5 team 4
DESCRIPTION
ÂTRANSCRIPT
GROUP 4
ANDI BELULAJ
PANAGIOTIS AIVALIS
FANI DIMOPOULOU
BETTINA RIEDMANN
JUDITH SCHÖBI
KARIN WIDLER
URBAN & RAILWAY DEVELOPMENT IN PATRAS
9-16 JUNE 2013
overview
Patras Athens
suburban train in Patras: successful
?
high speed line Athens - Patras?
high-speed line ends in the old port (1)
Code Patras leads through the existing
corridor to the old port
+ city centre and bus terminal are nearby
+ port and rail can be combined
– conflicts with the surburban train
– consequences for the urban fabric
/ divides the city due to design of high speed
– possible cargo port activities near the centre and marina
high-speed line ends in the old port (2)
Code Patras leads through through a by-
pass tunnel to the old port
+ city centre and bus terminal are nearby
+ port and rail can be combined
– possible cargo port activities near the
centre and marina
– feasibility?
– high costs!
high-speed line ends in the new port (1)
Code Patras leads through the existing
corridor to the new port
+ all port activities concentrated
+ brownfields: potential for city and central station development
– negative consequences for the urban fabric
/ divides the city and divides city from the sea
– corridor splits the city center
– conflicts with the surburban train
high-speed line ends in the new port (2)
Code Patras leads through a by-pass tunnel
to the new port
+ all port activities concentrated
+ brownfields: potential for city development
+ suburban train fits perfect to it
– long tunnel needed due to the slopes!
– feasability? high costs!
Patras – Athens ends with metric gauge and
an interchange node
normal gauge, double track
normal gauge, single track
small gauge
Interchange node for passengers on the outskirt of Patras, possibilities are in
Rio, Rododafni or Diakopto
Rododafni
Diakopto
Rio
suggested railway standards
one track line
Normal speed
second path reserved
one track metric gauge,
futurally electrified
second path reserved
double track fully equipped
high speed
double track corridor
1 track fully equipped
high speed
0 0,5 1 1,5 2 2,5 3 3,5 4
Car
Former Metric Rail (with stops)
New line (change in Rododafni)
New line (change in Rio)
Travel time (in hours)
travel time Patras to Athens
Patras: metropolitan line
improvement of suburban to a metropolitan line
new stations
connections to busses
connection between metropolitan railway and
normal gauge has to be assured
development of metropolitan line
New Stop
Concept of service
Suburban line (train) every hour, synchronised with Intercity to/from Athens
Inner city line (tram) every 15’, connected to blue line in Bozaitika and new Port
Patra, New Port: 5 trains stop per hour and direction
Existing stop
Suburban line (train)
Inner city line (tram)
Future connections
a vision for the metropolitan line
interchange for passengers
existing lines and plannings OSE
2013 2015 2016 2020 2025 2030
CODE Patras
Athens - Kiato in operation
Kiato - Rododafni
Rododafni - Rio
Rio - Patras
Patras Suburban train
A. Andreas (P.) - A. Vassileos (R.) in operation
to Arachovitika (north Rio) ?
corrections and suggestions
2013 2015 2016 2020 2025 2030
Code Patras
Athens - Kiatoin operation
Kiato - Rododafni only 1 track should be equipped for now
Rododafni - Rio
Rio - Patras
Suburban train
A. Andreas (P.) - A. Vassileos (R.)in operation
to Arachovitika (north Rio) ?
addition south: to new port
additional innercity stops and train
addition north: to join the normal-gauge
Slow down
Plan it integral
costs
project planned costs suggested difference in %
Kiato - Rododafni 920 mio. € ca. 750 mio. € - ca. 25%
less maintenance
1 track equipped
Rododafni – Rio
normal gauge
500 mio. €
ca. 250 mio. € - ca. 50%
just one track
build
Rio - Patras < 1 billion €
(inkl.
underground)
electrification of metric
gauge ca 10 mio. €
- ca. 99%
metropolitan line
(more stops and
services)
- electrical trains
3 trains 9 mio. €
the next steps
initiate the study of suggested alternatives:
like
implementation of a planning process for the
questions: where to build the interchange node?
plan Rododafni – Rio and Rio – Patras integral and
divide it in onward-compatible, realistic projects
GROUP 4
ANDI BELULAJ
PANAGIOTIS AIVALIS
FANI DIMOPOULOU
BETTINA RIEDMANN
JUDITH SCHÖBI
KARIN WIDLER
Thank you for your attention
travel times
BY CAR Pirgos Araxos
Airport
Agios
Andreas
Patras Rio Rododafni Diakopto Kiato Athens
distance to
Patras (km)
100 45 2 7 30 50 110 222
time used
1h 22‘ 53‘ Patras 12‘ 33‘ 1h 1h 20‘ 2h 30‘
BY FORMER METRIC LINE Pirgos Airport Agios
Andreas
Patras Rio Rododafni Diakopto Kiato Athens
distance to Patras (km)
109 49 2 7 29 50 106 221
time used
1h 50‘ 1 h Patras 36‘ 53‘ 1h 30‘ 3 h 41‘
travel times (by railway)
CHANGE in RODODAFNI km/h average speed KIATO - ATHENS 1h 20‘ 100 km/h Expected /possible
traveltime KIATO - Athens 1h 10‘ 160 km/h KIATO - RODODAFNI ( 80
km) 40‘ 140 km/h
Rododafni- Rio 30‘ 60 km/h 2h 20‘
Train Changing time 10‘ Traveltime Patras - ATHENS 2h 30‘
CHANGE in RIO km/ha average
speeed
Expected /possible traveltime
KIATO - Athens 1h 10‘ 160 km/h
KIATO - RODODAFNI ( 80 km) 40 ‚ 140 km/h
RODODAFNI –RIO ( 30 km) 15 min 120 km/h
Traveltime Patras Athens 2h 15‘
Kiato – Athens: 1h 20‘
proposed timeschedule for combination of metric gauge and normal gauge
re-establishment to Rododafni:
90 Mio. Euros
re-establisehment to Rio:
possible solutions for cargo
dual gauge: 3 rails build 2 track sizes
examples for the metropolitan line
examples for the metropolitan line
interchange point for passengers