4058 73 da1 001 01 refractory dry out cycle
TRANSCRIPT
7/24/2019 4058 73 DA1 001 01 Refractory Dry Out Cycle
http://slidepdf.com/reader/full/4058-73-da1-001-01-refractory-dry-out-cycle 1/6
34 TPH GI&GL Furnace–SOUTHERN STEEL SHEET CO
LTD – Bien Hoa , VIETNAM
REFRACTORY DRY OUTPROCEDURE AND START UP
ACTIVITY
TECHNICAL SPECIFICATION
Doc. nr. 4058 73 DA1 001
Rev. 01
Pag. 1 of 6
Q U E S T O D
O C U M E N T O
E L E
I N F O R M A Z I O N I I N
E S S O C
O N T E N U T E S O N O
D I E S C L U S I V A P R O P R I E T A ' D I T E N O V A L O I I T A L I M P I A N T I . N E
E ' V I E T A T A L A C O P I A ,
R I P R O D U Z I O N E ,
P U B B L I C A Z I O N E , D I V U L G A Z I O N E E D
U S O , A N C H E
P A R Z I A L E , P E R S
C O P I D I V E R S I D A
Q U E L L O P
E R
C U I E ' S T A T O
P R E P A R A T O , S E N Z A
A U T O R I Z Z A Z I O N
E
S C R I T T A .
34 TPH GI&GL Furnace
SOUTHERN STEEL SHEET CO LTD
Bien Hoa - Dong Nai ProvinceVIETNAM
REFRACTORY DRY OUT PROCEDURE AND START UPACTIVITY
01 KSR HOT TRAIL/RUN PROCEDURE ADDED 19.07.2014
00 KSR First Issue 18.07.2014REV. BY DESCRIZIONE/ DESCRIPTION DATA /DATE
REDATTO/ ISSUED BY CONTROLLATO/ CHECKED BY APPROVATO/ APPROVED BY
KSR AVK MRM
7/24/2019 4058 73 DA1 001 01 Refractory Dry Out Cycle
http://slidepdf.com/reader/full/4058-73-da1-001-01-refractory-dry-out-cycle 2/6
34 TPH GI&GL Furnace–SOUTHERN STEEL SHEET CO
LTD – Bien Hoa , VIETNAM
REFRACTORY DRY OUTPROCEDURE AND START UP
ACTIVITY
TECHNICAL SPECIFICATION
Doc. nr. 4058 73 DA1 001
Rev. 01
Pag. 2 of 6
Check before proceeding to Refractory Dry Out Cycle and Hottrial/run:-
1) Cold trail must be done successfully with minimum to maximum strip
thickness and minimum to maximum strip width by bypassing the furnace and
through the furnace.
2) All the rollers must be started in idling mode.
3) Check whether back up power available at site. This we require for safety
point of view for equipments in case power supply fails.
4) Start cooling water supply and ensure that the flow is in healthy condition.
5) Check emergency cooling water supply is available. This is required from
safety point of view for equipments (like heat exchanger of Jet cooler, DFH
hearth roller) in case if main cooling water supply fails or power fails.
6) Required N2 flow should be maintained through all equipments/instruments.
7) Compressed Air pressure switch should be in healthy condition. This is
required to ensure proper working of furnace damper actuator andcombustion blower actuator.
8) RC fan must be in OFF condition and RC fan damper should be in closed
position.
9) Threading valve (Gate Valve) at hot bridle section and snout portion should
keep open for air to flow inside the furnace.
7/24/2019 4058 73 DA1 001 01 Refractory Dry Out Cycle
http://slidepdf.com/reader/full/4058-73-da1-001-01-refractory-dry-out-cycle 3/6
34 TPH GI&GL Furnace–SOUTHERN STEEL SHEET CO
LTD – Bien Hoa , VIETNAM
REFRACTORY DRY OUTPROCEDURE AND START UP
ACTIVITY
TECHNICAL SPECIFICATION
Doc. nr. 4058 73 DA1 001
Rev. 01
Pag. 3 of 6
Refractory Dry Out Cycle:-
1) After satisfying all above conditions, start the exhaust fan at approx 30%
speed and open the furnace pressure damper approx 50%.
2) Start Hot bridle heaters, Static heaters and RCS heaters with set point of
100°C in auto mode.
3) On 2nd day increase the temperature to 200°C.
4) On 3rd day start the soaking heaters and maintain 200°C. Increase the
temperature of RCS, Static and HBR to 300°C.
5) On 4th day increase temperature of soaking to 300°C. Increase the
temperature of RCS, Static and HBR to 400°C.
6) On 5th day increase temperature of soaking to 400°C. Increase the
temperature of RCS, Static and HBR to 500°C.
7) On 6th day maintain temperature of 500°C for soaking, RCS, Static and HBR
and hold this temperature for rest of cycle.
8) On 7th day Fire RTF burner and maintain the temperature of 500°C. Increase
temperature of soaking to 600°C.
9) On 8th day maintain the temperature of 700°C for soaking section. Increase
temperature of RTF to 600°C
10) On 9th day maintain the temperature of 800°C for soaking section. Increase
temperature of RTF to 700°C
11) On 10th day maintain the temperature of 900°C for soaking section. Increase
temperature of RTF to 800°C
12) On 11th day fire DFH zone 4 burners and maintain temperature of 900°C.
Maintain the temperature of 900°C for soaking section as well as for RTF
section and hold this temperature for rest of cycle.
13) On 12th day increase the temperature of DFH to 1000°C and hold this
temperature for rest of cycle.
14) At the end of 14th day, refractory dry out cycle will completed.
7/24/2019 4058 73 DA1 001 01 Refractory Dry Out Cycle
http://slidepdf.com/reader/full/4058-73-da1-001-01-refractory-dry-out-cycle 4/6
34 TPH GI&GL Furnace–SOUTHERN STEEL SHEET CO
LTD – Bien Hoa , VIETNAM
REFRACTORY DRY OUTPROCEDURE AND START UP
ACTIVITY
TECHNICAL SPECIFICATION
Doc. nr. 4058 73 DA1 001
Rev. 01
Pag. 4 of 6
Summary :
HBRStatic
(Homogenization)RCS (Jetcooler)
Soaking RTF DFH Remarks
Day 1 100°C 100°C 100°CStart of HBR, Staticand RCS heater
Day 2 200°C 200°C 200°CDay 3 300°C 300°C 300°C 200°C Start of Soaking HeaterDay 4 400°C 400°C 400°C 300°CDay 5 500°C 500°C 500°C 400°CDay 6 500°C 500°C 500°C 500°C
Day 7 500°C 500°C 500°C 600°C 500°C Fire RTF burner Day 8 500°C 500°C 500°C 700°C 600°C
Day 9 500°C 500°C 500°C 800°C 700°CDay 10 500°C 500°C 500°C 900°C 800°CDay 11 500°C 500°C 500°C 900°C 900°C 900°C Fire DFH burner
Day 12 500°C 500°C 500°C 900°C 900°C 1000°CDay 13 500°C 500°C 500°C 900°C 900°C 1000°CDay 14 500°C 500°C 500°C 900°C 900°C 1000°C
7/24/2019 4058 73 DA1 001 01 Refractory Dry Out Cycle
http://slidepdf.com/reader/full/4058-73-da1-001-01-refractory-dry-out-cycle 5/6
34 TPH GI&GL Furnace–SOUTHERN STEEL SHEET CO
LTD – Bien Hoa , VIETNAM
REFRACTORY DRY OUTPROCEDURE AND START UP
ACTIVITY
TECHNICAL SPECIFICATION
Doc. nr. 4058 73 DA1 001
Rev. 01
Pag. 5 of 6
7/24/2019 4058 73 DA1 001 01 Refractory Dry Out Cycle
http://slidepdf.com/reader/full/4058-73-da1-001-01-refractory-dry-out-cycle 6/6
34 TPH GI&GL Furnace–SOUTHERN STEEL SHEET CO
LTD – Bien Hoa , VIETNAM
REFRACTORY DRY OUTPROCEDURE AND START UP
ACTIVITY
TECHNICAL SPECIFICATION
Doc. nr. 4058 73 DA1 001
Rev. 01
Pag. 6 of 6
Start of HOT trial/Run after refractory dry out cycle.
1) Lower the DFH section to 800°C, RTH and Soaking to 500°C. Maintain static
and HBR at 500°C. Put off Jet cooler heater and open the JC damper. Start
RC fan with 10% operating speed.
2) Switch ON all Glow heaters.
3) Seal the snout opening by dipping it into zinc bath. Close the threading valve
at HBR section or any openings in furnace. Once again check all
flanges/covers tighten properly to ensure no leakage from the furnace.4) Start purging of nitrogen (N2) with 3% H2 to achieve require dew point and
O2 level minimum 1 day. This N2H2 purging need to be carried out to remove
air present inside the furnace.
5) After getting required dew point, put off all burners, heaters and N2H2 supply.
6) Bring down the furnace temperature upto temperature suitable for threading.
Start threading of strip (recommended size of 0.25 to 0.3 mm thk X 1000mm
strip width) for CQ production.
7) After completion of threading, close the threading valve and openings.
Ensure the openings are closed properly.
8) Start HBR and static heater at 500°C set point. Put RC fan in auto mode.
Maintain soaking temperature around 700°C and RTF temperature around
750°C.
9) Simultaneously start purging of nitrogen (N2) with 3% H2.
10) After getting require dew point and O2 level in acceptable limit (in ppm), fire
DFH zone 4 burners with excess air to burn hydrogen. Increase the H2%
upto 25%.
11) If strip temperature increases beyond acceptable temperature, then jog the
Strip for few meters to keep the temperature within limits.
12) Keep check dew point and O2 level, and after 25 to 30 min. line can be
started. Set all section/zone temperature at required temperature/settings and
start the production.