5.09.2006v. bobillier1 cable installation status

12
5.09.2006 V. Bobillier 1 Cable installation status

Upload: dora-stone

Post on 18-Jan-2018

219 views

Category:

Documents


0 download

DESCRIPTION

V. Bobillier3 Long distance links installation (from CH to PP) Cabling

TRANSCRIPT

Page 1: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 1

Cable installation status

Page 2: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 2

Long distance links installation (from CH to PP)

Work progress (cable pulling) :

• Velo service cables (motion, cooling and vacuum ctrl) done • Calorimeter : All cables done • Muon : All cables done except some HV cables (due to late ordering).• All sub-detectors : Cables for Maraton LVPS (pwr + ctrl) done• Links to bunker racks : done

Remaining main tasks :

• Velo, TT, Rich1 cable pulling• Cutting cable at right lengths• Installation of all connectors• Installation of optical fiber cables• Tests of all cables

Cabling

Page 3: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 3

Long distance links installation (from CH to PP)

Cabling

Page 4: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 4

Cabling

Page 5: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 5

Long distance links installation (from CH to PP)

Missing information and material :

For all long distance links:

• Cable allowance on both ends. Use Rackwizard to enter that in the cable DB.

If information is not in rackwizard on time we will simply not be able to cut your cables at the right lengths and install connectors. Reminders will be made individually to sub-detector rackwizard responsible 2 weeks prior to deadline.

Cabling

Page 6: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 6

Long distance links installation (from CH to PP)

Missing information and material :

For specific sub-detector cables :

• Precise drawings are required (with detailed explanation when particular care must be taken). This is particularly important for certain connectors. Good examples of cable drawings can be found here :

https://edms.cern.ch/nav/EDA-01313https://edms.cern.ch/nav/EDA-01314

• Specific connectors must be received at pit 8 one week before they are planed to be installed.

Cabling

Page 7: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 7

Patch cord cables (in CH and from PP to sub-det)

REMINDER “Who is responsible for what” :

• Cable ordering: Sub-detectors• Cable installation: Sub-detectors with help from CERN

(to be discussed case by case in more detail). • Connectors: Sub-detectors with help from CERN

(to be discussed in more detail).

• Exception : TELL1 boards: sub-detectors only have to take care of MPO patch cords.

Further discussions are needed with sub-detectors requiring help for installation !

Cabling

Page 8: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 8

Patch cord cables (in CH and from PP to sub-det)

Who does what:

• Rich: Cabling done by themselves• OT: Same• Calorimeter: Same• Muon: Not defined yet.• ST: Help from CERN needed (to be discussed more precisely)• Velo: Help from CERN needed (to be discussed more precisely)

Things to consider before cable pulling when done by sub-detectors:

• Identify cable duct covers before removing them (easier to remount them)• Store them in a safe place (to avoid people walking on it)• Protect sharp angles and edges in the ducts (plastic joint and tape)• Pull thick cables first• (Identify cables)

Cabling

Page 9: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 9

All racks other than TELL1 in CH and in cavern

Remaining main tasks :

• Big mechanical work still to be done in all other non-TELL1 racks. This means :

• Sub-detectors must define the rack layout in rackwizard.• Buy required equipment (deflector, heat exchangers, etc if standard recuperated ones are not ok).• Rack internal cabling must be thought (equipment size, front/rear connection, air flow and other constraints must be taken into account).• Metallic side plates have to be cut at right length and installed (fixed layout needed).• Sliding bars have to be mounted (fixed layout needed).• When standard HE, deflectors are used they can be installed (fixed layout needed).

Goal: Have the racks prepared as much as possible so it can be nearly “plug and play” to install your equipments.

If information is not received well in advance we will not be able to prepare your racks mechanically !

Planning: We need to know when you plan to come to pit 8 with the first equipment ?

Racks and crates

Page 10: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 10

All racks other than TELL1 in CH and in cavern

For the moment, all other racks look like that :

• No side plates for air flow• No internal support for cables• No sliding bars• No heat exchangers• No flexible cooling pipes connecting HE• No deflectors• Already a turbine (as we receive them and there is no much choice where to install them)

If information is not received on time, your racks may look like that when you come with electronics equipment !

Racks and crates

Page 11: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 11

Very simple conclusion :

• Use rackwizard to enter all information concerning your rack layout and cabling.

• Make precise drawing of specific cables (with explanations when particular care must be taken)

• Get the connectors (and special tools when needed) for long distance links to pit 8.

Conclusion

If we do not have information

on time, racks and cables might

look like that when you come at

pit 8 with your equipment…!

Page 12: 5.09.2006V. Bobillier1 Cable installation status

5.09.2006 V. Bobillier 12

Questions / Comments ???