1. OBJECTIVE AND DESCRIPTION
The following test cases are done in order to test and validate the power electronics components from the Engineering suite V6 Electrical library and analog components.
Case I: 4 staggered converters draw 24-pulse current feeding RL loads Four separate 6-pulse converters combine to draw a 24-pulse current from the power system. All converters feed identical RL loads.
Case II: 4 staggered converters draw 24-pulse current feeding H bridges that drive DC motors
Four separate 6-pulse converters combine to draw a 24-pulse current from the power system. All converters feed identical H bridges that drive 4-quadrant DC motors.
2. PROCESSES DATA
1. 4 staggered converters draw 24-pulse current (RL loads)
Source voltage (sine wave) and diode with snubber
Transformer Yy 0 degree
Phase shifting transformers (Zny 7.5 deg, Zny -22.5 deg, Zny -7.5 deg, Zny -37.5 deg)
Loads
-
3
3
2. 4 staggered converters draw 24-pulse current (DC motors) Source voltage (sine wave) and diode with snubber
Transformer Yy 0 degree
Phase shifting transformers (Zny 7.5 deg, Zny -22.5 deg, Zny -7.5 deg, Zny -37.5 deg)
DC motors
Maximum current and smoothing inductor are respectively 20 A and 10 mH
The speed PI controller
( )
Hysteresis current control: 2 A
IGBT without snubber
The load torque is proportional to motor speed:
Reference speed: Initially 1000 rpm (104.72 rad/s), at 0.8 s set to -1000 rpm (-104.72 rad/s)
3. SIMULATION PARAMETERS
The simulation was run in time domain with sample time of
-
4
4
4. PROCESSES REPRESENTATION IN ES V6
4 staggered converters draw 24-pulse current (RL loads)
-
5
5
4 staggered converters draw 24-pulse current (DC motors)
-
6
6
6. ENGINEERING SUITE V6 RESULTS
4 staggered converters draw 24-pulse current (RL loads)
-
7
7
NETWORK CURRENT FOURIER ANALYSIS
-
8
8
4 staggered converters draw 24-pulse current (DC motors)
-
9
9
-
10
10
-
11
11
-
12
12
-
13
13
NETWORK CURRENT FOURIER ANALYSIS
Conclusion
The following conclusions can be made:
the network current in steady state contains less harmonics (2.5 %) as displayed above.
the inrush current (network) is due to the capacitor charging. One can avoid that by using a precharged capacitor or another circuit to precharge.
the motors current dont exceed the maximum allowed (20 A).
7. REFERENCE BOOKS
-
14
14
1. Power electronics. Converters, applications and design, 2nd edition. Mohan / Underland / Robbins.
2. Power electronics. Converter Harmonics. Multipulse methods for clean power. Derek A. Paice
3. Electric Motor Drives. Modeling, Analysis, and Control. R. Krishnan.