30nos. distributaries under the 3 canals are in progress and are to be completed by 3/2006
DESCRIPTION
Discharge : 950 Cusecs Ayacut : 55,000 Ac. Length : 67.60 Km. Capacity : 78 TMC FRL : 330’(+100.58M) Ayacut : 4.14L Acrs. Discharge : 380 Cusecs Ayacut : 43,000 Ac. Length : 72.92Km. - PowerPoint PPT PresentationTRANSCRIPT
• 30Nos. Distributaries under the 3 canals are in progress and are to be completed by 3/2006.
• Lining works for all 3 Main Canals proposed in package 94, 95 & 96 for Rs.95Cr.
• The Project will be completed by 6/2006 & IP of 4.14 Lakh Acres (Stab. 2.75 Lakh acres + New 1.39 Lakh acres) will be created.
• Funded by AIBP.
• 30Nos. Distributaries under the 3 canals are in progress and are to be completed by 3/2006.
• Lining works for all 3 Main Canals proposed in package 94, 95 & 96 for Rs.95Cr.
• The Project will be completed by 6/2006 & IP of 4.14 Lakh Acres (Stab. 2.75 Lakh acres + New 1.39 Lakh acres) will be created.
• Funded by AIBP.
• Head works, 3 main canals & Structures completed.• Head works, 3 main canals & Structures completed.
SOMASILA PROJECT (2 years period)
NE
LL
OR
E
AN
ICU
T
SA
NG
AM
AN
ICU
T
PENNA RIVER
BA
Y O
F B
EN
GA
L
SOMASILA- KANDALERU FLOOD FLOW CANAL
KA
VA
LI C
AN
AL
(PK
G94
)
KANIGIRI RESERVOIR
SOUTH FEEDER CANAL (PKG 95)
SO
MA
SIL
A R
ES
ER
VO
IR
Capacity : 78 TMC FRL : 330’(+100.58M) Ayacut : 4.14L Acrs.
North fe
eder canal (P
KG 96)
Discharge : 380 Cusecs
A
yacut :
43,000 Ac.
Length :
72.92Km
KANDALERU RESERVOIR
Dis
char
ge :
950
Cus
ecs
Aya
cut
:
55,0
00 A
c.
Len
gth
:
67.6
0 K
m
Discharge : 353 Cuses Ayacut : 41,000 Ac. Length : 72.00Km
AP
– T
N
B
oard
er
PoondiReservoir
Capacity : 68.05TMC Ayacut : 3Lakh Acres. FRL : + 279’
Cap.2
.75 T
MC
1 Project Profile: Across river Pennar at Somasila (V), Nellore (Dt.)
2 No. of EPC Packages : 3 No
4 Agreement value of 3 packages : Rs.94.87 Crs.
5Budget provision for 2006-07
: Rs.150.00 Crs.
6Expenditure of the project
2004 – 05 : Rs. 550.75 Crs.
2005 – 06 : Rs. 44.28 Crs.
Cum. Exp. : Rs. 595.03 Crs
7 Utilisation : 48.54 TMC
8 Ayacut New Ayacut : 1,39,000 acres
Stabilisation : 2,75,000 acres
Total : 4,14,000 acres
9 Land Acquisition
Required : 133.44 acres
Requisitioned : 13.44 acres
Acquired : 21.61 acres
10 Forest land : 636.90 acres for canals
11 Estimated Cost of LA : Rs.50.00 Crs.
SOMASILA PROJECT
12 Mob. Advance (Rs. in Crores) : Paid Recovered
2004-05 : 1.83 --
2005-06 : 7.08 --
Total : 8.91 --
13Target date of completion
: 7/2006
PKG No.
DescriptionAgt. Value &
DateAgt.
PeriodName of the contractor
94
Providing cement concrete lining of Kavali canal between KM 1.609 and KM 67.619
Rs. 36.603 Cr.Dt: 23.3.05
24 MonthsM/s SRK Bhailal Bhai, JV, Hyd
95
Providing cement concrete lining in bed and side slopes of somasila project in between KM 11.4000 to KM 74.725
Rs. 28.81 CrDt:25.3.05
24 MonthsM/s MSK – SURYACON (JV), Nellore
96
Providing cement concrete lining of GK canal (NFC) between 13.00 and KM 72.920
Rs. 29.4643 CrDt: 25.3.05
24 MonthsM/s MSK – SURYACON (JV), Nellore
SOMASILA PROJECT
Pkg.No. 94/Cat-II : Easening of slops 1:5:1 providing cement concrete lining with paver in bed and side slopes of Kavali canal of Somasila Project in between Km.1.609 to Km.67.619 including Investigation, Design and estimation.
SOMASILA PROJECT
Name of the Contractor : M/s. S.r.K. Bhailal Bhai (JV)Agreement Amount : Rs. 36.60 Crs.Agreement Date : 23-03-2005Period of completion : 24 Months(8 milestones)Target date of completion : 3/2007
Designs : HPs approved
Execution : work not in progress due to water released into
the canal
Qty. of earth work done : 70,000 cum against 7,27,907cum
Machinery : Deployed 45 Nos. (Excavators-7, Tippers-19,paver-
2,concrete mixers-4 Nos)
Expenditure : 2004-2005 - Rs.
1.83 Crs.
2005-2006 - Rs. 1.83 Crs.
Cum. Exp. Mob. Adv. only - Rs. 3.66 Crs.
Bottle Neck : Forest clearance.
Forest land : Required 319.81 acres
Pkg.No. 95/Cat-II : Construction of distributary system of create irrigation potential of 912 Acres including investigation, design and estimation.
SOMASILA PROJECT
Name of the Contractor : M/s. M.S.K. Surya Con(JV)
Agreement Amount : Rs. 28.81 Crs.
Agreement Date : 25-03-2005
Period of completion : 24 Months(8 months)
Target date of completion : 3/2007
Investigation : 63.325 Km length against 81.40 Km
Design : 2.00 Km length against 81.40 Km
Execution : 14 Kms length against 81.40 Kms.
Qty. of earth work done : 3,37,000 cum against 10,23,380cum
Qty. of concrete work done : 3000 cum against 61,990 cum
No. of Machinery : 43 Nos. (Excavators-5, Tippers-4, pavers-4,
concrete Mixers-6)
Expenditure : 2005-2006 - Rs. 4.83 Crs.
(Inc. Mob. Adv.)
Land Acquisition : Required 133.44 ac., Acquired 21.61 ac.
Bottle neck : Forest clearance and land acquisition.
Forest Land : Required 168.83 acres
Pkg.No. 96/Cat-II : Easening of slops 1:5:1 providing cement concrete lining with paver in bed and side slopes of G.K. Canal (NF.C) of Somasila Project in between Km.13.00 and Km.72.920 including Investigation, Design and estimation.
SOMASILA PROJECT
Name of the Contractor : M/s. M.K.S. Surya Const(JV)
Agreement Amount : Rs. 29.46 Crs.
Agreement Date : 25-03-2005
Period of completion : 24 Months(8 milestones)
Target date of completion : 3/2007
Investigation : Completed.
Designs : In progress
Execution : 9.73 Km length against 59.92 Kms.
Qty. of earth work done : 1,25,000 cum against 9,53,297 cum
Machinery : Deployed 5 Nos. (Excavator-1, Tippers-4)
Expenditure : 2005-2006 - Rs. 3.53 Crs. (Inc. Mob. Adv.)
Forest land : Required 148.26 acres
Bottle Necks : Forest clearance