    INTRODUCTION

    Offer tendering and construction site are very important

    themes for every engineer. Without understanding these

    terms and process, a lot of problems will occur such as :

    why we didnt get this project? Why the other company or

    designers are getting the jobs and not us?

    This kind of questions can be answered if the designer (

    engineer ) learns the realtion between designing and

    winning in tender.

    Without the tenderation there are no projects, which means

    that designers will have no jobs to do.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    3/24

    TENDER OFFER FROM THE CLIENT'S AND

    ARCHITECT'S PERSPECTIVE

    Perception of the stages of a construction project oftenvaries between the client/architect and the contractor.

    Client and architect are involved in the project for monthsbefore the actual construction work commences, for acontractor however stages of the project include only thetender offer and construction stages.

    Tender procedure, from clientsand architectspoint of view,is regulated by NJCC (National Joint ConsultativeCommittee for Building).

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    4/24

    TENDER OFFER FROM THE CLIENT'S AND

    ARCHITECT'S PERSPECTIVE

    Most small projects apply the "Single Stage Selective

    Tenderingwhich can be characterized in the following way:

    Invitation to tenderthe contractors are contacted if they would be

    willing to tender. The enquiry is issued in writing 4-6 weeks beforethe tender and it should contain a brief description of the investment

    and the commencement date.

    Number of contractors tendering recommended maximum

    number of contractors is 6, with additional in reserve. The limitationis due to the fact, that the tenders tend to be expensive and it is

    irresponsible to unnecessarily inflate prices in the construction

    industry.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    5/24

    TENDER OFFER FROM THE CLIENT'S AND

    ARCHITECT'S PERSPECTIVE

    Tender documentation the aim of tender documentation all offers

    will be presented on the same basis, so the competition may only be

    about the price. It is assumed that each contractor will complete

    works in a way specified in documentation.

    Time to prepare tender offer in smaller projects it is usually 3-4

    weeks, in bigger and more complex investments it can take longer.

    Changes in tender documentationcontractors should not make any

    changes. They should instead send an enquiry min. 10 days before

    the tender date. Architect should send a reply to all contractors to

    provide them all the same chances.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    6/24

    TENDER OFFER FROM THE CLIENT'S AND

    ARCHITECT'S PERSPECTIVE

    It is often disregarded in practice, due to the short time

    allowed to prepare an estimate or vagueness.

    Withdrawal of the offer tender offer can be withdrawn by the

    contractor at all times, as long as it has not been chosen by theinvestor. Acceptance of an offer constitutes an agreement between

    the investor and contractor.

    Tender offers analysistender offers should be analyzed soon after

    they were returned. After the contract is awarded architect should

    inform all participants about the offers received, without naming the

    companies, which put them forward. Even though it gives contractors

    an insight into competitors pricing policy, it is often disregarded.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    7/24

    TENDER OFFER FROM THE CLIENT'S AND

    ARCHITECT'S PERSPECTIVE

    Error check the winning estimate is checked and the erroneous

    calculations are sent back to the contractor. There are two

    procedures to resolve those: "Alternative 1" where the contractor

    can confirm or withdraw the offer and "Alternative 2" - where the

    contractor can confirm the offer or correct mistakes.

    Price negotiation procedures allow pricing negotiations leading to

    lowering the prices if the lowest offer exceeds investorsbudget.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    8/24

    BASICS OF COST ESTIMATE PREPARATION

    Preparation of tender offer requires various documentation

    types, as specified by an architect or an investor. They

    involve different terms of settlement and risk.

    Regardless of the type of documentation one should take

    into account costs not directly connected with corresponding

    construction works, e.g. cost of the toilet, on-site safety,

    company standing costs etc. Those costs are usuallyincluded in the "Preliminaries", at the beginning of the

    estimate.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    9/24

    SPECIFICATION & DRAWINGS

    This type of documentation contains drawings and

    specification; it can also contain a separate scope of works

    to clarify the full costs.

    Contractor is responsible for surveying the works. Any errors

    in measurements and cost estimates will not be taken into

    consideration and the contractor will be required to conduct

    all the works indicated in the documentation, regardless of

    whether they are specified by the scope of work. It meansthat contractor needs to check all documentation carefully,

    since each its element included in any part of

    documentation constitutes part of contract and needs to be

    completed.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    10/24

    BILL OF QUANTITIES

    In case of bigger projects, tender documents often consist of

    "Bill of Quantities" (BoQ). It is a list of all required works

    (with all measurements already made) the contractor

    needs to provide their rates for each of the works.

    BoQ is prepared by "Quantity Surveyor" employed by the

    investor, according to Standard Method of Measurement -

    SMM.

    The latest version is SMM7, but the smaller project still often

    use.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    11/24

    BILL OF QUANTITIES

    The rates given in BoQ will be used to calculate the cost

    of additional works of the same type during the project,

    it is therefore worth to try to foresee potential additional

    works and raise the rate for the corresponding type of

    works.

    The errors in the BoQ are the liability of the investor the

    contractor needs to be paid for all works required, even if

    they are erroneous or if some works are omitted. Becauseof that BoQ is not used often anymore.

    If the investor cannot state exact measurements, the

    approximate quantities are applied.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    12/24

    SCHEDULE OF RATES

    "Schedule of Rates" is the list of the rates and its used veryrarely, only in case if the scope of work is impossible to define.

    The contractor is accountable for completed works according to

    the time and agreed hourly or daily rates.

    It is of course an ideal basis for cooperation from contractor'spoint of view, because they are not at any risk and all thematerials and employees working time is being paid for.

    In case of such cooperation form it is crucial to keep a detailedrecord of time and resources spent during the project. Those arenecessary to establish the payment and eliminate potentialconflicts between contractor and investor.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    13/24

    SCHEDULING AND PLANNING CONSTRUCTION

    WORKS

    Without proper planning it is difficult to make a constructionproject run smoothly and be completed on time and withinbudget. Of course, smaller and less complex projects very oftendo not have a formulated formal plan or schedule, since allplanning takes place in managershead.

    It is an acceptable solution, however everyones perception hasits limits, and in most cases it is impossible to manage all aspectsof a months-long project without the use of additional tools. Themain reasons for planning in construction works can be summedup as:

    Improved management of works and resources, their sequence andconsequences of any changes that may take place

    Ability to establish a realistic completion date

    Improved efficiency control

    Facilitated risk assessment process of the project

    Basis for solving contractual claims resulting from delays

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    14/24

    SCHEDULING AND PLANNING CONSTRUCTION

    WORKS

    Appropriate schedule of works allows to establish

    completion dates for all stages and elements of works, e.g.

    when will the electrician be needed, when will the garden

    door be installed, floor panels delivered etc. Of course,

    scheduling is not about planning works a week in advancethis can be done by every skilled worker.

    A correctly designed work schedule allows such information

    to be provided months in advance. Such information oftenproves crucial, especially when orders have to be made

    long before the delivery.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    15/24

    PLANNING TECHNIQUES

    The only technique commonly applied in small and middle

    sized projects is Gantt chart" or "Bar chart (both names

    refer to the same method).

    Other techniques (arrow diagrams, precedence diagrams,line of balance, time-chainage diagrams) are only applied to

    large projects, often involving infrastructural works. Please

    contact us for further information about these methods.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    16/24

    GANTT CHART

    Gantt or Bar chart is the easiest available planningtechnique, and probably the only one commonly understoodwithout prior training. Despite its simplicity, a correctlydesigned chart will provide a lot of information necessary to

    complete the project.

    Each line on the chart indicates a task or group of tasksnecessary in the project. The length of a bar is relative tothe time necessary to carry out a task.

    Individual tasks stand in dynamic dependency relationshipsthat reflect the order of completion. This allows for a fastcheck of how, e.g. a delay of task A will influence the

    completion of task C, taking place 2 months later.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    17/24

    GANTT CHART

    Appropriately prepared chart indicates the critical tasks, i.e.

    the ones that determine the timely completion of the entire

    project. These form a "critical path". This allows for more

    attention to be given to the most important tasks.

    Each task can be assigned necessary resources, workers,

    equipment and material, which facilitates the procedures of

    placing orders and workforce management.

    Additionally, the chart may include, or be the basis for a

    detailed analysis of financial flow in the project and risk

    management.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    18/24

    GANTT CHART

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    19/24

    TYPES OF SCHEDULES

    Schedules can be classified depending on the type and precision of

    information provided.

    Master program : It is a general project plan, which does not include

    any details, and only shows the main stages of works. It is mainly useful

    for the clients and architects supervising the completion time. The

    master program must be provided to architect by the contractor.

    Detailed program : It is an expansion of a master program, which

    includes all activities and details of works completion. It is used by thecontractor to manage works and resources. Usually it is not passed on

    to client or architect. Due to the large amount of information it contains,

    the detailed program is often prepared to only embrace a specific period

    of time (e.g. 1 or 2 weeks of works).

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    20/24

    TYPES OF SCHEDULES

    Purchase Schedule : Additional schedules are created as

    necessary by filtering the data included in Detailed

    program. The most popular is "the purchase schedule",

    which indicates the deadlines for making orders. All data is

    dynamically related, and therefore if the installation ofwindows, which have to be ordered 4 weeks in advance, is

    delayed, the schedule will automatically suggest new order

    date.

    Using schedules greatly facilitates site management and

    reduces risk of making a mistake or missing out important

    tasks.

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    21/24

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    22/24

    RISK MANAGEMENT

    Using planning software makes it possible to expand thefunctions of schedules to include project risk management. Easyscenarios analysis processes allow preparation of many variantsof project, e.g. what will the consequences of a delay for aparticular task be and how to deal with them. This kind of

    theoretical analysis allows better understanding the mechanismsbehind the project and preparing alternative plans, shouldproblems emerge.

    Risk analysis can be summed up with the following:

    Hazard identification ( Identification of dangerous things ) Probability and consequences estimate

    Deciding on risk management method (avoidance, reduction, sharingand retention)

    Management and supervision

    Conclusion and report

  • 8/13/2019 4 Offer Tendering Site 120413102124 Phpapp02

    23/24

    PROBLEMS WITH SCHEDULES

    Planning and schedules are not problem-free and, as it happens, their

    benefits are not fully used.

    One must bear in mind that schedule is a dynamical tool which needs to

    be regularly updated in order to serve us most efficiently. Every

    construction plan is appropriate only until the project has started. It can

    be often seen, that our plans do not reflect reality, in which case the plan

    must be updated, otherwise it will lose its adequacy.

    Plan is only as good as the person who created it. Software is only a

    tool, not a magical solution to all our problems. If the project deadline we

    set is not realistic, there is no plan which will make completion on time

    possible.