

    target over time

    List of all projects

    that affect KPI and

    progress against

    each

    ILLUSTRATIVE

  • 7/28/2019 3 Step Problem Solving - Step 3

    24/27

    3b) KEY QUESTIONS FOR REVIEW MEETINGS

    1. Did we do what we said wed do?

    2. Are we getting the impact?

    3. What are we going to do about it?

    4. What else should we be doing to improve?

    TARGET CONTROL SHEETSubject: Reduction of Equipment Downtime

    Responsible: JohnMiller Dept. : Production13B Date: Nov. 26, 1998

    m on th w ee k 1 2 3 4 5 6 7 8 9 10 11 12

    Plan 11 11 10.5 9.5 9.2 8.7 8.5 8.2 7.8 7.5 7 6.5

    Act. 11.8 11.5 10.0 9.0 8.9 8.3 8.0 7.9 7.7

    Activities

    1 . T ra in o pe ra to rs a nd P la n

    MA's onproblem

    solving Act.

    2. Introducechangeover Plan

    reductionprogram

    Act.

    3. Changeall o ldrollers Plan

    andbearings at

    conveyors Act.

    4. IntroducePreventive Plan

    MaintenanceProgram

    Act.

    5. Establishautonomous Plan

    work teams withowner-s hi p fo r eq ui pm en t A ct .

    6. Focusedproblem solvingPlan

    totacklespecific

    problems Act.

    Plan

    Actual

    Unit:[ %oftotal

    runtime ]

    8

    7

    6

    10

    9

    11

    Chara

    cteristic:

    Dow

    ntime

  • 7/28/2019 3 Step Problem Solving - Step 3

    25/27

    Daily

    Weekly or

    bi-weekly

    Monthly

    3b) SAMPLE AGENDA FOR WEEKLY TEAM PROGRESS REVIEWS

    Annual

    ILLUSTRATIVE

    1. Review performance identifying root causes of

    what went well/didnt

    2. Review action plans Did we do what we said we

    would do for the period? Are we on track?

    3. Discuss any improvement actions required. Agree

    on revisions to actions plans:

    Changes to actions for existing ideas

    Need for more problem solving

    Example Agenda

    Level:

  • 7/28/2019 3 Step Problem Solving - Step 3

    26/27

    3b) SAMPLE PROCESS FOR MONTHLY MANAGEMENT REVIEWSILLUSTRATIVE

    TARGET CONTROL SHEETSubject: Reduction of Equipment Downtime

    Responsible: JohnMiller Dept. : Production13B Date: Nov. 26, 1998

    m on th w ee k 1 2 3 4 5 6 7 8 9 10 11 12

    Plan 11 11 10.5 9.5 9.2 8.7 8.5 8.2 7.8 7.5 7 6.5

    Act. 11.8 11.5 10.0 9.0 8.9 8.3 8.0 7.9 7.7

    Activities

    1 . T ra in o pe ra to rs a nd P la n

    MA's onproblemsolving Act.

    2. Introducechangeover Plan

    reductionprogramAct.

    3. Changeall o ldro llers Plan

    andbearings atconveyors Act.

    4. IntroducePreventive Plan

    MaintenanceProgramAct.

    5. Establishautonomous Plan

    work teams with owner-s hip for e qu ip me nt A ct .

    6. Focusedproblem solvingPlan

    tot acklespecific

    problems Act.

    Plan

    Actual

    Unit:[ %oftotal

    runtime ]

    8

    7

    6

    10

    9

    11

    Characteristic:

    Downtime

    Bring background

    data for detailed

    discussion of

    problems

    Pareto equipment downtime

    2. Review actual

    performance vs. target.

    3. Review progress of

    planned projects.

    Understand delays in

    projects or lack of impact.

    Decide additional activities

    or adjust detailed action

    steps

    1. Bring updated TargetControl Sheet to the

    monthly review

    meeting

  • 7/28/2019 3 Step Problem Solving - Step 3

    27/27

    3b) ACTION TRACKING BEST PRACTICES

    This phase is critical, without impact the project will have been

    worse than simply a waste of time

    Tried that, didnt work syndrome tough to restart

    Work to create a culture of disciplineWe do what we

    commit to, and we raise issues early

    Best practice Common pitfalls

    Milestone tracking provides early

    warning system for possible delays,

    removal of barriers

    Meetings focused on identifying and

    solving implementation problemswhat

    are we going to do about it?

    Celebrate wins/successes

    Issues not discussed or addressed until

    project slippage has occurred

    Meetings focus on assigning blame

    May cause people to hide issues

    until they become crises

    Wins go uncelebrated, lose

    improvement momentum