3g scenareo

97
For internal use only 2 © Nokia Siemens Networks / 3G Node B solutions for UP (West)

Upload: rakesh012

Post on 26-Nov-2014

127 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: 3G Scenareo

For internal use only2 © Nokia Siemens Networks /

3G Node B solutions for UP (West)

Page 2: 3G Scenareo

For internal use only3 © Nokia Siemens Networks /

Assumptions

• All Sites of UP (West) handed over to NSN are RFAI.•All Sites will be provided with additional Poles for 3G antenna.

Page 3: 3G Scenareo

For internal use only4 © Nokia Siemens Networks /

RF Scenarios

Scenario 1 – OD Distributed BBU + RRU (Node B inside the Existing Outdoor Transmission Rack/ OD Flexi BTS & RF Module on Pole)

Scenario 2 – OD Classic On RTT (System Module & RF Module on Pole)

Scenario 3 – ID Distributed (System Module Inside Existing Transmission rack / Flexi BTS & RF Module on Pole)

Scenario 4- OD Classic On Pole (System Module & RF Module on Pole)

Scenario 5 – ID Distributed with Antenna Swap (System Module inside the existing Transmission rack & RF Module on Pole

Scenario 6 – ID Classic (System & RF Module Inside the Shelter in the existing Transmission Rack)

Scenario 7 – ID Distributed (System Module inside the shelter Transmission rack / Flexi BTS & Single RF Module on Pole)

Page 4: 3G Scenareo

For internal use only5 © Nokia Siemens Networks /

Scenario 1- System Module inside the Out door Transmission Rack & RF Module on Pole

Proposed 3G System Module inside the Outdoor Transmission Rack & RF Module on Pole.New 3G antenna needs to be added.

Page 5: 3G Scenareo

For internal use only6 © Nokia Siemens Networks /

Scenario 1 – OD Distributed BBU + RRU (Node B inside the Existing Outdoor Transmission Rack/ OD Flexi BTS & RF Module on Pole)

BB1PP

Existing 2G Outdoor

Proposed 3 G FSMD

Sect 1 Sect 2

Sect 3

Additional 3G Antenna

Existing 2G Antenna

FRGP

Note the Jumper cable can be of Max. 7 mtrs. length

Jumper Cable

Feeder Cable

Optical Cable

Power Cable

Outdoor Trx Rack

Jumper Cable towards RF Module

Less than 25 kg weight for the RF module to mounted on Pole for 3 SectorsExtreme Flexible NodeB deploymentBetter coverageNo MHA No long Feeders

OVP

OVP

Page 6: 3G Scenareo

For internal use only7 © Nokia Siemens Networks /

Scenario 1 – OD Distributed BBU + RRU (Node B inside the Existing Outdoor Transmission Rack/ OD Flexi BTS & RF Module on Pole)

Sr. No. Activity Duration

1 Material Delivery-- 3G Antenna & Node B Day 1

2 Installation Of System Module inside the Outdoor Transmission Rack and RF Module On Pole. 2 Hours - Day 2

3 Routing of Power Cable to System Module 1 Hour - Day 2

4 Routing of Power and Fiber Cable from System Module to RF Module 1 Hour - Day 2

5 Ethernet Cable Routing From DDF to System Module 1 Hour - Day 2

6 Installation of 3G Antenna On Pole and feeder Routing for Two sectors 2 Hours - Day 2

7 Connecting the Jumpers from RF Module to Antenna 0.5 Hours -Day 2

Page 7: 3G Scenareo

For internal use only8 © Nokia Siemens Networks /

Commissioning, Integration and Acceptance testing of Node B

Sr. No. Activity Duration

1 Powering The Node B 0.5 Hours - Day 3

2 Commissioning of Node B 0.5 Hours - Day 3

3 Integrating of Node B with RNC 1 Hour - Day 3

4 Acceptance Testing 3 Hours - Day 3

Page 8: 3G Scenareo

For internal use only9 © Nokia Siemens Networks /

Reverse Logistics

Sr. No. Activity Duration

1 Dismantling of Unused Antenna 2 Hours - Day 3

2 Packing of Extra Material at site 2 Hours - Day 3

3 Transportation of packed unused material to warehouse 2 Hours - Day 3

Page 9: 3G Scenareo

For internal use only10 © Nokia Siemens Networks /

Scenario 2- OD Classic On RTT (System Module & RF Module on Pole)

Proposed 3G System Module & RF Module on Pole.New 3G antenna needs to be added.

Page 10: 3G Scenareo

For internal use only11 © Nokia Siemens Networks /

Scenario 2 – OD Classic On RTT (System Module & RF Module on Pole)

BB1 BB2PP

Door

Existing 2G BTS

Sect 1 Sect 2 Sect 3

Additional 3G Antenna

Existing 2G Antenna

Proposed 3G FSMD & FRGP

RTT

DDF

Note the Jumper cable can be of Max. 7 mtrs. length

Jumper Cable

Power CableE1/Ethernet Cable

Less than 25 kg weight for the RF module to mounted on Pole for 3 SectorsExtreme Flexible NodeB deploymentBetter coverageNo MHA No long Feeders Zero Footprint

Page 11: 3G Scenareo

For internal use only12 © Nokia Siemens Networks /

Scenario 2 – OD Classic On RTT (System Module & RF Module on Pole)

Sr. No. Activity Duration

1 Material Delivery-- 3G Antenna & Node B Day 1

2 Installation Of System Module and RF Module On RTT. 2 Hours - Day 2

3 Routing of Power Cable to System Module 1 Hour - Day 2

4 Routing of Power and Fiber Cable from System Module to RF Module 1 Hour - Day 2

5 Ethernet Cable Routing From DDF to System Module 1 Hour - Day 2

6 Installation of 3G Antenna On Pole 2 Hours - Day 2

7 Connecting the Jumpers from RF Module to Antenna 0.5 Hours -Day 2

Page 12: 3G Scenareo

For internal use only13 © Nokia Siemens Networks /

Commissioning, Integration and Acceptance testing of Node B

Sr. No. Activity Duration

1 Powering The Node B 0.5 Hours - Day 3

2 Commissioning of Node B 0.5 Hours - Day 3

3 Integrating of Node B with RNC 1 Hour - Day 3

4 Acceptance Testing 3 Hours - Day 3

Page 13: 3G Scenareo

For internal use only14 © Nokia Siemens Networks /

Reverse Logistics

Sr. No. Activity Duration

1 Dismantling of Unused Antenna 2 Hours - Day 3

2 Packing of Extra Material at site 2 Hours - Day 3

3 Transportation of packed unused material to warehouse 2 Hours - Day 3

Page 14: 3G Scenareo

For internal use only15 © Nokia Siemens Networks /

Scenario 3 – ID Distributed (System Module Inside Existing Transmission rack / Flexi BTS & RF Module on Pole)

Proposed 3G System Module Inside Existing Transmission rack & RF Module on Pole.New 3G antenna needs to be added.

Page 15: 3G Scenareo

For internal use only16 © Nokia Siemens Networks /

BB1 BB2PP

Door

Existing 2G Indoor BTS

Proposed 3G FSIA

Sect 1 Sect 2 Sect 3

Additional 3G Antenna

Existing 2G Antenna

FRGP

Scenario 3 – ID Distributed (System Module Inside Existing Transmission rack / Flexi BTS & RF Module on Pole)

Existing TX Rack

RTT/GBT

Note the Jumper cable can be of Max. 7 mtrs. length

No additional footprint inside the shelter.Use of existing 19” rack. Triple RF Unit on Pole and System Module Indoor,• No additional feeder• Better coverage

OVP

Page 16: 3G Scenareo

For internal use only17 © Nokia Siemens Networks /

Scenario 3 – ID Distributed (System Module Inside Existing Transmission rack / Flexi BTS & RF Module on Pole)

Sr. No. Activity Duration

1 Material Delivery-- 3G Antenna & Node B Day 1

2 Installation Of System Module Inside Existing Transmission Rack and RF Module On Pole. 2 Hours - Day 2

3 Routing of Power Cable to System Module 1 Hour - Day 2

4 Routing of Power and Fiber Cable from System Module to RF Module 1 Hour - Day 2

5 Ethernet Cable Routing From DDF to System Module 1 Hour - Day 2

6 Installation of 3G Antenna On Pole 2 Hours - Day 2

7 Connecting the Jumpers from RF Module to Antenna 0.5 Hours -Day 2

Page 17: 3G Scenareo

For internal use only18 © Nokia Siemens Networks /

Commissioning, Integration and Acceptance testing of Node B

Sr. No. Activity Duration

1 Powering The Node B 0.5 Hours - Day 3

2 Commissioning of Node B 0.5 Hours - Day 3

3 Integrating of Node B with RNC 1 Hour - Day 3

4 Acceptance Testing 3 Hours - Day 3

Page 18: 3G Scenareo

For internal use only19 © Nokia Siemens Networks /

Reverse Logistics

Sr. No. Activity Duration

1 Dismantling of Unused Antenna 2 Hours - Day 3

2 Packing of Extra Material at site 2 Hours - Day 3

3 Transportation of packed unused material to warehouse 2 Hours - Day 3

Page 19: 3G Scenareo

For internal use only20 © Nokia Siemens Networks /

Scenario 4- OD Classic On Pole (System Module & RF Module on Pole)

Proposed 3G System Module & RF Module on Pole where Existing 3G is Outdoor.New 3G antenna needs to be added.

Page 20: 3G Scenareo

For internal use only21 © Nokia Siemens Networks /

Scenario 4- OD Classic On Pole (System Module & RF Module on Pole)

Existing 2G Outdoor

Sect 1 Sect 2 Sect 3

Additional 3G Antenna

Existing 2G Antenna

BB1PP

Proposed 3G FSMD & FRGP

Note the Jumper cable can be of Max. 7 mtrs. length

DDF

Jumper Cable

Feeder Cable

Optical Cable

Power Cable

E1/Ethernet Cable

Less than 50 Kg weight for the entire Node B!Extreme Flexible Node B Deployment Zero Foot Print

Page 21: 3G Scenareo

For internal use only22 © Nokia Siemens Networks /

Scenario 4- OD Classic On Pole (System Module & RF Module on Pole)

Sr. No. Activity Duration

1 Material Delivery-- 3G Antenna & Node B Day 1

2 Installation Of System Module and RF Module On Pole. 2 Hours - Day 2

3 Routing of Power Cable to System Module 1 Hour - Day 2

4 Routing of Power and Fiber Cable from System Module to RF Module 1 Hour - Day 2

5 Ethernet Cable Routing From DDF to System Module 1 Hour - Day 2

6 Installation of 3G Antenna On Pole 2 Hours - Day 2

7 Connecting the Jumpers from RF Module to Antenna 0.5 Hours -Day 2

Page 22: 3G Scenareo

For internal use only23 © Nokia Siemens Networks /

Commissioning, Integration and Acceptance testing of Node B

Sr. No. Activity Duration

1 Powering The Node B 0.5 Hours - Day 3

2 Commissioning of Node B 0.5 Hours - Day 3

3 Integrating of Node B with RNC 1 Hour - Day 3

4 Acceptance Testing 3 Hours - Day 3

Page 23: 3G Scenareo

For internal use only24 © Nokia Siemens Networks /

Reverse Logistics

Sr. No. Activity Duration

1 Dismantling of Unused Antenna 2 Hours - Day 3

2 Packing of Extra Material at site 2 Hours - Day 3

3 Transportation of packed unused material to warehouse 2 Hours - Day 3

Page 24: 3G Scenareo

For internal use only25 © Nokia Siemens Networks /

Scenario 5 – ID Distributed with Antenna Swap (System Module inside the existing Transmission rack & RF Module on Pole

Proposed 3G System Module inside the shelter Tx rack.RF Module would be installed on the Pole.2G Antenna needs to be swapped with Dual or Tri-band antenna.

Page 25: 3G Scenareo

For internal use only26 © Nokia Siemens Networks /

Scenario 5 – ID Distributed with Antenna Swap (System Module inside the existing Transmission rack & RF Module on Pole

BB1 BB2PP

Door

Existing 2G Indoor

Proposed 3G FSIA

Sect 1 Sect 2 Sect 3

Swap of 2G antenna with

Dual Band Antenna

Existing 2G Antenna

FRGP

Day Activity

Night Activity

Existing TX Rack

No additional footprint inside the shelter.Use of existing 19” rack. Triple RF and System Module Inside Tx Rack,• No tower loading• Better coverage

OVP

Page 26: 3G Scenareo

For internal use only27 © Nokia Siemens Networks /

Scenario 5 – ID Distributed with Antenna Swap (System Module inside the existing Transmission rack & RF Module on Pole

Sr. No. Activity Duration

1 Material Delivery-- 3G Antenna & Node B Day 1

2 Installation Of System Module inside the shelter Tx rack and RF Module On Pole. 2 Hours - Day 2

3 Routing of Power Cable to System Module 1 Hour - Day 2

4 Routing of Power and Fiber Cable from System Module to RF Module 1 Hour - Day 2

5 Ethernet Cable Routing From DDF to System Module 1 Hour - Day 2

6 Swapping of 2G Antenna & Installation of 3G – Night Activity 3 Hours - Day 2

7 Connecting the Jumpers from RF Module to Antenna 0.5 Hours -Day 2

Page 27: 3G Scenareo

For internal use only28 © Nokia Siemens Networks /

Commissioning, Integration and Acceptance testing of Node B

Sr. No. Activity Duration

1 Powering The Node B 0.5 Hours - Day 3

2 Commissioning of Node B 0.5 Hours - Day 3

3 Integrating of Node B with RNC 1 Hour - Day 3

4 Acceptance Testing 3 Hours - Day 3

Page 28: 3G Scenareo

For internal use only29 © Nokia Siemens Networks /

Reverse Logistics

Sr. No. Activity Duration

1 Dismantling of Unused Antenna 2 Hours - Day 3

2 Packing of Extra Material at site 2 Hours - Day 3

3 Transportation of packed unused material to warehouse 2 Hours - Day 3

Page 29: 3G Scenareo

For internal use only30 © Nokia Siemens Networks /

Scenario 6 – ID Classic (System & RF Module Inside the Shelter in the existing Transmission Rack)

Proposed 3G System & RF Module inside the Existing BTS Room in the existing Transmission Rack.New 3G antenna needs to be added.

Page 30: 3G Scenareo

For internal use only31 © Nokia Siemens Networks /

Scenario 6 – ID Classic (System & RF Module Inside the Shelter in the existing Transmission Rack)

BB1 BB2PP

Door

Existing Indoor BTS

Proposed 3G FSIA & FRGP Modules inside

Existing Tx Rack

Sect 1 Sect 2 Sect 3

Additional 3G Antenna

Existing 2G Antenna

Existing Tx Rack

No additional footprint inside the shelter.Use of existing 19” rack. Triple RF and System Module Inside Tx Rack,• No tower loading• Better coverage

Page 31: 3G Scenareo

For internal use only32 © Nokia Siemens Networks /

Scenario 6 – ID Classic (System & RF Module Inside the Shelter in the existing Transmission Rack)

Sr. No. Activity Duration

1 Material Delivery-- 3G Antenna & Node B Day 1

2 Installation Of System & RF Module in the Existing Transmission rack beside existing BTS. 2 Hours - Day 2

3 Routing of Feeder Cable 2 Hour - Day 2

4 Routing of Power and Fiber Cable from System Module to RF Module 1 Hour - Day 2

5 Ethernet Cable Routing From DDF to System Module 1 Hour - Day 2

6 Installation of 3G Antenna On Pole 2 Hours - Day 2

7 Connecting the Jumpers from RF Module to Antenna 0.5 Hours -Day 2

Page 32: 3G Scenareo

For internal use only33 © Nokia Siemens Networks /

Commissioning, Integration and Acceptance testing of Node B

Sr. No. Activity Duration

1 Powering The Node B 0.5 Hours - Day 3

2 Commissioning of Node B 0.5 Hours - Day 3

3 Integrating of Node B with RNC 1 Hour - Day 3

4 Acceptance Testing 3 Hours - Day 3

Page 33: 3G Scenareo

For internal use only34 © Nokia Siemens Networks /

Reverse Logistics

Sr. No. Activity Duration

1 Dismantling of Unused Antenna 2 Hours - Day 3

2 Packing of Extra Material at site 2 Hours - Day 3

3 Transportation of packed unused material to warehouse 2 Hours - Day 3

Page 34: 3G Scenareo

For internal use only35 © Nokia Siemens Networks /

Scenario 7 – ID Distributed (System Module inside the shelter Transmission rack / Flexi BTS & Single RF Module on Pole)

Proposed 3G System module inside the Transmission rack & Single RF Module on Pole.New 3G antenna needs to be added.

Page 35: 3G Scenareo

For internal use only36 © Nokia Siemens Networks

Scenario 7 – ID Distributed (System Module inside the shelter Transmission rack / Flexi BTS & Single RF Module on Pole)

BB1 BB2PP

Door

Existing 2G Indoor

Proposed 3G FSIA

Sect 1 Sect 2

Sect 3

Additional 3G Antenna

Existing 2G Antenna

FRGG

Jumper Cable

Feeder Cable

Optical Cable

Power Cable

FRGG

FRGG

Note the Jumper cable can be of Max. 7 mtrs. length

Existing Tx rack

Page 36: 3G Scenareo

For internal use only37 © Nokia Siemens Networks /

Scenario 7 – ID Distributed (System Module inside the shelter Transmission rack / Flexi BTS & Single RF Module on Pole)

Sr. No. Activity Duration

1 Material Delivery-- 3G Antenna & Node B Day 1

2Installation Of System Module inside the shelter Transmission rack and Single RF Modules On sector Poles. 2 Hours - Day 2

3 Routing of Power Cable to System Module 1 Hour - Day 2

4 Routing of Power and Fiber Cables from System Module to RF Modules 1 Hour - Day 2

5 Ethernet Cable Routing From DDF to System Module 1 Hour - Day 2

6 Installation of 3G Antenna On Pole. 2 Hours - Day 2

7 Connecting the Jumpers from RF Module to Antenna 0.5 Hours -Day 2

Page 37: 3G Scenareo

For internal use only38 © Nokia Siemens Networks /

Commissioning, Integration and Acceptance testing of Node B

Sr. No. Activity Duration

1 Powering The Node B 0.5 Hours - Day 3

2 Commissioning of Node B 0.5 Hours - Day 3

3 Integrating of Node B with RNC 1 Hour - Day 3

4 Acceptance Testing 3 Hours - Day 3

Page 38: 3G Scenareo

For internal use only39 © Nokia Siemens Networks /

Reverse Logistics

Sr. No. Activity Duration

1 Dismantling of Unused Antenna 2 Hours - Day 3

2 Packing of Extra Material at site 2 Hours - Day 3

3 Transportation of packed unused material to warehouse 2 Hours - Day 3

Page 39: 3G Scenareo

For internal use only40 © Nokia Siemens Networks

MW Scenario Idea UP-West

Page 40: 3G Scenareo

For internal use only41 © Nokia Siemens Networks

MW Scenario Idea UP-West

Scenario 1 : 2 New SDH Hybrid+ 1 New PDH Hybrid

Scenario 2 : 2 New SDH Hybrid, 2 PDH (1 New Hopper+1 Existing Hopper)

Scenario 3 : 2 New SDH Hybrid Links

Scenario 4 : 2 New SDH Hybrid, 2 New PDH Hopper

Scenario 5 : 2 New SDH Hybrid, 2 PDH (1 New Hopper+1 Existing Hopper)

Scenario 6 : Existing Single PDH Hopper

Scenario 7 : 2 PDH (1 New Hybrid+1 Existing Hopper)

Scenario 8 : 3 New Flexi Hybrid + 1 New PDH Hopper

Scenario 9 : 2 New SDH Hybrid, 1 New PDH Hopper

Scenario 10: 2 New SDH IP-10, 2 New PDH (1 Hopper + 1 Hybrid)

Scenario 11: 1 New PDH Hybrid

Page 41: 3G Scenareo

For internal use only42 © Nokia Siemens Networks

Scenario-1

Scenario-2

Scenario-3Scenario-4

Scenario-5

Scenario-6

Scenario-7

Connectivity Cluster-1

Page 42: 3G Scenareo

For internal use only43 © Nokia Siemens Networks

Scenario-8

Scenario-9

Scenario-11

Connectivity Cluster-2

Page 43: 3G Scenareo

For internal use only44 © Nokia Siemens Networks

Scenario-10

Connectivity Cluster-3

Page 44: 3G Scenareo

For internal use only45 © Nokia Siemens Networks

2GBTS

E1/T1

FlexihybridFlexihybrid

Flexihybrid (2+0)Fiber

MUX

NodeB

FTIB

FLEXIHYBRID 1+0

Flexihybrid

Similar scenario would be applicable for Flexi 2G BTS with FIPA Card

Scenario 1

SADARBZR(POP Location)

• 2 New SDH Hybrid+ 1 New PDH Hybrid

AI_MOHANPURAArjun

A_BALU GANJ

Page 45: 3G Scenareo

For internal use only46 © Nokia Siemens Networks /

Scenario – 1 NEW SDH

Sr. No. Activity Duration Outage/ Non Outage

1 ODU & Antenna Installation. 2 Hours - Day 2Non Outage

2 IF Cable Laying and termination 1 Hour - Day 2Non Outage

3 Hybrid IDU Installation in 19” Rack. 0.25 Hour -Day 2Non Outage

4 Power Cable Laying & termination. 0.25 Hour -Day 2Non Outage

5 DDF Block Installation, E1 & Ethernet Termination. 0.25 Hour -Day 2Non Outage

6 Commissioning Near End and Far End 0.25 Hour -Day 2Non Outage

7 Link Alignment 2 Hours - Day 2Non Outage

8 E1 Patching and testing 0.5 Hour - Day 2Non Outage

9 Acceptance Testing 2 Hours - Day 2Non Outage

Page 46: 3G Scenareo

For internal use only47 © Nokia Siemens Networks

2GBTS

RRI

FlexihybridFlexihybrid

FIU19

Flexihybrid (2+0)Fiber

MUX

NodeB

FTIB

FLEXIHYBRID 1+0

Flexihybrid

Similar scenario would be applicable for Flexi 2G BTS with FIFA Card

Scenario 1.1

SADARBZR(POP Location)

2 New SDH Hybrid+ 1 New PDH Hybrid

AI_MOHANPURAArjun

A_BALU GANJ

Page 47: 3G Scenareo

For internal use only48 © Nokia Siemens Networks /

Scenario – 1.1 NEW SDH/PDH

Sr. No. Activity Duration Outage/ Non Outage

1 ODU & Antenna Installation. 2 Hours - Day 2Non Outage

2 IF Cable Laying and termination 1 Hour - Day 2Non Outage

3 Hybrid IDU Installation in 19” Rack. 0.25 Hour -Day 2Non Outage

4 Power Cable Laying & termination. 0.25 Hour -Day 2Non Outage

5 DDF Block Installation, E1 & Ethernet Termination. 0.25 Hour -Day 2Non Outage

6 Commissioning Near End and Far End 0.25 Hour -Day 2Non Outage

7 Link Alignment 2 Hours - Day 2Non Outage

8 E1 Patching and testing 0.5 Hour - Day 2Non Outage

9 Acceptance Testing 2 Hours - Day 2Non Outage

Page 48: 3G Scenareo

For internal use only49 © Nokia Siemens Networks

2GBTSFIPA

FlexihybridFlexihybrid

FIU19

Flexihybrid (2+0)

Scenario 2

AI_MOHANPURA (2G Site)

2 New SDH Hybrid, 2 PDH (1 New Hopper+1 Existing Hopper)

PDH Hopper

PDH Hopper

SADARBZR SHAHGANJ

BaluIDGAH

Similar scenario would be applicable for Ultra 2G BTS with E1/T1 Card

Page 49: 3G Scenareo

For internal use only50 © Nokia Siemens Networks /

Scenario – 2 Existing PDH with FIU & EPIU

Sr. No. Activity Duration Outage/ Non Outage

1 New FIU with EPIU Installation in 19” Rack. 0.5 Hours - Day 2Non Outage

2 Power Cable Laying & termination. 0.5 Hours - Day 2Non Outage

3 DDF Block Installation, E1 & Ethernet Termination. 0.5 Hours - Day 2Non Outage

4 Configuration of FIU 0.5 Hours - Day 2Outage

5 E1 Testing 0.5 Hours - Day 2Outage

6 Traffic Shifting 0.5 Hours - Day 2Outage

8 Acceptance Testing 1 Hour - Day 2Outage

Page 50: 3G Scenareo

For internal use only51 © Nokia Siemens Networks

2GBTSFIFA

FlexihybridFlexihybrid

FIU19 + FB3/FB4

Flexihybrid (2+0)

Similar scenario would be applicable for Ultra 2G BTS with RRI Card

Scenario 2.1

AI_MOHANPURA (2G Site)

2 New SDH Hybrid, 2 PDH (1 New Hopper+1 Existing Hopper)

PDH Hopper

SADARBZR SHAHGANJ

Balu

PDH Hopper

IDGAH

Page 51: 3G Scenareo

For internal use only52 © Nokia Siemens Networks /

Scenario – 2.1 Existing PDH with FIU & EPIU + FB3/FB4

Sr. No. Activity Duration Outage/ Non Outage

1 New FIU with EPIU & FB3/FB4 Installation in 19” Rack. 0.5 Hours - Day 2Non Outage

2 Power Cable Laying & termination. 0.5 Hours - Day 2Non Outage

3 DDF Block Installation, E1 & Ethernet Termination. 0.5 Hours - Day 2Non Outage

4 Configuration of FIU 0.5 Hours - Day 2Outage

5 E1 Testing 0.5 Hours - Day 2Outage

6 Traffic Shifting 0.5 Hours - Day 2Outage

8 Acceptance Testing 1 Hour - Day 2Outage

Page 52: 3G Scenareo

For internal use only53 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid

Flexihybrid (2+0)

Scenario 3

SHAHGANJ

2 New SDH Hybrid Links

NodeB

FTIB

ManasAI_MOHANPURA

E1/T1

Similar scenario would be applicable for Flexi 2G BTS with FIPA Card

Page 53: 3G Scenareo

For internal use only54 © Nokia Siemens Networks /

Scenario – 3 NEW SDH

Sr. No. Activity Duration Outage/ Non Outage

1 ODU & Antenna Installation. 2 Hours - Day 2Non Outage

2 IF Cable Laying and termination 1 Hour - Day 2Non Outage

3 Hybrid IDU Installation in 19” Rack. 0.25 Hour -Day 2Non Outage

4 Power Cable Laying & termination. 0.25 Hour -Day 2Non Outage

5 DDF Block Installation, E1 & Ethernet Termination. 0.25 Hour -Day 2Non Outage

6 Commissioning Near End and Far End 0.25 Hour -Day 2Non Outage

7 Link Alignment 2 Hours - Day 2Non Outage

8 E1 Patching and testing 0.5 Hour - Day 2Non Outage

9 Acceptance Testing 2 Hours - Day 2Non Outage

Page 54: 3G Scenareo

For internal use only55 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid

Flexihybrid (2+0)

Scenario 3.1

SHAHGANJ

2 New SDH Hybrid Links

NodeB

FTIB

ManasAI_MOHANPURA

FIU19

RRI

Similar scenario would be applicable for Flexi 2G BTS with FIFA Card

Page 55: 3G Scenareo

For internal use only56 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid

Flexihybrid (2+0)

Scenario 4

Manas2 New SDH Hybrid, 2 New PDH Hopper

NodeB

FTIB

FIU19

PDH Hopper

PDH Hopper

T_Sivaji

T_Anjani puram

SHAHGANJArjunE1/T1

Similar scenario would be applicable for Flexi 2G BTS with FIPA Card

Page 56: 3G Scenareo

For internal use only57 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid

Flexihybrid (2+0)

Scenario 4.1

Manas2 New SDH Hybrid, 2 New PDH Hopper

NodeB

FTIB

FIU19

PDH Hopper

T_Sivaji

T_Anjani puram

SHAHGANJArjun

FIU19

PDH Hopper

RRI

Similar scenario would be applicable for Flexi 2G BTS with FIFA Card

Page 57: 3G Scenareo

For internal use only58 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid

FIU19

Flexihybrid (2+0)

Scenario 5

Arjun 2 New SDH Hybrid, 2 PDH (1 New Hopper+1 Existing Hopper)

PDH Hopper

PDH Hopper

NodeB

FTIB

Manas SADARBZR

A_Kedar Nagar

A_Arjun Nagar

E1/T1

Similar scenario would be applicable for Flexi 2G BTS with FIPA Card

Page 58: 3G Scenareo

For internal use only59 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid

FIU19

Flexihybrid (2+0)

PDH Hopper

FIU19

PDH Hopper

Scenario 5.1

Arjun 2 New SDH Hybrid, 2 PDH (1 New Hopper+1 Existing Hopper)

NodeB

FTIB

Manas SADARBZR

A_Kedar Nagar A_Arjun Nagar

RRI

Similar scenario would be applicable for Flexi 2G BTS with FIFA Card

Page 59: 3G Scenareo

For internal use only60 © Nokia Siemens Networks

2GBTSFIFA

PDH Hopper

Scenario 6

A_Arjun Nagar

Existing Single PDH Hopper

NodeB

FTFB

FTFB

Arjun

Similar scenario would be applicable for Ultra 2G BTS with RRI Card

Page 60: 3G Scenareo

For internal use only61 © Nokia Siemens Networks

2GBTSFIPA

PDH Hopper

Scenario 6.1

A_Arjun Nagar

Existing Single PDH Hopper

NodeB

FTIB

FIU19

Arjun

Similar scenario would be applicable for Ultra 2G BTS with E1/T1 Card

Page 61: 3G Scenareo

For internal use only62 © Nokia Siemens Networks

Scenario 7

A_BALU GANJ2 PDH (1 New Hybrid+1 Existing Hopper)

2GBTSFIPA

FlexihybridPDH Hopper

FIU19

Flexihybrid (1+0)

NodeB

FTIB

SADARBZRA_Adresh Nagar

Similar scenario would be applicable for Ultra 2G BTS with E1/T1 Card

Page 62: 3G Scenareo

For internal use only63 © Nokia Siemens Networks

Scenario 7.1

A_BALU GANJ2 PDH (1 New Hybrid+1 Existing Hopper)

2GBTSFIFA

FlexihybridPDH Hopper

FIU19

Flexihybrid (1+0)

NodeB

FTIB

SADARBZRA_Adresh Nagar

Similar scenario would be applicable for Ultra 2G BTS with RRI Card

Page 63: 3G Scenareo

For internal use only64 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid

FIU19

Flexihybrid (2+0)

PDH Hopper

Fiber

MUX

NodeB

FTIB

FLEXIHYBRID 1+0

Flexihybrid

Scenario 8

Sanjay Complex-BKamlangr Entry

Nehru

Akriti

SANJAYCPLX(POP Location)

3 New Flexi Hybrid + 1 New PDH Hopper

E1/T1

Similar scenario would be applicable for Flexi 2G BTS with FIPA Card

Page 64: 3G Scenareo

For internal use only65 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid

FIU19

Flexihybrid (2+0)

PDH Hopper

Fiber

MUX

NodeB

FTIB

FLEXIHYBRID 1+0

Flexihybrid

Scenario 8.1

Sanjay Complex-BKamlangr Entry

Nehru

Akriti

SANJAYCPLX(POP Location)

3 New Flexi Hybrid + 1 New PDH Hopper

RRI

Similar scenario would be applicable for Flexi 2G BTS with FIFA Card

Page 65: 3G Scenareo

For internal use only66 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid

FIU19

Flexihybrid (2+0)

Scenario 9

WHITEHOUSE

2 New SDH Hybrid, 1 New PDH Hopper

PDH Hopper

NodeB

FTIB

AkritiKhandari

Khandari 1

E1/T1

Similar scenario would be applicable for Flexi 2G BTS with FIPA Card

Page 66: 3G Scenareo

For internal use only67 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid

FIU19

Flexihybrid (2+0)

Scenario 9.1

WHITEHOUSE

2 New SDH Hybrid, 1 New PDH Hopper

PDH Hopper

NodeB

FTIB

AkritiKhandari

Khandari 1

RRI

Similar scenario would be applicable for Flexi 2G BTS with FIFA Card

Page 67: 3G Scenareo

For internal use only68 © Nokia Siemens Networks

Scenario 10

2GBTSIP-10

IP-10

FIU19

CERAGON-IDU

PDH Hopper

Fiber

MUX

NodeB

FTIB

FLEXIHYBRID 1+0

Flexihybrid

ECI-BG-20 Mux

Delhi Gate

RAJA_KI_MANDIA_Loha mandi

A_TRANSPORT NGR SEC-4

Hariparvat

2 New SDH IP-10, 2 New PDH (1 Hopper + 1 Hybrid)

E1/T1

Similar scenario would be applicable for Flexi 2G BTS with FIPA Card

Page 68: 3G Scenareo

For internal use only69 © Nokia Siemens Networks

2GBTS

FIU19

CERAGON-IDU

PDH

Fiber

MUX

NodeB

FTIB

FLEXIHYBRID 1+0

Flexihybrid

ECI-BG-20 Mux

IP-10IP-10

PDH Hopper

Flexihybrid

RAJA_KI_MANDIA_Loha mandi

A_TRANSPORT NGR SEC-4

Hariparvat

Scenario 10.1

Delhi Gate

2 New SDH IP-10, 2 New PDH (1 Hopper + 1 Hybrid)

RRI

Similar scenario would be applicable for Flexi 2G BTS with FIFA Card

Page 69: 3G Scenareo

For internal use only70 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid (1+0)

Scenario 11

1 New PDH Hybrid

NodeB

FTIB

Gandhi

Kamlangr EntryE1/T1

Similar scenario would be applicable for Flexi 2G BTS with FIPA Card

Page 70: 3G Scenareo

For internal use only71 © Nokia Siemens Networks

2GBTSFlexihybrid

Flexihybrid (1+0)

Scenario 11.1

1 New PDH Hybrid

NodeB

FTIB

Kamlangr Entry

Gandhi

FIU19

RRI

Similar scenario would be applicable for Flexi 2G BTS with FIFA Card

Page 71: 3G Scenareo

For internal use only72 © Nokia Siemens Networks

Sr. No POP Site A Site Name_A 2G/ 3G_A BTS Type ID/ OD Site B Site Name_B 2G/ 3G_B Link Status Priority Tx ScenarioRF

Scenarios

1 3209 SADARBZR 2G+3G ULTRASITE ID 3252 Arjun 2G+3G New Hybrid SDH P1 Scenario-12 3252 Arjun 2G+3G ULTRASITE ID 3236 Manas 2G+3G New Hybrid SDH P2 Scenario-53 3236 Manas 2G+3G ULTRASITE ID 3207 SHAHGANJ 2G+3G New Hybrid SDH P2 Scenario-44 3207 SHAHGANJ 2G+3G ULTRASITE ID 895 AI_MOHANPURA 2G New Hybrid SDH P2 Scenario-35 895 AI_MOHANPURA 2G FLEXI EDGE ID 3209 SADARBZR 2G+3G New Hybrid SDH P1 Scenario-26 3252 Arjun 2G+3G ULTRASITE ID 3297 A_Arjun Nagar 2G+3G Existing FlexiHopper P2 Scenario-57 3252 Arjun 2G+3G ULTRASITE ID 3296 A_Kedar Nagar 2G+3G Reuse FlexiHopper P3 Scenario-58 3236 Manas 2G+3G ULTRASITE ID 3244 T_Sivaji 2G+3G Reuse FlexiHopper P3 Scenario-49 3236 Manas 2G+3G ULTRASITE ID 3256 T_Anjani puram 2G+3G Reuse FlexiHopper P3 Scenario-4

10 895 AI_MOHANPURA 2G FLEXI EDGE ID 3224 IDGAH 2G+3G Reuse FlexiHopper P3 Scenario-211 895 AI_MOHANPURA 2G FLEXI EDGE ID 3240 Balu 2G+3G Existing FlexiHopper P2 Scenario-212 3209 SADARBZR 2G+3G ULTRASITE ID 3042 A_BALU GANJ 2G+3G New Hybrid PDH P1 Scenario-113 3042 A_BALU GANJ 2G+3G FLEXI EDGE ID 3045 A_Adresh Nagar 2G Existing FlexiHopper P2 Scenario-714 3045 A_Adresh Nagar 2G FLEXI EDGE ID 3048 HI_Chhipitola 2G Reuse FlexiHopper P3

15 3200 SANJAYCPLX 2G+3G ULTRASITE ID 3242 Akriti 2G+3G New Hybrid SDH P1 Scenario-816 3242 Akriti 2G+3G ULTRASITE OD 3205 WHITEHOUSE 2G+3G New Hybrid SDH P1 Scenario-917 3205 WHITEHOUSE 2G+3G ULTRASITE ID 3237 Khandari 2G+3G New Hybrid SDH P1 Scenario-918 3200 SANJAYCPLX 2G+3G ULTRASITE ID 3279 Sanjay Complex-B 2G New Hybrid PDH P3 Scenario-819 3200 SANJAYCPLX 2G+3G ULTRASITE ID 3238 Nehru 2G+3G Reuse FlexiHopper P3 Scenario-820 3200 SANJAYCPLX 2G+3G ULTRASITE ID 3265 Kamlangr Entry 2G+3G New Hybrid PDH P1 Scenario-821 3265 Kamlangr Entry 2G+3G ULTRASITE OD 3245 Gandhi 2G+3G New Hybrid PDH P2 Scenario-1122 3242 Akriti 2G+3G ULTRASITE OD 3251 Shah mkt 2G New Hybrid PDH P3 Scenario-123 3205 WHITEHOUSE 2G+3G ULTRASITE ID 392 Khandari 1 2G+3G Reuse FlexiHopper P3 Scenario-924 3237 Khandari 2G+3G ULTRASITE ID 3258 Vidya 2G+3G Reuse FlexiHopper P3 Scenario-925 3237 Khandari 2G+3G ULTRASITE ID 3261 Khandari A 2G New Hybrid PDH P2 Scenario-926 3261 Khandari A 2G ULTRASITE ID 3053 A_MAYAPURI 2G New Hybrid PDH P3 Scenario-3

SAD

AR

BZR

SAN

JAYC

PLX

Link Details

Page 72: 3G Scenareo

For internal use only73 © Nokia Siemens Networks

MW Scenario Idea Haryana

Page 73: 3G Scenareo

For internal use only74 © Nokia Siemens Networks

Existing 1 PDH,1 NEW PDH Hops

Existing 1 PDH Hop

1 SDH, 1 NEW PDH

Existing 2 PDH Hops

1 NEW PDH Hop

PDH Replace with Flexi Hybrid

1 NEW HYBRID, 1 UPGRADE TO HYBRID

MW Scenario Idea Haryana

Scenario 1 :Scenario 2 :Scenario 3 :Scenario 4:Scenario 5:Scenario 6:Scenario 7:

Page 74: 3G Scenareo

For internal use only75 © Nokia Siemens Networks

Scenario 4

Scenario 2

Cluster 1

Page 75: 3G Scenareo

For internal use only76 © Nokia Siemens Networks

Scenario 6

Scenario 7

Cluster 2

Page 76: 3G Scenareo

For internal use only77 © Nokia Siemens Networks

Scenario 5Scenario 3

Scenario 1

Cluster 3

Page 77: 3G Scenareo

For internal use only78 © Nokia Siemens Networks

NodeB

2GBTS

FTIB

FIPA

Scenario 1

FIU 19

PDH PDH

Option 1 : Existing FB interface Option 2 : Existing E1 interface

PDH PDH

NodeB

2GBTS

FTFB

FIFA

FTFBEIPU Card

Similar scenario would be applicable for Ultra 2G BTS with RRI Card

Towards Samrat Woolen Mill Towards Samrat Woolen MillTowards Noorwala

Towards Noorwala

Barshat Road

Existing 1 PDH,1 NEW PDH Hops

Page 78: 3G Scenareo

For internal use only79 © Nokia Siemens Networks /

Scenario – 1 Existing PDH with FIU & EPIU

Sr. No. Activity Duration Outage/ Non Outage

1 New FIU with EPIU Installation in 19” Rack. 0.5 Hours - Day 2Non Outage

2 Power Cable Laying & termination. 0.5 Hours - Day 2Non Outage

3 DDF Block Installation, E1 & Ethernet Termination. 0.5 Hours - Day 2Non Outage

4 Configuration of FIU 0.5 Hours - Day 2Outage

5 E1 Testing 0.5 Hours - Day 2Outage

6 Traffic Shifting 0.5 Hours - Day 2Outage

8 Acceptance Testing 1 Hour - Day 2Outage

Page 79: 3G Scenareo

For internal use only80 © Nokia Siemens Networks

Scenario 2

1 Existing PDH Hop

NodeB

2GBTS

FTFB

RRI NodeB

2GBTS

FTIB

E1T1

FTFB

Similar scenario would be applicable for FLEXI 2G BTS with FIFA Card

PDH PDH

Towards Pachranga Towards Pachranga

Sethi Chowk

FIU 19

Page 80: 3G Scenareo

For internal use only81 © Nokia Siemens Networks /

Scenario – 2 Existing PDH with FTFB

Sr. No. Activity Duration Outage/ Non Outage

1 FTFB Installation in NodeB. 0.5 Hours- Day 2 Non Outage

2 DDF Block Installation, E1 & Ethernet Termination. 0.5 Hours- Day 2 Non Outage

3 IF Cable Replacement with IF Connectorisation at Antenna end. 0.5 Hours- Day 2 Outage

4 Coaxial cable connectivity from FTFB to existing FIFA/RRI. 0.5 Hours- Day 2 Outage

5 Commissioning Near End and Far End 0.5 Hours- Day 2 Outage

6 E1 Testing 0.5 Hours- Day 2 Outage

7 Acceptance testing 1 Hour -Day 2 Outage

Page 81: 3G Scenareo

For internal use only82 © Nokia Siemens Networks

• 1 SDH, 1 NEW PDH

2GBTS

RRI

Ceragon IP-10

FIU19

Ceragon-IDU

PDH

Fiber MUX

FTFB

Similar scenario would be applicable for FLEXI 2G BTS with FIFA Card

ECI-BG-20 Mux

Scenario 3

Towards Samrat Woolen Mill

Towards Bichpuri

Yamuna Enclave

Page 82: 3G Scenareo

For internal use only83 © Nokia Siemens Networks /

Scenario – 3 Existing PDH with FIU & EPIU

Sr. No. Activity Duration Outage/ Non Outage

1 New FIU with EPIU Installation in 19” Rack. 0.5 Hours - Day 2Non Outage

2 Power Cable Laying & termination. 0.5 Hours - Day 2Non Outage

3 DDF Block Installation, E1 & Ethernet Termination. 0.5 Hours - Day 2Non Outage

4 Configuration of FIU 0.5 Hours - Day 2Outage

5 E1 Testing 0.5 Hours - Day 2Outage

6 Traffic Shifting 0.5 Hours - Day 2Outage

8 Acceptance Testing 1 Hour - Day 2Outage

Page 83: 3G Scenareo

For internal use only84 © Nokia Siemens Networks

• 1 SDH, 1 NEW PDH

2GBTSE1T1

Ceragon IP-10

FIU19

Ceragon-IDU

PDH

Fiber MUX

FTFB

Similar scenario would be applicable for FLEXI 2G BTS with FIPA Card

ECI-BG-20 Mux

Scenario 3.1

Towards Samrat Woolen Mill

Towards Bichpuri

Yamuna Enclave

Page 84: 3G Scenareo

For internal use only85 © Nokia Siemens Networks /

Scenario – 3.1 Existing PDH with FIU & EPIU

Sr. No. Activity Duration Outage/ Non Outage

1 New FIU with EPIU Installation in 19” Rack. 0.5 Hours - Day 2Non Outage

2 Power Cable Laying & termination. 0.5 Hours - Day 2Non Outage

3 DDF Block Installation, E1 & Ethernet Termination. 0.5 Hours - Day 2Non Outage

4 Configuration of FIU 0.5 Hours - Day 2Outage

5 E1 Testing 0.5 Hours - Day 2Outage

6 Traffic Shifting 0.5 Hours - Day 2Outage

8 Acceptance Testing 1 Hour - Day 2Outage

Page 85: 3G Scenareo

For internal use only86 © Nokia Siemens Networks

NodeB

2GBTS

FTIB

E1T1

Scenario 4

Existing 2 PDH Hops

FIU 19

PDH PDH

Option 1 : Existing FB interface Option 2 : Existing E1 interface

PDH PDHNodeB

2GBTS

FTIB

RRI

Similar scenario would be applicable for FLEXI 2G BTS with FIFA Card

Towards SukhdevnagarTowards Sukhdevnagar

Towards Sethi Chowk

 Pachranga

FIU 19

Towards Sethi Chowk

Page 86: 3G Scenareo

For internal use only87 © Nokia Siemens Networks

Scenario 5

1 NEW PDH Hop

NodeB

2GBTS

FTFB

RRI NodeB

2GBTS

FTFB

E1T1

FTFB

Similar scenario would be applicable for FLEXI 2G BTS with FIFA Card

Towards Yamuna Enclave

Bichpuri

FIU 19

Towards Yamuna Enclave

PDHPDH

Page 87: 3G Scenareo

For internal use only88 © Nokia Siemens Networks /

Scenario – 5 NEW PDH

Sr. No. Activity Duration Outage/ Non Outage

1 ODU & Antenna Installation. 2 Hours - Day 2Non Outage

2 IF Cable Laying and termination 1 Hour - Day 2Non Outage

3 Hybrid IDU Installation in 19” Rack. 0.25 Hour -Day 2Non Outage

4 Power Cable Laying & termination. 0.25 Hour -Day 2Non Outage

5 DDF Block Installation, E1 & Ethernet Termination. 0.25 Hour -Day 2Non Outage

6 Commissioning Near End and Far End 0.25 Hour -Day 2Non Outage

7 Link Alignment 2 Hours - Day 2Non Outage

8 E1 Patching and testing 0.5 Hour - Day 2Non Outage

9 Acceptance Testing 2 Hours - Day 2Non Outage

Page 88: 3G Scenareo

For internal use only89 © Nokia Siemens Networks

NodeB

2GBTS

FTIB

E1T1

Scenario 6

PDH Replace with Flexi Hybrid

FLEXIHYBRID 1+0

NodeB

2GBTS

FTIB

RRI

FLEXIHYBRID 1+0

Option 1 : Existing FB interfaceOption 1 : Existing E1 interface

Similar scenario would be applicable for FLEXI 2G BTS with FIPA Card

Towards Lal Bati Panipat Towards Lal Bati Panipat

Gur Mandi Panipat

FIU19 FIU19

Page 89: 3G Scenareo

For internal use only90 © Nokia Siemens Networks /

Scenario – 6 PDH TO SDH

Sr. No. Activity Duration Outage/ Non Outage

1 Hybrid IDU Installation. 0.5 Hours- Day 2 Non Outage

2 New FIU Installation in 19” Rack. 0.5 Hours- Day 2 Non Outage

3 Power Cable Laying & termination. 0.5 Hours- Day 2 Non Outage

4 DDF Block Installation, E1 & Ethernet Termination. 0.5 Hours- Day 2 Non Outage

5 ODU Replacement with IF Connectorisation at Antenna end. 0.5 Hours- Day 2 Outage

6 Coaxial cable connectivity from FIU to existing RRI. 0.5 Hours- Day 2 Outage

7 Commissioning Near End and Far End 0.5 Hours- Day 2 Outage

8 E1 Testing 0.5 Hours- Day 2 Outage

9 Traffic Shifting on new Flexi Hybrid Hop 0.5 Hours- Day 2 Outage

10 Acceptance testing 1 Hour -Day 2 Outage

Page 90: 3G Scenareo

For internal use only91 © Nokia Siemens Networks

• 1 NEW HYBRID, 1 UPGRADE TO HYBRID

2GBTS

RRI

Flexihybrid Upgrade to Hybrid

FIU19

Flexihybrid (2+0)

NodeB

FTIB

Scenario 7

Similar scenario would be applicable for FLEXI 2G BTS with FIFA Card

Towards Ashram Road

Towards Gur Mandi Panipat

Lal Bati Panipat  

Page 91: 3G Scenareo

For internal use only92 © Nokia Siemens Networks /

Scenario – 7 PDH TO SDH

Sr. No. Activity Duration Outage/ Non Outage

1 Hybrid IDU Installation. 0.5 Hours- Day 2 Non Outage

2 New FIU Installation in 19” Rack. 0.5 Hours- Day 2 Non Outage

3 Power Cable Laying & termination. 0.5 Hours- Day 2 Non Outage

4 DDF Block Installation, E1 & Ethernet Termination. 0.5 Hours- Day 2 Non Outage

5 ODU Replacement with IF Connectorisation at Antenna end. 0.5 Hours- Day 2 Outage

6 Coaxial cable connectivity from FIU to existing RRI. 0.5 Hours- Day 2 Outage

7 Commissioning Near End and Far End 0.5 Hours- Day 2 Outage

8 E1 Testing 0.5 Hours- Day 2 Outage

9 Traffic Shifting on new Flexi Hybrid Hop 0.5 Hours- Day 2 Outage

10 Acceptance testing 1 Hour -Day 2 Outage

Page 92: 3G Scenareo

For internal use only93 © Nokia Siemens Networks

Sr No

Node IDPop

Location

Priority

Site_A_NameSite Type

BTS Type

Flexi/Ultra Site_B Link Status Site Name_B 2G/

3G_B Tx Scenario

1 PNP141

Samrat Woolen

Mill

P1Samrat Woolen Mill GBT Indoor ULTRASITE     Samrat Woolen Mill 3G Connected on Fiber

2 PNP142P2

Barshat Road RTT Outdoor FLEXI EDGE PNP141 Existing PDH Samrat Woolen Mill 3G Scenario 1

3 PNP159P2

Babarpur RTT Outdoor ULTRASITE PNP141 Existing PDH Samrat Woolen Mill 3G Scenario 2

4 PNP169P2

Yamuna Enclave GBT Indoor ULTRASITE PNP141Existing Ceragon

IP-10 Samrat Woolen Mill 3G Scenario 3

5 PNP182P2

Narula_Panipat RTT Indoor ULTRASITE PNP141 Existing PDH Samrat Woolen Mill 3G Scenario 4

6 PNP184P2

Jawahar_Panipat GBT Indoor ULTRASITE PNP141 Existing PDH Samrat Woolen Mill 3G Scenario 1

7 PNP3513P3

Kabri Road GBT Indoor ULTRASITE 3503 Existing PDH   3G Scenario 4

8 PNP3520P3

Siddharth Nagar RTT Indoor ULTRASITE PNP182 Existing PDH Narula_Panipat 3G Scenario 2

9 PNP3523P3

Barsat Road RTT Outdoor FLEXI EDGE PNP184 New PDH Jawahar_Panipat 3G Scenario 5

10 PNP346P3

Bichpuri RTT Indoor ULTRASITE PNP169 New PDH Yamuna Enclave 3G Scenario 5

11 PNP3580P3

Kabri GBT Indoor FLEXI EDGE 3513 Existing PDH Kabri Road 3G Scenario 2

12 PNP51P3

Noorwala GBT Outdoor FLEXI EDGE PNP142 NEW PDH Barshat City 3G Scenario 5

13 PNP144P2

Gur Mandi Panipat RTT Indoor ULTRASITE PNP153 Upgrade to hybrid Lal Bati, Panipat 3G Scenario 6

14 PNP153

Sukhdevnagar

P2Lal Bati, Panipat   RTT Outdoor ULTRASITE PNP3524 New Hybrid Ashram Road 3G Scenario 7

15 PNP347P2

Ashok Vihar GBT Indoor ULTRASITE PNP348 Existing PDH Sukhdevnagar 3G Scenario 4

16 PNP348P1

Sukhdevnagar RTT Indoor FLEXI EDGE       3G Connected on Fiber

17 PNP3510P3

Sethi Chowk RTT Indoor ULTRASITE PNP3516 Existing PDH Pachranga 3G Scenario 2

18 PNP3516P2

 Pachranga RTT Indoor ULTRASITE PNP348 Existing PDH Sukhdevnagar 3G Scenario 4

19 PNP3524P2

Ashram Road RTT Indoor ULTRASITE PNP153Existing Ceragon

IP-10 Lal Bati, Panipat 3G Scenario 7

20 PNP3525P2

Adarsh Nagar Panipat RTT Indoor ULTRASITE PNP3524 Upgrade to hybrid Ashram Road 3G Scenario 6

21 PNP3581P3

Indira Colony RTT Indoor FLEXI EDGE PNP347 Existing PDH Ashok Vihar 3G Scenario 2

22 PNP3518P3

Patel Nagar Panipat RTT Indoor ULTRASITE PNP182 Existing PDH Narula_Panipat 3G Scenario 2

Page 93: 3G Scenareo

For internal use only94 © Nokia Siemens Networks /

3G Core Upgrades for UP (West) & Haryana

Page 94: 3G Scenareo

For internal use only95 © Nokia Siemens Networks

UP-West Network – User Plane (3G Phase1)

Meerut ZoneAgra Zone

Moradabad Zone

VAS Zone

MGW

4

MGW

12

MGW

9

MGW

14

MGW

11

MGW

8

MGW

7

GMGW

4

GMGW

5

MSS

4

MSS

3

GCS

3

MSS

2

MSS

5

GMGW

3

GCS

2

GMGW

2

GCS

1

GMGW

1

MGW

5

SCP

SMS

MGW

17

MSS

8

MGW

16MGW

10

MSS

6

MGW

2

MGW

1

MSS

1

User Plane over IP

User Plane over TDM

MGW

6

MGW

13

Dehradun Zone

MSS

7

MGW

15

HLR2

HLR1

HLR3

Agra RNC

D’dun RNC

Mbd RNC

Mrt RNC

MGW

18MSS

9

Page 95: 3G Scenareo

For internal use only96 © Nokia Siemens Networks Presentation / Author / Date

Haryana Network – User Plane (3G Phase1)

Ambala Zone

Sonipat Zone

Hissar Zone

MGW

1

MSS

1

HLR1

VAS Zone

SCP

SMS

MGW

4

MSC

1

MSC

2

TDM Mesh

TDM Mesh

User Plane over IP

User Plane over TDM

MSS

2MGW

3

MGW

5

GCS

1

GMGW

1

Amb RNC

Soni RNC

Hiss RNC

MGW

3

MSS

6

Page 96: 3G Scenareo

For internal use only97 © Nokia Siemens Networks

Core 2G Nodes Rollout Plan – UP(West)

Node Project Site Node Name RFS Date Duration Current Status

MGW Exp 12K U4 to 20K U4 UDAAN Moradabad MGW14 10-Sep-10 3days Delivered Onsite

MGW Exp 12K U4 to 20K U4 UDAAN Dehradun MGW15 10-Sep-10 3days Delivered Onsite

MSS M14 600K UDAAN Moradabad MSS09 17-Sep-10 24 days Installation In Progress

MGW 20K Model U4 HW ** UDAAN Moradabad MGW18 10-Sep-10 24 days Installation In Progress

GMGW 20K Model U4 HW ** UDAAN Meerut GMGW07 10-Sep-10 18 days Delivered Onsite

** The duration mentioned includes Installation , C&I ,Acceptance Testing & Live Cutover

Core 2G Nodes Rollout Plan – Haryana

Node Project Site Node Name RFS Date Duration Current Status

MSS M14 600K** UDAAN Ambala MSS03 29-Sep-10 24 days In Transit

MGW 20K Model U4 HW ** UDAAN Ambala MGW07 30-Sep-10 24 days In Transit

Page 97: 3G Scenareo

For internal use only98 © Nokia Siemens Networks

Details of Activities & Timelines for various CORE rollouts.

MGW/GMGW Expansion 12K U4 to 20K U4 (3 Days):

• Creation of Units(TCU, ISU,IWS1, MXU), Diagnosis of new Units,

IP Allocation, VMGW Creation

• NIWU shifting

MSS 600K/MGW 20K (24 Days):

• The duration mentioned includes Installation , C&I ,Acceptance Testing & Live Cutover

GMGW (18 days):

• The duration mentioned includes Installation , C&I ,Acceptance Testing & Live Cutover

Power & Space Requirements :

NETWORK ELEMENT Max No. Of Rack(s) Cabinet Cabinet Size(WxDxH) Estimated/Rated Power In

WattsTypical/Operating Power In

WattsMCB/Fuse

Requirements/RackMGW Exp 12K to 20K 1 CAMC 600x600x2100 mm 4800 2100 2x100A

NETWORK ELEMENT Max No. Of Rack(s) Cabinet Cabinet Size(WxDxH) Estimated/Rated Power

In WattsTypical/Operating Power

In WattsMCB/Fuse

Requirements/RackMGW U4 20K/GMGW 3 CAMA 600x600x2100 mm 4800 2300 2x100A

CAMB 600x600x2100 mm 4800 2200 2x100A CAMC 600x600x2100 mm 4800 2100 2x100A

NETWORK ELEMENTMax No. Of

Rack(s) Cabinet Cabinet Size(WxDxH)Estimated/Rated Power

In WattsTypical/Operating Power

In WattsMCB/Fuse

Requirements/RackRNC 2 RNAC 600x600x2100 mm 4800 2600 2X125A RNBC 600x600x2100 mm 4800 2800 2X125A