500mw starting procedures

Upload: thangarajm1984

Post on 02-Jun-2018

249 views

Category:

Documents


6 download

TRANSCRIPT

  • 8/10/2019 500MW Starting Procedures

    1/38

    CONTENTS

    SL.NO. DESCRIPTION01. COLD START - UP

    02. INTEGRATED START UP PROCEDURE COLD START UP

    03. HOT AND WARM START UPS.

    04. INTEGRATED START UP PROCEDURE WARM START UP

    05. INTEGRATED START UP PROCEDURE HOT START UP.

    06.

    START UP BY CURVES FOR ABSOLUTE COLD START WITH HP/LP BYPASSSYSTEM.

    07. START UP CURVES AFTER 48 HOURS SHAT DOWN WITH HP/LP BYPASSSYSTEM.

    08. START UP PROCEDURE AFTER 8 HOURS SHUT DOWN WITH HP/LP BYPASSSYSTEM.

    09. TECHNICAL DATA LIMIT CURVES FOR TURBINE VALVES WALL OF THE

    CASING SHAFTS.

    10. WARMING UP AND STARTING THE TURBINE TEMPERATURE CRITERIA.

    11. TECHNICAL DATA REACTIVE CAPACITY CURVE FOR TURBO GENERATORS.

    COLD START UP

    (With Aux Steam available)

    A cold start up is by definition, one of which the maximum of HP casing and HP shaft isless than 1500C. This normally means that the unit is shut down from the maximum load

    for more than five days. If machine is started from ambient temperature (HPC/HP shaft

    temp approx. 400C), heating up of casting is required. This is accomplished by soakingthe machine at 360 rpm at warming up steam parameters (40kg/cm2, 3600 C), till theTSE margin are satisfactory.

    The rifle construction of the water wall combined with the boiler circulating waterpumps permits very high rate of pressure rising of boiler. An upper limit of 2000C/hrsaturation temperature gradient can be allowed, i.e. approximately the boiler pressurecan be brought to 20 kg/cm2within an hour of cold start up. But actual temperaturegradient is limited by the thick walled Y piece provided in the main steam and HRH lines.A main steam line heating is to be started as early as possible (at approx. 4 kg/cm2) asmaximum differential temperature allowed between inner (98%) and mid wall

    temperature (50%) is 400C. So boiler loading is accordingly regulated. It may be

    preferably to start only two CC pumps in order to minimise flashing in down comers (and

    subsequent vibration) when the boiler water is in range of 850C to 1250C. The thirdpump should be started before drum pressure reaches 7 kg/cm2to minimise the

    http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#COLDSTARTUPhttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#COLDSTARTUPhttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#INTEGRATEDSTARTUPPROCEDURECOLDSTARTUPhttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#INTEGRATEDSTARTUPPROCEDURECOLDSTARTUPhttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#INTEGRATEDSTARTUPPROCEDURECOLDSTARTUPhttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#INTEGRATEDSTARTUPPROCEDURECOLDSTARTUPhttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#WARM%20AND%20HOT%20START%20UPS%C2%A0http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#WARM%20AND%20HOT%20START%20UPS%C2%A0http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#WARM%20START%20UP%20(AFTER%2048%20HOURS%20SHUT%20DOWN).http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#WARM%20START%20UP%20(AFTER%2048%20HOURS%20SHUT%20DOWN).http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#WARM%20START%20UP%20(AFTER%2048%20HOURS%20SHUT%20DOWN).http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#WARM%20START%20UP%20(AFTER%2048%20HOURS%20SHUT%20DOWN).http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#hothttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#hothttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#hothttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#hothttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#hothttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#WARM%20START%20UP%20(AFTER%2048%20HOURS%20SHUT%20DOWN).http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#WARM%20AND%20HOT%20START%20UPS%C2%A0http://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#INTEGRATEDSTARTUPPROCEDURECOLDSTARTUPhttp://www.bhelpswr.co.in/Technical/COMMISSIONING%20PROCEDURES/comm%20proced11.htm#COLDSTARTUP
  • 8/10/2019 500MW Starting Procedures

    2/38

    temperature transients experienced by the pump casing (this is to avoid fast load outback on the boiler in the event of any CC pump tripping).

    To get the rolling parameters, normally two elevation oil guns are taken withapprox. 70 to 80t/hr flow through HP-LP bypass. At that time M.S. parameters would be40 kg/cm2and 3600C, HRH parameters would be 12 kg/cm2and 3600C.

    As soon as the turbine loading has started, HP/LP bypass closes and gets completely

    closed as the turbine reaches the boiler load. First mill is put into operation around 10%of generator load. Second mill is put into operation around 25% while third mill is at40% of generator load. Fourth and fifth mills are put into operation at 60% and 80% ofgenerator load respectively. Sixth mill is taken to reach full generator load.

    During loading the RH outlet steam temperature has to be kept as close as possibleto SH outlet steam temperature Burner tilt, SH spray, RH spray controls has to beadjusted accordingly. The turbine-loading rate is decided by a selection circuit which

    compares the external load gradient, TSE margin and time dependant gradient (setinternally) and frequency influence.

    INTEGRATED START-UP PROCEDURE

    COLD START-UP

    (AUXILIARY STEAM AVAILABLE)

    REF. DRG NO. 20 BPE691

    STEP TIME UNIT CONDITION OPERATION NOTES

    0 ..Boiler pr. 0 kg/cm2(g)and Ambienttemperature

    Charge Aux. Steamheader 16 ata, 2600C,from existing units.

    -

    - - -

    Charge steam to fueloil pump house,

    atomising steam andtracing steamdeaerator warming up.

    All the steam tracinglines and electricaltracings in pump house

    & boiler to be charged.

    - - -Start tank heating ofLSHS oil.

    -

    - - -

    Start one LSHS pumpon recirculation as soonas the sufficient oiltemperature at inlet is

    achieved.

    -

    - - -

    Charge LSHS to boilerfront and keep it onlong recirculation, with

    heaters control set onAuto to maintain 110-1290C.

    -

    - - -Fill water in drum upto+200mm.

    Ensure that the suctionand discharge valves of

    all the CC pumps areopen and the pumpsuction and discharge

    lines are vented.

  • 8/10/2019 500MW Starting Procedures

    3/38

    - - -

    Start Bearing coolingwater system pumps

    for Boiler, Turbine andTG auxiliaries .

    Check all circuits have

    sufficient flow. Beforestarting the pumps, theemergency coolingwater tank level to be

    checked and madenormal.

    - - -

    Start instrument aircompressor and checkthat all the lines toBoiler and TG arecharged.

    Check that all circuitshave sufficient airpressure.

    - - -

    Start service aircompressor and fill theair receiver tanks ofSRAPH & PRAPH are

    filled.

    -

    - - -

    Ensure that purge air to

    HEA is open in allcorners.

    -

    - - -Line up Air and flue gas

    circuits for startup.

    Check dampers and

    gates register position.

    - - -ESP ready in allrespects.

    -

    - - -Furnace bottom ashsystem and sealthrough lined up.

    -

    - - - FSSS panel ready in allrespects.

    -

    - - -EAST panel ready in all

    respects.-

    - - -Excitation panel readyin all respects.

    -

    - - -

    Generator protection

    panel ready in allrespects.

    -

    - - -Generator H2gas

    pressure is 4 kg/cm2

    Check purity of H2gas

    is normal.

    - - -Generator stator watersystem ready in allrespects.

    Check purity ofgenerator stator wateris normal.

    - - -H2cooling watersystem ready in allrespects with SLC on.

    -

    - - -LP & HP chemicaldozing system is ready.

    Check for level in

    Hydrazine, Ammoniaand phosphatepreparation tanks.

  • 8/10/2019 500MW Starting Procedures

    4/38

    - - - SADC panel readiness.

    Check for air pressure

    in all the corners andelevations.

    - - -Power supply for all thevalves and dampers are

    ON.

    Ensure Aux. airdampers and

    modulating.

    - - -

    Supply for allauxiliaries of SG,Turbine and Generatoris ensured.

    -

    - - -Readiness of HP bypasspanel in all respects.

    Ensure the oil unit isrunning and all thebypass and sprayvalves are closed.

    - - -Start one of the CC

    pumps.

    Ensure drum level is+200 mm, and the

    drum air vents areclosed.

    - - -Start the second CCpump.

    Ensure drum level isnormal.

    - - - Start scanner air fan. -

    - - -

    Start both thesecondary air

    preheaters.

    Ensure that all the inletand outlet air gas

    dampers are open.

    - - -Start both the primaryair preheaters.

    Ensure that the gasdampers are closed.

    - - -Start one set of ID andFD fans.

    Adjust 30% air flow,and furnace draftminus 5 to 10 mmWCL.

    - - -

    Charge steam coilpreheater concerned

    with the running FDfans.

    -

    - - -Initiate Boiler Purge

    (duration 5 minutes).

    After purge completionBoiler trip valves willget reset.

    - - - -

    Also, after purge,adjust the wind boxdampers to get 30-40mm WCL. Wind box

    dp.

    - -Lub oil system

    stopped.

    Start one vapourextraction fan, keepother fan standby.

    Check oil level in MOT.

    - - -Line up lub oil coolerand thrust bearing filterStart one AOP.

    Put on SLCs for otherAOP and EOP.

    - - - - Check out auto start ofAOP and EOP.

  • 8/10/2019 500MW Starting Procedures

    5/38

    - -- -Put lub oil temperaturecontroller on.

    -

    - - - Start one JOP.Put on SLCs for otherJOP and DC-JOP.

    - -- - - Check out auto start ofJOP and DC-JOP.

    - - -Put off SLCs JOP 1, 2 &3. Stop running JOP.

    -

    - - -Open gate valve

    gearing.

    Switch on SLC gate

    valve gearing.

    - - -

    Start one JOP and

    switch on SLCs forJOPs.

    -

    - - - M/c. comes on barring.

    MOT level 50 mm oil

    temp. 45

    0

    C JOP headerpr. 140 kg/cm2speed

    80 100 rpm.

    - - -

    The sequentialoperation narratedabove on Lub oil

    system stopped isachieved by SGC mode.

    If the programme gets

    interrupted, the stepand criteria to bechecked and to befulfilled for the

    programme to proceedfurther.

    - - M/c on barring.Start centrifuge withboth heaters

    -

    - -FRF system in stoppedcondition.

    Check FRF tank level. +200 mm.

    - - -

    Line up FRF cooler andduplex filters in 32-barsystem start one CEP.Check auto start ofstandby CEP.

    -

    - - -

    Establish control fluidsupply to variousservices.

    FRF tank level O

    (normal).

    - - - Start one VEF. -

    - - -

    Start one recirculation

    pump and include oneFilters earth and ultrafine.

    -

    - - -

    Switch on FRF heaterand keep SLC ON fortemperature control,

    and control fluidpumps.

    FRF temperature 550C.

    - - -Switch ON control fluidSGC.

    -

  • 8/10/2019 500MW Starting Procedures

    6/38

    - -FRF system, SGC is

    on.

    The sequential

    operation narratedabove in FRF systemstopped condition isachieved by SGC-FRF

    system on startingprogramme mode.

    If the programme getsinterrupted the stepand criteria to be

    checked and fulfilled forthe programme to

    proceed further.

    01 ooBoiler ready for lightup and Turbine onTurning gear.

    Start 4 burners in ABelevation with LSHS.

    Check that SH & RHvents are open.

    - - - -SH & RH drains areopen.

    - - - -

    MSVs closed anddrains before MSV

    open.

    - - -

    Regulate oil pressure to

    8-10 kg/cm2.

    Ensure atomising

    steam pressure about 6kg/cm2.

    - - -

    After 30 minutes, takeadditional burners, soas to ensure a drum

    metal temperatureraise of about 20C/min.

    Insert furnace probe

    and ensure that thetemperature is below5350C.

    - - - -Check drum level andgive blow down.

    - - - -

    Keep open the Eco.recirculation valve

    when there is nofeeding to drum.

    - - -Start motor driven feedpump on recirculation.

    Check deaerator level.

    - - -

    Charge the feed line

    upto feed controlstation.

    -

    - - -Charge heating steamto deaerator from Aux.PRDS.

    -

    - - -Start condensatepumps and feed todeaerator as and when

    required.

    Check hotwell level.

    -- - -

    Start hotwell make uppumps and feed hotwellas and when required.

    -

    - - -Aux. PRDS steam15kg/cm2(g) 2600C

    -

    - - - CW system is charged. -

    - - - CW boxes to ensureventilating of water

    -

  • 8/10/2019 500MW Starting Procedures

    7/38

    boxes.

    - - -Start one gland steamexhauster fan.

    -

    - - -

    Line up vacuum pumpsand start one by one Gradually admit glandsteam when condenservacuum reaches

    0.2kg/cm2(g).

    Ensure gland steamadmission temperature

    is always above 2000C.

    - - -

    Vacuum building can be

    done through SGC vacuum on startingprogramme mode,gland steam exhausterhas to be started

    manually.

    -

    - -Vacuum 0-9kg/cm2(g).

    Open all drainsconnected to flashtanks and flash boxes

    connected tocondenser.

    -

    -- - -Open HPBP warm upvalves.

    -

    - - - Switch on SLC drains. -

    02 60'Boiler pressure 2kg

    /cm2

    Close SH & RH headervents.

    -

    - - -Close SH & RH headerdrains.

    -

    - - -Open MSV by passlines.

    MS, HRH, & CRH lineswill get warmed up.

    03 100Boiler pressure 5kg

    /cm2.

    Switch on automaticcontrol interface of LPbypass.

    As soon as the fixed setpoint reaches 12kg/cm2, it seizes.

    -

    -

    -

    Open Main steam

    valves.

    Automatic controlinterface gets switchedoff when the hot reheat

    steam pressure reaches13kg/cm2i.e. aftersynchronisation.

    - - - Open HP by pass. -

    - - -Start third C.C. pumpwhen boiler pressurereaches 9 kg/cm2.

    -

    - - -Take additional guns in

    CD & EF elevation.

    Air heater soot blowing

    to be carried out.

    - - -Close HPBP warm up

    valves.

    -

    A ROLLING THROUGH HYDRAULIC GOVERNOR

  • 8/10/2019 500MW Starting Procedures

    8/38

    04 150

    Boiler pressure:15kg/cm2

    Temperature:180-2000C

    HRH Pressure:8-12Kg/cm2

    Open HPESVs & IPESVsfor warming up byoperating startingdevice to

    approximately 42%.

    Check and ensure thatspeed set point is zero

    and speeder gear is 0%

    position.

    - - - -

    Ensure TSE influence isswitched on andavailable margins aregreater than = 30 0K.

    05 -300

    M. S. Pr. 50 kg/cm2

    M.S. temp. 3500C

    H. R. H. Pr. 12 kg/cm2

    HRH temp. : 3500C

    Raise the speed setpoint of EHC to 3200

    rpm

    If the oil system of EHC

    is isolated at speedGov. rack, speed set

    point need not beraised.

    - - -

    Gradually raise thestarting device to bring

    the speed to 360 rpm

    Starting device positionapproximately 56%.

    - -Turbine ready forRolling.

    Hold the speed at 360rpm for about 35 to 40

    mts.

    Ensure closure of gate

    valve gearing at 240rpm. Monitor bearingvibrations, shaftvibrations, TSE

    margins, bearingtemperature &Turbosupervisory

    readings at 360 rpm.

    06 -360M. S. Pr. 50kg/cm2/3500C. Turbine

    running at 360 rpm.

    Raise the speed upto

    2400 rpm throughstarting device at therate of 600 rpm.

    Ensure tripping of JOPat 540 rpm.

    - -Raise further speedupto 3000 rpm through

    speeder gear.

    Starting device will beat 90%.

    - - - -

    Monitoring bearingtemperature andvibrations, shaftvibrations, TSE marginsand Turbovisory

    readings, Seal oil,Primary water and gastemperatures &Generator windingtemperature.

    - - - -Ensure trippinf of AOPat 2950 rpm.

  • 8/10/2019 500MW Starting Procedures

    9/38

    - - - -

    Speeder gear position

    will be approximatelyat 50 to 60%.

    07 370

    MS Pr. 50 kg/cm2.Temperature:

    3500C Turbine runningat 3000 rpm.

    Put AVR on Auto. -

    - - - Close field breaker. -

    - - -

    Set manually thegenerator voltage to

    grid voltage.

    -

    - - -

    Synchronise thegenerator with grid.

    Pick up 50 MW load by

    operating speeder gear.

    -

    - - -Increase HPBP setpoint.

    Ensure closure of HPBPsteam valves & spray

    valves.

    - - -

    Close other drains,

    M.S. HRH, keeping SLCdrains on.

    Drain pot drains of MS,

    CRH & HRH andextraction steam lineswill operate as per theactuation of levelswitches.

    B - ROLLING THROUGH EHC.

    04 150'

    MS Pr.: 15 kg/cm2.Temperature:180-

    2000C HRHPressure:8to12kg/cm2.

    Open HPESVs & IPESVs

    for warming up byoperating startingdevice toapproximately 42%.

    Check and ensure thatTSE influences isswitched on and

    available margins are

    greater than 300K.

    - - - -

    Check and ensure thatspeed set point is zeroand speeder gear is 0%

    position.

    05 300'

    MS Pressure: 50kg/cm2

    MSTemperature:3500C

    HRH Pressure:12kg/cm2

    HRH Temperature:3500C.

    Turbine Ready forrolling

    Raise the startingdevice to about 70%.

    Check and ensureopening of valves in

    HP/IP secondary fluidlines to EHC at speedcontrol rack.

  • 8/10/2019 500MW Starting Procedures

    10/38

  • 8/10/2019 500MW Starting Procedures

    11/38

    picked upto 20MW.

    - - -

    Raise the speed setpoint and pick up the

    load to 50 MW.

    -

    - - -Increase HPBP setpoint.

    Ensure closure of HPBPsteam valves & spray

    valves.

    - - -

    Close other drains of

    MS, CRH, HRH, keepingSLC drains 'ON'.

    Drain pot drains of MS,

    CRH, HRH andextraction steam lineswill operate as per theactuation of levelswitches.

    C - ROLLING THROUGH SGC - TURBINE.

    04 150'

    MS Pressure: 15kg/cm2

    MS Temp.:180-2000C

    HRH Pressure: 12kg/cm2

    Switch on the start upprogramme of SGC Turbine.

    Ensure TSE influence isswitched on.

    - - - -

    If the programmeinterrupts the particularstep and criteria to be

    checked and corrected

    for the programme toproceed further.

    - - - -

    All operations asexplained under EHC

    rolling will be carriedout by SHC Turbineprogrammesequentially.

    05 300'

    MS Pressure: 50kg/cm2

    MS Temperature:3500C

    HRH Pressure: 12kg/cm2

    HRH Temp.: 3500C.

    Turbine Ready forrolling

    Turbine speed will beraised to 360 rpmthrough SGC

    Programme.

    Ensure closure of gatevalve gearing at 240rpm.

    - - - -

    Monitor bearingvibration, bearing

    temperature, shaftvibration, TSE margins

  • 8/10/2019 500MW Starting Procedures

    12/38

  • 8/10/2019 500MW Starting Procedures

    13/38

    08 390'

    Load : 55 MW

    M.S. :54kg/cm2/3500C

    HRH : 12kg/cm2/3400C

    Start seal air fan andPA fan and take first

    mill in service.

    Before starting P.A.fan, ensure that air andgas dampers of Primary

    Air Preheaters are

    open.

    - - - Charge ESP fieldsEnsure Ash handling

    system is ready.

    - - -Start the second set ofID & FD fans.

    Make ready SH & RHspray systems.

    - - -Cut in L.P. heaters 2 &3.

    Ensure switching on ofload controller above

    60MW.

    - - -

    Cut out heating steamfrom Aux. P.R.D.S. toDeaerator.

    -

    - - -

    Peg Deaerator fromCRH steam graduallyupto 2 kg/cm2.

    -

    - - - Cut in auto controllers. -

    - -

    Load : 55 MW

    M.S. :54kg/cm2/3500C

    HRH : 12kg/cm2/3400C

    Charge Aux. PRDSstation from CRH. Cutin spray and maintain atemperature of 2500C.

    Ensure energizing ofsolenoid in trimmingdevice at and above100 MW load.

    - - -Peg Deaeratorgradually to 4 kg/cm2.

    Raise the pressure set

    point of Deaeratorpressure controllergradually.

    - - -Cut in IInd mill and cutin auto controllers.

    -

    - - -Start withdrawing oilsupport gradually.

    Ensure fire ball scannerhealthiness

    - - -Control main steamand reheat steamtemperatures by usingspray if required.

    -

    10 440'

    Load : 160 MW

    M.S. :90kg/cm2/3800C

    HRH : 20kg/cm2/3800C

    Steam flow : 580t/hr.

    Increase the wind box

    to furnace differentialpressure to 100mmW.C. by adjustingSADC.

    -

  • 8/10/2019 500MW Starting Procedures

    14/38

    - - -Charge H.P. heaters

    5A, 5B, 6A and 6B.-

    - - - Put controllers on auto. -

    - - -Start first TDBFP &second CEP.

    -

    - - -

    Charge Deareatorpegging steam flowCRH to Extractionaround 200 MW load.

    Ensure DeareatorPressure controller

    remains as auto.

    11 480'

    Load : 250 MW

    M.S. :120kg/cm2/4200C

    HRH : 26kg/cm2/3400C

    Steam flow : 820t/hr.

    Cut in IIIrd mill and cutin auto controllers.

    -

    - - - Start second P.A. Fan.

    Before starting P.A. fanensure that air and gas

    dampers of PAPHs areopen.

    12 510'

    Load : 320 MW

    M.S. :125kg/cm2/3500C

    HRH : 28-30kg/cm2/3400C

    Steam flow : 1040t/hr.

    Cut in IVth mill and cut

    in auto controllers.

    -

    - - -Cut of oil supportcompletely.

    Ensure healthiness offire ball scanners.

    13

    550'

    Load : 405 MW

    M.S. :145kg/cm2/4600C

    HRH : 33kg/cm2/4600C

    Steam flow : 1310

    t/hr.

    Cut in Vth mill and cut

    in auto controllers. -

    - - -

    Cut in second TD BFP

    and switch off motordriven BFP.

    -

    14 590'

    Load : 500 MW

    M.S. : 170

    kg/cm2

    /4750

    C

    If full load is notreached cut in VIth millalong with its

    controllers. Increasethe set point of SH &

    -

  • 8/10/2019 500MW Starting Procedures

    15/38

    HRH : 40.5

    kg/cm2/4750C

    RH spray controllers

    such that ratedparametes areachieved gradually.

    15 670'

    Load : 405 MW

    M.S. :145kg/cm2/4600C

    HRH : 33kg/cm2/4600C

    Steam flow : 1310

    t/hr.

    - -

    WARM AND HOT START UPS

    (With Aux. Steam Available).

    A warm start up is, by definition, one which the maximum of HP casing/HP

    shaft temperature is between 1500C and 3500C. This normally means that the unit is

    shut down from the maximum load for one to four days. Depending upon the absolute

    temperature of HP casing and HP shaft, steam parameters are derived. A hot start up is

    by definition one which the maximum of HP casing/shaft temperature is more than

    3500C. In this case to get the rolling parameters two mills are taken into service keeping

    HP, LP by pass in operation. (Again the flow rate is restricted by the Y pieces

    constraints i.e., 400C). In both the cases, curves are given to derive the rolling

    parameters. In case when machine is rolled through EAST, curve generators, calculate

    and give permissive for rolling.

    INTEGRATED START-UP PROCEDURE

    WARM START UP (AFTER 48 HOURS SHUT DOWN).

    STEPTIME INMINUTES

    UNIT CONDITION OPERATION NOTES.

    - -

    One CC pump in

    operation and scannerfan in operation.

    Motor operated BFP isrun as and whenrequired to maintain

    the drum level.

    -

    - -Both SAPHs and

    PAPHs in operation. - -

  • 8/10/2019 500MW Starting Procedures

    16/38

    - -

    Turbine on bearinggear with AOP, JOPand seal oil pumps inoperation.

    - -

    - -

    Control fluid system

    ready in all respects.One circulating pumpin operation with oneearth filter and ultrafine filter in circuit.

    - -

    - -

    Generator gassystem, seal oilsystem and primarywater system inoperation.

    - -

    - -Bearing cooling watersystem in operation.

    - -

    - -

    HT and LT auxiliariespower supply

    available.

    - -

    - -HP bypass systemready in all respects.

    - -

    - -ESP ready in allrespects.

    - -

    - -EAST panels ready inall respects.

    - -

    - -

    Furnace bottom ash

    system and sealtrough lined up.

    - -

    - -Vacuum pumps linedup and ready for

    operation.

    - -

    - -

    Gland steam and leak

    steam controllers arelined up and ready foroperation.

    - -

    - -

    Generator protectionpanel and exciter

    panels ready in allrespects.

    - -

    - -

    Boiler drum pressure= 0 kg/cm2. SHtemperature between

    1300C and 1500C.

    1.Charge auxiliarysteam header fromexisting units. Pr.

    16ata temp. 2600C.

    -

    - - -

    2.Charge steam tofuel oil pump house,atomising steam andtracing steam.

    -

    -

    -

    -

    3.Start tank heating

    of LSHS oil. -

  • 8/10/2019 500MW Starting Procedures

    17/38

    - - -

    4.Start one LSHSpump on recirculationas soon as sufficient oiltemp. at inlet is

    achieved.

    -

    - - -

    Start instrument oilcompressor andservice aircompressors and checkthat all lines to boiler

    and TG are charged.

    -

    - - -

    Charge LSHS pump toboiler front and keep iton long recirculationwith heaters controlset on auto to maintain1200C.

    -

    - - -

    Start circulating waterpump for condenserand deaerate the

    condenser waterboxes.

    -

    - - - Start second CC Pump.

    Ensure running ofmotor driven BFPcontinuously formaintaining drum

    level.

    - - -Start one set of ID and

    FD fans.-

    - - - Initiate boiler purge. -

    - - -Start one CEP andkeep the hot well makeup in service.

    -

    - - -

    Start one of the controlfluid pumps and keepthe second as auto

    standby.

    -

    - - -

    Keep the control fluid

    temperature control onauto.

    -

    - - -

    Line up main steam,CRH and HRH steamlines for charging by

    opening respective linedrains.

    -

    - - -Line up FSSS panels inall respects

    -

    - - -

    Charge heating steam

    line to Deaerator fromAux. PRDS.

    -

  • 8/10/2019 500MW Starting Procedures

    18/38

    01 oo

    Boiler ready for lightup and turbine onturning gear.

    Start 4 burners in ABelevation with LSHS.

    Check that SH & RHvents are open.

    - - - -SH & RH drains areopen.

    - - - -MSVs closed anddrains before MSVopen.

    - - - -Ensure atomisingsteam pressure of

    about 6 kg/cm2

    - - - -

    Ensure motoroperated BFP is inservice.

    - - -Start Gland steamExhauster.

    -

    - - -Start one by onevacuum pumps.

    -

    - - -

    Admit gland steamwhen vacuum reaches0.2 kg/cm2.

    Ensure gland steamadmission

    temperature is alwaysabove 2000C.

    - - -

    Vacuum building canbe done through SGCvacuum on startingprogramme mode.

    Gland steam exhauster

    has to be startedmanually.

    -

    - - -

    Open all drainsconnected to flash

    tanks and flash boxesconnected tocondenser.

    Ensure condenser

    vacuum of 0.8kg/cm2.

    - - - Switch on SLC drains. -

    - - -Close SH & RH headervents and drains.

    Ensure boiler pressureis 2kg/cm2.

    - - -Open HPBP warmingup valves. -

    - - -Open MSV bypasslines.

    -

    - - -

    Switch Automaticcontrol interface of LP

    bypass.

    As soon as the fixedset point reaches

    12kg/cm2, it seizes.

    - - - -

    Automatic controlinterface getsswitched off when thehot reheat steampressure reaches13kg/cm2(i.e.) after

  • 8/10/2019 500MW Starting Procedures

    19/38

    synchronisation.

    - - -Open Main steam stopvalves.

    Ensure MS, CRH &HRH lines get warmedup.

    - - -

    Open HP bypass andclose the HPBP warmup valves.

    Ensure Boiler pressure

    is 5kg/cm2.

    - - - Start third CC pump.Ensure Boiler pressureis 9kg/cm2.

    - - -

    Put HP bypasscontroller on auto and

    vary the set point

    according to thegradient of pipeline

    temperatures.

    Ensure Boiler pressure

    is 10kg/cm2

    - - -Put HP bypass spray

    control on auto.-

    - - -

    Take additional guns

    according to therequirement.

    Air heater soot

    blowing to be carriedout.

    A ROLLING THROUGH HYDRAULIC GOVERNOR.

    02 180'

    MS: 50 kg/cm2/3650C

    HRH: 12kg/cm2/3250C

    By pass steam flow:170t/hr.

    Open HPESV andIPESV for warming up

    by operating startingdevice to approx. 42%

    Check and ensurethat speed set point is

    zero and speeder gearis 0%.

    - - - -

    Ensure TSE influenceis switched on and

    available margins are

    greater than 300K.

    03 210'

    MS: 60 kg/cm2/4000C

    HRH: 12kg/cm2/3500C

    By pass steam flow:200t/hr.

    Raise the speed setpoint of EHC to 3200rpm.

    If the oil system ofEHC is isolated atspeed Gov. rack,speed set point need

    not be raised.

    - - -Gradually rise thestarting device to bringthe speed to 360 rpm.

    Starting devicepositionapproximately 56%.

    - - -

    Hold the speed at 360rpm for about 5minutes.

    Ensure closure of gatevalve gearing at 240rpm.

  • 8/10/2019 500MW Starting Procedures

    20/38

    - - - -

    Monitor bearingvibrations, shaftvibrations, TDEmargins, bearing

    temp. & Turbovisory

    readings at 360rpm.

    04 215'Turbine running at360 rpm.

    Raise the speed upto2400 rpm throughstarting device at therate of 600 rpm.

    Ensure tripping of JOPat 540 rpm.

    - - -

    Raise further speedupto 3000 rpmthrough speeder gear.

    Starting device will beat 90%.

    - - - -

    Monitor bearing temp& vibrations, shaftvibrations, TSEmargins and

    Turbovisory readings.Seal oil, Primarywater and gas

    temperatures &Generator windingtemperature.

    - - - -Ensure tripping ofAOP at 2950 rpm.

    - - - -

    Speeder gear positionwill be approx. at 50to 60 %.

    05 220'Turbine running at

    3000 rpmPut AVR on auto. -

    - - - Close field breaker. -

    - - -Set manually thegenerator voltage to

    grid voltage.

    -

    - - -

    Synchronise the

    generator with grid.Pick up 50 MW load byoperating speeder

    gear.

    -

    - - -Increase HPBP setpoint.

    Ensure closure ofHPBP steam valves &spray valves.

    - - -Close other drains,M.S. HRH, keeping SLCdrains on.

    Drain pot drains ofMS, CRH, and HRHand extraction steamlines will operate as

    per the actuation oflevel switches.

    -

    -

    -

    -

    Further load raisingwill be done by

    operating the speedergear according to the

  • 8/10/2019 500MW Starting Procedures

    21/38

    start up curve.

    B ROLLING THROUGH EHC

    02 180'

    MS: 50 kg/cm2/3650C

    HRH: 12kg/cm2/3250C

    By pass steam flow:170t/hr.

    Open HPESVs and

    IPESVs for warming upby operating startingdevice to approx. 42%.

    Check and ensurethat TSE influence is

    switched on andavailable margins are

    greater than 300K.

    - - - -

    Check and ensurethat speed set point iszero and speeder gearis 0%.

    03 210'

    MS: 60 kg/cm2/4000C

    HRH: 12kg/cm2/3500C

    By pass steam flow:200t/hr.

    Turbine ready forrolling.

    Raise the startingdevice to about 70%.

    Check and ensureopening of valves in

    HP/IP secondary fluidlines to EHC at speedcontrol rack.

    - - -

    Raise the speed setpoint to 360 rpm and

    watch the actualspeed.

    If tracking device is

    switched on startingdevice position willautomatically trackthe EHC position

    - - -Raise the speeder gearto 100%.

    Ensure closure of gatevalve gearing at 240

    rpm.

    - - -

    Hold the speed at 360rpm for about 5minutes.

    Monitor bearingvibrations bearingtemperatures, shaftvibrations, TSE

    margins & turbovisoryreadings.

    04 215'Turbine running at

    360rpm.

    Raise the speed set

    point to 3000 rpm.

    Ensure tripping ofJacking oil pump at340 rpm.

    - - - -

    Monitor bearingvibrations and temps,

    shaft vibration,turbovisory readingsand TSE margins.

    - - - -Ensure tripping ofAOP at 2950 rpm.

  • 8/10/2019 500MW Starting Procedures

    22/38

    05 225'Turbine speed: 3000rpm.

    Put AVR on auto closeField breaker.

    -

    - - -Set manuallygenerator voltage togrid voltage.

    -

    - - -Synchronise thegenerator with grid.

    Speed set point willbe raise automaticallyby about 8 rpm & load

    will be picked upto 20MW.

    - - -Raise the speed setpoint and pick up theload to 50 MW.

    -

    - - -Increase HPBP setpoints.

    Ensure closure ofHPBP steam valves

    and spray valves.

    - - -

    Close other drains ofMS, CRH, and HRHkeeping SLC drains

    ON.

    Drain pot drains ofMS, CRH, HRH andextraction steam lineswill operate as per theactuation of levelswitches.

    C ROLLING THROUGH SGC TURBINE.

    02 180'

    MS: 50 kg/cm2/3650C

    HRH: 12kg/cm2/3250C

    By pass steam flow:170t/hr.

    Switch on the start upprogramme of SGC

    Turbine.

    Ensure TSE influence

    is switched on.

    - - - -

    If the programmeinterrupts theparticular step and

    criteria to be checkedand corrected for theprogramme toproceed further.

    - - - -

    All operations as

    explained under EHCrolling will be carriedout by SGC Turbineprogramme

    sequentially.

  • 8/10/2019 500MW Starting Procedures

    23/38

    03 210'

    MS: 50 kg/cm2/3650C

    HRH: 12kg/cm2/3250C

    By pass steam flow:170t/hr.

    Turbine ready forrolling.

    Turbine speed will be

    raised to 360 rpmthrough SGC-Programme.

    Ensure closure of gatevalve gearing at 240rpm.

    - - - -

    Monitor bearingvibration, bearingtemp, shaft vibration,TSE margins and

    Turbovisory readings.

    - - - -

    To achieve the

    programme as per thestarting curve, themain steam

    temperature shouldbe maintainedsteadily till loadingupto 50 MW.

    04 215'

    MS: 60 kg/cm2/4000C

    Turbine running at

    360 rpm.

    Turbine speed will beraised upto 3000 rpm

    through SGCProgramme.

    Ensure tripping of JOPat 540 rpm. Ensure

    tripping of A.O.P. at2950 rpm.

    - - - -

    Monitor bearing temp& vibrations, shaftvibrations, TSE

    margin andturbovisory readings,seal oil, primary

    water, Hydrogen gasand Generator

    windingtemperatures.

    05 225'

    MS: 60 kg/cm2/4000C

    Turbine speed: 3000rpm.

    SGC programme will

    switch ON fieldbreaker, put AVR onauto, synchronise andpick up load upto 20MW.

    Ensure SGC Startup programme iscompleted.

    - - -Raise the speed setpoint and pick up loadupto 50 MW.

    -

  • 8/10/2019 500MW Starting Procedures

    24/38

  • 8/10/2019 500MW Starting Procedures

    25/38

    - - -Peg Deaeratorgradually upto 4kg/cm2.

    Raise the pressure setpoint of Deaeratorpressure controllergradually

    - - -

    Cut in H.P. heaters and

    put the level controlson auto.

    -

    - - -

    Start first TD BFP and

    second CEP around aload of 170 MW.

    -

    - - -

    Increase the windboxto furnace diff.pressure to 100mm.W.C. by adjustingSADC.

    -

    08 270'

    Load: 200 MW

    MS: 100kg/cm2/4350C

    HRH: 19kg/cm2/4000C

    Main steam flow:750t/hr.

    Cut in IInd mill and cutin auto controllers.

    -

    - - -Start withdrawing oilsupport gradually.

    Ensure healthiness offire ball scanners.

    - - -Control main steamand reheat steam

    temperature by usingspray if required.

    -

    - - -

    Change Deaeratorpegging steam fromCRH to Extraction

    steam.

    Ensure Deaeratorpressure controllerremains on auto.

    - - -Cut in IIIrd mill and

    cut in auto controllers.-

    - - - Start second P.A. fan.

    Before starting P.A.

    fan ensure that airand gas dampers ofPAPH are open.

    09 300'

    Load: 320 MW

    MS: 125kg/cm2/4500C

    HRH: 30kg/cm2/4300C

    Main steam flow:

    1080t/hr.

    Cut in IVth mill and cut

    in auto controllers.-

  • 8/10/2019 500MW Starting Procedures

    26/38

    - - -Cut off oil supportcompletely.

    Ensure healthiness offire ball scanners.

    - - -Cut in Vth coal mill andcut in auto controllers.

    -

    - - -

    Start second TDBFPand switch off motordriven BFP.

    -

    - - -Cut in VIth coal milland cut in autocontrollers.

    -

    10 340'

    Load: 500 MW

    MS: 170kg/cm2/4800C

    HRH: 40.5

    kg/cm2/4800C

    Main steam flow:1620t/hr.

    Check all parametersat full load and ensure

    them within limits.

    -

    - - -

    Increase the set pointof SH & RH spraycontrollers such that

    rated parameters areachieved.

    -

    11 420'

    Load: 500 MW

    MS: 170kg/cm2/5350C

    HRH: 40.5kg/cm2/5350C

    Main steam flow:1570t/hr.

    - -

    INTEGRATED START UP PROCEDURE

    HOT START UP (AFTER 8 HOURS SHUT DOWN)

    STEPTIME IN

    MINUTES.UNIT CONDITION OPERATION NOTES.

    - -Two CC pumps inoperation and scanner

    fan in operation.

    Motor operated BFP isrun as and whenrequired to maintain

    the drum level. Ifnecessary BFP should

    -

  • 8/10/2019 500MW Starting Procedures

    27/38

    be kept runningcontinuously.

    - - Both SAPHs andPAPHs in operation.

    - -

    - -

    Turbine on barringgear with AOP, JOPand seal oil pumps inoperation.

    - -

    - -

    Control fluid pump inoperation. Onecirculating pump inoperation with one

    earth filter and ultrafine filter in circuit.

    - -

    - -

    Generator gassystem, seal oilsystem and primarywater system inoperation.

    - -

    - -Bearing cooling watersystem in operation.

    - -

    - -Condenser circulatingwater system inoperation.

    - -

    - -Service air andinstrument aircompressors inoperation.

    - -

    - -

    One condensate pumpin operation and hotwell make up in

    service.

    - -

    - -Aux. steam headercharged from existingunits (16ata 2600C).

    - -

    - -

    LSHS pump inoperation on longrecirculation uptoboiler front withheaters control set on

    - -

    - -HP bypass systemready in all respects.

    - -

    - -LP & HP and chemicaldosing system ready.

    - -

    - -ESP panels ready inall respects.

    - -

    - - EAST panels ready inall respects.

    - -

  • 8/10/2019 500MW Starting Procedures

    28/38

    - -

    Furnace bottom ashsystem and sealtrough lined up.

    - -

    - -

    Vacuum pumps linedup and ready for

    operation.

    - -

    - -

    Gland steam and leaksteam controllers are

    lined up and ready foroperation.

    - -

    - -

    Generator protectionpanel and exciterpanels ready in allrespects.

    - -

    - -FSSS panel ready in

    all respects.- -

    - -

    Boiler drum Pr. 75kg/cm2SH. Temp.

    between 4150C and4300C.

    Line up main steam,CRH and HRH steamlines for charging byopening respective linedrains.

    Ensure MSV is closed.

    - - -Start one gland steam

    exhauster.-

    - - -Start one by one

    vacuum pumps.-

    -

    -

    -

    Admit gland steam

    when vacuum reaches0.2 kg/cm2.

    Ensure gland steam

    admission

    temperature is alwaysabove 2000C.

    - - -

    Vacuum building canbe done through SGC

    vacuum on startingprogramme mode.Gland steam exhausterhas to be started

    manually.

    -

    -

    -

    -

    Open all drains

    connected to flash

    tanks and flash boxesconnected tocondenser.

    Ensure condenser

    vacuum of 0.8kg/cm2.

    - - -Ensure condenser

    vacuum of 0.8 kg/cm2.-

    - - -Open HPBP warming

    up valves.-

    - - -Switch Automaticcontrol interface of LPbypass.

    As soon as the fixedset point reaches 12kg/cm2, it seizes.

  • 8/10/2019 500MW Starting Procedures

    29/38

  • 8/10/2019 500MW Starting Procedures

    30/38

    - - -Start both P.A. fansand seal air fans.

    Before starting P.A.Fans ensure that airand gas dampers ofPrimary air preheaters

    are open.

    - - - Line up milling systemfor starting.

    -

    A ROLLING THROUGH HYDRAULIC GOVERNOR

    02 40'

    MS: 85 kg/cm2/4850C

    HRH: 12kg/cm2/4400C

    Bypass steam flow:280t/hr.

    Cut in first coal mill &cut in auto controllers.

    Make ready SH andRH spray system.

    - - - Charge ESP fields.

    Ensure Ash handlingsystem is ready.

    - - -

    Increase the windboxto furnace diff.Pressure to 100mm

    W.C. by adjustingS.A.D.C.

    -

    - - -Cut in second mill andcut in auto controllers.

    -

    - - -Peg the deaerator fromCRH gradually upto 2kg/cm2.

    -

    - - -

    Open HPESVs andIPESVs for warming up

    by operating startingdevice toapproximately 42%.

    Check and ensurethat speed set point iszero and speeder gear

    is at 0%.

    - - - -

    Ensure TSE influenceis switched on andavailable margins are

    greater than 300K.

    03 50'

    MS Pressure: 85kg/cm2

    MS Temperature:5000C

    HRH Pressure: 12kg/cm2

    HRH Temperature:4500C.

    Bypass steam flow:

    360t/hr.

    Raise the speed setpoint of EHC to 3200rpm.

    If the oil of EHC isisolated at speed Gov.rack, speed set pointneed not be raised.

  • 8/10/2019 500MW Starting Procedures

    31/38

    Turbine Ready forrolling

    - - -

    Gradually raise thestarting device to bringthe speed to 360 rpm

    Starting devicepositionapproximately 56%.

    -

    -

    -

    -

    Ensure closure of gate

    valve gearing at 240rpm.

    - - - -

    Monitoring bearingvibrations, shaft

    vibrations, TSEmargins, bearingtemp & Turbovisoryreadings at 360 rpm.

    04 52'Turbine running at360rpm.

    Raise speed upto 2400rpm through startingdevice at the rate of600 rpm.

    Ensure tripping of JOPat 540 rpm.

    - - -

    Raise further speedupto 300 rpm throughspeeder gear.

    Starting device will beat 90%.

    - - - -

    Monitor bearing tempand vibrations, shaftvibrations, TSEmargins andturbovisory readings.

    Seal oil Primary waterand gas temperaturesand Generator

    winding temperature.

    - - - -Ensure tripping of

    AOP at 2950 rpm.

    - - - -

    Speeder gear positionwill be approximatelyat 50 to 60%.

    05 56'Turbine running at3000rpm

    Put AVR on auto. -

    - - - Close field breaker. -

    - - -

    Set manually thegenerator voltage togrid voltage.

    -

  • 8/10/2019 500MW Starting Procedures

    32/38

    - - -

    Synchronise theGenerator with grid.Pick up 50 MW load byoperating speeder

    gear.

    -

    - - -Increase HPBP setpoint.

    Ensure closure ofHPBP steam valves &spray valves.

    - - -Close other drains,M.S. CRH, HRH,keeping SLC drains on.

    Drain pot drains ofMS, CRH, and HRHand extraction steamlines will operate asper the actuation oflevel switches.

    - - - -

    Further load raisingwill be done byoperating the speeder

    gear according to thestart up curve.

    B ROLLING THROUGH EHC

    02 40'

    MS Pressure: 85kg/cm2

    MS Temperature:4850C

    HRH Pressure: 12kg/cm2

    HRH Temperature:4400C.

    Bypass steam flow:280t/hr.

    Cut in first coal mill &cut in auto controllers.

    Make ready SH & RHspray systems.

    - - - Charge ESP fields.Ensure Ash handlingsystem is ready.

    -

    -

    -

    Increase the windbox

    to furnace diff.

    Pressure to 100mmW.C. by adjustingS.A.D.C.

    -

    - - -Cut in second mill andcut in auto controllers.

    -

    - - -Peg the deareator fromCRH gradually upto 2kg/cm2.

    -

    - - -

    Open HPESVs andIPESVs for warming upby operating startingdevice to

    approximately 42%.

    Check and ensurethat speed set point is

    zero and speeder gear

    is at 0%.

  • 8/10/2019 500MW Starting Procedures

    33/38

    - - - -

    Ensure TSE influenceis switched on andavailable margins are

    greater than 300K.

    03 50'

    MS Pressure: 85

    kg/cm2

    MS Temperature:5000C

    HRH Pressure: 12kg/cm2

    HRH Temperature:4500C.

    Turbine Ready forrolling. Bypass steamflow: 360t/hr.

    Raise the startingdevice to about 70%.

    Check and ensureopening of valves inHP/IP secondary fluidlines to EHC at speed

    control rack.

    - - -

    Raise the speed setpoint to 360 rpm andwatch the actualspeed.

    If tracking device isswitched on startingdevice position willautomatically trackthe EHC position.

    - - -Raise the speeder gearto 100%.

    Ensure closure of gate

    valve gearing at 240rpm.

    - - -

    Hold the speed at 360rpm for about 5minutes.

    Monitor bearingvibrations, bearingtemperatures, shaftvibrations, TSEmargins andturbovisory readings.

    04 52'Turbine reading at360 rpm.

    Raise the speed setpoint to 300 rpm.

    Ensure tripping ofJacking oil pump at

    540 rpm.

    - - - -

    The rate of

    acceleration will be600 to 800 rpm2.

    - - - -

    Monitor bearingvibrations andtemperatures, shaftvibration, turbovisory

    readings and TSEmargins.

    - - - -

    Monitor and control,seal oil temperatures,primary water

    temperature.Hydrogen gastemperature andwinding temperature.

  • 8/10/2019 500MW Starting Procedures

    34/38

    - - - -Ensure tripping ofAOP at 2950 rpm.

    05 56'Turbine speed: 3000rpm.

    Put AVR on auto Closefield breaker.

    -

    - - -

    Set Manually generatorvoltage to grid voltage. -

    - - -Synchronise thegenerator with grid.

    Speed set point willbe raisedautomatically byabout 8 rpm and load

    will be picked upto 20MW.

    - - -Synchronise thegenerator with grid.

    -

    - - -Increase HPBP set

    point.

    Ensure closure ofHPBP steam valves

    and spray valves.

    - - -

    Close other drains of

    MS. CRH and HRH,keeping SLC drains

    ON.

    Drain pot drains ofMS, CRH, HRH and

    extraction steam lineswill operate as per theactuation of level

    switches.

    C ROLLING THROUGH SGC TURBINE.

    02 40'

    MS: 85 kg/cm2/4850C

    HRH: 12kg/cm2.

    Bypass steam flow:

    280t/hr.

    Cut in first coal mill &cut in auto controllers.

    Make ready SH & RHspray systems.

    - - - Charge ESP fields.Ensure Ash handling

    system is ready.

    - - -

    Increase the windbox

    to furnace diff.Pressure to 100mmW.C. by adjusting

    S.A.D.C.

    -

    - - -Cut in second mill and

    cut in auto controllers. -

    - - -

    Peg the deaerator from

    CRH gradually upto 2kg/cm2.

    -

    - - -

    Switch on the start upprogramme of SGC-Turbine.

    Ensure TSE influenceis switched ON.

    - - - -

    If the programmeinterrupts, theparticular step and

    criteria to be checkedand corrected for the

  • 8/10/2019 500MW Starting Procedures

    35/38

    programme toproceed further.

    - - - -

    All operations asexplained under EHC

    rolling will be carriedout by SGC-Turbineprogrammesequentially.

    03 50'

    Turbine ready forrolling.

    MS: 85 kg/cm2/5000C

    HRH: 12kg/cm2/4500C

    Bypass steam flow:

    360t/hr.

    Turbine speed will be

    raised to 360 rpm

    through SGC-programme.

    Ensure closure of gatevalve gearing at 240

    rpm.

    - - - -

    Monitor bearingvibration, bearingtemperature, shaftvibration, TSEmargins andTurbovisory readings.

    - - - -

    To achieve the

    programme as per thestart up curve, themain steam

    temperature shouldbe maintainedsteadily till loading of50 MW.

    04 52'Turbine reading at

    360 rpm.

    Turbine speed will beraised upto 3000 rpm

    through SGC-programme.

    Ensure tripping of JOP

    at 540 rpm.

    - - - -Ensure tripping ofAOP at 2950 rpm.

    - - - -

    Monitor bearingtemperature andvibrations, shaftvibrations, TSEmargins, Turbovisoryreadings, seal oil,

    primary water,Hydrogen gas andGenerator windingtemperatures.

  • 8/10/2019 500MW Starting Procedures

    36/38

    05 56'

    Turbine speed: 3000rpm.

    MS: 85 kg/cm2/5000C

    HRH: 12kg/cm2

    /4500

    C

    Bypass steam flow:360t/hr.

    SGC Programme willswitch ON fieldbreaker, put AVR onauto synchronise and

    pick up load upto 20MW.

    Ensure SGC-start upprogramme is

    completed.

    - - -Raise the speed setpoint and pick up loadupto 50 MW.

    -

    - - -Increase HPBP setpoint.

    Ensure closure ofHPBP steam valves &spray valves.

    - - -

    Close other drains ofM.S, CRH and HRH,keeping SLC drains

    ON.

    Drain pot drains of

    MS, CRH, HRH andExtraction steam lineswill operate as per theactuation of level

    switches.

    06 60'

    LOAD: 60 MW.

    MS: 85 kg/cm2/5000C

    HRH: 16kg/cm2/4700C

    Cut in L.P. heaters 2

    and 3.

    Ensure switching onof load controller at60 MW.

    - - -

    Cut out heating steam

    from Aux. PRDS toDeaerator.

    -

    - - -Raise the generatorpressure from2kg/cm2to 4kg/cm2.

    Raise the pressure setpoint of Deaeratorpressure controller.

    - - - Cut in auto controller. -

    - - -Start withdrawing oilsupport gradually.

    Ensure healthiness offire ball scanners.

    07 65'

    LOAD: 150 MW.

    MS: 100kg/cm2/5000C

    HRH: 20kg/cm2/4800C

    Main steam flow:1620t/hr.

    Trimming device is inOFF.

    Charge Aux. PRDSstation from CRH. Cutin spray and maintaina temperature of

    2500C.

    -

    - - -

    Cut in H.P. heaters andput the level controls

    on auto.

    -

  • 8/10/2019 500MW Starting Procedures

    37/38

    - - -

    Start first TD BFP andsecond CEP around aload of 170 MW.

    -

    - - -

    Control main steamand reheat steam

    temperature by usingspray if required.

    -

    - - -

    Change deaerator

    pegging steam fromCRH to Extractionsteam.

    Ensure Deaeatorpressure controller

    remains on auto.

    - - -Cut in IIIrd mill andcut in auto controllers.

    -

    08 70'

    LOAD: 230 MW.

    MS: 120

    kg/cm2/5000C

    HRH: 20kg/cm2/4950C

    Main steam flow:820t/hr.

    Cut in IVth mill and cutin auto controllers.

    -

    - - -Cut off oil support

    completely.

    Ensure healthiness of

    fire ball scanners.

    - - -Cut in Vth coal mill and

    cut in auto controllers.-

    - - -

    Start second TD BFP

    and switch off motordriven BFP.

    -

    - - -

    Cut in VIth coal milland cut in autocontrollers.

    -

    09 86'

    LOAD: 500 MW.

    MS: 170kg/cm2/5000C

    HRH:

    40.5kg/cm2/5000C

    Main steam flow:

    1620t/hr.

    Check all parametersat full load and ensurethem within limits.

    -

    - - -

    Increase the set point

    of SH & RH spraycontrollers such thatrated parameters are

    achieved.

    -

  • 8/10/2019 500MW Starting Procedures

    38/38

    10 135'

    LOAD: 500 MW.

    MS: 170kg/cm2/5000C

    HRH: 40.5kg/cm2/4800C

    Main steam flow:1570 t/hr.

    - -

    ********************