53681209 project design of ehv substation at fact udl

Upload: jayadevdamodaran

Post on 14-Oct-2015

13 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    1/55

    DESIGN OF EHV SUBSTATION AT FACT UDL

    A Project Report

    Submitted by

    Arunkumar M.P

    Bijesh K.B

    Jijo Francis

    Lipin A.K

    In partial fulfillment of the requirements for award of the degree of Bachelor of

    TechnologyinElectrical & Electronics Engineering

    FEDERAL INSTITUTE OF SCIENCE AND TECHNOLOGY (FISAT)

    Angamaly-683577, Ernakulam

    MAHATMA GANDHI UNIVERSITY

    Kottayam-686560

    May 2011

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    2/55

    DESIGN OF EHV SUBSTATION AT

    FACT UDL

    A Project Report

    Submitted by

    Arunkumar M.P

    Bijesh K.B

    Jijo Francis

    Lipin A.K

    In partial fulfillment of the requirements for award of the degree of Bachelor of Technology

    inElectrical & Electronics Engineering

    FEDERAL INSTITUTE OF SCIENCE AND TECHNOLOGY (FISAT)

    Angamaly-683577, Ernakulam

    Affiliated to

    MAHATMA GANDHI UNIVERSITY

    Kottayam-686560

    May 2011

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    3/55

    FEDERAL INSTITUTE OF SCIENCE AND TECHNOLOGY (FISAT)

    Mookkannoor (p.o), Angamaly-683577

    CERTIFICATEThis is to certify that the project report titled DESIGN OF EHV SUBSTATION AT

    FACT UDC submitted by Jijo Francis, towards partial fulfillment of the

    requirements for the award of the degree of Bachelor of Technologyin Electronics

    and Instrumentation Engineering is a record of bonafide work carried out by them

    during the academic year 20072011.

    Internal Guide Head of the Department

    Name Ms. Sreeja Dr. Pailo Paul

    Designation Lecturer Asst. professor

    Department of EEE Department of EEE

    FISAT FISAT

    Place: Mookkannoor

    Date:

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    4/55

    ACKNOWLEDGEMENT

    First we would like to express our sincere thanks to God Almighty for giving us

    enough strength to complete our project successfully

    We have unique pleasure in thanking our teacher Ms. Sreeja for her unflinching

    devotion and help, which led us to completion of this project.

    We place on record our sincere thanks to our external guide Mr. Gopala Krishnan,

    Assistant Engineer, FEDO Department, FACT in providing necessary guidance and

    back up throughout the whole course of our project.

    The project that we did at FACT (UDL DIVISION) was quiet inspiring and we

    gained a lot of knowledge. We do hope that this project would be of help to other

    electrical students.

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    5/55

    ABSTRACT

    The major requirement of a power system to an industry is a well designed

    electrical system with stability and minimum interruption. This project deals with

    the design of electrical system of FACT Udyogamandal division which lies under

    continuous process category. The contract demand is 16MVA. Hence in this project

    the design of substation and its auxiliaries, earthing, etc are carried out in detail.

    This project deals with the design of an 110KV, 20 MVA Industrial type outdoor

    substation. The main source of power in this substation is from a 16MW turbo

    generator and KSEB supply. The KSEB supply is taken from the nearby parent

    station through over head XPLE cables. Since all connections are made using over

    head cables, lighting arresters are used.

    The existing 110KV substation is installed in 1947. The installed capacity of the

    circuit breakers is 250MVA. But, now the fault level of 110KV systems is 5445MVA.

    So the circuit breakers used cannot withstand fault level. Two 12.5/20 MVA

    transformers are used.

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    6/55

    CONTENTS

    Chapter 1 INTRODUCTION.1

    Chapter 2 SINGLE LINE DIAGRAM..2

    Chapter 3 FAULT LEVEL CALCULATION..4

    Chapter 4 EARTHING RESISTANCE MEASUREMENT...7

    Chapter 5 SUBSTATION..13

    Chapter 6 SUBSTATION COMPONENTS17

    Chapter 7 CONCLUSION..40

    Chapter 8 REFERENCES..41

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    7/55

    INTRODUCTION

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    8/55

    Federal Institute of Science And Technology (FISAT)

    1. INTRODUCTION

    A substation is a part of an electrical generation, transmission, and distribution system,

    where voltage is transformed from high to low, or the reverse, or many other important functions.

    Electric power may flow through several substations between generating plant and consumer, and

    may be changed in voltage in several steps.

    A substation that has a step-up transformer increases the voltage while decreasing the current,

    while a step-down transformer decreases the voltage while increasing the current for domestic and

    commercial distribution. The wordsubstationcomes from the days before the distribution system

    became a grid. The first substations were connected to only one power station where the

    generators were housed, and were subsidiaries of that power station.

    For economical transmission and distribution, higher voltage should be achieved as follows. But

    the consumers do not use very high voltages such as, 220KV, 110 KV etc. So they must be

    transformed into low voltages by means of transformers in sub-stations. Thus, a substation may

    be called as link between the generating stations and consumers.

    Electrical & Electronics Engineering 1

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    9/55

    SINGLE LINE DIAGRAM

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    10/55

    Federal Institute of Science And Technology (FISAT)

    Electrical & Electronics Engineering 2

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    11/55

    Federal Institute of Science And Technology (FISAT)

    Electrical & Electronics Engineering 3

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    12/55

    FAULT LEVEL CALCULATION

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    13/55

    Federal Institute of Science And Technology (FISAT)

    3. FAULT LEVEL CALCULATION

    Kalamassery fault level = 3600 MVA

    25% future expansion = 4500 MVA

    10% voltage Regulation = 5445 MVA

    Base MVA = 100 MVA

    Source Impedance = =

    = 1.8365

    Length of ACSR = 5.1 Km

    Ohmic impedance of the conductor = = = 0.6458/km

    = 0.6458 5.1=3.29% Z =

    =

    = 2.72%

    % impedance of 110 KV bus at UDL = 1.8365 +2.72 = 1.8365+2.72

    = 4.5565

    Fault level = = 2194.67 MVA

    Electrical & Electronics Engineering 4

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    14/55

    Federal Institute of Science And Technology (FISAT)

    Fault current = = 11.53KA

    % Impedance of 20 MVA Transformer = 15.6%

    % Impedance of 100 MVA base =

    = 78

    % Impedance of 11 KV side of Transformer = 78+4.5565 = 82.5565

    Fault level of 11 KV side of Transformer = 21.13 /

    = 6.365 KA

    3.1 DESIGN OF SUBSTATION

    Earth Resistivity 4 spike method

    Earth Resistance 10mm distance - 0.03

    5m distance - 0.45

    Earth pit - 0.31

    P, C, are shorted and is connected to the earth pit. P2 & C2 are connected to the two terminals

    which are connected to the 2 electrodes which are at 20m distances.

    3.2 SITE SELECTION

    Main points to be considered while selecting the site for EHV Sub-Station are as follows:

    i) The site chosen should be as near to the load center as possible.ii) It should be easily approachable by road or rail for transportation of equipments.iii) Land should be fairly leveled to minimize development cost.

    Electrical & Electronics Engineering 5

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    15/55

    Federal Institute of Science And Technology (FISAT)

    iv) Source of water should be as near to the site as possible. This is because water isrequired for various construction activities; (especially civil works, earthing and for

    drinking purposes etc.)

    v) The sub-station site should be as near to the town/city but should be clear of publicplaces, aerodromes, and Military/police installations.

    vi) The land should be have sufficient ground area to accommodate substationequipments, buildings, staff quarters, space for storage of material, such as store yards

    and store sheds. With roads and space for future expansion.

    vii) Set back distances from various roads such as National Highways, State Highwaysshould be observed as per the regulations in force.

    viii) While selecting the land for the substation preference to be given to the Govt. landover private land.

    ix) The land should not have water logging problem.x) The site should permit easy and safe approach to outlets for EHV lines.

    Electrical & Electronics Engineering 6

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    16/55

    EARTH RESISTANCE MEASUREMENT

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    17/55

    Federal Institute of Science And Technology (FISAT)

    4. EARTH RESISTANCE MEASUREMENT

    4.1 RESISTIVITY

    r =

    =

    = 20.93

    4.2 EARTH GRID AREA CALCULATIONS

    (Ac)2 = If (tc.r.rr.104/TCAP) / ln (1 + (Tm-Ta) (K0+ Ta))

    Where, If = Fault current = 25980 A

    Tc = Fault current duration = 1 Sec

    lr = Efficient of thermal expansion = 0.00423

    rr = Soil resistivity = 20.93mTCAP = Thermal capacity / unit volume in J/cm3

    0c = SHSW4.184

    = 4.184 0.114 07.8 = 3.749Where, SH = Specific heat

    SW = Specific weight

    TM = Maximum allowable temp in0C

    = 6200C

    Ta = Ambient temp in0C

    = 500C

    K0 =

    = 216.64

    Electrical & Electronics Engineering 7Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    18/55

    Tr = reference temperature for material constant = 200C

    Earth grid area, Ac2

    = 25.980 (1

    0.00423 x10

    4

    20.93/3.749) / ln (1 + (620-50) / (216 + 50))

    = 533501.28m2

    Ac = 730.41m2

    By including earth satellite earth mat the area of the earth grid can be increased to

    : 875 m2

    (35 25)

    4.3 DESIGN

    4.3.1 Conductor size:

    Ondor clonks formula provides a reasonable method to compute the area of cross section of

    electrode for earthing.

    A = Ix Where, A = Area of iron section in m

    2

    I = rms current in amps

    Tm = Max allowable temp in0C

    Ta = Ambient Temperature in0C

    Max allowable temp for steel in 6200C for welded joint and 310

    0C for bolted joints.

    The formula is simplified as: A = KI

    Electrical & Electronics Engineering 8Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    19/55

    4.3.2 Initial design

    Assume a preliminary layout of 21m x 18m grid with equally spied conductors and shown in

    figure with spacing D = 15 m, grid burial depth h = 0.75m

    Ground rod Grid conductor

    4.4 Grounding mat design:

    Considering further expansion, fault current for the design procedure as 259804.

    For grounding mat and welded joint are to be provided.

    Area of cross section = A = KI = 0.0122 25980= 317m2Area of 40 mm diameter Rod = 40 317 = 1257 m2Hence area of cross section is sufficient.

    Earth mat is designed at a normal spacing of 15m between conductors. As per initial design

    length of earth grid including down rods = 36220m

    No: of towers is assumed as 3 and lower foot resistance as 10

    Resistance of three towers = 10/3 = 3.33

    Total resistance of line = Resistance of tower + Resistance of ground wire

    Electrical & Electronics Engineering 9Federal Institute of Science And Technology (FISAT)

    31

    23

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    20/55

    Resistance of ground wire is assumed as 3

    Total resistance of one line = 3.33 + 3 = 6.33

    Total resistance of two lines together = 6.33/2 = 3.165

    The resistance of the earth grid may be calculated as R = (r/4r) +(r/L)

    r= 20.93 m

    R = Radius of the equivalent surface of the grid

    = = = 16.68m

    R = (20.93/416.68 + 20.93/36220) = 0.31Value of electrode resistance = 1/ [(1/0.31) + (1/3.165)] = 0.28

    For fault current of 25980 A in 110Kv bas grid ground return current = 0.357 0.28 11530 =1152.54A

    Minimum length of ground conductor required:

    L = Km Ki rIg / (116 + 0.174 Cs rs)Where,

    K = 1/2[ln [[D2/ 16 h.d] + [h / 4d]] + [Kit / Kh] (2n1)]D = spacing of conductor = 15m

    d = diameter of conductor = 0.04m

    h = depth of buried conductor = 0.75m

    n= = 16Ki = 0.656 + 0.172 16 = 3.4Kit = 1

    Kh = = 1.322Km = 0.677

    Electrical & Electronics Engineering 10Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    21/55

    Mini grid length L =

    = 87.03m

    4.5 EARTHING CONDUCTOR SIZE REQUIRED FOR LV SIDE

    Soil resistivity = 20.93m

    Permeable current density (for 3sec) for copper = 118A/mm2

    Fault current = 6.365 KA

    Earthing conductor size required =

    = 53.94mm2

    4.6 Tolerable step voltage

    E step actual = Ks r Ig/L

    Ks = (1/) [(1/2h) (1/Dh) + (1/D)] = 0.255

    E step actual = 0.255 3.4 20.93 1152.54/36220= 0.58v

    E touch actual = Km x Ki x rx Ki x Ig/ L

    = 0.677 3.4 20.938 1152.54 / 36220 =1.53V

    Electrical & Electronics Engineering 11Federal Institute of Science And Technology (FISAT)

    4.6.1 Safe let go touch voltage

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    22/55

    E touch let go = (R3 + R2Fp)/ Ib

    Rbe Human body, R = 1000 (assumed)

    R2Fp = Contact resistance of two feet in parallel = 1.5 Cs x rs

    Ib = Safe let go current = 0.009 A (assumed)

    E touch let go = (1000 + (1.5 1 3000) 0.009) = 49.5V

    To establish a value of sustained current within the limit of let go value of body current.

    49.5 V Km x Ki x Cs x rx Tsust/ L

    Isust = 49.5 Hence ground relays clearing ground fault current must be set for a mini pick up value less than

    260A.

    Electrical & Electronics Engineering 12

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    23/55

    SUBSTATION

    Federal Institute of Science And Technology (FISAT)

    5. SUBSTATION

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    24/55

    The substation may be defined us onassembly of apparatus which transforms the characteristics

    of electrical energyfrom one form to another, say for example from alternating current to direct

    current or from one voltage to another. For economical transmission, higher and higher voltagesshould be achieved. At present normal voltages are66KV, 110K.V and 220 KV; however440KV

    will be used for the national grid system in future.

    The consumers do not use such high voltages and so it must be transformed to low

    voltages by means of substation. Transformation may take place in several stages in sequence

    starting at the generating plant where the voltage is increased for transmission purposes and is

    then progressively reduced to the voltage required for household or industrial use. Thus a

    substation may be called as link between the generating stations and the consumer. The

    distribution voltages generally used in practice are 6.6 KV, 11KV and 33KV.

    Substations or switching stations arc integral part of transmission system, and function as

    a connection or switching point for transmission lines, substation feeders, generating circuits and

    step up and step down transformers. Substations of voltages 66KV to 400 KV are termed as EHV

    substations. Above 500 KV, they come under the terminology of UHV system.

    Substations generally contain one or more transformers and have switching, protection

    and control equipment. In a large substation, circuit breakers are used to interrupt ay short circuits

    or overload currents that may occur on the network.

    Electrical & Electronics Engineering 13Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    25/55

    In a large substation, circuit breakers arc used to interrupt any short-circuits or overload

    currents that may occur on the network. Smaller distribution stations may use autorecloser circuit

    breakers or fuses for protection of branch circuits.

    A typical substation will contain line termination structures, high-voltage switchgear, one or

    more power transformers, low voltage switchgear, surge protection, controls, grounding

    (earthing) system, and metering. Other devices such as power factor correction capacitors and

    voltage regulators may also be located at a substation. Substations may be on the surface in

    fenced enclosures, underground, or located in special-purpose buildings. High-rise buildings may

    have indoor substations. Indoor substations are usually found in urban areas to reduce the noise

    from the transformers, for reasons of appearance, or to protect switchgear from extreme climate or

    pollution conditions. Where a substation has a fence, it must be properly grounded to protect

    people from high voltages that may occur during a fault in the transmission system. Earth faults at

    a substation can cause ground potential rise at the fault location.

    An important function performed by a substation is switching, which is the connecting and

    disconnecting of transmission lines or other components to and from the system. Switching events

    may be "planned" or "unplanned". A transmission line or other component may need to be de-

    energized for maintenance or for new construction: for example, adding or removing a

    transmission line or a transformer. To maintain reliability of supply, no company ever brings

    down its whole system for maintenance. All work to be performed, from routine testing to adding

    entirely new substations, must be done while keeping the whole system running. Perhaps more

    importantly, a fault may develop in a transmission line or any other component. Some examples

    of this: a line is hit by lightning and develops an arc, or a tower is blown down by a high wind.

    The function of the substation is to isolate the faulted portion of the system in the shortest

    possible time.

    Electrical & Electronics Engineering 14Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    26/55

    5.1 VARIOUS PHASE OF SUBSTATION DESIGN

    5.1.1 Planning

    Planning includes the determination of the needed capacity, evaluation of alternative methods of

    service, selection of the service voltage and required facilities and the related financial

    requirements. This stage concludes with a contract between the utility and the plant.

    5.1.2 Design

    This stage includes the developments of detailed engineering drawings, finalizing of facility

    requirements, building documentation and specifications for the facilities and then changes

    required. This stage concludes with the lifting of construction contracts. This stage is the detailed

    following up to all the works in the planning by using the preliminary single line diagram

    developed and agreed upon in the planning stage. From this and other related design parameters

    developed in the planning stage, detailed design and engineering drawings and specifications

    along with construction cost estimates are developed.

    5.1.3 Construction

    This includes the construction and energizing the substation facilities.

    5.1.4 Operation

    This includes the development implementation and the documentation of the procedures for

    operating and maintaining the substation. These procedures are typically developed during the

    design and construction stages and completed prior to energizing the substation.

    5.1.5 Site testing

    Site testing should be done to determine the load-bearing strength of the ground. While

    preliminary testing can be performed at an early stage, it is more useful if a plot plan layout is

    available and equipment weights are known.

    Electrical & Electronics Engineering 15Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    27/55

    The testing is generally performed by specialized soil boring and test companies.

    Soil boring companies can sufficient test boring to determine the deign parameters for foundation

    needed for the utility's incoming towers, circuit breakers, transformers and the plant's primary

    switch gear building. Land that has been filled even 15 or 20 years ago may not have developed

    sufficient load bearing capabilities, installing caissons or piles to support the foundation may be

    necessary, especially for a large substation.

    Electrical & Electronics Engineering 16

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    28/55

    SUBSTATION COMPONENTS

    Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    29/55

    6. SUBSTATION COMPONENTS

    6.1 POWER TRANSFORMERS

    A transformer has been defined by ANSI/IEEE as a static electrical device, involving no

    continuously moving parts, used in electric power systems to transfer power between circuits

    through the use of electromagnetic induction. The termpowertransformer is used to refer to those

    transformers used between the generator and the distribution circuits and are usually rated at 500

    kVA and above. Power systems typically consist of a large number of generation locations,

    distribution points, and interconnections within the system or with nearby systems, such as a

    neighboring utility.

    Figure 1.1: POWER TRANSFORMER

    Electrical & Electronics Engineering 17

    Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    30/55

    The complexity of the system leads to a variety of transmission and distribution voltages. Power

    transformers must be used at each of these points where there is a transition between voltage

    levels. Power transformers are selected based on the application, with the emphasis towardscustom design being more apparent the larger the unit. Power transformers are available for step-

    up operation, primarily used at the generator and referred to as generator step- up (GSU)

    transformers, and for step-down operation, mainly used to feed distribution circuits.

    Power transformers are available as a single phase or three phase apparatus. The construction of a

    transformer depends upon the application, with transformers intended for indoor use primarily

    dry-type but also as liquid immersed and for outdoor use usually liquid immersed.

    Two number power transformers each of 12.5 /20 MVA ratings at the 110 KV substations shall

    be provided. The transformer shall be ONAN / ONAF type. On load tap changer shall be

    provided for voltage variation up to -10% to 10%. Necessary primary protection shall be

    provided for the protection of the transformer. The transformer shall be provided with the

    forced air cooling system with suitable enhanced 'MVA' capacity. Adequate provision shall be

    there for connecting 1000A, XLPE cable to secondary terminals.

    Power transformers are usually the largest single item in a substation. For economy of service

    roads, transformers are located on one side of a substation, and the connection to switchgear is by

    bare conductors. Because of the large quantity of oil, it is essential to take precaution against the

    spread of fire. Hence, the transformer is usually located around a sump used to collect the excess

    oil. Transformer that are located and a cell should be enclosed in a blast room.

    Electrical & Electronics Engineering 18Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    31/55

    6.1.1. Selections of transformers

    Load = 15MW

    Full load current =

    = 1231.61AStarting current = 7 The Transformers should provide the starting current also ;

    The transformers should provide this much current primary side

    Transformer voltage on secondary side is 11 KV

    Transformer Rating = 11

    = 23.465MVA30% future expansion = 30.509 MVA

    Two 20MVA 110/11KV Transformer is selected.

    Electrical & Electronics Engineering 19Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    32/55

    Maker TELK-TRANSFORMER WITH ON-

    LOAD TAP-CHANGER

    Transformer Specification Ref. No.IS

    2026-1977

    Makers Sl. No. 120270-2

    Type SALOCR

    Form 3NYCP

    Year of Manufacture 1988

    Rated KVA HV 12500/20000

    LV 12500/20000

    Voltsno load HV 110000 VLV 11000 V

    Amperes HV 65.7/105.1

    LV 657 / 1051

    Type of cooling ONAN / ONAF

    Impedance Voltage (20MVA base)

    HV/LV

    15.60%

    Phases HV 3

    LV 3

    Frequency C/S 50 Hz

    Vector Symbol Y N y n O

    Transportation Mass 24000 Kg

    Un-tanking Mass 20000 Kg

    Mass of oil 9495 Kg

    Total Mass 41000 Kg

    Oil liters 10550 Liters

    Air Circulation 8 x 90 m3 / min

    Electrical & Electronics Engineering 20Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    33/55

    POSITION HV CONNECTION HV VOLTS HV CURRENT

    1 1N15 116600 99.2

    2 IN-14 114950 100.6

    3 IN-13 113300 102

    4 IN-12 111650 103.5

    5 IN-11 110000 105.1

    6 IN-10 108350 106.1

    7 IN-9 106700 108.4

    8 IN-8 105050 10.1

    9 IN-7 103400 111.8

    10 IN-6 101750 113.6

    11 IN-5 100100 115.5

    12 IN-4 98450 117.4

    13 IN-3 96800 119.4

    6.2 SWITCHING EQUIPMENTS

    The design of the high-voltage substation must include consideration for the safe operation and

    maintenance of the equipment. Switching equipment is used to provide isolation, no load

    switching, load switching, and/or interruption of fault currents. The magnitude and duration of the

    load and fault currents will be significant in the selection of the equipment used. System

    operations and maintenance must also be considered when equipment is selected. One significant

    choice is the decision of single-phase or three-phase operation. High-voltage power systems are

    generally operated as a three- phase system, and the imbalance that will occur when operating

    equipment in a single- phase mode must be considered.

    The main classes of equipment are as follows:

    Isolators Switches

    Fuse-switch combinations Circuit breakers Earthing switches

    Electrical & Electronics Engineering 21

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    34/55

    Federal Institute of Science And Technology (FISAT)

    6.2.1 CIRCUIT BREAKER

    Circuit Breaker is equipment which can make or break a circuit at all conditions i.e. no load, full

    load and short-circuits conditions.

    6.2.1.1 Principles of Operation

    A circuit breaker consists of a fixed and moving contact called electrodes. These contacts remain

    closed under normal operating conditions. It will open automatically when the system becomes

    faulty. When the fault occurs on any part of the system, the moving contacts are pulled apart by

    some mechanism, contacts of the circuit breaker are separated under fault condition, and an arc is

    formed between them. The current in this circuit unable to continue until the discharge stops. The

    production of are not only delays the current-interruption process but it also generates a large

    amount of heat which may cause damage to the system or to the breaker, itself. Therefore the

    main problem in a circuit breaker is to extinguish the arc within the shorted possible time. So that

    heat generated by it may not reach a dangerous value.

    6.2.1.2 Circuit Breaker Rating

    1. Breaking capacity2. Making capacity3. Short time rating.

    6.2.1.3 Breaking Capacity

    It is the current that a CB is capable of breakable at a given recovery voltage and under specified

    conditions, (e.g. power factor, rate of re-striking voltage)

    Breaking capacity in MVA = 3 breaking current rated voltage.

    Electrical & Electronics Engineering 22

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    35/55

    Federal Institute of Science And Technology (FISAT)

    6.2.1.4 Making capacity

    The peak value of the current during the first cycle of current wave after closure of Circuit

    Breaker is known as making capacity.

    Making capacity : 2.56 Symmetrical breaking capacity.

    6.2.1.4 Short time rating

    It is the period for which the CB is able to carry fault current while remaining closed.

    Figure 1.2: CIRCUIT BREAKER

    Electrical & Electronics Engineering 23

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    36/55

    Federal Institute of Science And Technology (FISAT)

    6.2.1.5 Classification of Circuit Breakers

    The circuit breaker can be classified according to the voltage below 100V are called Low voltageCircuit Breaker, and above 1000V are called High Voltage Circuit Breakers.

    Circuit Breakers are classified according to the medium of are extinction. It is shown below.

    (a)Air break CB(b)Oil CB(c)Air blast CB(d)Sulphur hexa fluoride CB (SF6)(e)Vacuum CB.

    6.2.1.6 Sulphur hexa fluoride (SF6) Circuit Breaker

    The SF6 CBs are used for high voltage service. The SF6 gas is used as the arc quenching

    medium. The SF6 is an electronegative gas and gas a strong tendency to absorb free electronics.

    The contacts of the breaker are opened in a high pressure flow of SF6 gas and arc is struck

    between them. The conducting free electronics in the arc are rapidly captured by the gas to form

    relatively immobile negative ions. The decreasing conducting electronics in the are quickly

    increase ions. The decreasing conducting electronics in the arc quickly increase the insulation

    strength to extinguish the arc.

    Electrical & Electronics Engineering 24Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    37/55

    6.2.1.7Construction of SF6 Breaker

    SF6 circuit breaker consists of two parts namely:

    (i) The interrupt unit (ii) the gas system.

    i) The Interrupt Unit:This consists of fixed contacts which comprise a set of current carrying fingers and an arising

    probe. When the breaker is in the closed position, the fingers make contact round the

    circumstance of moving contact which has the arising probe enclosed within its hollow end. The

    contacts are surrounded by interrupting nozzles and a blast shield which controls are displacement

    and movement of the hot gas. The moving contact is in the form of hollow nozzle sliding in a

    second set of spring loaded fingers. Side vents in the moving contact allow the high pressure gas

    into the main tank.

    As soon as the moving contact is withdrawn from the fixed contacts, an arc is drawn between the

    moving nozzle and the arcing probe. As the contacts move further apart, the arc is extended and

    attenuated. It is finally extinguished by the gas flow from high pressure to the low pressure

    system.

    ii) The gas-system:The closed circuit gas system is used in SF6 circuit breakers. Since the gas pressure is very high,

    lot of care is to be taken to prevent gas leakages at joints by providing perfect sealing. The low

    and high pressure system are filled with low pressure alarm and a set of lock-out switched which

    gives a warning the moment the gas pressure drops below a certain value, because otherwise there

    will be reductions in the dielectric strength and are generating ability of the breaker is endangered.

    If the damaged limit is reached, the safety devices immobile the Circuit Breaker, the over-riding

    safety devices see to it that a fault in the control circuit does not permit compressor to build up

    excessive pressure in the high pressure reservoir or continue to pump gas into the atmosphere in

    the event of a major leak. The gas is stored in the high pressure chamber at 16 atmosphere.

    Electrical & Electronics Engineering 25

    Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    38/55

    Whereas the gas pressure on the low pressure side is 3 atmospheres. There temperature is 20oC. In

    order to prevent liquidification of the gas in the high pressure chamber at low temp, heater is

    fitted in the high pressure chamber. A thermostat is set to switch on when the ambient temp falls

    below 16oC.

    6.2.1.8 SHORT CIRCUIT CURRENT RATING

    The short circuit current rating determines the minimium size of cable conductor to

    be used:

    Fault level for 11KV = 121.13 MVA

    Isc =

    = 6.365 KA

    Electrical & Electronics Engineering 26

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    39/55

    Federal Institute of Science And Technology (FISAT)

    As per table

    Mini cable size for secondary side is 70mm2.

    Current rating of 11KV XLPE (cable)

    As per tables:

    For secondary side 3 runs of 3 core 70mm2(cable)

    Primary Circuit breaker for 110 11KV 20MVA Transformer:The full load secondary current is =

    = 1049.73 KA

    Primary current is = 104.97 A

    Thus, SF6 CB is selected (3150A)

    FEEDER CIRCUIT BREAKER

    Make Crompton Greaves EverydaySolutions

    Type Gas circuit breaker 120-SFM-328Year of manufacture 2006

    Rated voltage 145 kV

    Rated Frequency 50 Hz

    Rated Normal Current 3150 A

    Rated making Capacity 100 kAp

    Rated Short circuit breakingcapacity

    40 kA

    Rated short time current 40 kA

    Rated lighting impulse withstandvoltage

    650 kVp

    First pole to clear factor 1.5

    Rated opr. Seq 0--.3SecCo3 MinCO

    Rated Gas Pressure 7 Kg /cm2g (at 200C)

    Gas Wt 8 Kg

    Total weight 1550 Kg

    Electrical & Electronics Engineering 27

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    40/55

    Federal Institute of Science And Technology (FISAT)

    TRANSFORMER CIRCUIT BREAKERS

    Make Crompton Greaves Nasik, INDIA

    Type GAS CIRCUIT BREAKER 120 SFM32A

    Year of manufacture 1990

    Rated Voltage 145 kV

    Rated Frequency 50 Hz

    Rated Normal Current 3150 A

    Rated Making Capacity

    Rated Short Circuit BreakingCapacity

    31.50kA

    Rated short time current 31.5 kA for 3 seconds

    Rated lighting impulse withstandvoltage

    650 kVp

    First pole to clear factor 1.5

    Rated opr. Pressure (Air) 15 Kg/Sq CM

    Rated Gas Pressure 5 Kg / cm2g (at 200C)

    Gas Wt 9 Kg

    Total Weight 2000 Kg

    6.2.2 ISOLATORS

    Isolators are disconnecting switches which operate under no load conditions. It doesnt have any

    specified current breaking capacity making capacity. Isolators are sued in addition to circuit

    breakers, while opening a circuit, the circuit breaker is opened first, then Isolator. While closing a

    circuit the Isolator is closed first then the circuit breakers. Isolators are necessary on supply side

    of circuit breakers in order to ensure isolation of the circuit breaker from live parts for the purposeof maintenance.

    Electrical & Electronics Engineering 28

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    41/55

    Federal Institute of Science And Technology (FISAT)

    Isolator design is considered in the following aspects:

    Space Factor

    Insulation Security

    Standardization

    Ease of Maintenance

    Cost

    Some types of isolators include:

    Horizontal Isolation types

    Vertical Isolation types

    Moving Bushing types

    6.2.2.1 Working

    Isolators used in power system are generally 3 pole Isolator. The 3 pole Insulators have 3 identical

    poles. Each pole consists of two or three Isolator posts mounted on a fabricated support. The

    conducting parts are supported on the Insulator posts. The conducting part consists of conducting

    Cu or AI rod, fixed and moving contacts. During the opening operation the conducting rod swings

    apart and Isolation is obtained. The simultaneous operation of the 3 poles is obtained by

    mechanical interlocking of the 3 poles.

    The operating mechanism is manual plus one of the following.

    a. Electrical motor mechanismb. Pneumatic mechanism.

    Electrical & Electronics Engineering 29

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    42/55

    Federal Institute of Science And Technology (FISAT)

    6.2.2.2 TYPES OF ISOLATORS

    According to the constructional details the Isolators are classified as:

    1. HORIZON BREAK CENTRE ROTATING DOUBLE BREAK ISOLATORIn this type, there are 3 Insulator stacks per pole, the two on each side are fixed and one of the

    centers is rotating type. The central Insulator stack cans wing about its vertical axis through about

    90o. The fixed contacts are provided on the top of each of the Insulator stacks on the side. The

    contact bar is fixed horizontally on the central Insulator stack. In closed position, the contact shaft

    connects the two fixed contacts. While opening, the central stack rotates through 90oand the

    contacts shaft swings horizontally giving a double break. The Insulators are mounted on a

    galvanized, rolled steel frame. The 3 poles are interlocked by means of steel shaft.

    2. PANTOGRAPH ISOLATIONThese types of Isolators are preferred for rotted voltages 420KV and above. While closing the

    linkages of pantograph are brought nearer by rotating the insulator column, in closed position two

    arms of the pantograph close on the overhead station bus bar giving a grip. The current carried by

    the upper bus bar to the lower bus bar through the conducting arms of the pantograph.

    While opening the rotating Insulator column is rotated about its axis. Thereby the pantograph

    blades collapse in vertical plane and vertical Isolator is obtained between the line terminal and

    pantograph upper terminal. The Insulator covers less floor area. Each pole can be located at a

    suitable point in a plane at desired angle with the bus axis.

    3. VERTICAL BREAK TYPE

    These are outdoor air break disconnecting switches and are designed for all out door applications

    including isolation of circuit breakers, transformer banks, lighting arrestors and line sections.

    Horizontal upright mounted switched can be equipped with crossing horns for interruptions of

    small currents such as line charging or transformer magnetizing currents.

    Electrical & Electronics Engineering 30

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    43/55

    Federal Institute of Science And Technology (FISAT)

    4. EARTHING SWITCH

    Earthing switch is connected between the line conductor and normally it is open when the line is

    disconnected, the earthing switch is closed so as to discharge the energy trapped in capacitance or

    inductance of the line. Though the line is disconnected, there is some voltage on the line to which

    the capacitance between the line and earth is charged. This voltage is significant to high voltage

    system. Normally, the earthing switches are mounted on the frame of Isolator.

    These are essentially off load devices although they are capable of dealing with small charging

    currents of Bus bars and connections. The design of isolators is closely related to the design of

    substations.

    Figure 1.3: ISOLATOR

    Electrical & Electronics Engineering 31

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    44/55

    Federal Institute of Science And Technology (FISAT)

    To carry out maintenance on particular items of plant, it is necessary to provide isolating

    switches on each of the circuits to which the plant is connected. Except for outdoor installations,

    these normally operate under no load conditions ensured by suitable interlocks. Outdoor isolators

    for the higher voltages may however have to break the significant transformers magnetizing and

    line charging currents. Earthing switches are also needed commonly in preference to temporary

    earth connections. With indoor cubicle mounted or metal clad switchgear the isolators may be

    simple knife switches that are incorporated in the structure and interlocked with the circuit

    breaker; alternately, with a clad gear they make the form of plugs through which the circuit

    breaker is connected to the bus bars and feeder, the circuit breaker being drawn out horizontally

    or lowered vertically to effect isolation.

    FEEDER ISOLATORS WITH EARTH SWITCH

    Make GR POWER SWITCH GEAR LTD,

    JEEDIMETLA, HYDERABAD,500055

    Type DB

    KV Rating 123

    Current Rating 1600A

    Year of manufacture 2005

    Impulse Voltage 550 kV peak

    Short time current for 1 sec 26.24 kA rms

    Operating Mechanism Motor

    Control voltage 110V DC

    Drive 3f, 415V, AC, 1500 RPM, InductionMotor

    Electrical & Electronics Engineering 32

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    45/55

    Federal Institute of Science And Technology (FISAT)

    6.3 CURRENT TRANSFORMERS

    Current transformer (CT) is used for measurement of electric currents. Current transformers are

    also known as instrument transformers. When current in a circuit is too high to directly apply to

    measuring instruments, a current transformer produces a reduced current accurately proportional

    to the current in the circuit, which can be conveniently connected to measuring and recording

    instruments. A current transformer also isolates the measuring instruments from what may be

    very high voltage in the primary circuit.

    Figure 1.4: CURRENT TRANSFORMER

    Current transformers are commonly used in metering and protective relays in the electrical power

    industry. Like any other transformer, a current transformer has a primary winding, a magneticcore, and a secondary winding. The alternating current flowing in the primary produces a

    magnetic field in the core, which then induces current flow in the secondary winding circuit.

    A primary objective of current transformer design is to ensure that the primary and secondary

    circuits are efficiently coupled, so that the secondary current bears an accurate relationship to theprimary current. The most common design of CT consists of a length of wire wrapped many times

    around a silicon steel ring passed over the circuit being measured.

    Electrical & Electronics Engineering 33

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    46/55

    Federal Institute of Science And Technology (FISAT)

    The CTs primary circuit therefore consists of a single turn of conductor, with a secondary of

    many hundreds of turns. The primary winding may be a permanent part of the current

    transformer, with a heavy copper bar to carry current through the magnetic core. Window-typecurrent transformers are also common, which can have circuit cables run through the middle of an

    opening in the core to provide a single-turn primary winding. When conductors passing through a

    CT are not centered in the circular (or oval) opening, slight inaccuracies may occur.

    Current transformers are basically used to take the readings of the currents entering the

    substation. This transformer steps down the current from 800 amps to 1 amp. This is done

    because we have no instrument for measuring of such a large current. The main use of this

    transformer is (a) distance protection; (b) backup protection; (c) measurement.

    Current transformer LV side

    Type 132 kV CT

    Core 1 core 2 core 3

    Ratio (A/A) 800/1 400/1 800/1 400/1 800/1 400/1

    Sec. Conn: 1S1-1S2 2S1-2S3 3S1-3S3

    Accuracy class: 0.2 5P 10 PS

    Burden (VA): 30 15 NA

    Highest system

    Voltage: 145 kV insulation burn 275 kV/ 65014 Vp

    FEEDER CURRENT TRANSFORMER -1 (FCT -1)

    Ring Winding Transformers

    Make Brown BoveriStromwandler

    Type TMRg 110

    Year of Manufacture 1957

    Voltage 110/220kV

    Ratio 300 -1 5075 - /1/1/1Power 60VA

    Class 0.5 & S20

    1 Therm 23/12/6

    1 Dyn 60/30/15

    Electrical & Electronics Engineering 34

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    47/55

    Federal Institute of Science And Technology (FISAT)

    TRANSFORMER CT s (TCT -4)

    Make Transformer and Electrical KeralaLtdTELK

    Manufacturing No. 220104

    Sl No. 1R, 2R, 3R

    PO No. 1910211 Dt: 21/1/95

    Type NPOULVZR

    Basic Ins Level 230/550kV

    Rated Voltage 126kV

    Frequency 50Hz

    6.4 VOLTAGE TRANSFORMER

    There is a step down transformer, which step down the high voltage to a value that can bemeasured using the measuring instruments in the control room.

    This has an additional core for the carrier communication. The CVT are connected between phase and ground in parallel to the circuit

    Figure 1.5: CVT

    Electrical & Electronics Engineering 35

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    48/55

    Federal Institute of Science And Technology (FISAT)

    6.5 BUS BAR

    Used to interconnect the loads and sources of electrical power.

    It connects generator and main transformer in power plant

    Material used: Copper or Aluminum

    Size of bus bar is used to determine maximum amount of current passed.

    6.5.1 Bus bar sizing calculations

    Short time rating of ACSR Zebra conductor

    I = A x ln [ ]

    Where,

    I = RMS Current in KA = 25.98 KA

    (ACSR Zebra conductor)

    r20 = R20 a/1R20 = 0.06079/ Km

    a = 4.275 cm2

    l = 1Km

    r20 = 2.598 micro cm

    Ko = 230

    I = 37.38 KA, which is greater than 25.98 KA specified.

    Hence section of ACSR zebra conductor is safe.

    Electrical & Electronics Engineering 36

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    49/55

    Federal Institute of Science And Technology (FISAT)

    6.6 LIGHTNING ARRESTOR

    A lightning arrester is a device used on electrical power systems to protect the insulation on thesystem from the damaging effect of lightning. Metal oxide varistors (MOVs) have been used for

    power system protection since the mid 1970s. The typical lightning arrester also known as surge

    arrester has a high voltage terminal and a ground terminal. When a lightning surge or switching

    surge travels down the power system to the arrester, the current from the surge is diverted around

    the protected insulation in most cases to earth.

    Figure 1.6: LIGHTNING ARRESTOR

    These lightening arrestors are used to prevent the lightening from damaging the instruments in

    the substation. Lightening arrestors are the instrument that are used in the incoming feeders so

    that to prevent the high voltage entering the main station. This high voltage is very dangerous to

    the instruments used in the substation. Even the instruments are very costly, so to prevent anydamage lightening arrestors are used.

    Electrical & Electronics Engineering 37Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    50/55

    The lightening arrestors do not let the lightening to fall on the station.

    If some lightening occurs the arrestors pull the lightening and ground it to the earth. In any

    substation the main important is of protection which is firstly done by these lightening arrestors.

    The lightening arrestors are grounded to the earth so that it can pull the lightening.

    6.6.1 WHAT EXACTLY DOES A LIGHTNING ARRESTOR DO?

    It does not absorb the lightning It does not stop the lightning It does divert the lightning to ground It does clamp (limit) the voltage produced by the lightning It only protects equipment electrically in parallel with it.

    6.6.2 Selection of lighting arrestor

    When an arrestor connected between phase and earth it is a 3system, the rated voltage must be

    equal to or greater than the highest RMS value of power frequency voltage which can be applied

    to it under normal and abnormal condition of operation including fault. Conduction of risk of

    damage is to be avoided.

    System Voltage = 110KV

    Rated arrestor voltage = 1.1 x 110 x 0.8 (coefficient of earthing)

    = 96.8 KV

    Standard rating available = 96KV

    Electrical & Electronics Engineering 38Federal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    51/55

    Rated frequency = 50 Hz

    Power frequency spark voltage = 1.5x rated arrest voltage

    = 1.5 x 96 KV = 144 KV

    Electrical & Electronics Engineering 39

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    52/55

    CONCLUSIONFederal Institute of Science And Technology (FISAT)

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    53/55

    7. CONCLUSION

    The 66kV substation that is designed in this project is strictly based on the design procedures

    accepted by the authorities. The intense care was taken through the whole procedure to ensure

    protection for the equipment as well as the personnel in case of any failure or over current which

    are possible to appear in the power system. The circuit breakers and the protective relays are

    assigned for these purposes with proper design. The protective signs and symbols are also

    employed for the workers to take precaution against failures. First of all a proper site to the

    substation has to be identified such that some basic requirements have to be satisfied. From the

    purely economic point of view, a major EHV substation would necessarily be of the outdoor type.

    There should be enough space for the further developments of the plant because in future evenhigher capacity may be needed to fulfill the power requirements. In order to protect the whole

    plant from lightning, the lightning arresters and the earthing screens are provided above the

    substation with suitable design criteria. These devices are capable to withstand the high current

    due to lightning and also to pass this current safely to the earth without altering the present active

    supply system. The other important equipments in the substation such as transformers, bus bars,

    switch gear, potential transformers and current transformers, fuses, cables earth wires, batteries

    etc are designed as per the requirements of the power system. The main objective of earthing is

    protection from short circuits and over voltages that may occur in the power system due to many

    reasons. A properly designed earthing system can protect the entire equipments and person that

    comes under that specific power network. For proper designing of a power system, a deep

    knowledge about the various faults that occur in the power system is necessary. Earthing is

    considered as the one of the most important step in the design of a typical substation because the

    proper earthing ensures the reliability of power supply- without many faults also ensures the

    safety of the equipments as well as the personnel, So intense care has to be taken while designing

    an earthing system for an extra high voltage substation.

    Electrical & Electronics Engineering 40

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    54/55

    REFERENCES

  • 7/13/2019 53681209 Project Design of Ehv Substation at FACT UDL

    55/55

    Federal Institute of Science And Technology (FISAT)

    8 REFERENCES

    [1]IEEE RED DATA BOOK, 1993[2]NEWNESS ELECTRICAL ENGINEERS HAND BOOK, D.F.WAENE, SECOND

    EDITION.

    [3]ISO MANUAL ELECTRICAL SYSTEM STUDY AND FAULT LEVELCALCULATION BY FEDO.

    [4]POWER GENERATION OPERATION ANDCONTROL BY ALLEN JWOOD ANDBRUDE T W WOLLENBERG.

    [5]ISO MANUAL FOR EARTHING AND SYSTEM STABILITY CALCULATION BYFEDO.

    [6]STD 80-2000 IEEE GUIDE FOR SAFETY