4 resettlement policy framework final - world bank...project management no. 6 resettlement policy...

30
PROJECT MANAGEMENT NO. 6 RESETTLEMENT POLICY FRAMEWORK 1 RURAL TRANSPORT PROJECT NO.3 RESETTLEMENT POLICY FRAMEWORK UPDATED FOR ADDITIONAL FINANCING PROJECT Final October,2011 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 25-Jan-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 1

    RURAL TRANSPORT PROJECT NO.3

    RESETTLEMENT POLICY FRAMEWORK UPDATED FOR ADDITIONAL FINANCING PROJECT

    Final

    October,2011

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    Pub

    lic D

    iscl

    osur

    e A

    utho

    rized

    wb406484Typewritten TextRP1183 v5

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 2

    1. Introduction

    The Third Rural Transport Project (RT3) includes rehabilitation and improvement of rural

    district, commune roads in 33 provinces in Vietnam, through the use of low-cost

    engineering techniques and spot improvements. The project will be planned, designed and

    implemented in a phased fashion.

    The project is being implemented by Ministry of Transport (MoT) through its Project

    Management Unit No. 6 (PMU6) which is working with counterparts in Provincial

    Departments of Transport (PDOTs), each of which had established a Provincial Project

    Management Unit (PPMU) for the project.

    The project will be implemented in phases between 2005 and 2010. The first phase

    includes the preparation of documents for four pilot provinces and 100 km of road

    rehabilitation and will be followed by phases based on annual work programs. The second

    phase will include approximately 1,500 km in 16 provinces.

    To meet the requirements of World Bank’s OP 4.12 Involuntary Resettlement policy, this

    Project Framework has been developed. The Policy Framework has been applied to the

    plans prepared for the four pilot provinces and will be applied to all future resettlement

    plans to be prepared in the 33 provinces for roads to be upgraded under the project.

    2. Legal Framework

    2.1 Laws regarding land acquisition in Vietnam

    The main laws and decisions regarding land acquisition include:

    The Land Law No. 13/2003/QH11 (December 2003);1

    Decree No. 181/2004/ND-CP (October 2004) on guiding the implementation of the Land

    Law;

    Decree No. 197/2004/ND-CP (December 2004) on compensation, assistance and

    resettlement when the State recovers land;

    Circular 116/2004/TT-BTC (December 2004) on guiding the implementation of Decree

    197;

    Decree No. 188/2004/ND-CP (November 2004) on methods for determining land process

    for various types of land; and

    Circular 114 /2004/TT-BTC (November 2004) on guiding the implementation of Decree

    188;

    Decree No 69/2009/ND-CP (August 13, 2009) to amend a number of provisions on land

    use planning, land rental rates, land reclamation, and resettlement and compensation.

    Circular 14/2009/TT-BTNMT (October 01,/2009) on detailed compensation , assistance

    and resettlement, process and regulations of land acquisition, land allocation, land lease

    management ( be effective from November, 16, 2009)

    The Land Law 2003 is a comprehensive law that establishes the regulations of land

    allocation, lease management, land acquisition for development purposes, changes of

    land value under market mechanisms, and gives people access to land through land-user

    rights via land use right certificates (LURCs), which are similar to private ownership. In

    essence the law allows the State to recover land in cases of national defence or security,

    1 The latest version updates and supersedes the 1993 and 1987 versions, it was approved in December 2003 and came into

    effect on July 1st 2004.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 3

    or national and public interest. In these cases, under Article 27, the land user will be

    compensated for loss of land or assets2.

    The new Decree 197 go a long way to closing the gaps that previously existed between

    Government’s and standards required under the World Bank policy on involuntary

    resettlement (OP 4.12). However, still there are some gaps between national policies and

    OP 4.12 of the World Bank and waivers of a number of articles of the Land Law and

    Decrees will be required to ensure that the World Bank’s policy is complied with. Such

    waivers of Vietnamese law and decrees are provided for under both Decree 197 and

    Decree 17/ND-CP (May 2001), which regulates the management and use of official

    development assistance. Under Decree 197, Article 1 (2) states that in the case where

    Viet Nam has signed an agreement for official development aid and the agreement or

    treaty contains regulations that are different from the regulations provided in the decree,

    then the regulations of the agreement or treaty shall be applied. While under Decree 17,

    Article 29 stipulates that where an international aid agreement has provisions that are

    inconsistent with the provisions of Viet Nam law, the provisions of the official

    development assistance agreement shall prevail.

    2.2 The World Bank Policy on Resettlement and Waivers Required

    As noted above, the new Land Law and Decrees have come a substantial way in closing

    the gaps between Government and the World Bank requirements in respect of

    resettlement, but there are still differences between the Vietnamese requirements as set

    out in the Land Law and new Decree and World Bank’s Policy OP 4.12. The key

    differences are:

    The ‘significance’ of impact is triggered by a loss of 30 per cent or more of agricultural

    land in Decree 197, in OP 4.12 the trigger is a loss of 10 per cent or more of productive

    land/assets.

    Decree 197 recognizes non-legal users or users without papers or documents ONLY if

    they have been using the land to be affected by a project in a stable manner since PRIOR

    to 15th

    October 1993;

    Land Law and Decree 197 provide for deductions from both land and assets

    compensation in a number of circumstances;

    Houses and structures will not be compensated if they have been constructed without

    permission, constructed in contravention of a land use plan, or if they have encroached

    upon a demarcated safety protection corridor;

    Houses and structures will only be compensated to 80 per cent of their value or

    compensation rate if they have been built on land that is ineligible for compensation;

    Decree 197 recognizes businesses or economic entities as PAPs only if they hold a

    business certificate (i.e. excludes non-registered businesses);

    Decree 197 recognizes PAPs losing employment only on a permanent basis (i.e. if they

    are made redundant) and only if the PAP has an employment contract and is employed by

    a business or economic entity holding a business certificate;

    Systems of machinery and production lines will only be compensated to the value of

    dismantling, transporting and re-installation. The Decree does not include any

    compensation for income lost or foregone associated with the impact;

    2 “National and public interest" is defined as including infrastructure projects.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 4

    Under Decree 197, assistance for occupational change and job creation is only provided

    to PAPs engaged directly in agricultural production and in cases where more than 30 per

    cent of their agricultural land is affected;

    The requirements for consultation in the Land Law and Decree 197 are limited to

    “informing” PAPs rather than providing information and seeking feedback from those

    directly affected; and

    Decree 198 on the price frame for lands limits the upper prices for land and thus in some

    cases land will not be compensated at the replacement cost.

    2.3. Project Policy Framework

    2.3.1. Basic Principles

    The Policy Framework is prepared based on relevant Government laws and decrees and

    World Bank policy OP 4.12 on involuntary resettlement.

    The principle objective of the framework is to ensure that, under the project, all PAP's will

    be compensated for their losses sufficient to replace their losses and provided with

    rehabilitation measures to assist them to improve, or at least maintain, their pre-project

    living standards and income earning capacity.

    The project policy framework lays down the principles and procedures that will guide the

    compensation, resettlement and rehabilitation of PAPs.

    2.3.2. Project Policies

    The following policies will be applied to the project to ensure that the principles and

    objectives stated above will be met:

    1. Acquisition of land and other assets, and resettlement of people will be minimized as much as possible;

    2. All PAPs residing, working, doing business or cultivating land in the right-of-way of the roads of the project as of the date of the detailed measurement

    survey (DMS) and who are affected are entitled to be provided with

    rehabilitation measures sufficient to assist them to improve, or at least

    maintain, their pre-project living standards, income earning capacity and

    production levels;

    3. Lack of legal rights to assets lost will not bar PAPs from entitlement to such rehabilitation measures;

    4. Replacement residential and productive land will be as nearby as possible to the land that was lost, and acceptable to the PAPs;

    5. Assistance for severely affected PAPs will be provided under the project to assist these PAPs to at least restore, if not improve, their standards of living;

    6. Plans for acquisition of land and other assets and provision of rehabilitation measures will be carried out in consultation with the PAPs, to ensure minimal

    disturbance. Entitlements will be provided to PAPs prior to expected start-up

    of works at the respective subproject sites;

    7. Any acquisition of, or restriction of access to, resources owned or managed by the affected community as a common property should be mitigated by

    arrangement ensuring access to improved or at least restored resources or

    access;

    8. Financial and physical resources for resettlement and rehabilitation will be made available and as where and when required; and

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 5

    9. Monitoring and evaluation of the implementation of the plan will be carried out.

    2.3.3. Project Affected People

    The PAPs include the following persons (individual, institution), affected by the project

    as identified in the inventory of losses (IOL) and DMS:

    Persons whose houses or other structures and/or residential land are affected;

    Persons whose agricultural land or structures (i.e. rice bins) are affected;

    Persons whose commercial land and/or structures are affected;

    Persons whose crops (annual and perennial) and trees are affected;

    Persons whose fishpond or any other land is affected;

    Persons who temporarily or permanently lose employment ;

    Persons who are affected through impacts upon community property resources and land

    (including infrastructure and services); and

    Persons who are affected through loss of, or impacts upon, non-productive assets such as

    wells, graves and shrines etc.

    The whole community that temporarily or permanently loses i.e. places for community

    gathering, worship places, access to ponds etc.

    Criteria for Eligibility

    The cut-off date for eligibility for entitlement is when the DMS is completed. Persons

    who encroach on the area after the cut-off-date are not entitled to compensation or any

    other form of resettlement assistance.

    PAPs eligible for compensation under the project will include:

    (a) Those that have formal legal rights to land or other assets;

    (b) those who initially do not have formal legal rights to land or other assets but

    have a claim to legal rights based upon the laws of the country; upon the

    possession of documents such as land tax receipts and residence certificates;

    or upon the permission of local authorities to occupy or use the project

    affected plots; and

    (c) Those who have no recognizable legal right or claim to the land they are

    occupying.

    Persons occupying an area required for the project prior to the cut-off date and covered

    under (a) and (b) are provided compensation for the land and assets they lose, and are

    also entitled to other assistance.

    Persons occupying an area required for the project prior to the cut-off date and covered

    under (c) are provided for compensation for structures, crops or trees, and resettlement

    assistance - in lieu of compensation for the land they occupy - and other assistance, as

    necessary, to achieve the objectives set out in the policy framework.

    Persons who encroach on the area after the cut-off date as defined in this plan are not

    entitled to compensation or any other form of resettlement assistance.

    2.3.4. Project Impacts & Entitlement

    Based on the type of impacts expected to be created by the project, PAPs will be entitled to

    the following types of rehabilitation and assistance measures:

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 6

    1. Loss of productive land and crops (including fishponds and fish crops)

    a. Land that is temporarily taken for works by the project (for a period of one year or less) will be rented from the PAP; compensation for any loss of income, standing

    crops, and for the cost of soil restoration and repair of any damaged infrastructure.

    Land will be fully rehabilitated and hand back to the PAP after subproject

    construction. If the project requires the land for more than one year the PAP will

    have the choice to either continue the rental agreement or to sell the land to the

    project at replacement cost;

    b. For PAPs with LURCs or legalizable rights to land use or using land in a stable manner that such land is dispute free- if the land lost is LESS THAN twenty-five

    per cent of the total area of the landholding, and the remaining land is still a

    viable economic holding, cash compensation, at full replacement cost for the

    acquired area will be provided to the PAP. If the land lost is EQUAL or MORE

    THAN twenty-five per cent and/or LESS THAN twenty-five per cent of the total

    area of the landholding and the remaining holding is NOT viable, then the project

    will acquire the entire landholding and provide as a priority land-for-land (land of

    equal productive capacity and satisfactory to the PAP, if compensated land of

    lower productive capacity, cash balance for different values of land types).

    However, if the PAP prefers to receive cash instead of land or land is not

    available, and then cash compensation at replacement cost is applied and PAP is

    entitled to a restoration package. For PAPs with lease rights or temporary land use

    rights - Cash compensation for loss of net income for the remaining leased or

    assigned period, whichever is higher. For the PAP using land assigned by State-

    owned agricultural or forestry farms or public land of community on a contractual

    basis for use for agricultural, forestry, aquaculture purposes shall be compensated

    only for remaining expenses invested in land, but not for land. However, the PAP

    would be assisted with the highest level of support shall be equal to the price of

    land to be recovered.

    c. For PAPs who do not meet the conditions for compensation prescribed above, the People’s Committees of competent levels shall assign them new land as suitable

    to the local conditions Landless PAPs will not be displaced until they have been

    allocated other land; and

    d. For all PAPs, regardless of status of rights to use the land, compensation for loss of standing crops will be at market price based on the highest crop production

    during the three previous years, productive trees will be compensated at

    replacement cost for their size, age and productive capacity. PAPs have the right

    to salvage trees without any deduction in value of compensation.

    2. Loss of residential land and houses (or other structures)

    a. Land that is temporarily taken for works by the project (for a period of one year or less) will be compensated for loss of any crops or trees, and for the cost of

    restoration and/or repair of any damaged structures. Land will be fully

    rehabilitated after subproject construction;

    b. If the land is partially affected and the remaining area is SUFFICIENT for reorganizing (i.e. not less than 60 m

    2 in urban areas and 100 m

    2 in

    rural areas

    ) and

    the house or structure is not, or only partially, affected (the affected area does not

    impact upon remaining structure), compensation for loss of land will be cash

    compensation at replacement cost, and cash compensation at full replacement cost

    for house and structures affected, WITHOUT deduction for depreciation or

    deductions for salvaged materials or compensation in kind (materials), according

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 7

    to PAPs choice, and cash compensation for any other assets, trees or crops

    affected;

    c. If the land lost renders the remaining area INSUFFICIENT for reorganizing (i.e. less than 60 m

    2 in urban areas and 100 m

    2 in

    rural areas and/or more than 60 m

    2 in

    urban areas and 100 m2

    in rural areas), the PAPs have their choices to (i)

    compensation for loss of land will be either provision of replacement residential

    land (house site and garden) of equivalent size and satisfactory to the PAP or cash

    compensation at replacement cost, and cash compensation at full replacement cost

    for house and structures affected, WITHOUT deduction for depreciation or

    deductions for salvaged materials or compensation in kind (materials), according

    to PAPs choice, and cash compensation for any trees or crops affected; The

    unaffected area will be handed over to local authorities; (ii) to rebuild house on

    the remaining areas and cash compensation for the affected part. PAPs will be

    exempt from fees for issuance of LURCs for the new land or these fees (if

    required) will be included in the compensation package for land;

    d. Tenants, who have leased a house for residential purposes will be not be compensated for land or the house or structure.. The PAP will be compensated

    for any improvements, renovations, or upgrades they have made to either the land

    or the structure, and will also be entitled to rent a house, for the same rental price,

    in the resettlement area. If a house is not available in the resettlement area, the

    PAP will be assisted to find alternative accommodation for themselves through

    cash assistance equal to 60 per cent of the value of the rented property (land and

    house); and

    e. All relocating PAPs, including tenants, will be provided with a relocation allowance (transportation assistance for removal and relocation) as set out in 6 i.

    f. When land lying with safety corridors is not recovered by the project, compensation shall be paid for damage caused by the restricted usability of such

    land.

    3. Loss of business or employment

    a. For businesses that are registered and will be affected on a temporary basis (i.e. business can re-establish on same site), compensation will be cash compensation

    for affected part of commercial structure at full replacement cost, without

    depreciation; and cash compensation for the loss of income for the period for

    which the business can not operate (i.e. during the rebuilding period) or a

    maximum of three months;

    b. For businesses that are not registered and will be affected on a temporary basis (i.e. business can re-establish on same site), compensation will be cash

    compensation for affected part of commercial structure at full replacement cost,

    without depreciation; and cash compensation to the value of 80 per cent of lost

    income for the period for which the business can not operate (i.e. during the

    rebuilding period) or a maximum of three months;

    c. For businesses that are registered and will experience a permanent loss of business (i.e. business has to discontinue or relocate to another site) will be

    provision of alternative business site of equal size and accessibility to customers,

    satisfactory to the PAP; cash compensation for lost commercial structure at full

    replacement cost, without depreciation; for business that can re-establish at

    another site cash compensation for loss of income for the period the business can

    not operate (is rebuilding) or for businesses that can not re-establish at another

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 8

    site cash compensation for the loss of six months’ income; and assistance for

    occupational change and job creation if required;

    d. For businesses that are not registered and will experience a permanent loss of business (i.e. business has to discontinue or relocate to another site) will be

    provision of alternative business site of equal size and accessibility to customers,

    satisfactory to the PAP; cash compensation for lost commercial structure at full

    replacement cost, without depreciation; for business that can re-establish at

    another site cash compensation to the value of 80 per cent of lost income for the

    period the business can not operate (is rebuilding) or for businesses that can not

    re-establish at another site cash compensation to the value of 80 per cent of the

    loss of six months’ income; and restoration package ; and

    e. Compensation for temporary or permanent loss of employment will be the cash equivalent of the PAP’s wages for the period of discontinuity of the business or

    production, up to a maximum of six months.

    4. Loss of other fixed assets

    Compensation at full replacement cost, without deduction for depreciation and or

    deduction for any salvaged materials for any other fixed assets (such as tombs, water

    wells, hand pumps etc) affected by the project.

    5. Loss of community property

    Restoration or repair, as the case may be, by PPMU, at NO COST to the community,

    of any community infrastructure [such as schools, water sources (including pipes and

    wells), roads and tracks, sewage systems etc] damaged by the project.

    6. Livelihood restoration package

    Besides direct compensation for the losses, PAPs will also be entitled to additional

    assistance (allowances and other measures) for livelihood restoration as stipulated in

    Decree 197 and this Policy Framework. These include:

    Relocation/transportation allowance - according to Article 27 of Decree 197, all PAPs

    moving away from their original residence but relocating within the province are

    entitled to a maximum allowance of 3 million VND and all PAPs relocating beyond

    the province are entitled to a maximum allowance of 5 million VND. This allowance

    is for the transportation of their household contents, salvaged materials and any other

    living facilities;

    Restoration package (livelihood and production stabilization allowance) - according

    to Article 20 (i) of Decree 69, all PAPs that are either relocating or experience

    significant impacts on their productive land shall receive a cash allowance equivalent

    to 30 kg of rice per family member per month for a period of six months if they are

    not relocating and for a period of twelve months if they are relocating. If PAP has to

    be relocated to a place of difficult socio-economic conditions this subsidy will be

    extended to a period of two years. In the cases that PAPs losing over 70 percent of

    productive land, they should receive a cash allowance equivalent to 30 kg of rice per

    family member per month for a period of twelve months if they are not relocating and

    for a period of twenty four months if they are relocating. .If PAP has to be relocated

    to a place of difficult socio-economic conditions this subsidy will be extended to a

    period of three years.

    Restoration package for PAPs with businesses severely affected (i.e. can not re-

    establish at the same site) will receive a cash allowance equivalent to 30 kg of rice per

    family member per month for a period of three months if they are not relocating and

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 9

    for a period of six months if they are relocating, and assistance for training and

    alternative employment;

    Assistance for occupational change – according to Article 22 of Decree 69, all PAPs

    of working age that are engaged in agricultural, or similar, production and experience

    significant impacts on their productive land shall receive assistance to attend

    vocational training centers for a change in occupation; and

    Special assistance for poor and vulnerable PAPs - all poor and vulnerable PAPs shall

    receive a cash allowance equivalent to 30 kg of rice per family member per month for

    a period of six months. If the PAP household is both poor and severely affected they

    shall receive only one package. Other assistance can be provided on a case-by-case

    basis.

    The project entitlement matrix is included as Table 2.1.

    2.4. Timing of Compensation Payment

    The PAPs will receive compensation for crops, trees and partially affected land and

    houses ONE month prior to land clearance.

    The PAPs will receive compensation for fully affected land and houses THREE months

    prior to land clearance.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 10

    Table 2.1 – RT3 Entitlement Matrix

    No Type of Impact Application Entitled PAPs Compensation Policy Implementation Issues

    1. Productive land

    i

    Temporary acquisition (i.e.

    less than one year)

    All PAPs that

    are using land or

    have trees, crops,

    or any other

    assets affected

    by the project

    PAPs with LURC or

    able to prove claim

    for land prior to cut-

    off date and included

    in the inventory

    Compensation for the area of land required

    by the project as rent paid to the PAP; AND

    Cash compensation for affected trees and

    structures at replacement cost, and crops at

    market price based on total yield (for all

    harvests per year) from affected area in three

    previous years; AND

    Full rehabilitation of land after project

    construction to pre-project conditions and

    productive capacity.

    Full compensation at least ONE month before land clearance.

    Local authorities to determine, and ensure that, compensation for

    trees will be at replacement cost, and for crops at market price.

    Affected land in right-of-way will be rehabilitated by contractors

    after the project construction and land in right-of-way could be used

    with the restricted purposes.

    If use likely to continue for more than one year PAP has the choice of

    continuing the arrangement or selling the land to the project at full

    replacement cost.

    ii

    Permanent acquisition of

    LESS THAN 25 per cent of

    total productive landholding

    All PAPs

    occupying land

    and properties

    associated with

    land to be

    permanently

    acquired by the

    project

    PAPs with LURC or

    able to prove claim

    for land prior to cut-

    off date and included

    in the inventory

    Cash compensation for the area acquired at

    replacement cost if the remaining plot is still

    economically viable; AND

    Compensation for trees and crops at market

    value and affected structures at replacement

    cost.

    Consultation with PAPs about options for land compensation. PAPs

    will be granted with LURC to replacement land without payment of

    administrative or other fees.

    PPMU and CARB to determine and ensure that compensation will be

    at replacement cost at the time of decision on land recovery if no

    longer than one year has elapsed.

    Full compensation for crops, trees and any other properties associate

    with the land at least ONE month before land clearance. PAP has

    right to use/replant salvageable trees.

    PAPs with lease or

    temporary rights to

    land use or able to

    prove land

    occupancy prior to

    cut-off date and

    included in the

    inventory

    Cash compensation for loss of net income for

    the remaining leased or assigned period;

    AND

    Compensation for trees and crops at market

    value and affected structures at replacement

    cost.

    Cash assistance in addition to compensation to cover losses of

    property associated with land and compensation for lost income will

    ensure that PAPs that are leasing land will not be worse off.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 11

    No Type of Impact Application Entitled PAPs Compensation Policy Implementation Issues

    PAPs without title or

    LURC or able to

    prove land

    occupancy prior to

    cut-off date (without

    dispute) included in

    the inventory

    No compensation for land but entitled to cash

    compensation for loss of standing crops and

    trees at market prices.

    Landless PAPs will not be displaced until they have been allocated

    other land.

    PPMU and CARB to determine and ensure that compensation will be

    at replacement cost at the time of payment.

    Full compensation for crops, trees and any other properties associate

    with the land at least ONE month before land clearance. PAP has

    right to use/replant salvageable trees.

    iii

    Permanent acquisition of 25

    per cent or MORE and/or

    LESS THAN 25 per cent of

    total productive landholding

    and remaining holding is not

    viable

    All PAPs

    occupying land

    and properties

    associated with

    land to be

    permanently

    acquired by the

    project

    PAPs with LURC or

    able to prove claim to

    land prior to cut-off

    date (without

    dispute)

    If the landholding is still economically viable

    the PAP can opt for one of the following:

    Land for land for the area to be acquired and

    of similar productive capacity to the

    satisfaction of PAP; if compensated land of

    lower productive capacity, cash balance for

    different values of land types) OR If land is

    not available, cash compensation at

    replacement cost for the area to be acquired;

    AND

    Compensation for trees and crops at market

    value and affected structures at replacement

    cost.

    If the landholding is no longer economically

    viable:

    As a priority, land for land of the same

    productive capacity as land to be acquired, in

    a location to the satisfaction of PAP; OR

    Cash compensation at replacement cost for

    the total landholding; AND

    Compensation for trees and crops at market

    value and affected structures at replacement

    cost; AND

    Assistance [refer to item 6]

    Consultation for PAP’s options on land compensation. Identification

    of replacement land suitable to PAPs. PAPs will be granted LURC to

    replacement land without payment of administrative or other fees.

    PPMU and CARB to determine and ensure that compensation will be

    at replacement cost at the time of payment.

    Full compensation for trees and fruit trees to PAPs at least ONE

    month before land clearance. PAP has right to use/replant salvageable

    trees.

    For severely affected PAPs when there is no land available for

    compensation, PPMU and CARB to consult with PAPs who are

    eligible for assistance or other measures to discuss options and

    prepare proposal for livelihood restoration program in the period of

    RP implementation. Clear inform the PAP in advance at least 90 days

    prior to time of land acquisition for the project.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 12

    No Type of Impact Application Entitled PAPs Compensation Policy Implementation Issues

    PAPs with lease or

    temporary rights to

    land use or able to

    prove land

    occupancy prior to

    cut-off date and

    included in the

    inventory. The PAP

    using land assigned

    by State-owned

    agricultural or

    forestry farms or

    public land of

    community on a

    contractual basis for

    use for agricultural,

    forestry, aquaculture

    purposes

    Lease rights to land for the area to be

    acquired and of similar productive capacity

    to the satisfaction of PAP; OR If land is not

    available, cash compensation for 30 per cent

    of replacement cost for the area to be

    acquired or cash compensation for loss of net

    income form the area affected for the

    remaining leased or assigned period; AND

    If the land is not longer viable - as a priority,

    lease rights to land for land of the same area

    and productive capacity as land to be

    acquired, in a location to the satisfaction of

    PAP; The PAP would be assisted with the

    highest level of support shall be equal to the

    price of land to be recovered.

    OR If land is not available - cash

    compensation for loss of net income for the

    remaining leased or assigned period; AND

    Compensation for trees and crops at market

    value and affected structures at replacement

    cost; AND

    Assistance for economic restoration [refer to

    item 6]

    Consultation for PAP’s options on land compensation. Identification

    of replacement land suitable to PAPs. PAPs are not liable for

    administrative or other fees.

    For severely affected PAPs when there is no land available for

    compensation, PPMU and CARB to consult with PAPs who are

    eligible for assistance or other measures to discuss options and

    prepare proposal for livelihood restoration program in the period of

    RP implementation.

    iv

    Land lying with safety

    corridors is not recovered by

    the project.

    All PAPs

    occupying land

    and properties

    associated with

    land to be

    permanently

    acquired by the

    project

    -do-

    PAPs without title or

    LURC included in

    the inventory

    No compensation for land but entitled to cash

    compensation for loss of standing crops and

    trees at market prices ; AND

    Subsistence allowance and rehabilitation

    measures will be provided.

    Compensation shall be paid for damage

    caused by the restricted usability of such

    land.

    Consultation for PAP’s options on land compensation. Identification

    of replacement land suitable to PAPs. PAPs will be granted LURC to

    replacement land without payment of administrative or other fees.

    Landless PAPs will not be displaced until they have been allocated

    other land.

    For severely affected PAPs when there is no land available for

    compensation, PPMU and CARB to consult with PAPs who are

    eligible for assistance or other measures to discuss options and

    prepare proposal for livelihood restoration program in the period of

    RP implementation.

    Full compensation for crops, trees and any other properties associate

    with the land at least ONE month before land clearance. PAP has

    right to use/replant salvageable trees.

    2. Residential (including garden) land

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 13

    No Type of Impact Application Entitled PAPs Compensation Policy Implementation Issues

    i

    Temporary acquisition (i.e.

    less than one year)

    All PAPs that

    are using land or

    have trees, crops,

    or any other

    assets affected

    by the project

    PAPs with LURC or

    able to prove claim to

    land prior to cut-off

    date and included in

    the inventory

    Cash compensation for area of land required

    by the project paid as rent to the PAP; AND

    Cash compensation for affected trees and

    structures at replacement cost, and crops at

    market price based on yield from affected

    area in three previous years; AND

    Full rehabilitation of land after project

    construction to pre-project conditions.

    Full compensation to PAPs at least ONE month before land

    clearance. Affected land in right-of-way will be rehabilitated by

    contractors after project construction.

    If use likely to continue for more than one year PAP has the choice of

    continuing the arrangement or selling the land to the project at full

    replacement cost.

    ii

    Permanent acquisition and

    remaining land

    SUFFICIENT for

    reorganizing (i.e. is not less

    than 60 m2 in urban areas

    and 100 m2 in rural areas)

    and no, or partial, effect on

    house or structure (i.e.

    affected area does NOT

    affect remaining house or

    structure)

    All PAPs living

    or residing in

    area affected by

    the project

    PAPs with LURC or

    able to prove claim to

    land prior to cut-off

    date and included in

    the inventory

    Cash compensation for area of land acquired

    at replacement cost; AND

    Compensation, in cash or kind, for directly

    affected area of structure at replacement cost

    without deduction for salvageable materials;

    AND

    Any trees or crops affected to be

    compensated at market price.

    Demolition of house & structures regulated by Article 8 of Decree

    54/1999/ND-CP. Full compensation to PAPs for affected part of

    house or structure at least THREE months before land clearance. PAP

    has right to any salvageable materials.

    PAPs will be responsible for clearing the required area and

    reconstructing houses themselves.

    PPMU and CARB to determine and ensure that compensation will be

    at replacement cost at the time of payment.

    Full compensation for trees and crops at least ONE month before land

    clearance. PAP has right to salvageable trees.

    PAPs without title or

    LURC included in

    the inventory

    No compensation for land.

    Compensation, in cash or kind, for directly

    affected area of structure at replacement cost

    without deduction for salvageable materials;

    AND Any trees or crops affected to be

    compensated at market price.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 14

    No Type of Impact Application Entitled PAPs Compensation Policy Implementation Issues

    Permanent acquisition and

    remaining land is

    INSUFFICIENT for

    reorganizing (i.e. less than

    60 m2 in urban areas and 100

    m2 in rural areas and/or

    more than 60 m2 in urban

    areas and 100 m2 in rural

    areas)

    All PAPs living

    or residing in

    area affected by

    the project

    PAPs with LURC or

    able to prove claim to

    land prior to cut-off

    date and included in

    the inventory

    The PAPs have their choices to (i)

    compensation for loss of land will be either

    provision of replacement residential land

    (house site and garden) of equivalent size and

    satisfactory to the PAP or cash compensation

    at replacement cost, and cash compensation

    at full replacement cost for house and

    structures affected, WITHOUT deduction for

    depreciation or deductions for salvaged

    materials or compensation in kind

    (materials), according to PAPs choice, and

    cash compensation for any trees or crops

    affected; The unaffected area will be handed

    over to local authorities; (ii) to rebuild

    house on the remaining areas and cash

    compensation for the affected part. PAPs

    will be exempt from fees for issuance of

    LURCs for the new land or these fees (if

    required) will be included in the

    compensation package for land;

    Demolition of house & structures regulated by Article 8 of Decree

    54/1999/ND-CP. Full compensation to PAPs for affected part of

    house or structure at least THREE months before land clearance. PAP

    has right to any salvageable materials.

    PAPs will be responsible for clearing the required area and

    reconstructing houses themselves.

    PPMU and CARB to determine and ensure that compensation will be

    at replacement cost at the time of payment.

    Full compensation for trees and crops at least ONE month before land

    clearance. PAP has right to salvageable trees. Clear inform the PAP

    in advance at least 180 days prior to time of land acquisition for the

    project. Inform PAP about detail planning of relocation site

    development.

    iii

    Permanent acquisition and

    remaining land is

    INSUFFICIENT for

    reorganizing (i.e. less than

    60 m2 in urban areas and 100

    m2 in rural areas and/or

    more than 60 m2 in urban

    areas and 100 m2 in rural

    areas)

    All PAPs living

    or residing in

    area affected by

    the project

    PAPs with formal or

    informal rental

    agreement

    Compensation only if PAP has paid rent in

    advance, compensation will be cash for the

    amount of rent paid; AND

    Compensation for improvements,

    renovations, or upgrades made to land or the

    structure; AND

    Entitled to rent a house, for same rental price,

    in resettlement area; or assistance to find

    accommodation for themselves equivalent to

    60 per cent of the value of the rented

    property; AND

    Assistance for relocation [refer item 6].

    Owner of land or structure to agree improvements or renovations

    have been made. PPC to determine value of improvements,

    renovations, or upgrades on a case by case basis.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 15

    No Type of Impact Application Entitled PAPs Compensation Policy Implementation Issues

    iv

    Permanent acquisition and

    remaining land is

    INSUFFICIENT for

    reorganizing (i.e. less than

    60 m2 in urban areas and 100

    m2 in rural areas and/or

    more than 60 m2 in urban

    areas and 100 m2 in rural

    areas)

    All PAPs living

    or residing in

    area affected by

    the project

    PAPs are not eligible

    to land compensation

    as described above

    or able to prove land

    occupancy prior to

    cut-off date included

    in the inventory

    No compensation for land. PAP to be

    assisted in locating new residential plot;

    AND

    Compensation, in cash or kind, for directly

    affected area of structure at replacement cost

    without deduction for salvageable materials;

    AND

    Any trees or crops affected to be

    compensated at market price; AND

    Assistance [refer to item 6].

    Demolition of house & structures regulated by Article 8 of Decree

    54/1999/ND-CP. Full compensation to PAPs for house or structure at

    least FIVE months before land clearance.

    Replacement land, and resettlement sites developed to PAPs wishes

    i.e. relocation as community or self-relocation.

    PPMU and CARB to determine and ensure that compensation will be

    at replacement cost at the time of payment.

    Full compensation payment for trees and fruit trees to PAPs at least

    ONE month before land clearance. PAP has right for using

    salvageable trees.

    3. Loss of business or employment

    i

    Temporary effects on

    business (i.e. business can

    re-establish at same location)

    All PAPs

    experiencing

    impacts on

    business and

    production

    PAPs with business

    certificate or who are

    registered

    Cash compensation for affected part of

    commercial structure at replacement cost,

    without depreciation; AND compensation for

    loss of income during rebuilding period or

    for maximum of three months.

    Full compensation for affected structure and incomes to PAPs at least

    ONE month before land clearance.

    Unregistered PAPs or

    PAPs without

    business certificate

    Cash compensation for affected part of

    commercial structure at full replacement

    cost, without depreciation; AND

    Cash compensation for 80% of the value of

    loss of income during the rebuilding period

    or for maximum of three months.

    Full compensation for affected structure and incomes to PAPs at least

    ONE month before land clearance

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 16

    No Type of Impact Application Entitled PAPs Compensation Policy Implementation Issues

    ii

    Permanent effects on

    business (i.e. business has to

    discontinue or relocate to

    another site)

    All PAPs

    experiencing

    impacts on

    business and

    production

    PAPs with business

    certificate or who are

    registered

    Provision of alternative business site of equal

    size and accessibility to customers,

    satisfactory to the PAP; AND

    Cash compensation for lost commercial

    structure at full replacement cost, without

    depreciation; AND

    For business that can re-establish at another

    site cash compensation for loss of income for

    the period the business can not operate (i.e.

    period is rebuilding to a maximum of six

    months) or for businesses that can not re-

    establish at another site cash compensation

    for the loss of six months’ income; and

    assistance for occupational change and job

    creation if; AND

    Assistance [refer to item 6]

    Full compensation for affected structure and incomes to PAPs at least

    FIVE months before land clearance.

    PPMU and CARB to consult with PAPs who are eligible for

    assistance or other measures to discuss options and prepare proposal

    for livelihood restoration program in the period of RP

    implementation.

    PAPs with businesses that can not be re-established entitled to

    assistance including training and/or alternative employment.

    Unregistered PAPs or

    PAPs without

    business certificate

    Provision of alternative business site of equal

    size and accessibility to customers,

    satisfactory to the PAP; AND

    Cash compensation for lost commercial

    structure at full replacement cost, without

    depreciation; AND

    For business that can re-establish at another

    site cash compensation to the value of 80%

    of loss of income for the period the business

    can not operate (i.e. period is rebuilding to a

    maximum of six months) or for businesses

    that can not re-establish at another site cash

    compensation to the value of 80% of loss of

    six months’ income; and assistance for

    occupational change and job creation if;

    AND

    Assistance [refer to item 6]

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 17

    No Type of Impact Application Entitled PAPs Compensation Policy Implementation Issues

    iii

    Loss of employment All PAPs

    experiencing

    impacts on

    business and

    production

    PAPs with or

    without an

    employment contract

    with a business (with

    or without business

    certificate)

    Compensation equivalent of the PAP’s wages

    for the period of discontinuity of the business

    or production, up to a maximum of six

    months; AND

    Assistance [refer to item 6]

    Assistance for occupational change and job creation to be included in

    overall livelihood restoration program in the period of RP

    implementation.

    4. Loss of other fixed assets

    i

    Any other impacts on fixed

    assets owned or used by

    PAPs

    All PAPs that

    have any other

    assets in right-

    of-way

    PAPs with/without

    LURC included in

    the inventory or able

    to prove land

    occupancy prior to

    cut-off date

    Compensation at full replacement cost,

    without deduction for depreciation and or

    deduction for any salvaged materials

    Any other fixed assets (such as tombs, water wells, hand pumps etc)

    affected in part or in total by the project.

    5. Community property

    i

    Any other impacts on

    resources or assets held in

    public or community

    ownership or use

    Any other assets

    or community

    property affected

    by the project

    Restoration or repair, as the case may be, by

    PPMU, at NO COST to the community.

    Includes restoration of any land temporarily used, and repair to any

    community infrastructure [such as schools, water sources (including

    pipes and wells), roads and tracks, sewage systems etc] damaged by

    the project.

    6. Restoration package

    i

    Relocation or physical

    displacement

    All relocating

    PAPs

    PAPs included in the

    inventory

    PAPs moving away from their original

    residence but relocating within the province

    are entitled to a maximum allowance of 3

    million VND and all PAPs relocating beyond

    the province are entitled to a maximum

    allowance of 5 million VND.

    Allowance is for the transportation of their household contents,

    salvaged materials and any other living facilities, specific amount to

    be decided by PPC.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 18

    No Type of Impact Application Entitled PAPs Compensation Policy Implementation Issues

    ii

    Significant impacts on

    livelihood

    All relocating

    PAPs and PAPs

    losing more than

    25 per cent of

    productive land

    Severely affected

    PAPs

    In the case that

    PAPs losing over 70

    percent of

    productive land:

    Cash allowance equivalent to 30 kg of rice

    per family member per month for a period of

    six months if they are not relocating and for a

    period of twelve months if they are

    relocating. . If PAP has to be relocated to a

    place of difficult socio-economic conditions

    this subsidy will be extended to a period of

    two years.

    Cash allowance equivalent to 30 kg of rice

    per family member per month for a period of

    twelve months if they are not relocating and

    for a period of twenty four months if they

    are relocating... If PAP has to be relocated to

    a place of difficult socio-economic

    conditions this subsidy will be extended to a

    period of three years.

    Apply the article 20 of the Decree No 69/2009/ND-CP (August 13,

    2009)

    PPC has discretion to extend length of assistance up to one year if

    PAP has to be relocated to a place of difficult socio-economic

    conditions

    iii

    Significant impacts on

    livelihood

    PAPs losing

    business or

    production

    activities

    Severely affected

    PAPs who can not re-

    establish business

    PAPs that have to discontinue their business

    or production will receive assistance equal to

    a maximum of 30 per cent of one year’s

    revenue (based on the average revenue of the

    three preceding years after taxation)

    As provided for in Decree 197 specific rate of assistance to be

    stipulated by PPC and consistent with conditions of the locality.

    Assistance to be in addition to compensation for commercial structure

    and lost income.

    iv

    Significant impacts on

    livelihood

    PAPs losing

    business or more

    than 25 per cent

    of productive

    land

    Severely affected

    PAPs of working age

    Severely affected

    PAPs of working age

    can not receive

    productive land as a

    compensation

    Assistance for occupational change provided

    through training at vocational centers or other

    measures.

    For a change in occupation, PAPs can be

    received one assistance among two:i) cash

    allowance equivalent to whole productive

    land acquisition at the rate high as 1.5-5

    times of productive land price and total of

    land acquisition cannot be over the volume of

    productive land stipulated by local

    government; OR ii) an assistance by a

    portion of residential land or an apartment or

    a portion of un-agricultural –business land.

    The second assistance can be applied in the

    locations that have land fund and the

    assistance is over or equal to valuation of a

    portion of residential land/ an apartment / or

    un-agricultural –business land

    Measures to be discussed with PAPs.

    Specific rate of assistance and numbers of people to whom it shall

    apply to be stipulated by PPC and consistent with conditions of the

    locality.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 19

    No Type of Impact Application Entitled PAPs Compensation Policy Implementation Issues

    v

    Special assistance PAPs affected by

    the project

    Poor and vulnerable

    PAPs

    Cash allowance equivalent to 30 kg of rice

    per family member per month for a period of

    six months

    Assistance in identifying poor and vulnerable PAPs and ensuring

    only receive one assistance package.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 20

    3. Institutional Framework

    3.1. Project Management Unit No.6 (PMU6)

    MoT through PMU6 at national level, and PPMUs as a specific department of PDOT at

    provincial level, are responsible for the over-all planning, implementation and

    coordination of the project including resettlement and land acquisition activities. PMU6

    has assigned some fourteen staff to oversee RT3 implementation, two of whom are

    responsible for land acquisition and resettlement planning and will provide technical

    assistance, support, guidance and capacity building related to resettlement and land

    acquisition activities to PPMUs as required.

    PMU6 assisted by national resettlement specialists, will assist, support and supervise

    PPMUs in the preparation, implementation and monitoring of all resettlement plans.

    PMU6 will establish an internal and external monitoring and evaluation system.

    3.2. Provincial Project Management Units (PPMU)

    The PPMUs are required to assign at least two staff who shall be responsible for

    implementation of safeguards, of which at least one staff will be primarily responsible for

    the preparation and implementation of resettlement and social development activities. The

    resettlement officer will oversee the smooth and effective implementation of resettlement,

    compensation and rehabilitation measures and activities and will work closely with

    concerned districts and Compensation, Assistance & Resettlement Boards (CARBs) and

    provide support and guidance to the districts and communes.

    The main responsibilities of PPMU resettlement officer is to:

    • Undertake the screening of all roads proposed in each AWP and submit to PMU6 the list of roads requiring land acquisition;

    • Guide and assist the CARB in the undertaking of the IOL, DMS and support for the appraisal and verification of rates used for compensation;

    • Prepare the annual resettlement plans and compensation plans for each annual works programs (AWP);

    • Implement and monitor land acquisition and resettlement;

    • Coordinate with the provincial and district Land Administration Department related to land allocation and land use rights issues;

    • Coordinate all land acquisition and resettlement activities with construction activities according to the implementation schedule;

    • Establish proper PAP databases for each subproject;

    • Continue and maintain effective consultation with affected households and communities; and

    • Submit regular (quarterly) progress reports to PMU6 on land acquisition, civil works, construction and related activities.

    3.3. Responsibilities of People’s Committees

    3.3.1. Provincial People’s Committee

    In general the PPC will entrust the implementation of compensation, assistance, and

    resettlement to the CARB and the Land Bank Development Organization. However, as

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 21

    set out in Article 43 (1) of Decree 197, the PPC has the following main responsibilities

    for resettlement planning and implementation:

    Instruct agencies, departments and CPC to (i) develop resettlement areas if required by

    land acquisition; and (ii) devise schemes for compensation, assistance and resettlement in

    accordance with their power;

    Approve or authorize the DPC to approve compensation, assistance and resettlement

    schemes;

    Approve land prices, release a land and asset price table for the calculation of

    compensation each year and revise if required for a specific project, specify rates and

    measures of additional assistance for livelihood rehabilitation, resettlement arrangement

    schemes, and any schemes required for training for PAPs who have to change jobs; and

    If required, establish an Appraisal Board chaired by the Manager of the Department of

    Finance (DoF) for appraisal of compensation and resettlement arrangements (refer to

    Section 3.3.1).

    3.3.2. District People’s Committee

    Under Article 43 (2) of Decree 197, the DPC has the following responsibilities:

    Instruct, organize, make notifications, mobilize organizations and individuals on

    compensation, assistance, resettlement and site clearance that conforms with the relevant

    policies;

    Instruct the CARB at the same level to organize the implementation of compensation,

    assistance and resettlement schemes. Implement the approval of compensation, assistance

    and resettlement schemes as authorized by the PPC;

    Work in collaboration with departments, organizations and agencies and project owners

    to implement projects, and implement the plans and schemes for resettlement areas when

    they are required and authorized by the PPC; and

    Deal with complaints and grievances from PAPs concerning compensation, assistance

    and resettlement; and

    Coordinate with any other departments with functions relevant to implementation of land

    acquisition and resettlement activities.

    3.3.3. Commune People’s Committee

    Under Article 43 (3) of Decree 197, the responsibilities of the CPCs include:

    Organizing consultations and public information about land acquisition, policies of

    compensation, assistance and resettlement of projects;

    Work in collaboration with the CARB to conduct the inventory that will identify PAPs

    and their affected land and property; and

    Co-ordinate with PPMU and CARB to organize the payment of compensation,

    implementation of measures for assistance, support and assist with resettlement

    arrangements for PAPs required relocating and enabling site clearance.

    3.4. District Compensation, Assistance and Resettlement Boards

    The CARBs assist the People’s Committees of the same level to implement

    compensation, assistance and resettlement. The CARB, at district level, will be chaired by

    the chairman or deputy chairman of the DPC and will include; a representative of Finance

    Department as Deputy Chairman of CARB; the project developer – as a standing

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 22

    member; a representative of Department of Natural Resources and Environment

    (DONRE) as a member; a representative of the CPC from where the land is recovered as

    a member; representatives of PAP households, as well as any other members to be

    decided by the Chairman of the CARB in accordance with the actual situations and

    localities.

    According to Article 40 (2) the members of CARBs are responsible for the following:

    The chairman instructs members of the CARB to submit for approval, and then

    implement the schemes for compensation, assistance, and resettlement arrangement.

    Project developers have responsibilities to help the CARB’s chairman prepare the

    schemes for compensation, assistance and resettlement, and to ensure sufficient

    expenditure to pay compensation, assistance and development resettlement sites in a

    timely manner; and

    Overall, the CARB is responsible for the accuracy of the statistics and figures, the

    legitimacy of land and properties eligible for compensation, and implementation of

    schemes for compensation, assistance, and resettlement.

    3.5. Responsibilities of Provincial Government Departments

    3.5.1. Department of Finance

    The DoF is responsible for the following tasks:

    Chair, and collaborate with, relevant agencies to submit to PPC for approval the land and

    property prices and table to calculation compensation, rates of assistance, measures of

    assistance and resettlement at localities to submit to the PPC for decisions;

    Working with other relevant agencies, chair the appraisal of compensation schemes; and

    Examine the payment of compensation and any assistance, and costs for the

    implementation of compensation, assistance and resettlement at localities.

    3.5.2. Department of Natural Resources & Environment

    DONRE is responsible for:

    Guide the identification of land areas, categories of land, types and conditions of land in

    order to assist in determining the eligibility for compensation;

    Guide the identification of users of land in order to assist in determining the eligibility for

    compensation and assistance for each PAP; and

    Coordinate with Department of Planning and Investment (DPI), Department of

    Construction (DoC) to submit to PPC the decisions on the scale of land acquisition.

    3.5.3. Department of Planning & Investment

    Responsibilities of the Department of Planning and Investment (DPI) include guiding and

    inspecting the implementation of resettlement under the various regulations and law on

    management of investment construction.

    The DPI is also responsible for guiding and examining the planning of resettlement and

    monitoring the implementation of resettlement.

    3.6. Responsibilities of Various Groups during Compensation Payment

    For payment of compensation the PPMUs and CARBs will:

    Inform PAPs regarding payment schedule at least two weeks in advance;

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 23

    Prepare the list of PAPs and their corresponding entitlements and payment;

    Prepare three copies of all compensation forms/documents (copies for PAPs, CARB, and

    PPMU); and

    Submit quarterly progress reports to PMU6 attaching the list of PAPs and signed

    compensation forms documents for proper monitoring.

    Each PPMU’s resettlement officer will:

    Witness payment process based on the schedule made by PPMU and CARB;

    Encourage various representatives (Women’s Union and/or Farmer’s Association) to

    witness the compensation payment process;

    Ensure that PAP is aware of his/her rights and entitlements, and document grievances if

    there are any;

    Sign as witness to the compensation activity, and get copies of all compensation forms

    made; and

    Update PMU the computerized data base.

    4. Process For Resettlement Plan Preparation

    A resettlement plan will be prepared for AWP for the roads that require land acquisition.

    The resettlement plans for the four pilot provinces prepared prior to loan appraisal of the

    project and will be updated following detailed engineering. Annual resettlement plans of

    each province for all other subprojects will be prepared by PPMU based on this policy

    framework and submitted to the project team of IDA at least three months prior to

    beginning of coming years for its review and concurrent.

    4.1. Resettlement Tools

    The following are the main resettlement tools for the project:

    1. Resettlement policy;

    2. Annual Resettlement Plan - (either abbreviated or full) refer to Section 4.5; and

    3. The Policy Framework and resettlement will be approved by the Prime Minister.

    Resettlement plans prepared for the pilot provinces will be reviewed and cleared by

    IDA and approve by Government prior to loan negotiation. For all subsequent road

    subprojects, the annual resettlement plan will be prepared by PPMU and submitted

    to PMU6 and will be approved by PPC and MoT without prior review of the

    World Bank. Implementing agency needs to provide evidences showing their

    adequate institutional capacity to review resettlement plans and ensure their

    consistency with the World Bank’s policies. All draft and official version of these

    documents must be submitted to World Bank for disclosure as required and for

    random check. Implementation of the resettlement plans is subject to ex post

    review by the Bank and the independent monitoring organization

    4.2. Resettlement Screening

    During the annual planning, and selection of roads for the AWP, the PPMU resettlement

    staff will complete a screening, along with the engineers. The purpose of the screening is

    three-fold; one is to explore measures to minimize impacts, the second is to determine

    what type of resettlement plan is required, and the last is to propose a timetable for

    resettlement planning. The screening criteria for the roads in each AWP are:

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 24

    No resettlement effect – roads will not require temporary or permanent land acquisition,

    and there are no impacts involving the loss of land, structures, crops and trees, businesses

    or income. No resettlement plan is required but the PPMU shall submit the letter of

    confirmation; or

    MINOR impacts i.e. where no households have to be relocated (physically displaced),

    where no households lose more than 25% of their productive land or less than 200

    persons are affected by land acquisition the annual resettlement plan will be an

    abbreviated resettlement plan; or

    SIGNIFICANT impacts i.e. where households have to be relocated (physically

    displaced), where households lose more than 25% of their productive land or where more

    than 200 persons are affected by land acquisition the annual resettlement plan will be a

    full resettlement plan.

    The PPMUs, with cooperation from CPCs and CARBs will carry out plan preparation

    based on a census and inventory of affected assets for all PAPs, as well as a sample socio-

    economic baseline survey of at least 20 per cent of PAPs in cases where a FULL

    resettlement plan is required:

    For the four pilot provinces the resettlement plans prepared prior to project appraisal will

    be updated based on a DMS following detailed engineering design;

    For subsequent subprojects resettlement plans will be prepared based on the IOL

    following preliminary design and will be updated as a compensation plan based on

    detailed engineering design. The compensation plan will be the DMS and updated cost

    estimate or budget; and

    The socio-economic survey will be carried out following a review of the IOL when the

    scale of impacts are known and only be for severely affected PAPs.

    4.3 Inventory of Losses & Detailed Measurement Survey

    The IOL is undertaken based on preliminary design and serves to provide an estimate of

    land acquisition in terms of impacts and costs on which to base preparation of the

    resettlement plan. The DMS is based on detailed design and usually follows demarcation

    of the actual extent of works on the ground, and will be used to prepare the compensation

    plan.

    4.4. Socio-Economic Survey of Severely Affected PAPs

    For AWPs that require a FULL resettlement plan (i.e. PAPs require relocation, more than

    200 persons affected by land acquisition, or PAPs will lose more than 25 per cent of their

    productive land or assets), additional information is required from severely affected

    PAPs. The PPMU with support from CARBs will conduct a socio-economic survey of

    PAPs (Form 8.4). At a minimum, the survey will collect data from a sample of 20 per

    cent of severely affected people and be disaggregated by gender, ethnicity if applicable,

    and type of loss.

    The scope of data to be collected includes:

    • Household head: name, sex, age, livelihood or occupation, income, education and ethnicity;

    • Household members: number, employment status, school age children and school attendance, and literacy, disaggregated by gender;

    • Living conditions: access to water, sanitation and energy for cooking and lighting; Ownership of durable goods;

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 25

    • Tenure, ownership and use of land and other assets; and

    • Sources of household income: primary and secondary sources of household income; household member(s) responsible for primary source of income; total household

    income; and, whether affected land is primary source of income.

    4.5. Preparation of Resettlement Plans

    In parallel with the preparation of the abbreviated or full annual resettlement plan, the

    PPMU and CARBs will continue consultations with PAPs to identify their preferences

    and special needs, and incorporate such provisions in the plans. In addition, information

    on market prices for land, crops, structures and other assets collected through an appraisal

    to verify the PPC rates will enable resettlement cost estimates.

    An abbreviated annual RP will cover all roads requiring land acquisition in the AWP and

    include:

    1. A census survey, inventory of losses and valuation of assets (indicating numbers of households losing assets by type);

    2. Description of compensation and resettlement assistance to be provided;

    3. Consultations with PAPs about options and alternatives;

    4. Institutional responsibility for implementation (organizational responsibilities and structure), procedures for grievance redress, arrangements for monitoring

    and implementation; and

    5. A timetable (implementation schedule) and budget (cost estimate).

    A full annual RP will cover all roads in the AWP requiring land acquisition and include:

    • Executive summary;

    • Introduction to the project and description of socio-economic characteristics of PAPs (based on survey);

    • A census survey, inventory of losses indicating numbers of households losing assets by type;

    • Legal framework and entitlements that apply to the subprojects in the AWP;

    • Institutional responsibility for implementation (organizational responsibilities and structure) and procedures for grievance redress;

    • Consultations with PAPs about options and alternatives;

    • Compensation, assistance and resettlement (income restoration strategies);

    • Implementation timing, schedule and arrangements for monitoring; and

    • Budget and cost estimate (including valuation of assets and compensation amounts for all types of losses).

    Following the detailed design, the PPMUs will update the annual RPs and submit them as

    compensation plans. The compensation plans will consist only of (i) updated inventory

    based on the DMS; and (ii) updated budget and cost estimate.

    4.6. Public Disclosure

    (i) Draft Policy Framework and draft resettlement plans to be disclosed prior to

    the appraisal mission. The draft documents will be disclosed in accessible

    places including commune offices, PPMU offices and Viet Nam Development

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 26

    Information Centre in Ha Noi, and will be in a form, manner and language

    understandable to PAPs and stakeholders;

    (ii) The final Policy Framework and plans i.e. as approved by Government and

    cleared by World Bank (IDA) prior to loan negotiation will be disclosed in

    accessible places including commune offices, PPMU offices and Viet Nam

    Development Information Centre in Ha Noi and in a form, manner and

    language understandable to PAPs and stakeholders;

    (iii) Distribution of a Public Information Booklet (PIB) in Vietnamese and, as

    required, ethnic minority language(s); and

    (iv) Disclosure of all approved documents in places that are publicly available,

    including in the Viet Nam Development Information Centre in Ha Noi.

    5. Public Consultation, Participation & Grievance Redressal

    The consultative process will include not only PAPs, but also representatives of local

    governments in the subproject areas, community leaders of host communities, civil

    society organizations such as NGOs and members of local people’s organizations (e.g.,

    Women’s Union, Fatherland Front, Youth Union and Farmer’s Association). Special

    attention will be paid to identifying the needs of vulnerable groups such as the poor,

    ethnic minorities, women, children and elderly, and ensure that their views are considered

    in the formulation of the resettlement plan. Requirements on consultation depend on the

    magnitude and nature of land acquisition impacts.

    5.1. Consultation during Resettlement Plan Preparation

    Consultation during plan preparation will include distribution of project information

    through various media (announcements through loudspeaker system, meetings, and

    leaflets). Specific consultative measures to be carried out during preparation of

    resettlement plans include:

    PPMUs in each province of a subproject requiring land acquisition inform district and

    commune authorities about the requirements for resettlement, including the roles and

    responsibilities of local organizations;

    PPMU works with district authorities and CARBs to distribute letters to people living on

    subproject roads, to inform them of the project, the need to acquire land and provisions

    for compensation;

    Village meetings will be held, and minutes recorded and included in the resettlement

    plans. The meetings can discuss the project, entitlements, verification of compensation

    rates, and possible livelihood restoration measures required for any PAPs that might be

    severely affected;

    Data related to land acquisition and resettlement is collected: vulnerable groups that may

    be adversely affected by the project, resettlement preferences of affected households,

    measures to reduce impacts and adequacy of compensation prices; and

    Distribution of the PIB, and a summary of the policy framework will be made available in

    an accessible place. The PIB will be distributed to ensure that the PAPs and various

    stakeholders are informed about the project. The general contents of the PIB will include

    the following (a draft PIB is attached in Appendix 8.3 as Form 8.5):

    Brief description of the project;

    Types of impacts expected;

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 27

    Basic compensation policy and entitlements;

    Consultation and participation of PAPs and community; and

    Who to contact for additional information.

    NOTE: Donations are not encouraged under this project. If after providing full

    information about project, its implications, and consequences, PAPs still would

    like to donate land, assets, cash, labour etc. responsible agencies are requested to

    properly document every donation per government regulations (e.g. consent of

    both spouses (and all adult household members of household, if applicable),

    witness and certification). These records also need to be included in the final

    report on resettlement and compensation. In every subproject having donations,

    PPMUs are requested to seek agreement from PMU 6, WB before the actual

    implementation.

    5.2. Consultation During Plan Implementation

    For each subproject, apart from the regular meetings with PAPs, PPMU, CARBs and

    other relevant agencies, the approved (or provincially endorsed) resettlement plan, or at

    least information about resettlement, compensation, and options, must be disclosed to

    PAPs in a form and language that they can understand. The draft resettlement plan or

    summary of the plan will be made available at a place accessible to, and in a form,

    manner and language understandable to PAPs and stakeholders. Once the draft

    documents have been accepted and approved, they will be made publicly available,

    including in the Viet Nam Development Information Centre in Ha Noi (refer to section

    4.6).

    5.3. Grievance Redressal Mechanisms

    For the purpose of grievance redressal, the commune, district and CARBs shall also serve

    as the grievance redressal committees at all levels. Attempts should be made to settle the

    issues at the commune level through community consultation, involvement of social and

    resettlement experts as required, NGOs and mediators and facilitators if required. PAPs

    will be exempt from all administrative fees incurred, pursuant to the grievance redressal

    procedures except for cases filed in court by PAPs. A four-step procedure for redress of

    grievances is proposed as below.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 28

    1. Complaints of PAPs on any aspect of compensation, relocation, or

    unaddressed losses shall be lodged verbally or in written form to the

    CPC. The complaint can be discussed in an informal meeting. It will be

    the responsibility of the CPC to resolve the issue within fifteen days

    from the date the complaint was received.

    2. If no understanding or amicable solution was reached or no response

    has been received from the CPC, the PAP can register the complaint

    with the CARB. The PAP must lodge the complaint within one month

    of lodging the original complaint with the CARB and must produce

    documents which support his/her claim.

    3. The CARB will provide the decision within fifteen days of the PAP

    registering the complaint. The CARB’s decision must be in

    compliance with the project’s Policy Framework and entitlements.

    Copies of the CARB’s decision will be provided to the PAP, PPMU,

    and DPC.

    4. If the PAP is not satisfied with the decision of, or in the absence of

    any response by the, CARB or its representatives, the PAP can appeal

    to the PPC.

    The PPC, together with CARB, will provide decision on the appeal

    within thirty days from the day it is received by the PPC.

    5. If the PAP is still not satisfied with the decision, the PAP can appeal

    to higher authorities, such as the District Court.

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 29

    6. Implementation Schedule

    The overall project will be implemented over a five year period and is scheduled to

    commence upon loan approval. Implementation of resettlement and related activities will

    take place after the safeguards team has mobilized either as part of the project supervision

    team or as a subcontracted activity managed by the project supervision consultant and

    PMU6, who will work closely with, and assist, the PPMU in all resettlement and related

    activities, and the training TA has commenced.

    The process for land acquisition will commence after the screening and identification of

    roads in each AWP that require land acquisition.

    The civil works contract for each subproject will only be awarded after all compensation

    and relocation has been satisfactorily completed for each subproject and rehabilitation

    measures are in place.

    7. Monitoring

    Implementation of the RPs will be regularly supervised and monitored by the respective

    PPMUs in coordination with the respective CARB and DPCs. The findings will be

    recorded in quarterly reports to be furnished to PMU6. The report must include the data

    on any donations given by PAPs. PMU6 will summarize the reports and submit them to

    World Bank every six months.

    7.1 Internal Monitoring

    Internal monitoring and supervision will:

    Verify that the baseline information of all PAPs has been carried out and that the valuation

    of assets lost or damaged, and the provision of compensation, resettlement and other

    rehabilitation entitlements has been carried out in accordance with the provisions of this

    Policy Framework and the respective RP;

    Oversee that the RPs are implemented as designed and approved;

    Verify that funds for implementing the RPs are provided to the PPMUs in a timely manner

    and in amounts sufficient for their purposes, and that such funds are used by the PPMUs in

    accordance with the provisions of the RP; and

    Record all grievances and their resolution and ensure that complaints are dealt with in a

    timely manner.

    7.2. Independent/External Monitoring

    An independent monitoring organization (IMO) will be retained by PMU6 to periodically

    carry out external monitoring and evaluation of the implementation of the RPs. The

    independent agencies will be academic or research institutions, non-Governmental

    Organizations (NGOs) or independent consulting firms, all with qualified and experienced

    staff and terms of reference acceptable to World Bank.

    In addition to verifying the information provided in the PPMU sign-offs on implementation

    and furnished in the internal supervision and monitoring reports of PPMUs, the external

    monitoring agency will visit a sample of 20 per cent of household PAPs in each relevant

    province six months after each RP implementation to:

    Determine whether the procedures for PAPs participation and delivery of compensation and

    other rehabilitation entitlements has been done in accordance with this Policy Framework

    and the respective RP;

  • PROJECT MANAGEMENT NO. 6

    RESETTLEMENT POLICY FRAMEWORK 30

    Assess if the Policy Framework objective of enhancement or at least restoration of living

    standards and income levels of PAPs have been met;

    Gather qualitative indications of the social and economic impact of project implementation

    on the PAPs; and

    Suggest modification in the implementation procedures of the RPs, as the case may be, to

    achieve the principles and objectives of this Policy Framework.

    8. Costs and Flow of Funds

    8.1. Cost Estimate

    Each annual RP will include detailed cost of compensation and other rehabilitation

    entitlements and relocation of PAPs, if that be the case, with a breakdown by compensation

    for land by type, main and secondary structures, other losses (income, businesses or

    employment losses), any other assets (including community property), and allowances and

    other assistance.

    The cost estimates will make adequate provision for contingencies (20 per cent) and Cost of

    management and administration (20 percent)

    8.2. Funding Source and Flow of Funds

    The flow of funds will follow the general model set out for the three financial models

    associated with progression from a centralized model, through a semi-autonomous stage,

    eventually to full budget support at provincial level;

    Centrally managed implementation with all payments made through PMU6 but as many

    implementation functions decentralized to the provincial level as possible. This will

    include implementation of resettlement plans and payment of compensation;

    Partial Swap operation with decentralized implementation and all payments made through

    the state treasury system and donor funds identified as a separate line item. All

    implementation functions will be managed by the province and PMU6 will retain a

    coordination and supervisory role, particularly through monitoring and evaluation. The

    costs and budget required for land acquisition and any associated measures (livelihood

    rehabilitation) will be identified as a line item within the pool of donor funds for each

    AWP; and

    Full Swap system or full budget support where donor funds are not identified separately

    from the state budget. Implementation will be fully decentralized. Provinces will prepare

    the budgets and costs for land acquisition and effect compensation payments after receipt

    of funds.