4-jan-16s.movchan straw manufacturing and qc1 straw tracker manufacturing procedure dubna: assembly...
TRANSCRIPT
Apr 21, 2023 S.Movchan Straw manufacturing and QC 1
Straw tracker manufacturing procedure
• Dubna: assembly halls• procedure• conclusion
Presented by S.Movchan
Apr 21, 2023 S.Movchan Straw manufacturing and QC 2
Bld. 217: 3-D model of halls
Total: S=250 m2
Room 114
Room 112-113
Room 110-111 S=150 m2
S=50 m2
S=50 m2
Apr 21, 2023 S.Movchan Straw manufacturing and QC 3
Room 114: common view
Condition system
Crane: F=0.5 t
S=16.6x9=149.4 m2 h=(7-8) m
Apr 21, 2023 S.Movchan Straw manufacturing and QC 4
conclusion after first look: we need many areas (~ 4) for chamber assembly
definitions:layer - 121 strawsview - 4 layersmodule – 2 viewschamber – 2 modulestracker – 4 chambers (8 modules)
Apr 21, 2023 S.Movchan Straw manufacturing and QC 5
Chamber assembly: 2 areas option
Assemblyarea 1
Assemblyarea 2
Vacuum testChambergeometry
measurement
Cosmic test area 1
Cosmic test area 2
Apr 21, 2023 S.Movchan Straw manufacturing and QC 6
Step 1: chamber cleaning
1 week
Chamber cleaningarea
Apr 21, 2023 S.Movchan Straw manufacturing and QC 7
Step 2: chamber vacuum test
1 week
Apr 21, 2023 S.Movchan Straw manufacturing and QC 8
Step 3: chamber geometry measurements
2.5 day per side, total: 1 week
Apr 21, 2023 S.Movchan Straw manufacturing and QC 9
Step 4: module assembly procedure2 weeks + 1 spare = 3 weeks per layer (121 straws)
Start up (steps 1-3): 3 weeks + 1 spare (for vacuum tests) = 4 weeks 1 month per module
Apr 21, 2023 S.Movchan Straw manufacturing and QC 10
Steps 1 and 3: straw insertion to frame and glue
Straws glue: tools per 28+28 straws (2 x half of module) glue rate: (3-5) min per each end plug
per layer: 2 days + 0.5 spare= 2.5 days/2 technicians
Module position for straw glue:
Apr 21, 2023 S.Movchan Straw manufacturing and QC 11
Steps 2 and 4: straw tension measurement
Layer by layer
Straw tension measurement: F=(1.5 +/- 0.1) kg
straw tension rate: 1 day per layer
Apr 21, 2023 S.Movchan Straw manufacturing and QC 12
Steps 5 and 6: WEBs installation and wiring
121 straw wiring: nominal tension – 80 g wiring rate: 4 min per wire (layer per day)
WEBs + wiring: 4 days/2 technicians
Apr 21, 2023 S.Movchan Straw manufacturing and QC 13
Steps 7 and 8: wire tension measurement
Wire tension measuremennt method: by wire vibration + sensor for frequency measurement
straw tension: nominal tension – (80+/-5) g
wire tension measurement rate: 1 day
Wire reparation – 1 day
Apr 21, 2023 S.Movchan Straw manufacturing and QC 14
Layer assembly summary
Per layer (121 straws):straw glue: 2.5 days/2 technicians 0.5 weekstraw tension: 1.0 day 0.2 weekWEBs installation + wiring: 1.0 days/2 technicians 0.2 weekwire tension and reparation: 1.0 day 0.1 week
Total: 1 week +1 spare=2 weeks (spare: for straw and wire reparation)
Per module:6 months (8 layers x 2 weeks = 16 weeks)
We have 2 assembly areas:so, expected production rate will be 2 module per 4 months
Apr 21, 2023 S.Movchan Straw manufacturing and QC 15
Step 5: final chamber geometry measurements
1 day per side, total: 2 days
Apr 21, 2023 S.Movchan Straw manufacturing and QC 16
Step 6: final chamber vacuum test
1 week
Apr 21, 2023 S.Movchan Straw manufacturing and QC 17
Step 7: tests + cosmic
cosmic
• HV test
• gas system test
• connectivity test
• cosmic test
3 months/chamber
Apr 21, 2023 S.Movchan Straw manufacturing and QC 18
Step 8: chamber package and store
2 weeks per chamber4 weeks
Apr 21, 2023 S.Movchan Straw manufacturing and QC 19
Steps 1- 8: summary
Per 2 module:Step 1: module cleaning 1 weekStep 2: module vacuum test 1 weekStep 3: module geometry measurements 1 week
spare (vacuum test) 1 weekStep 4: module assembly 16 weeks
spare (straw and wire reparation) 4 weeksStep 5: final module geometry measurements 1 weekStep 6: final module vacuum test 1 week
Total: 26 weeks
Step 7: chamber tests + cosmic 12 weeksStep 8: chamber package and store 4 weeks
Total: 42 weeks (1 year per chamber)
Apr 21, 2023 S.Movchan Straw manufacturing and QC 20
Conclusion
Chamber rate production at Dubna – about 1 year (with 2 assembly area)
Straw tracker:- first chamber - Dubna- second chamber - we need start chamber production at CERN too
- 3-d chamber:Option 1:
used additional facility for production 3-d chamber in 2011Than it will be install in 2012 too
- 3 and 4 stations:Option 2:
Dubna + CERN can produce 3-d and 4-th chambers but it will be install only in 2013
Apr 21, 2023 S.Movchan Straw manufacturing and QC 21