4 noise impact assessment 4.1 introduction 4.2 … · 4.1 introduction 4.1.1 this chapter presents...
TRANSCRIPT
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-1
4 NOISE IMPACT ASSESSMENT
4.1 Introduction
4.1.1 This Chapter presents an assessment of the potential noise impact arising from the
construction and operation of the Project. Mitigation measures have been identified to
alleviate the impact and their effectiveness has been evaluated.
4.2 Environmental Legislation, Standards and Guidelines
Construction Noise
4.2.1 The Noise Control Ordinance (NCO) (Cap. 400) provides the statutory framework for
noise control in Hong Kong. Assessment procedures and standards are set out in the
respective Technical Memoranda (TM) promulgated under the NCO. The following
TMs are applicable to the assessment and control of construction noise.
Technical Memorandum on Noise from Construction Work other than
Percussive Piling (TM-GW);
Technical Memorandum on Noise from Percussive Piling (TM-PP); and
Technical Memorandum on Noise on Construction Work in Designated
Areas (TM-DA)
Technical Memorandum on Noise from Places other than Domestic
Premises, Public Places or Construction Sites (TM-IND)
4.2.2 Both the percussive piling and construction work under restricted hours require a
construction noise permit (CNP) in order to carry out such work. As the issuance of a
CNP by the Noise Control Authority would depend on the compliance of percussive
piling noise impact or construction noise impact with the limits set out within the TM-
PP and TM-GW/TM-DA, the assessment of this type of noise would not be covered in
the EIA report.
4.2.3 For construction, there is no statutory limit on daytime construction noise under the
NCO and related TMs. Nevertheless, the “Technical Memorandum on Environmental
Impact Assessment Process” (EIAO-TM) stipulates noise standards for daytime
construction activities, as shown Table 4-1.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-2
Table 4-1: Construction Noise Standards during Non-Restricted Hours
Uses
Noise Standards [1] , Leq (30 mins) dB(A)
0700 to 1900 hours
on any day not being a
Sunday or general
holiday
1900 to 0700 hours
or any time on Sundays or
general holiday
All domestic premises including
temporary housing
accommodation
75
(See Note 2) Hotels and hostels 75
Educational institutions including
kindergartens, nurseries and all
others where unaided voice
communication is required
70 65 (During
examinations)
Notes:
[1] The above standards apply to uses that rely on opened windows for ventilation.
[2] The criteria laid down in the relevant technical memoranda under the NCO for designated areas and
construction works other than percussive piling may be used for planning purpose. A Construction
Noise Permit (CNP) shall be required for the carrying out construction work during the period.
Construction Noise during Restricted Hours
4.2.4 The NCO provides statutory control on general construction works (excluding
percussive piling) conducted during restricted hours (i.e. 1900 to 0700 hours (of the
next day) from Monday to Saturday and at any time on Sundays or in public holidays).
A Construction Noise Permit (CNP) is required for carrying out of any general
construction activities involving the use of any Powered Mechanical Equipment (PME)
within restricted hours from the Authority under the NCO. The noise criteria and the
assessment procedures for issuing a CNP are specified in the TM-GW under the NCO.
4.2.5 The use of Specified PME (SPME) and/or the undertaking of Prescribed Construction
Work (PCW) within a Designated Area (DA) under the NCO during the restricted
hours are controlled by the TM-DA. The relevant technical details in Technical
Memorandum on Noise from Construction Work in Designated Areas (TM-DA) under
NCO can be referred. The acceptable noise levels for construction during the restricted
hours are summarized in Table 4-2 below.
Table 4-2: Construction Noise Standards during Restricted Hours
Uses
Acceptable Noise Level for Area Sensitive Ratings, dB(A)
A B C
All weekdays during the evening
(1900 to 2300 hours), and general
holidays (including Sundays)
during the day and evening (0700 to
2300 hours)
60 65 70
All days during the night-time
(2300 to 0700 hours) 45 50 55
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-3
4.2.6 The Area Sensitive Rating depends on the type of area and the degree of impact that
Influencing Factors (IFs) have on the NSRs and is determined from Table 4-3 below.
Industrial area, major road or the area within the boundary of Hong Kong International
Airport shall be considered to be an IF.
Table 4-3: Area Sensitivity Ratings (ASRs)
Type of Area containing NSR Degree to which NSR is affected by IF
Not Affected
Indirectly Affected
Directly Affected
(i) Rural area, including country parks or village type
developments A B B
(ii) Low density residential area consisting of low-rise or
isolated high-rise developments A B C
(iii) Urban area B C C (iv) Area other than those above B B C
4.2.7 According to the preliminary construction programme, it is very likely that the
proposed construction works would be carried out during non-restricted hours only.
For carrying out any general construction activity involving the use of any Powered
Mechanical Equipment (PME) within restricted hours, a Construction Noise Permit
(CNP) is required from the authority under the NCO. The noise criteria and the
assessment procedures for issuing the CNP are specified in the TM-GW under the
NCO. There is no guarantee that a CNP will be issued for the project construction. The
Noise Control Authority will consider a well justified CNP application, once filed, for
construction work within restricted hours as guided by the relevant TMs issued under
the NCO. It is the Contractor’s responsibility to ensure compliance with the NCO and
the relevant TMs in case of any construction activities during restricted hours.
4.2.8 The Noise Control Ordinance (NCO) and Technical Memorandum on Environmental
Impact Assessment Process (EIAO-TM) were followed for assessing the noise from
powered mechanical equipment (PME) for different sensitive uses.
Construction Ground-Borne Noise
4.2.9 According to the TM-GW, the Area Sensitivity Rate of the area in which the identified
NSRs are located is “A”. Moreover, the TM-IND under NCO mentioned that where
the noise under investigation is transmitted primarily through the structural elements
of the building or if the assessment point is at an internal location of a building, an
adjustment of -10 dB(A) should be made to relevant acceptable noise levels (ANLs).
The relevant noise limits for ground-borne noise are tabulated in Table 4-4.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-4
Table 4-4 Ground-borne Construction Noise Limits
Time Period Uses Noise Standard
(Leq, 30 min dB(A))
(1)Day-time
Domestic Premises 65
Educational institutions (normal
periods) 60
Educational institutions (during
examination periods) 55
(1)Evening-time All Noise Sensitive Uses 50
(1)Night-time All Noise Sensitive Uses 35
(1) assessment point is at a particular internal location
Operational Noise
4.2.10 Noise from the proposed sewage treatment plant (STP) is considered as the only fixed
noise source during the operation phase of the Project. Operational noise is controlled
under the Noise Control Ordinance (NCO)’s Technical Memorandum on Noise from
Places other than Domestic Premises, Public Places or Construction Sites (TM-IND).
4.2.11 According to the TM-IND, appropriate Area Sensitivity Ratings should be determined
for the NSRs under consideration from Table 1 of the TM-IND. Then, the appropriate
Acceptable Noise Level (ANL) for a given NSR and the time period under
consideration could be read from Table 3 of TM-IND. According to the TM-IND, the
ANLs for different Area Sensitivity Ratings (ASRs) of noise sensitive receivers
(NSRs) are given in Table 4-5.
Table 4-5 Acceptable Noise Levels
Time Period ASR A ASR B ASR C
All days during the evening (1900 to 2300 hours), and
general holidays (including Sundays) during the day-
time and evening (0700 to 2300 hours)
60 65 70
All days during the night-time (2300 to 0700 hours) 50 55 65
4.2.12 More stringent criteria for fixed plant noise impacts recommended in Table 1A of the
EIAO-TM for planning purposes are as follow:
5 dB(A) below the appropriate ANL set out in the TM-IND (the ANL–5 dB(A)
criterion), or
The prevailing background noise level where the prevailing background noise
level is 5 dB(A) below the appropriate ANL (although during the operation the
NCO will be the controlling legislation).
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-5
4.2.13 In this Project, the study area covering 300m from the proposed works boundary (as
shown in Figure 4-1) is identified as rural area consisting village type developments
without being affected by IF thus the NSRs are assigned an Area Sensitive Rating of
“A”.
4.2.14 In order to determine the appropriate criteria for noise assessment, background noise
survey was carried out during the course of the EIA process at two locations to
determine the baseline noise levels. Noise monitoring was conducted for 14
consecutive days in November 2014. Locations of the monitoring stations are
summarised in Table 4-6 and shown on Figure 4-1. For those sensitive receivers
which were found to experience prevailing noise levels lower than the ANL-5dB(A)
criterion, fixed plant noise impact were assessed against the prevailing background
noise levels.
Table 4-6 Background Noise Monitoring Results at Selected NSRs in Po Toi O
Time Period Measurement
Parameter
Noise Level (dB(A))
NM1 - Near Local
Resident
NM2 - Near Fairway
Vista
Max. Min. Average Max. Min. Average
Daytime 0700 -1900 Leq30min 62 52 57 66 51 58
Evening
Time 1900 - 2300 Leq5min 62 53 57 59 49 53
Night
Time
2300 - 0700
of next day Leq5min 56 46 51 53 47 50
4.2.15 The lowest recorded background noise level during daytime/evening period was 49
dB(A). Since the background noise level was 6 dB(A) lower than the ANL -5 dB(A),
the noise criteria for daytime/evening time periods will adopt the prevailing
background noise level of 49 dB(A). As the lowest nighttime background noise level
was 1 dB(A) higher than the ANL-5dB(A), noise criterion of 45 dB(A) is adopted for
nighttime period. The operational phase noise criteria are summarized in Table 4-7.
Table 4-7 Acceptable Noise Levels (ANLs) during Operational Period
Time Period
Acceptable
Noise Levels
(ANLs),
dB(A)
(ANL -5)
dB(A)
Prevailing
Background
dB(A)
*Noise
Criteria
dB(A)
Day (0700 to 1900 hours) 60 55 49 49
Evening (1900 to 2300 hours)
Night (2300 to 0700 hours) 50 45 46 45
* ANL – 5dB(A) or the prevailing background noise levels (for quiet areas with level 5dB(A) below the
ANL).
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-6
4.3 Descriptions of Environment
4.3.1 The village to be sewered is situated within a quiet rural area, with some of the
surrounding open land used as a golf course, recreational areas and seafood
restaurants. Noise levels in this village are generally very low with little noise
influence from outside of the village.
4.4 Identification of Potential Noise Impact
4.4.1 During the construction phase, use of powered mechanical equipment (PME) will
inevitably generate construction noise and hence may cause noise nuisance to the
nearby residences. During the operational phase, equipment noise from the proposed
sewage treatment plant will be the main noise source with potential noise impact on
the NSR.
4.5 Noise Sensitive Receivers
4.5.1 The Study Area covered 300m from the proposed works boundary as shown in Figure
4-2. Given the proximity of the STP and associated sewerage works to the Po Toi O
village, noise sensitive receivers in the village are likely to be affected by the Project
during its construction and operation. Noise sensitive receivers have been identified
from the Approved Clear Water Bay Peninsula South Outline Zoning Plan, S/SK-
CWBS/2, and 1:1000 survey plans of the area. In addition, site visits have been carried
out to identify the NSR and representative worst impact points of the identified NSR.
In general, the sewers are laid 2m away from and in parallel to NSRs. A list of the
identified NSR and their locations are depicted in Figure 4-2 and listed in Table 4-8
below. Photographic record can be found in Appendix 4.4.
Table 4-8 Representative Noise Sensitive Receivers
NSR Description Land
Use
Ground
mPD
Notional Noise Distance (m) from
NSR No. of
Storey Pipes
Po Toi O
Chuen Road
Sewer Pipe
Sewage
Treatment
Plant
PTO_N1 Village House in
PTOCR 28 Village 6 4 37.8 77.5 2
PTO_N2 Village House in
PTOCR 7A Village 4.1 4.2 167.4 203.4 *3
PTO_N3
Temporary
Structure for
living
Village 4.5 5.9 332.6 356.8 1
FV_N1 Fairway Vista
House 12 Village 7.5 2 331.5 352.6 3
SC_N1
Seacrest Villas
in PTOCR No.
64
Village 25.1 10.2 195.8 213.3 3
Noted: PTOCR = Po Toi O Chuen Road
* Ground floor of PTO_N2 is a seafood restaurant. Only first and second floors are considered as NSR.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-7
4.5.2 The village zone within or near the proposed sewerage works covers the Po Toi O
Village, Seacrest Villas and Fairway Vista. The land on both sides of the proposed
pipe alignment has already been fully occupied by houses. No future addition of NSR
is expected. Even if a house will be squeezed into the already crowded land, it will
only be of similar distance or further away from the sewerage works when compared
with the existing houses. This noise assessment will be sufficient in assessing and
evaluating the potential noise impact.
4.6 Assessment Methodology, Prediction and Evaluation of Environmental Impacts
4.6.1 Noise impact assessment was conducted in accordance with the requirements in
EIAO-TM Annex 5 and 13.
Construction Noise
4.6.2 The Project comprises three main works including the construction of sewage
treatment plant (STP), underground sewers and rising mains, and the submarine outfall.
4.6.3 Detailed construction method, sequence of works and the plant inventory in different
work stages were proposed at the time of this EIA. Until a contractor is appointed, full
details of the types and utilization of construction plants will not be known exactly.
Typical types and number of powered mechanical equipment (PME) needed for
various construction activities for the construction of STP and pipes installation have
been assigned as shown in Tables 4-9 to 4-13 below. PME that will likely be used
concurrently have been grouped within the same works stage. The project engineer has
reviewed the currently proposed construction programme and methodology including
list of PME items, percentage on-time assumptions, etc. such that they are considered
practicable and appropriate for this project.
4.6.4 As not every item of PME would be operated all the time when it is on site, a typical
percentage on time was assumed for each PME based on experience in actual site
practice so that the noise prediction exercise would be a more realistic one.
Accordingly, the effective sound power levels for each construction activity were
quantified and are listed in the same table.
Construction of Sewage Treatment Plant
4.6.5 The construction of STP will include earthworks, trench support and ground
compaction works, general concrete building works, backfilling and surfacing works.
Common construction plant including hydraulic breaker, excavator/loader, concrete
lorry mixer, vibratory poker, lorry and the like will be used. Typical plant list for STP
construction is shown in Table 4-9.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-8
Table 4-9: Typical PME to be used for Construction of Sewage Treatment Plant
Activity Noise Source
TM-GW
Reference
Number
Nos.
used
SWL,
dB(A)
% on
time
Effective SWL in
a 30 min period
Overall
SWL
Stage I Earth Works
1.1
Hydraulic breaker CNP 028 2 122 50% 122
123 Excavator / loader CNP 081 2 112 80% 114
Lorry CNP 141 2 112 30% 110
Stage II Trench Support & Ground Compaction
2.1
Vibrating hammer
(piling) CNP 172 2 115 80% 117
118
Roller, vibratory CNP 186 2 108 80% 110
Stage III Concrete Building Works
3.1
Vibratory poker CNP 170 2 113 80% 115
117 Concrete Lorry
Mixer CNP 044 2 109 100% 112
Stage IV Backfilling
4.1 Backhoe CNP 081 1 112 80% 111
112 Roller, vibratory CNP 186 1 108 60% 106
Stage V Surfacing
5.1
Vibratory poker CNP 170 1 113 80% 112
114 Concrete Lorry
Mixer CNP 044 1 109 100% 109
Installation of Gravity Sewers and Rising Mains
4.6.6 Trenchless method is proposed for the laying of rising mains from the STP to the
footpath between village house no.23 and no.28 of Po Toi O Village, which will be
deep down to 10m underground. Since the launching site is located at the STP, no
additional power mechanical equipment is required for excavation and backfilling
work for the launching site. Pipe jacking machine (e.g. hydraulic jack) would be
applied underground. Therefore, the noise generated for pipe laying under trenchless
method is relatively small when compared to other concurrent works and hence was
not considered in the quantitative construction noise assessment. The generator for
powering the pipe jacking machine will be located at the sewage treatment plant site
over 77.5m away from the nearest NSR. The noise from generator at NSR will be
reduced to low level that will have no major contribution to the overall construction
noise level at the NSR. This construction method is commonly applied in pipe laying
in village area. The ground compositions in the first few meters are soil and sand. No
significant groundborne noise impact is expected.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-9
Table 4-10: Typical PME to be used for Installation of Rising Mains (Trenchless
Method)
Activity Noise Source
TM-GW
Reference
Number
Nos.
used
SWL,
dB(A)
% on
time
Effective SWL in
a 30 min period
Overall
SWL
- Generator,
portable CNP 107 1 100 100% 100 100
4.6.7 Gravity sewers and rising mains will be laid within the first 3m below ground in the
village area. As there are different existing underground utilities located along
footpath in Po Toi O, trenchless method is considered risky for pipe laying in shallow
ground layer. Open trench method (cut and cover) will be adopted, in which
construction works generally take place in successive sequences as excavation, trench
support and ground compaction, pipe laying, backfilling, and surfacing. Construction
of pipelines in areas with restricted access in narrow alleys and pathways will mainly
use manual method or semi-PME method in order to reduce noise impact on the quiet
village. A typical plant list for construction of gravity sewers and rising mains in the
village area is provided in Table 4-11.
Table 4-11: Typical PME to be used for Installation of Gravity Sewers and Rising
Mains (Open Cut Method)
Activity Noise Source
TM-GW
Reference
Number
Nos.
used
SWL,
dB(A)
% on
time
Effective SWL in
a 30 min period
Overall
SWL
Stage I Excavation
1.1
Breaker, hand
held CNP 026 1 114 60% 112
112 Generator,
portable CNP 107 1 100 60% 98
Stage II Trench Support & Ground Compaction
No PME would be needed. Manual working for construction would be adopted.
Stage III Pipe-laying
No PME would be needed. Manual working for construction would be adopted.
Stage IV Backfilling
No PME would be needed. Manual working for construction would be adopted.
Stage V Surfacing
5.1 Vibratory poker CNP 170 1 113 80% 112 112
4.6.8 For the laying of gravity sewer on Po Toi O Chuen Road, larger scale of PMEs are
required for excavation and surfacing work. The plant list for open trench method for
pipe laying on Po Toi O Chuen is shown in Table 4-12.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-10
Table 4-12: Typical PME to be used for Installation of Gravity Sewers on Po Toi O
Chuen Road (Open Cut Method)
Activity Noise Source
TM-GW
Reference
Number
Nos.
used
SWL,
dB(A)
% on
time
Effective SWL in
a 30 min period
Overall
SWL
Stage I Earth Works
1.1
Hydraulic breaker CNP 028 1 122 50% 119
120 Excavator / loader CNP 081 1 112 80% 111
Lorry CNP 141 1 112 30% 107
Stage II Trench Support & Ground Compaction
2.1
Vibrating hammer
(piling) CNP 172 1 115 80% 114
115
Roller, vibratory CNP 186 1 108 80% 107
Stage III Pipe-laying
No PME would be needed. Manual working for construction would be adopted.
Stage IV Backfilling
4.1 Backhoe CNP 081 1 112 80% 111
112 Roller, vibratory CNP 186 1 108 60% 106
Stage V Surfacing
5.1
Vibratory poker CNP 170 1 113 80% 112
114 Concrete Lorry
Mixer CNP 044 1 109 100% 109
Construction of Submarine Outfall
4.6.9 The submarine outfall will be constructed by horizontal directional drilling (HDD). An
entry pit will be excavated within sheet piles at the rocky shore for insertion of the
drill head. The drill head will drill into the rock layer below seabed and the tunnel will
be enlarged by pre-reaming. After that, the rising mains will be pulled from the
diffuser installation point back to the entry site. The plant equipment for HDD will be
placed on the rocky shore, which is about 13.2m from the nearest sensitive receiver (a
house). The plant list for HDD method for construction of submarine outfall is shown
in Table 4-13. According to the Ground Investigation results, the rock layer is 10m
below ground. As drilling depth at the launching site is shallower where soft marine
deposits and alluvium are located, no significant groundborne noise is expected from
HDD works.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-11
Table 4-13: Typical PME to be used for Construction of Submarine Outfall (Land-
based Works)
Activity Noise Source
TM-GW
Reference
Number
Nos.
used
SWL,
dB(A) % on time
Overall
SWL
Stage I Plant Setup and Entry Pit Setup
1.1
Vibrating hammer (piling) CNP165 1 115 60% 112.8
Excavator / loader CNP081 1 112 60% 109.8
Concrete Mixer (petrol) CNP046 1 96 50% 93.0
Generator, silenced CNP102 1 100 100% 100.0
Welding and cuting set -- 1 89 30% 83.8
Stage II Pilot Drilling
2.1
Generator, silenced CNP102 1 100 100% 100.0
HDD Drill Rig -- 1 88 80% 87.0
Crane CNP049 1 95 40% 91.0
Mud pump CNP106 1 105 80% 104.0
Agitator CNP005 1 90 80% 89.0
Drilling fluid mixer CNP105 1 90 80% 89.0
Drilling Fluid pump CNP106 1 105 80% 104.0
Bentonite filtering plant CNP162 1 105 100% 105.0
Mud Tanks and recycling unit
(pump) -- 1 104 70% 102.5
Water / mud pump (electric) CNP281 1 88 80% 87.0
Generator (for drilling rig) CNP102 1 100 100% 100.0
Air compressor CNP001 1 100 70% 98.5
Hydraulic power pack CNP174 1 100 100% 100.0
Stage III Pre-Reaming & Cofferdam at Diffuser
3.1
Generator, silenced CNP102 2 100 100% 103.0
HDD Drill Rig -- 1 88 80% 87.0
Crane CNP049 2 95 40% 94.0
Mud pump CNP106 1 105 80% 104.0
Agitator CNP005 1 90 80% 89.0
Drilling fluid mixer CNP105 1 90 80% 89.0
Drilling Fluid pump CNP106 1 105 80% 104.0
Bentonite filtering plant CNP162 1 105 100% 105.0
Mud Tanks and recycling unit
(pump) -- 1 104 70% 102.5
Water / mud pump (electric) CNP281 1 88 80% 87.0
Generator (for drilling rig) CNP102 1 100 100% 100.0
Air compressor CNP001 1 100 70% 98.5
Hydraulic power pack CNP174 1 100 100% 100.0
Welding and cuting set -- 1 89 30% 83.8
Stage IV Pipe Installation & Installation of Diffuser & Removal of Cofferdam
4.1
Generator, silenced CNP102 2 100 100% 103.0
HDD Drill Rig -- 1 88 80% 87.0
Crane CNP049 2 95 40% 94.0
Mud pump CNP106 1 105 80% 104.0
Agitator CNP005 1 90 80% 89.0
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-12
Activity Noise Source
TM-GW
Reference
Number
Nos.
used
SWL,
dB(A) % on time
Overall
SWL
Drilling fluid mixer CNP105 1 90 80% 89.0
Drilling Fluid pump CNP106 1 105 80% 104.0
Bentonite filtering plant CNP162 1 105 100% 105.0
Mud Tanks and recycling unit
(pump) -- 1 104 70% 102.5
Water / mud pump (electric) CNP281 1 88 80% 87.0
Generator (for drilling rig) CNP102 1 100 100% 100.0
Air compressor CNP001 1 100 70% 98.5
Hydraulic power pack CNP174 1 100 100% 100.0
4.6.10 Phases of construction of the works were identified and unmitigated and mitigated
scenarios were assessed for noise impact at the identified NSR.
Prediction of Unmitigated Construction Noise Impact
4.6.11 The impact of construction noise on the identified NSRs was assessed in accordance
with the procedures laid down in Technical Memorandum on Noise from Construction
Work Other Than Percussive Piling. A +3 dB (A) façade correction was added to the
predicted noise levels to account for the façade effect at each NSR. In general, the
noise impact will be the highest when works are being carried out close to the NSRs
and, as the works areas gradually shift away, the noise would tend to diminish.
4.6.12 As a conservative approach to assessing the worst-case construction noise impacts, it
was assumed that all the proposed PMEs for each construction work stage were
operating concurrently. The predicted cumulative worst-case construction noise levels
at the NSRs due to construction of STP, laying of gravity sewer and rising mains on
Po Toi O Chuen Road and in the village, and construction of submarine outfall are
summarized in Table 4-14. Detailed calculations are provided in Appendix 4.1.
Table 4-14: Predicted Worst-case Cumulative Construction Noise Levels at
Representative NSRs - Unmitigated Scenario
NSR Description of NSR
Predicted Worst-case Construction Noise
Level dB(A)
Unmitigated
Results
Noise
Criteria Exceedance
PTO1_N1 Village House in
PTOCR 28 95 75 20
PTO_N2 Village House in
PTOCR 7A 95 75 20
PTO_N3 Temporary Structure
for Living 92 75 17
FV_N1 Fairway Vista House
12 101 75 26
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-13
NSR Description of NSR
Predicted Worst-case Construction Noise
Level dB(A)
Unmitigated
Results
Noise
Criteria Exceedance
SC_N1 Seacrest Villas in
PTOCR No. 64 90 75 15
4.6.13 Based on the effective sound power level of the PMEs and the distance of work site to
the noise sensitive receivers, unmitigated construction noise level for some work
stages were predicted to exceed the EIAO-TM of 75dB(A) guideline level by 15 to 26
dB(A). About 130 residential dwellings and 1 temple will be affected. Various
mitigation options have been considered in accordance with the guidelines laid down
in the Environmental Impact Assessment Ordinance, Guidance Note No. 9/2010
“Preparation of Construction Noise Impact Assessment under the Environmental
Impact Assessment Ordinance” (GN 9/2010) as discussed in Section 4.7.
Operational Noise
4.6.14 During the operational phase, equipment noise from the proposed sewage treatment
plant will be the main noise source with potential noise impact on the NSRs.
4.6.15 The equipment inventory of the Po Toi O STP will be similar to those for small
sewage treatment plants in Hong Kong, and this would include sewage pumps,
ventilation fans, deodourizing fans, mechanically raked fine screen and blower. A
typical equipment inventory based on the design at the time of preparation of this EIA,
is provided in Table 4-15. The inventory and operation modes were confirmed with
the project engineer. The typical Sound Power Levels (SWL) associated with these
equipment items are also provided.
Table 4-15: Typical Noisy Equipment for the Proposed Po Toi O Sewage
Treatment Plant
Location Equipment No. of
Units
Typical
SWL,
dB(A)
Sub-total
SWL,
dB(A)
Preliminary
Treatment Units
Submersible pump (Ref. 1) 2 85 88.0
Mechanically raked fine screen
(Ref. 3) 2 89 92.0
Deodourizing fan (Ref. 4) 2 85 88.0
Exhaust fan (Ref. 2) 1 79 79.0
MBR Equipment
Unit
Mechanically pump (Ref. 5) 3 92 96.8
Deodourizing fan (Ref. 4) 2 85 88.0
Exhaust fan (Ref. 2) 1 79 79.0
Sludge
Treatment Unit
Submersible pump (Ref. 1) 2 85 88.0
Deodourizing fan (Ref. 4) 2 85 88.0
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-14
Location Equipment No. of
Units
Typical
SWL,
dB(A)
Sub-total
SWL,
dB(A)
Exhaust fan (Ref. 2) 1 79 79.0
Air Blower
Room
Blower (Ref. 6) 1 85 85.0
Exhaust fan (Ref. 2) 1 79 79.0
Outfall Pumping
Station and
Header Tank
Mechanical pump (Ref. 5) 4 92 98.0
Deodourizing fan (Ref. 4) 2 85 88.0
Exhaust fan (Ref. 2) 2 79 82.0
Remark: -
SWL – Sound Power Level
Only noisy equipment is included in the table. Other equipment which do not have significant noise
emissions are excluded.
(Ref. 1) SWL referenced to CNP283.
(Ref. 2) SWL referenced to approved EIA of Harbour Area Treatment Scheme (HATS) Stage 2A (EIA-
148/2008) and Good Practices on Ventilation System Noise Control based on the flow rate of
1,300m3/hr.
(Ref. 3) SWL referenced to the approved EIA Report on Tai Po Sewage Treatment Works Stage V
(EIA-097/2004).
(Ref 4) SWL of plant refers to Good Practices on Ventilation System Noise Control based on the flow
rate of 17,000 m3/hr and 125 Pa.
(Ref 5) SWL of plant refer to Good Practices on Pumping System Noise Control based on the
horsepower of pumpset 20 hp at 1800 rpm.
(Ref 6) SWL of plant refers to the tender specification for Shatin STW Stage 3 Upgrading and approved
EIA of Harbour Area Treatment Scheme (HATS) Stage 2A (EIA-148/2008).
4.6.16 Standby equipment would only be used in case of failure or maintenance of duty units.
Therefore, concurrent operation of both duty and standby equipment will not occur
under the normal operation. As a reasonable worst case scenario assessment, the
maximum sound power levels during operation would be under the full operation of
all duty equipment which is given in Table 4-15.
4.6.17 The impact of operational noise on the identified NSRs was assessed in accordance
with the procedures laid down in Technical Memorandum on Noise from Places other
than Domestic Premises, Public Places or Construction Sites. A +3 dB (A) façade
correction was added to the predicted noise levels to account for the façade effect at
each NSR.
4.6.18 All identified noisy equipment items of the STP would be confined inside the building
structure except exhaustion fans. A reduction of 20 dB(A) can be achieved if the
building enclosure is built using suitable material such as concrete with surface density
of 25 kg/m2. Equipment items to be confined within the building structure of
PTOSTW with noise reduction consideration are summarized in Table 4-16.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-15
Table 4-16: Proposed Design Measures For Operation of Po Toi O Sewage
Treatment Plant
Location Equipment Mitigation
Measures
Noise
Reduction
dB(A)
Preliminary
Treatment
Units
Submersible pump Enclosed Inside
Building Structure
-20
Mechanically raked
fine screen
-20
Deodourizing fan -20
Exhaust fan -- 0
MBR
Equipment Unit
Mechanically pump
(Ref. 5)
Enclosed Inside
Building Structure
-20
Deodourizing fan
(Ref. 4)
-20
Exhaust fan (Ref. 2) -- 0
Sludge
Treatment Unit
Submersible pump
(Ref. 1)
Enclosed Inside
Building Structure
-20
Deodourizing fan
(Ref. 4)
-20
Exhaust fan (Ref. 2) -- 0
Air Blower
Room
Blower (Ref. 6) Enclosed Inside
Building Structure
-20
Exhaust fan (Ref. 2) -- 0
Existing Outfall
Pumping
Station and
Header Tank
Mechanical pump
(Ref. 5)
Enclosed Inside
Building Structure
-20
Deodourizing fan
(Ref. 4)
-20
Exhaust fan (Ref. 2) -- 0
4.6.19 The predicted worst-case noise levels at identified NSRs due to the operation of STP
would comply with the noise criteria at all time. The predicted noise levels at
representative NSRs are summarized in Table 4-17 and detailed in Appendix 4.2.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-16
Table 4-17: Predicted Worst-case Operation Noise Levels at Representative NSRs
- Unmitigated Scenario
NSR NSR Description Predicted
Unmitigated
Noise Level,
dB(A)
Day-time
Noise
Criterion,
dB(A)
Night-time
Noise
Criterion,
dB(A)
PTO_N1 Village House in
PTOCR 28 45 49 45
PTO_N2 Village House in
PTOCR 7A 37 49 45
PTO_N3 Temporary Structure
for living 32 49 45
FV_N1 Fairway Vista House
12 32 49 45
SC_N1 Seacrest Villas in
PTOCR No. 64 37 49 45
4.6.20 In fact, typical concrete wall has better noise insulation performance. The assumption
of 20 dB(A) reduction has been conservative. Also, with some of the equipment stored
underground, the noise impact will be further reduced. Furthermore, the acoustic
louvres are designed to face the slope but not the village, avoiding direct view of the
noise source from NSR. The maximum allowable sound power levels of equipment
items would be specified in the tender specification to ensure the operational noise
impact complying with relevant noise criteria.
4.6.21 Most of the noisy equipment items in the sewage treatment plant are fully enclosed
underground or enclosed by concrete structure. With noise reduction due to distance
between the STP and the nearest NSR, no operational noise impact is anticipated and
therefore no mitigation is required.
4.7 Evaluation and Recommendation of Noise Mitigation Measures
Construction Noise
4.7.1 Mitigation at source or path should be the most effective way to reduce the impact.
There are 4 ways in doing that viz. : -
by use of quiet plants and working methods to mitigate at source;
by use of mobile noise barriers/enclosures along the path of noise propagation;
by adopting good site practice to limit noise emissions at source;
by scheduling of work to minimize work scale and duration of impact.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-17
Use of Quiet Plants and Working Methods
4.7.2 Silenced plants or quality powered mechanical equipment (QPME) are quieter than
those noise levels given in TM-GW for the equivalent type of equipment. These
silenced equipment items are known to be available in Hong Kong and hence should
be adopted as far as practical. Table 4-18 shows the possible alternative quieter PME
which are taken from BS:5228: Part 1:2009 or available noise label. These quieter
PMEs are available in the market and have been successfully applied to other projects
and have achieved noticeable noise reductions. The quieter PMEs to be used for the
works shall meet the following SWLs, or lower:
Table 4-18 Quiet PME and Associated Sound Power Level Proposed for the
Project
Description of PME Equivalent Quiet PME SWL, dB(A)
Hydraulic breaker BS5228 Tab. D8-12 106
Excavator / loader EPD-00081 99
Lorry BS5228 Tab. D8-25 96
Vibrating hammer (piling) BS5228 Tab. D4-12 94
Roller, vibratory BS5228 Tab. D3-115 102
Vibratory poker BS5228 Tab. D6-40 98
Backhoe BS5228 Tab. D3-108 97
Breaker, hand held Noise Label NB-0022-13-001 100
Ref:
BS 5228-1:2009. BSI British Standards. Code of practice for noise and vibration control on
construction and open sites – Part 1: Noise
EPD Issued Noise Emission Label:
https://epic.epd.gov.hk/eForm/lic_epd119/lrrf031_list.jsp?epic_lic_no=002030606&a119_or_119_i
nd=A&lang=eng
4.7.3 In addition to use of breaker for breaking up road surface in the village area, drilling
with chemical agent will be considered as far as practicable in the construction phase
according to local situation.
Use of Mobile Noise Barriers/Enclosures
4.7.4 Mobile noise barriers can be effective in screening noise from reaching sensitive
receivers, particularly for the low-rise houses in this case. 3m high mobile barriers
with skid footing and a small cantilevered upper portion can be located within a few
metres of stationary plants and within about 5m of more mobile plant such as
hydraulic breaker. All these PMEs are slow moving or usually stationary when they
are operating and hence the position of the mobile barriers will not need to be
frequently adjusted.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-18
4.7.5 Some sections of gravity sewers and rising mains construction would be aligned close
to the village houses. As the handheld breaker is the noisy PME for excavation work,
it shall be fitted with mufflers to minimize noise emission. A movable enclosure made
up of plywood is proposed to surround both worker and breaker during breaking
process. The internal wall of the enclosure should be laid with sound absorbent such as
mineral wool. Without direct view of the noisy part of the breaker from NSR, this
design can achieve 15dB(A) reduction, which has already taken into account sound
leakage through the gaps. A typical drawing of the enclosure can be found in
Appendix 4-5.
4.7.6 For construction of submarine outfall using HDD, the work area is large enough to
accommodate semi-enclosure. It should enclose the stationary plant equipment on
three sides with cover. Only the side facing the sea shall be opened for heat
exhaustion.
Schedule of Work
4.7.7 As the footpath between village houses is very narrow, pipe laying in close proximity
of the NSRs cannot be avoided. Construction work will be divided into short sections
(10m) to reduce the duration of localized work (about one month per workfront).
Three workfronts will progress at the same time. Each workfront should be separated
from each other by at least 100m to minimize cumulative effect.
4.7.8 During laying of gravity sewers and rising mains near NSRs PTO_N1 and PTO_N3,
major concurrent noisy activities are laying of Po Toi O Chuen Road sewer and
horizontal directional drilling (HDD) respectively. The 10m workfront of gravity
sewers and rising mains installation near the two NSRs shall be scheduled at different
times from these noisy activities to minimize cumulative noise impact.
4.7.9 As the prevailing noise level in restricted hours is lower than daytime (averaged 50 –
51 dB(A) vs 57 - 59 dB(A) based on baseline monitoring), construction works will be
carried out in daytime to avoid nuisance during evening and night time.
Adoption of Good Site Practice
4.7.10 Good site practice and noise management can significantly reduce the impact of a
construction site’s activities on nearby NSRs. Although the reduction in noise level is
not readily predictable and quantified, the following measures should be useful during
each phase of construction:
Only well-maintained plant should be operated on-site and plant should be
serviced regularly during the construction programme;
Machines that may be in intermittent use should be shut down between work
periods or should be throttled down to a minimum;
Silencer and mufflers on construction equipment should be utilised and should
be properly maintained during the construction programme;
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-19
Noisy activities can be scheduled to minimise exposure of nearby NSRs to
high levels of construction noise. For example, noisy activities can be
scheduled for midday. Avoid carrying out noisy activities at the same time;
For the installation of gravity sewers and rising mains near residence, hand-
held breaker may be used to break the hard concrete layer. The manual
equipment should be used as far as practicable to avoid using the PME. If
found necessary, the percentage on time should be limited to reduce continuous
contributions;
Plant known to emit noise strongly in one direction should, wherever possible,
be orientated so that the noise is directed away from the nearby NSRs;
Mobile plant should be sited as far away from NSRs as possible; and
Material stockpiles and other structures should be effectively utilised, wherever
practicable, in screening noise from on-site construction activities.
4.7.11 During excavation works for gravity sewers and rising mains installation, generator
and breaker will be operated at the same time. Generator should be placed at a fixed
location and screened by noise barrier. It should be at least 5-6m away from the NSRs
whenever excavation work has to be carried out at their front doors (calculations in
Appendix 4.3 refers). These measures can minimize the noise contribution from the
generator and the total sound power level at NSRs.
4.7.12 Only one vibratory poker is proposed for surfacing work after pipe laying. To further
minimize noise nuisance, vibratory poker will only be operated 4m away from NSR
and with noise barrier properly erected. This can reduce the construction noise level at
the NSR to 75B(A) as shown in Appendix 4.3 (NSRs PTO_N1 & FV_N1). Surfacing
work within 4m from NSR will be carried out by manual method.
4.7.13 “Recommended Pollution Control Clauses for Construction Contracts” is available on
EPD website. It contains the recommended noise pollution control measures to be
implemented by the contractor during the construction stage. The predicted noise
levels are summarized in Table 4-19. Detailed calculations are provided in Appendix
4.3.
Table 4-19: Predicted Cumulative Construction Noise Levels at Representative
NSRs - Mitigated Scenario
NSR Description of
NSR
Predicted Worst-case Construction Noise
Level dB(A)
Mitigated
Results
Noise
Criteria Exceedance
PTO1_N1 Village House in
PTOCR 28 75 75 -
PTO_N2 Village House in
PTOCR 7A 75 75 -
PTO_N3 Temporary
Structure for living 74 75 -
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-20
NSR Description of
NSR
Predicted Worst-case Construction Noise
Level dB(A)
Mitigated
Results
Noise
Criteria Exceedance
FV_N1 Fairway Vista
House 12 75 75 -
SC_N1 Seacrest Villas in
PTOCR No. 64 71 75 -
4.7.14 With the adoption of quiet PMEs and temporary barrier/enclosure/semi-enclosure, no
construction noise exceedance is expected. When the works areas gradually shifted
away, the noise would tend to diminish.
Cumulative Noise Impact Due to Concurrent Project
4.7.15 The following discusses the potential cumulative interface issues between concurrent
projects as indicated in Chapter 2 – Project Description. There may be two potential
concurrent projects in the area, i.e.
Roundabout near the minibus stop
Fish culture zone (FCZ) dredging and relocation
4.7.16 During the course of the study, CEDD has confirmed that there was no programme for
the fish culture zone dredging and relocation. There was also no information on when
the roundabout would be constructed. Therefore, no cumulative noise impact is
expected.
4.7.17 Should there be concurrent project in the vicinity, continuous discussion between
contractors shall be conducted to plan the location and programme of construction
work to minimize cumulative impact.
4.8 Evaluation of Residual Impacts
4.8.1 After implementation of mitigation measures as mentioned in Section 4.7,
construction noise impact on NSRs would comply with the daytime noise guideline
75dB(A). Upon completion of the sewage treatment plant, noisy plant equipment will
be operated within the building structure or underground. The fixed equipment noise
will comply with the daytime/evening time and nighttime noise criteria. Therefore, no
residual noise impact is expected in both construction and operational phases.
Drainage Services Department Agreement No. CE 41/2013 (EP)
Port Shelter Sewerage, Stage 3 – Sewerage Works at Po Toi O
Environmental Impact Assessment Studies - Investigation
Environmental Impact Assessment Report
IA13070/EIARpt v2.3 Cinotech 4-21
4.9 Environmental Monitoring and Audit Requirements
4.9.1 With the implementation of proposed construction noise mitigation measures such as
use of quality powered mechanical equipment (QPME), use of mobile noise barriers,
enclosure and semi-enclosure, good site practice and management, and construction
noise monitoring and audit programme, construction noise impact could be reduced
down to acceptable levels. Regular monitoring of noise level should be carried out at
noise monitoring stations near representative sensitive receivers before and throughout
construction work to ensure that relevant noise standard can be met.
4.9.2 Since the noisy equipment items in the sewage treatment plant are fully enclosed
underground or enclosed by concrete structure, operational noise impact is expected to
be acceptable. Operational noise monitoring is considered unnecessary.
4.9.3 General EM&A requirements were presented in Chapter 12.
4.10 Conclusion
4.10.1 Construction noise arising from typical types and numbers of powered mechanical
equipment items (PME) for the construction of sewage treatment plant, rising
mains/sewer installation and submarine outfall have been assessed. Based on the
effective sound power levels of the PMEs and the notional noise distances to the noise
sensitive receivers, unmitigated construction noise levels would exceed the 75dB(A)
guideline level for the non-restricted hours for all NSRs. At source mitigation
measures have been proposed including the use of quality plants, use of mobile noise
barriers, semi-enclosure, enclosure, strategic work scheduling and good site practice.
With the proposed mitigation measures, no construction noise exceedance is expected.
4.10.2 Most of the noisy equipment items in the sewage treatment plant would be fully
underground or enclosed by concrete structure. With noise reduction due to distance
between the STP and the nearest NSR, operational noise impact is anticipated to be
acceptable.