5.1 case study - highways escobedo v final

Upload: anonymous-2x8ywqt

Post on 10-Apr-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    1/32

    PPPInternational Best Practice and Regional Application

    Tegucigalpa, Honduras

    April 23 - 25, 2008

    Sponsored by the Spanish Trust Fund

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    2/32

    Highways

    Case StudySession 5.1

    Sabino Escobedo, TAG Financial Advisors

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    3/32

    PrivateSectorView

    Session 5.1

    PPP

    Approach

    Day 1: Session 1.1

    Overview ofPPP

    Day 1:Session 1.2

    Challenges:LatinAmerica

    Day 1:Session 1.3

    ConsideringPrivate

    Participation

    Day 1:Session 2.1

    Planning theProcess

    Day 1:Session 2.3

    InvolvingStakeholders

    Day 1:Session 3

    Case Study:Transmission

    Day 2:Session 5

    Case Studies:(1)Highways

    (2)Water& Sanitation(3) Ports

    Day 2 :Session 4.1

    Standards,Tariffs, Subsidy,

    Financials

    Day 2 :Session 4.2

    Selecting anOperator

    Day 1:Session 2.2

    Regulation& Institutions

    UpstreamPolicy

    Readinessof

    Government

    CapacityBuildingForPPP

    Day 2 Session 6

    Readiness of Government

    Day 1- Session 5

    Case Study:Highways

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    4/32

    Session 5.1PPPs in the Transport Sector

    PPPs in theS

    ector Case Studies

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    5/32

    Developing Effective PPPs in

    the TransportS

    ectorMain Objective:

    Mobilize Private Capital andManagement into TransportInfrastructure Development

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    6/32

    Transport Infrastructure Investment The Economics of Transport Infrastructure Fiscal Space (Public Investment) The Real Gap : Cost Recovery and Affordability Key Drivers of our clients demands

    Public Private Partnerships (PPPs) Leveraging Public Money Public Sector options for Infrastructure investment Risk Assessment and Risk Allocation

    Banks response to infrastructure finance needs The shift in development burden from central to local entities Performance based subsidies Innovative risk mitigation products

    Way Forward

    Contents

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    7/32

    The Economics of Transport

    Infrastructure Investments Infrastructure investments are inherently lumpy (involve huge sunk costsand create assets that are long-lived and location-specific).

    Creation of Infrastructure has economics both of scale and scope (i.e.,minimum size of facilities, inelastic adjustment of capacity to demand, longterm project completion, etc.).

    Infrastructure supply systems contain elements of natural monopoly

    (competition). Demand is wide spread (difficult to target). Revenues are usually in local currency (mismatch if foreign debt financing). Transport services have an essentiality component that raise legitimate

    public policy concerns of affordability.

    However .. Sound transport infrastructure allows countries to integrate to the global

    economy and increases competitiveness (transport and telecom sectorsare the highest contributors to a countrys competitiveness) impactingeconomic growth.

    Transport infrastructure development has a strong impact oncompetitiveness, growth, poverty alleviation and MDGs.

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    8/32

    Public Investments needs are sizeable in most countries but difficult toquantify.

    Countries face important trade-offs between infrastructure spending andother expenditure items (i.e., health and education).

    Little empirical evidence that reductions in public investments had anadverse impact on growth.

    Countries with relatively high public debt burden have a limited scope forincreasing investment via public borrowing.

    Significant scope to improve the quality of infrastructure investment.

    Changes in fiscal accounting cannot create room for additional spendingfor infrastructure.

    Most of the public enterprises in the pilots did not meet the commerciallyrun criteria.

    Effective PPPs is encourage as a way to bring in leveraging and efficiencyin infrastructure investment.

    Fiscal limits to increased publicinvestments in infrastructure

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    9/32

    The Service Delivery Gap

    There is limited affordability in theprovision of most of infrastructureservices (when including the costs of therequired infrastructure facilities), speciallywhen considering low income end-users.

    Infrastructure services has strongcharacteristics as a public good andcreates major positive externalities.

    Full cost recovery is only possible insome situations (i.e., air transport). Most

    of the basic public services have stronglimitations to reach full cost recoveryeven in developed markets (masstransport systems).

    There is a role for the provision ofsmart subsidies to make possible the

    delivery of the service.

    Tariffs

    Time

    Affordability

    Cost recovery

    The ServiceThe Service

    Delivery GapDelivery Gap

    OutputOutput

    Based AidBased Aid

    ApproachesApproaches

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    10/32

    Key Drivers for Client Demands

    Change in the risk profile of our client base: 80s : developed and developing countries 2000s forward:

    Middle Income Countries

    Transition Economies Post Conflict Failed States

    Need to fill the service delivery gap (full cost recovery not possible

    at the required pace for market driven incentives to supportinvestments)

    Fiscal Space for Public Investments will be limited at best (limitednew borrowing capacities to allocate to infrastructure development)

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    11/32

    Need to reconcile infrastructure development needs withcriteria forfiscal prudence.

    Need to mobilize additional private capital to match thegap if infrastructure development is to keep its pacesustaining economic growth.

    Need to maximize private capital mobilization per unit ofpublic sector contribution (e.g., direct investment,subsidies, guarantees, etc.).

    Need to develop PPPs approaches as a procurement tool

    for better and efficient allocation of scarce public sectorresources (the concept of value for money).

    Need to develop an adequate risk management frameworkto manage contingent liabilities arising for public moneysupport to PPPs development.

    Leveraging Public Money

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    12/32

    PPPs : Spectrum of Options

    Transport InfrastructureTransport InfrastructureFacilitiesFacilities

    Provision of TransportProvision of TransportServicesServices

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    13/32

    PPPs in Transport

    Pure Public Option:Pure Public Option:

    Funded via ordinary revenues

    Funded via earmarked taxes (i.e., gas taxes for road networkdevelopment) Funded via public debt financing (i.e., future tax payers)

    Public Private Partnerships Options:Public Private Partnerships Options:

    Funded via tolls or tariffs (i.e., full cost recovery basis) Funded via tolls or tariffs with initial co-investment contribution (e.g.,

    Bridge Rosario-Victoria, Argentina) Funded via tolls or tariffs with minimumrevenue guarantee (e.g.,

    Motorway Santiago-Valparaiso, Chile) Funded via tolls or tariffs with supplemental subsidies (e.g., BA

    metro system)

    Funded via shadow tolls orsubsidies (e.g., Portugal toll roads)

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    14/32

    Public Sector Options forInfrastructure InvestmentsSSA Toll Roads Case (1):

    Parameters:

    40 KM toll road linking two important urban centers (existingroad under very poor conditions)

    Traffic Study : 70,000 vehicles per day

    Total Investment : $ 200 million

    Annual operating & maintenance costs: 5% of total investment($ 10 million)

    SSA Credit Rating: B+

    If private options are considered:

    Debt : Equity ratio : 75%-25%

    Debt services conditions: 10 year @ 10%

    Equity expected rate of return: risk free rate + premium =5%+11% (16%)

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    15/32

    Required Annual Cash Flows (including remuneration to debt &equity)

    Operating & Maintenance : $ 10 million

    Debt Service : $ 24 million

    Equity returns: $ 8 million

    Total = $ 42.4 needed in annual revenues ($ 3.52 million permonth assuming no seasonality

    Required Average tariff per vehicle

    $ 3.52 million / 70,000*30 = $ 1.68 pervehicle

    SSA Toll Roads Case (2):

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    16/32

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    17/32

    Scenario 2 : Willingness to pay = between zero and $ 1.68 perWillingness to pay = between zero and $ 1.68 pervehicle ($0.84 pervehicle)vehicle ($0.84 pervehicle)

    (C) PPP via a collected toll fare ($0.84) plus a supplemental subsidy

    ($0.84).Subsidy can be paid as a shadow toll or can be structured as atraffic minimum revenue guarantee (defining a predeterminedlevel of total revenues). Performance risk is transfer to the privatesector. No initial disbursement by the public sector.

    (D) PPP via a co-investment between the Public and Private sector.Size of public co-investment will be equal to the differencebetween total investment and the investment amount supportedby the existing tariff (i.e., $ 126.7). Performance risk is transfer tothe private sector. Initial disbursement by public sector.

    SSA Toll Roads Case (4):

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    18/32

    Scenario 3 : Willingness to pay = equivalent to required tariff ($ 1.68)Willingness to pay = equivalent to required tariff ($ 1.68)

    (E) PPP via a collected toll fare ($1.68)

    Depending on the robustness of the traffic studies and thewillingness to pay [affordability] analysis, government and/ordonors might need to provide some type of support to the trafficrevenue scheme. Performance risk is transfer to the private sector

    SSA Toll Roads Case (5):

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    19/32

    PPP : Risk Assessment

    Completion Risk (engineering &construction cost / time cost control)

    Operational Performance Risk(technical & operational know-how)

    Environmental Risk (future liabilities,project delays, costs overruns)

    Credit Risk (project leverage)

    Inflation, interest rate and exchangeexchangerate fluctuationsrate fluctuations

    Political Risk (expropriation, political

    violence, currency convertibility &transfer)

    Regulatory RisksRegulatory Risks. (Governmentsdefault on contractual obligations, i.e.,pricing formulas, right of way )

    Legal Environment (rule of lawrule of law, i.e.,judicial system, regulatory proceduresand arbitration)

    Project Specific RisksProject Specific Risks Country (Economy wide) RisksCountry (Economy wide) Risks

    Demand (traffic) Risk

    Pricing Risk (regulatedand non-regulated)

    Environmental (pastliabilities) Risk

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    20/32

    PPP : Risk Allocation

    Principle : Risk should be allocated to those best able to manage them

    Allocating PPP Risk Guidelines:

    Allocate to the party best able to influence the risk factor (e.g.,constructions costs completion risk).

    Allocate to the party that can best anticipate orrespond to the riskfactor --influence impact or sensitivity of risk factor on project value(e.g., adapting size of the facility to demand fluctuations)

    Allocate to the party best able to absorb the risk

    Natural hedges (correlation between risk factors and stakeholderassets and liabilities)

    Access to markets offering derivatives and insurance

    Access to specialized financial institutions (IFIs, MLAs, Donors, etc.)

    Ability to spread the risk among other risk bearers (shareholders andtaxpayers)

    Risk Aversion

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    21/32

    Toll Road Finance: Risk MitigationNon-Sovereign Sovereign

    Completion

    Risk

    Performance

    Risk

    Environment

    al Risk

    Demand Risk Political Risk Regulatory

    Risk (inc.

    Land

    Acquisition

    Risk)

    Macroecono

    mic Risk

    Cost overruns

    and delays.

    Revenue

    generation and

    operationalcosts increase

    Hidden

    liabilities

    Revenue

    generation

    Expropriation,

    transfer,

    convertibilityCease of

    revenue

    generation

    Revenue

    generation.

    TariffAdjustment;

    Right of Way,

    Termination

    payment

    Revenue

    generation.

    Devaluation /inflation

    impact of

    cash flows

    High Low Low High Low High High

    EPCContract

    and

    performance

    bonds

    Performance

    based

    contracts

    Environmental

    Assessment

    Traffic

    Minimum

    Revenue

    Guarantees /

    VPN

    Concession

    Partial Credit

    Guarantees

    Political Risk

    Insurance

    Concession

    Contract

    Partial Risk

    Guarantees

    Local

    currency

    financing

    Private Private Private Private/

    Public

    Private/

    Public

    Public TBD

    Risks

    Cash

    Floweffect

    Impact

    RiskMitigation

    Instrument

    Provider

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    22/32

    Developing Local CapitalMarkets : Chile

    By the early 1990s, a sizable infrastructure gap had emerged in Chile, and significantinvestment was needed to prevent transportation and other bottlenecks from becoming a majorobstacle to future growth

    A challenge for the government was to close this gap while maintaining fiscal disciplinethat had placed public debt on a rapidly declining path. The solution lay in promotingprivate sector involvement in the provision of public infrastructure through public-privatepartnerships (PPPs). Chile thus embarked on an ambitious concessions program in 1994,centered around a number of projects to develop the highway network.

    The concessions program in Chile covers 44 contracted projects with a total value ofUS$5.7 billion (about 6 percent of 2004 GDP). These include: 8 projects to rehabilitate andupgrade the Route 5 highway which runs the length of Chile, with financing from tolls (US$2billion); 11 other highway projects for connecting roads to Route 5 (US$1.3 billion); 10 airport

    projects (US

    $240 million); 6 urban road projects (US

    $1.8 billion); and 9 other projects (includingprisons, public buildings, a reservoir, for US$360 million). Approximately 75% was funded inthe local capital markets via local currency infrastructure bonds.

    The government provides guarantees to concession operators. A minimum revenueguarantee is provided for highway and airport concessions, under which concession firms arecompensated when traffic or traffic revenue falls below an annual threshold. In return for theminimum revenue guarantee, the concession firm enters into a revenue sharing agreement in

    which it shares a percentage of revenue with the government once a threshold is exceeded.

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    23/32

    PPP and Risk ManagementFramework

    Ministry of

    Public Works

    Ministry of

    Energy

    Ministry of

    Communication

    Ministry of

    Transport

    Ministry of

    SOEs

    Local

    Governments

    Other Public

    Institutions

    PPP

    Projects

    Water

    Roads

    Electricity

    Gas

    Airport

    Ports

    Railways

    Sanitation

    Telecom

    MOFRisk Management

    Selection Criteria

    Risk Exposure

    Pricing

    Monitoring

    Documentation

    Central PPP Unit

    Coordinating Role

    Procurement Rules

    Screening

    Monitoring

    Communication

    Coordinating Entity

    (MinisterorCouncilofMinisters)

    PPP SectorTeams

    Public Sector Support for PPP

    (guarantees, subsidies, etc.)

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    24/32

    Banks response to client demands(PPPs support)

    Shift in development burden from central to local entities :the challenge of financing sub-national entities (IFCMunicipalFund, WBG scale up currently under

    consideration)

    Use of performance based subsidies (OBA approaches)

    Innovative Risk Mitigation Products (new applicationspartial risk guarantees)

    Public Financial Support for PPPs development (riskmanagement framework)

    Infrastructure Finance Vehicles (guarantee funds)

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    25/32

    Infrastructure:Developing Local Capital Markets

    There is no best substitute for foreign exchange risk mitigation than matching thecurrency revenue generation with the currency of debt payment services (matching assetsand liabilities).

    Financing transport facilities and services (local currency based) in the foreign debt marketsadds substantial risk to the structuring of adequate PPPs creating the need for additional

    public money support.

    Local institutional investors (I.e., pension funds, insurance companies, life annuities, etc.)have a natural demand for long-term local currency debt instruments to match their liabilities.

    In most cases, local capital markets initiate their development via the creation of asovereign bond market (long-term yield curve). After the establishment of such market,investors develop a need to diversify the risk profile of their investments and the return mix,providing the incentives for the development of a private bond market, creating theopportunity for the introduction ofinfrastructure orutilities bonds (long-term annuities).

    It is in the governments best interest to stimulate, via adequate securities regulation andinstitutional investors overseeing, the development of local capital markets as a source of

    long-term local currency funding for needed PPPs infrastructure projects.

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    26/32

    Innovative Risk Mitigation Products

    Local Currency Debt Instruments

    Development of Local Capital Markets (e.g., Chile and Korea)

    IBRD (on-lending to private sector)

    Currency conversion option in fixed spread loans (FSL)

    Currency swap

    Rolling forward/1

    IFC Local Currency

    Loans and Hedging Products

    Partial Credit Guarantees (asset backed securities)

    Regulatory risk support

    Partial Risk GuaranteePartial Risk Guarantee supporting transaction related regulatory framework Privatization of electricity utilities in Romania.

    Guarantee Facility for Peru PPPs infrastructure development (15 projects,wholesaling PRGs)

    Nam Theun 2, PRG supporting LAOs government commitments (IDA andMIGA guarantees).

    Tariff Indexation Risk Transfer (supplemental subsidies)

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    27/32

    Internalize externalities (e.g., sanitation) Redistributing resources (e.g., subsidize access to

    services)

    Mitigate political and regulatory risks

    Closing the gap between cost recovery andaffordability

    Market failure in financial markets (e.g., lack ofdepth for local currency funding)

    When should governments offersupport topublic private partnerships:

    Public Financial Support forInfrastructure Development

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    28/32

    Public Financial Support forInfrastructure Development (2)

    Need to reconcile infrastructure investments needs with fiscal prudence.

    Ring-fenced government sponsored vehicles to limit amount of

    contingent liabilities arising from public support to public-private partnershipsprojects (i.e., co-investment, guarantees, subsidies, off-take contracts, etc.)and assist to improve governance and transparency of the allocation ofgovernment contribution (risk management).

    Funded by governments contribution (tax payers) and donors-multilateralinterventions.

    Limited experience with government sponsored vehicles (I.e., infrastructurefunds, guarantee funds, etc. )

    Relatively unsuccessful experiences with state-owned developmentbanks in the 80s and 90s

    Keen interest by some of our larger clients (e.g., Russia, India,Indonesia, etc..)

    Financing vehicles:

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    29/32

    Way Forward

    Rebuild and adapt the PPI Model of the 90s on the basis of the lessons and experiences of therecent years and the immediate needs to reach MDGs by 2015. Private sectorstill is a key driverto sustain infrastructure development and economic growth.

    Broader use ofPPP schemes as a way to maximize public money leveraging for infrastructuredevelopment. Need to develop adequate risk mitigation instruments to support public

    contribution to infrastructure projects. Options other than private ownership of infrastructure assetsare also effective to mobilize private capital and management into infrastructure development.

    MLAs and Donors direct engagement with sub-national entities (well run public utilities) withoutcentral government support to assist them accessing private financial markets. Need to improveaccountability and use of performance based incentives (commercially run entities).

    Development of local capital markets (local currency debt instruments) as a mechanism forimproving effective access to infrastructure financing by PPPs.

    Increasing use ofoutput based subsidies as a way to utilize better private sector resources viaeffective allocation of performance risks (PPPs to deliver services to poorer communities).

    Build solid institutional capacities in the public sector to improve good infrastructure PPPs as

    well as the risk management of contingent liabilities arising from PPP support .D

    evelopment ofspecialized financing vehicles (public sector driven).

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    30/32

    Highways

    Case StudySession 5.1

    Sabino Escobedo, TAG Financial Advisors

    THANK YOU!

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    31/32

    Contacts

    Forcomments or furtherdetails contact:

    Junglim Hahm [email protected]

    Richard Cabello [email protected]

    Sabino Escobedo [email protected]

    David Stiggers [email protected]

  • 8/8/2019 5.1 Case Study - Highways Escobedo v Final

    32/32

    Highways

    Case StudySession 5.1

    Sabino Escobedo, TAG Financial Advisors

    THANK YOU!