4D BIM Construction Scheduling on the 1885 St. James Pl. Project

● Dat Lien, President, Axoscape● Xavier Loayza, BIM Specialist, Axoscape

Page 3: 4D bim construction scheduling on the 1885 St. James pl. project
Page 4: 4D bim construction scheduling on the 1885 St. James pl. project

AgendaThe Project4D BIM IntroductionThe BIM modelThe ScheduleThe workflowOutputs

Page 5: 4D bim construction scheduling on the 1885 St. James pl. project

Nelson Murphree Legacy Partners15-story boutique office tower165,146-square-foot buildingNine floors of office spacesix levels of parkingUSGBC: LEED SilverArchitect: Jackson & RyanGC: Tellepsen BuildersBIM Consultant: Axoscape

1885 St. James Pl

Page 6: 4D bim construction scheduling on the 1885 St. James pl. project

The ProblemLimited SpaceExpensive Mast ClimbersComplex ScheduleCommunication

Page 7: 4D bim construction scheduling on the 1885 St. James pl. project

Mast Climber Layout

Floors 1 - 15

Floors 7 - 13

Page 8: 4D bim construction scheduling on the 1885 St. James pl. project

4D BIM for Pre-Construction Planning 3D + Time

Page 9: 4D bim construction scheduling on the 1885 St. James pl. project

BIM Model•Arch model(str+exterior+ext blockwall+ext stone + drywall model/framing•Dry-wall model 3d

Page 10: 4D bim construction scheduling on the 1885 St. James pl. project

BIM model and ScheduleLevel Of Detail (BIM) ≈ Level Of Detail (Schedule)

Page 11: 4D bim construction scheduling on the 1885 St. James pl. project

The SchedulerSelecting the Activities to perform

Page 12: 4D bim construction scheduling on the 1885 St. James pl. project

The ScheduleBuild on Critical path Method (CPM) base

Input by Linear Scheduling Method (LSM)

Sub-contractor Input (rates)

Page 13: 4D bim construction scheduling on the 1885 St. James pl. project

The Schedule: Activity Flow

Page 14: 4D bim construction scheduling on the 1885 St. James pl. project

The SchedulerCrew sizing

Page 15: 4D bim construction scheduling on the 1885 St. James pl. project

The Workflow

Page 16: 4D bim construction scheduling on the 1885 St. James pl. project

The Workflow1. Create Selection Sets 2. Create Activities from

Selection Sets

Page 17: 4D bim construction scheduling on the 1885 St. James pl. project

The Workflow3. Export Timeliner to MS Project

Page 18: 4D bim construction scheduling on the 1885 St. James pl. project

The Workflow4. Build the schedule based on the activities created in Navisworks

Page 19: 4D bim construction scheduling on the 1885 St. James pl. project

The Workflow5. Link the New schedule to Navisworks

6. Map the Activities to the Selection Sets

Page 21: 4D bim construction scheduling on the 1885 St. James pl. project

Q & A