37 · 2017. 8. 4. · prof. b v s viswanadham, department of civil engineering, iit bombay...

40
Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay 37

Upload: others

Post on 27-Jan-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    37

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Module 6:

    Lecture -2: Buried Structures

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Load on Pipes,

    Marston’s load theory for rigid and flexible pipes,

    Trench and Projection conditions,

    minimum cover,

    Pipe floatation and Liquefaction.

    Content in this module:

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Materials transported through buried pipes

    Crude and refined petroleum,

    Fuels - such as oil, natural gas and biofuels

    Waste products in a fluid sate including sewage,slurry and industrial wastes.

    Water used for drinking or irrigation

    In some cases, hydrogen gas, and highly toxicammonia have been transported.

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Buried pipelines

    Pipes that are buried underground are required tosustain other loads besides the internal fluidpressure.

    That is, they must support the soil overburden,groundwater, loads applied at the ground surface(like vehicular traffic) and forces induced by seismicmotion in seismic prone zones.

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Buried pipes are, therefore, structures as well asconduits for conveying fluid.

    Special design procedures are required to beadopted while designing buried pipelines, toensure that both the functions aresimultaneously fulfilled.

    Buried pipelines

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Significance of Buried pipelines

    As the pipelines are buried, more land space canbe utilized for construction above the ground.

    Buried pipelines ensure minimum number ofbends/crossing along the length of the pipe, asthey can pass in a relatively straight manner belowthe ground.

    This, in turn ensures minimum losses due tobending and joints.

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Significance of Buried pipelines

    As the pipes are placed below the ground, theyare relatively safe from sabotage point of view.

    Moreover, buried pipelines are a necessity in caseof pipelines carrying sewage, oil or hazardousend-products of complex industrial processes inorder to prevent contamination to the surroundingenvironment.

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Functions of buried pipe lines

    Hydraulic:

    Designed to carry fluids produced by public watersystems, sewers, drainage facilities, and manyindustrial processes.

    Structural:

    Designed to carry the weight of the ground andany load acting on it.

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Ditch conduit

    Various classes of conduits installation (Spangler & Handy, 1973)

    Pipe is installed in a narrowtrench (generally, trench width≤ 2 d) in undisturbed soil, thenbackfilled to natural groundsurface level.

    Examples of this type ofconduit are sewers, drains,water mains, gas mains, andburied oil pipelines.

    Buried pipes are divided into twomain categories: ditch conduits(trench conduits) and projectingconduits (embakment conduits)

    d

    BackfillH

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Various classes of conduits installation (Spangler & Handy, 1973)

    Positive projecting conduit

    Projecting conduits are further divided into two groups: Positive and Negative Projecting conduits.

    A positive projecting conduitis a conduit or pipe installedin shallow bedding with thetop of the pipe cross-sectionprojecting above the naturalground surface.

    Highway and railroad culvertsare often installed in this way.

    H

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Various classes of conduits installation (Spangler & Handy, 1973)

    Negative projective conduit

    A negative projecting conduit is aconduit installed in a relativelynarrow and shallow ditch with thetop of the conduit below thenatural ground surface; the ditch isthen backfilled with loose soil andan embankment is constructed.

    Effective in reducing the load onthe conduit, especially if thebackfill above the conduit is loosesoil.

    Compacted soil

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Imperfect ditch conduit

    Various classes of conduits installation (Spangler & Handy, 1973) Special case, similar to negative

    embankment condition, but morefavorable from standpoint of loadreduction on pipe, used in verydeep installations.

    Difficult to achieve for large-diameter pipes. This type ofconstruction is called imperfect-ditch conduit or induced-trenchconduit.

    Not recommended for wet areas

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Active arching (Flexible pipes)

    Stress distribution across plane above and below pipe

    Active arching occurs when the structure is morecompressible than the surrounding soil.

    If the structure deforms uniformly on plane above andbelow pipe, the stresses on it tend to be lower towardthe edges due to mobilized shear stresses in the soil.

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Passive arching (rigid pipes) In passive arching, the soil is more compressible than the

    structure. As a result, the soil undergoes large displacements, mobilizing

    shear stresses which increase the total pressure on the structurewhile decreasing the pressure on the adjacent ground.

    Assuming the structural deformations are uniform, the stresses are highest at the edges and lowest at the centerline.

    Stress distribution across plane above and below pipe

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Effect of soil settlement on flexible and rigid pipes

    Flexible pipe Rigid pipe

    Actual load on the pipe is less thanthe load of the central prism due tothe direction in which the shearingstresses

    Actual load on the pipe is more thanthe load of the central prism due tothe direction in which the shearingstresses

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Arching effect in underground conduits

    Rigid pipes

    Flexible pipes

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    What is the maximum load on a very rigid pipe in aditch excavated in sand? The pipe outside diameter(OD) is 0.45 m, the trench width is 1 m , the depth ofburial is 2.5 m, and the soil unit weight is 18.4 kN/m3.

    Example problem:

    Solution:

    Determine Cd

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Variation of Cdwith z/B for different values of Kµ

    For wet sand, K = 0.33 and µ =0.5 Kµ = 0.165

    z/B = H/B = 2.5/1 = 2.5

    For H/B = 2.5 & Kµ = 0.165

    Cd = 1.4

    W = CdγB2 = 1.4 x 18.4 x (1)2

    = 25.76 kN/m

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    In conjunction with positive projecting conduits, Marstondetermined the existence of a horizontal plane above the pipewhere the shearing forces are zero. This plane is called theplane of equal settlement.

    Above this plane, the interior and exterior prisms of soil settleequally. The condition where the plane of equal settlement isreal (it is located within the embankment) is called anincomplete projection or an incomplete ditch condition.

    If the plane of equal settlement is imaginary (the shear forcesextend all the way to the top of the embankment), it is called acomplete ditch or complete projection condition.

    Marston load theory (Embankment conditions)

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Positive projecting conduit

    In Case I, the ground at the sides of the pipe settlesmore than the top of the pipe.

    In Case II, the top of the pipe settles more than the soilat the sides of the pipe.

    Case I was called the projection condition by Marston and ischaracterized by a positive settlement ratio rsd

    The shear forces are downward and cause a greater load on theburied pipe for Case I.

    Case II is called the ditch condition and is characterized by anegative settlement ratio rsd . The shear forces are directedupward in this case and result in a reduced load on the pipe.

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Incomplete Projection condition

    Embankment conditions Not all pipes are installed in

    ditches (trenches); therefore, itis necessary to treat theproblem of pipes buried inembankments.

    An embankment is where thetop of the pipe above thenatural ground.

    This type of installation isdefined as positive projectingconduit.

    Case I

    Sf +dc < Sm +Sg

    H > He

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Case II is called the ditchcondition and is characterizedby a negative settlement ratiorsd . The shear forces aredirected upward in this caseand result in a reduced load onthe pipe.

    Ditch conditionCase II

    After Spangler and Handy(1982)

    Incomplete ditch condition

    H > He

    Sf +dc > Sm +Sg

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    sm = compression of soil at sides of pipe;sg = settlement of natural ground surface at sides of pipe;sf = settlement of foundation underneath pipe;dc = deflection of the top of pipe.

    Positive projecting conduit

    In conjunction with positive projecting conduits, Marstondetermined the existence of a horizontal plane above the pipewhere the shearing forces are zero. This plane is called the planeof equal settlement. Above this plane, the interior and exteriorprisms of soil settle equally.

    Where:

    Critical plane settlement = Sm (strainin side soil) +Sg (ground settlement).

    Settlement of the top of the pipe =Sf (conduit settlement) + dc (vertical

    pipe deflection).

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Positive projecting conduit

    The condition where the plane of equal settlement is real (it islocated within the embankment) is called an incompleteprojection or an incomplete ditch condition.

    If the plane of equal settlement is imaginary (the shear forcesextend all the way to the top of the embankment), it is called acomplete ditch or complete projection condition.

    Marston’s load equation for positive projecting(embankment) conduits is given by:

    For complete condition

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Positive projecting conduit

    The minus signs are for the complete ditch, and the plussigns are for the complete projection condition.For incomplete condition:

    where the minus signs are for the incomplete ditch andthe plus signs are for the incomplete projection condition.And He is the height of the plane of equal settlement.

    At H = He, the incomplete case becomes complete case.

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Cc is a function of the ratio of height of cover to pipediameter (H/Bc), the product of the settlement ratio (rsd) andprojection ratio (p), Rankine’s constant (K), and thecoefficient of friction (µ).

    Positive projecting conduit

    The value of the product Kµ is generally taken as 0.19 for the projection condition and 0.13 for the ditch condition.

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Complete projection condition: The top of the conduit settles lessthan the critical plane and the height of the embankment is lessthan the theoretical height of equal settlement.

    Incomplete projection condition: The top of the conduit settlesless than the critical plane and the height of the embankment isgreater than the height of equal settlement.

    Complete ditch condition: The top of the conduit settles morethan the critical plane and the height of the embankment is lessthan the height of equal settlement.

    Incomplete ditch condition: The top of the conduit settles morethan the critical plane and the height of the embankment is morethan the height of equal settlement.

    Four conditions classified according to Spangler

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Complete projection condition

    Incompleteprojectioncondition

    H < He

    Sf +dc < Sm +Sg Sf +dc <

    Sm +Sg

    H > He

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Diagram for coefficient Cc for positive projecting conduits

    After Spangler and Handy(1982)

    rsd p = 0, Cc = H/Bc

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    The settlement ratio rsd is difficult, if not impossible, todetermine even empirically from direct observations.

    Note that when rsd p = 0, Cc = H/Bc and Wc =γ HBc . This isthe prism load (i.e., the weight of the prism of soil over thetop of the pipe).

    When rsd = 0, the plane at the top of the pipe called thecritical plane settles the same amount as the top of theconduit

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Design values of settlement ratio After Spangler and Handy(1982)

    When a pipe is installed in a narrow,shallow trench with the top of the pipelevel with the adjacent naturalground, the projection ratio p is zero.

    The distance from the top of the structure to thenatural ground surface is represented by pBc

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Load transfer pattern in flexible and rigid pipesAs the loading increases, the vertical diameterdecreases and the horizontal diameter increases.

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Typical failure modes for flexible pipes

    After Spangler and Handy(1982)

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    For flexible pipes, Moser proposed the following formula(American Water Works Association manual) to calculateload on pipes:

    h

    W

    PipeD

    Trench with a flexible pipe

    W = γ Bd h

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Importance of proper bedding on buried pipe

    P1

    Width of trench

    Undisturbed soil

    Load on the pipe

    P1

    Width of trench

    Undisturbed soil

    Load on the pipe

    Proper beddingImproper bedding

    The area of contact between thepipe and soil is small so stress ismore and may damage the pipe.

    The area of contact between thepipe and soil is large so stress isless.

    (After NYSDOT Geotechnical design manual)

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Soil bed

    Cracks

    Soil bed

    Load is concentrated and creating cracks

    Load is uniformly distributed

    Importance of proper bedding on buried pipe

    (After NYSDOT Geotechnical design manual)

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    Types of load on pipe lines

    1. External Loads

    A. Dead load or overburden pressureB. Live LoadsC. Seismic Loads

    2. Internal Loads

    A. Internal Pressure and VacuumB. Pipe and associated contents

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    1.A. Dead load or overburden pressure

    This is the pressure due to weight of the soil and water above the pipe. The pressure increases with depth of the pipe, i.e. dead load for (P1

  • Prof. B V S Viswanadham, Department of Civil Engineering, IIT Bombay

    1.B. Live load

    This is the static or dynamic load acting on theground above the pipe and transmitted to thepipe through the soil.

    Vehicles, trains, aircrafts etc are the source of suchloads.

    Magnitude of such loads get reduced as thedepth of embedment is increased.

    Slide Number 1Slide Number 2Slide Number 3Slide Number 4Slide Number 5Slide Number 6Slide Number 7Slide Number 8Slide Number 9Slide Number 10Slide Number 11Slide Number 12Slide Number 13Slide Number 14Slide Number 15Slide Number 16Slide Number 17Slide Number 18Slide Number 19Slide Number 20Slide Number 21Slide Number 22Slide Number 23Slide Number 24Slide Number 25Slide Number 26Slide Number 27Slide Number 28Slide Number 29Slide Number 30Slide Number 31Slide Number 32Slide Number 33Slide Number 34Slide Number 35Slide Number 36Slide Number 37Slide Number 38Slide Number 39Slide Number 40