6 esia process and scoping - erm · environmental resources management kangra coal (p ty) ltd....
TRANSCRIPT
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
6-120
6 ESIA PROCESS AND SCOPING
An EIA is a systematic process that identifies and evaluates the potential
impacts a proposed Project may have on the biophysical and social
environment and develops mitigation measures that will be incorporated in
order to eliminate, minimise or reduce these impacts.
As described in Chapter 4, the process in South Africa is regulated by the
MPRDA, NEMA and the NEMA EIA Regulations (December, 2014). The
overall Scoping and EIA process is illustrated in Figure 6.1. This EIA process
that is being undertaken for this Project is aligned with the requirements of
these Regulations.
Figure 6.1 Environmental Impact Assessment Process
Source: DEA, 2014
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
6-121
6.1 APPROACH TO THE EIA PROCESS
A meeting was held between Kangra Coal, ERM and the DMR on 21st April
2016 to discuss the process for the EMPr Amendment application. In the
meeting DMR confirmed that undertaking an amendment of a Mining Right
involves three key amendments and that this is governed by two legal
documents. The amendments that need to be undertaken and the legal
documents that govern them are as follows:
• Amendments to the EMPr: governed by the National Environmental
Management Act (NEMA) as amended December 2014, Part 2
(Amendments where change in scope occurs) Regulation 31 and 32;
• Amendments to the Mine Works Programme: governed by the Mineral
and Petroleum Resources Development Act (MPRDA) of May 2004,
Section 102 (as amended 21 April 2009); and
• Amendments to the Social and Labour Plan: also governed by the MPRDA
(2004, Section 102, as amended 21 April 2009).
The proposed inclusion of the MWE underground works, the Central Discard
Dump, and the Adit 5, overland conveyor and servitude road with the
associated facilities would require an amendment of the Kangra Coal
Consolidated EMPr (133 MR). In practice, the DMR expects the holder of a
mining right to conduct an EIA and submit an EMPr prior to consent being
granted for the EMPr amendment.
These processes have already been undertaken for each of the three
components mentioned above and was noted by the DMR during the meeting
held on the 21st April 2016. Thus the proposed overarching strategy that was
discussed with, and accepted by, the DMR is as follows:
Kangra coal will undertake to incorporate the following three main processes
into a single Section 102 Amendment Application:
• The MWE underground works;
• The Adit 5, overland conveyor and servitude road with their associated
facilities; and
• The Central Discard Dump.
These three main Project components will be consolidated into the existing
133MR EMPr through the following stepwise process to be undertaken by
ERM on behalf of Kangra Coal:
1. Prepare Draft Scoping Report (DSR) (this report);
2. Lodge an Environmental Authorization application;
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
6-122
3. Undertake a Public Participation Process (PPP) in accordance with NEMA
Regulation 41 to include a 30 day public comment period;
4. Incorporate the Comments and Responses Report (CRR) from PPP into the
DSR;
5. Submit the Final Scoping Report to the DMR;
6. Develop the consolidated EMPr incorporating any comments from the
DMR; and
7. Public disclosure of the Draft EIR and EMPr including a 30 day public
comment period; and
8. Submit the amended 133 MR EMPr (incorporating the three processes
above) to the DMR.
The phases are discussed in the following sections.
6.2 SCOPING PHASE
A principal objective of the scoping phase is to identify the key environmental,
social and health issues and those project activities with the potential to
contribute to, or cause, impacts to the environmental and social receptors.
At the scoping stage, the key issues are identified (often together with input
from key stakeholders) and understood to a level which allows the definition
of the Plan of Study (PoS) for the EIA.
Issues that are not relevant are scoped out. This enables the resources for the
EIA to be focused on collecting required information and identifying
significant impacts while carrying out specialist studies and stakeholder
engagement activities in an effective and efficient manner.
Specifically, the objectives of the scoping phase are to:
• Understand the legislative context relevant to the Project;
• Establish a description of baseline conditions;
• Identify project alternatives and preferred options for the proposed
development;
• Identify stakeholders and plan or initiate communication with these
stakeholders so as to gather issues of concern;
• Identify potential significant impacts; and
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
6-123
• Develop the PoS for the EIA which sets out the proposed approach to the
EIA, potential impacts to be evaluated and methodology to be used.
6.2.1 Submission of Application Forms
The completed EMPr Amendment application form will be submitted to the
DMR together with the Draft Scoping Report. In terms of the 2014 EIA
Regulations the Final Scoping Report (FSR) is to be submitted to the CA
within 43 days of receipt of the acknowledgement letter.
6.3 PUBLIC PARTICIPATION PROCESS
Public participation is an inclusive and culturally appropriate process which
involves sharing information and knowledge, seeking to understand the
concerns of others and building relationships based on collaboration. It allows
stakeholders to understand the risks, impacts and opportunities of the Project
in order to achieve positive outcomes.
The main objectives of public participation are:
• to ensure that adequate and timely information is provided to those
potentially affected by the Project;
• to provide these groups with sufficient opportunity to voice their opinions
and concerns; and
• to ensure that comments are received in a timely manner so that they can
be taken into account in Project decisions.
The NEMA EIA Regulations (December, 2014) require that a Scoping Report
be submitted to the regulatory authorities within 44 days following their
receipt of the application form. This time is to include a 30 day comment
period from stakeholders.
The stakeholders will be given an opportunity to ask question s and raise their
concerns. These will be incorporated into the process going forward and will
be captured in the CRR and addressed as necessary.
Compilation of a Stakeholder Database
In terms of the NEMA, a register of interested and affected parties (I&APs)
must be kept by the stakeholder engagement practitioner. A preliminary
database of neighbouring landowners, relevant commenting authorities (local
and provincial), and other key stakeholders (ie local businesses) has been
compiled. The register will be updated with the details of involved I&APs
throughout the EIA process.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
6-124
Initial Notification of the Project
The Scoping Report will be made available to stakeholders through the Project
website (http://www.erm.com/kangracoal) and hard copies provided at
various locations for a period of 30 days. After the 30 day public comment
period a CRR will be compiled and included in the Final Scoping Report (FSR)
along with any other updates or changes. The FSR (including PoS) will be
submitted to the DMR for their consideration.
The Comments and Responses Report (CRR) will be included in the FSR and
distributed to registered I&APs as required.
6.3.2 Summary of PPP Undertaken to Date
A significant amount of PPP has already been undertaken for the various
components being applied for as part of this EMPr Consolidation. These are
summarised in Table 6.1, Table 6.2 and Table 6.3.
Table 6.1 Kransbank Adit and Overland Conveyor - PPP Activities
Activity Details
Distribution of Background
Information Document (BID)
Background Information Documents (BID) in English
and isiZulu placed at Pixley Ka Isaka Seme Local
Municipality Offices, Mkhondo Municipality Offices.
Volkust Public Library, Volksrust Post Office,
Wakkerstroom Library, Piet Retief Post Office, Piet Retief
Library, Driefontein Community Centre, Daggakraal
Clinic, Dirkiesdorp Clinic, Dirkiesdorp Police Station.
Placing of adverts • Adverts were published on 24 April 2015 in English
and isiZulu in the Excelsior News and The Recorder.
• Advert published on the 24 April 2015 in Afrikaans
in Die Beeld.
Putting up site notices • Site notices placed at the following locations on the
27th/28th April 2015: Dr Pixley Ka Isaka Seme Local
Municipality Offices, Mkhondo Municipality
Offices. Volkust Public Library, Volksrust Post
Office, Wakkerstroom Library, Piet Retief Post
Office, Piet Retief Library, Driefontein Community
Centre, Daggakraal Clinic, Dirkiesdorp Clinic,
Dirkiesdorp Police Station.
Notification of I&APs • An email to registered I&APs, landowners, ward
councillors and commenting authorities
(Department of Water and Sanitation, Local and
District Municipalities) has been sent to notify these
parties of the application and availability of the
Report.
• The EIA and EMP were made available at the
various locations from 28 April 2015 to 29 May 2015
(30 day public participation period, accounting for
public holidays).
Comments received from I&APs In addition to the stakeholder meetings, comments were
received via email correspondence during the public
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
6-125
Activity Details
participation period.
I&AP meetings Stakeholder meetings were held from Wednesday 6 May
2015 to Saturday 9 May 2015 to afford stakeholders the
opportunity to comment on the Project and engage with
the EIA team. During these meetings stakeholders
requested that formal responses to their comments and
queries be provided. Responses were therefore not
provided during the meetings, but are included in the
Comments and Responses Report (CRR). Hard copies of
the CRR were distributed to the stakeholder groups on
10 June 2015.
Table 6.2 Central Discard Dump - PPP Activities
Activity Details
Distribution of Background
Information Document (BID)
Background Information Documents (BID) in English
and isiZulu and distributed to the registered I&APs
(existing Kangra stakeholder database (via email, fax and
registered post). Copies of the BID was also placed at the
Piet Retief Post Office, Thusong Service Center and the
Maquasa East mine security office.
Placing of adverts • A newspaper advertisement was compiled in
English and Zulu and was placed in the Excelsior
News newspaper on Friday, 4 April 2014
Putting up site notices • Copies of the site notice (English and Zulu) were
printed in A2 and laminated and were placed at the
following 6 locations:
• Piet Retief Post Office (-27, 0043609198°S; 30,
8017042838°E).
• Maquasa East Mine Entrance (-27,0230294298S; 30,
4136015475°E).
• Thusong Service Station (-26, 9938231912°S; 30,
4145243112°E).
• Driefontein Community Hall (-26, 9928031974°S; 30,
4146885965°E).
• Kangra Community Park (-26, 9734803122°S; 30,
4288905580°E).
• Mkhondo Municipality Piet Retief (-27,
0080803894°S; 30, 8027010597°E).
Notification of I&APs • Sms notifications were sent on 7 April 2014 to notify
registered I&APs of the project.
• The EIA and EMP were also made available at the
Piet Retief Library, the Maquasa East Security
Office, Thusong Service Centre and on the GCS
website from 23 April 2014 to 26 May 2014, 9 July
2014 to 30 July 2014, 19 November 2015 to 18
January 2016 and 2 February 2016 to 23 February
2016.
Obtained comments from I&APs In addition to the stakeholder meetings, comments were
received via email correspondence during the public
participation period.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
6-126
Activity Details
I&AP meetings The Scoping Phase public meeting was held on 20 May
2014 (16:30 pm) at the Mkhondo Municipal Hall.
The minutes of the meeting were distributed via email
on 17 June 2014. Sms’s were also sent out on 17 June 2014
informing stakeholders of the availability of the public
meeting minutes on the GCS website (www.gcs-sa.biz)
and that the minutes would be sent to them via email or
post upon request.
Table 6.3 Kransbank underground workings – PPP Activities
Activity Details
Identification of IAPs In a project of this nature where an existing EMPr was
being amended, the I&APs had already been identified
and consulted with regards to the original project. Thus
for the integration of 209MR further networking was
done to identify, amongst others, the potentially affected
landowners and adjacent landowners of the expansion
project.
Background Information Document At the beginning of the scoping phase, Background
Information Documents (BID) were produced and
provided to the I&APs on the existing database. The BID
was translated from English into Zulu and Afrikaans. In
addition, BIDs were handed out to landowners affected
by the extension of the Maquasa West Underground
mine. The purpose of a BID document was to provide
I&APs with basic background information pertaining to
the proposed activities, the consultation process and the
specialist studies being conducted. It further provided
members of the public interested in the project with the
opportunity to register as I&APs, by completing the
registration sheet included in the BID. This ensured that
their names and contact details would be captured on the
database and that they would receive all project-related
information and invitations to meetings. A comment
sheet was also provided to enable I&APs to furnish the
consultants with written comments.
Individual Interviews and Meetings Individual meetings were held with important
stakeholders. These stakeholders were identified and
drawn from the existing I&APs list. These included
mainly surface rights holders on the affected property
and adjacent landowners.
6.4 SPECIALIST STUDY PHASE
Specialist studies have been identified to address key issues of concern. The
findings of these studies will be incorporated into the Environmental Impact
Assessment Report (EIR) that will close out the Integration and Assessment
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
6-127
Phase. Further information related to the approach to the specialist studies is
contained in the PoS for EIA in Section 8.
6.5 INTEGRATION AND ASSESSMENT PHASE
The final phase of the EIA is the Integration and Assessment Phase, which is
described in detail in the PoS for EIA (Chapter 8). The assessment of impacts
proceeds through an iterative process considering three key elements:
• Prediction of the significance of impacts that are the consequence of the
proposed development on the natural and social environment.
• Development of mitigation measures to avoid, reduce or manage the
impacts.
• Assessment of residual significant impacts after the application of
mitigation measures.
6.5.1 EIA Phase Public Participation
The Draft EIR and EMPr will be sent to registered I&APs for a further 30 day
public comment period in which any further comments or queries will be
addressed, the CRR updated and final amendments made to the EIR and
EMPr. The CRR will be appended to the Final EIR, which will be submitted to
DMR for decision-making.
All registered I&APs will be notified of the DMR’s decision regarding the
Environmental Authorisation (EA). The notification will include the details of
the appeal procedure in accordance with the National Appeal Regulations,
2014.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
7-128
7 IDENTIFICATION OF POTENTIAL IMPACTS
7.1 INTRODUCTION
A key part of the Scoping phase is a preliminary analysis of the ways in which
the Project may interact (positively and negatively) with environmental
(including physical and biological receptors) and social resources or receptors.
The impacts that are identified as potentially significant during the scoping
process provide focus for the studies undertaken during the EIA phase. Each
of the potential impacts will be discussed and assessed in more detail in the
draft EIA Report.
In order to complete the EIA scoping phase, the EIA team will draw upon:
• knowledge of sources of potential impacts;
• an identification of the main environmental and social resources and
receptors from the previous work undertaken on 133 MR; and
• the results of the initial scoping consultation and previous consultation
undertaken.
This Chapter provides a preliminary identification and evaluation of the
environmental and social impacts of the Project.
7.2 OUTCOMES OF THE SCOPING PROCESS
The scoping process identifies potential impacts through a systematic process
whereby the activities associated with the Project phases are considered with
respect to the potential to interact with identified resources and receptors.
Interactions are then classified in one of four categories:
• No interaction, where the Project is unlikely to interact with the
resource/receptor;
• Interaction likely, but not likely to be significant: where there is likely to
be an interaction, but the resultant effect is unlikely to change baseline
conditions in an appreciable way;
• Significant interaction, where there is likely to be an interaction, and the
resultant impact has a reasonable potential to cause a significant effect on
the resource or receptor; and
• Positive interaction, where there is likely to be a positive interaction, and
the resultant impact has a positive effect on the resource or receptor.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
7-129
The resources and receptors relevant to the baseline environment are listed in
the vertical axis of the matrix with the Project phases and whether the
resource/ receptor is scoped in or not are listed across the horizontal axis.
Each resulting cell on the scoping matrix thus represents a potential
interaction between a project phase and a resource or receptor. Those
interactions with the potential for significant effects will be subjected to a
detailed assessment during the EIA process.
The completed scoping matrix is presented in Table 7.1, Table 7.2 and Table
7.3. A discussion of the aspects that are scoped in is included in Table 7.4.
Table 7.1 Scoping Matrix - MWE Underground Works (209 MR)
Impact Assessed Applicable Phase of the Project Scoped IN/ OUT
Constru
ction
Operati
on
Decommis
sioning
Post-
closure
Soils, Land Use and Land Capability
Impact on soils, land use
and land capability
OUT – all activities will
be underground
Surface Water
Impacts on surface water
quality and quantity X X X
IN
Groundwater
Mine water inflows and
decant X X X
IN
Impact of water level
drawdown on
groundwater users
X X X
IN
Impacts on water quality X X X IN
Impact of reduced
baseflow on surface water
and wetlands
X X X
IN
Air Quality
Impacts on air quality X
OUT - all activities will
be underground
Noise
Impacts on noise X
OUT - all activities will
be underground
Blasting
Blasting Impacts X X IN
Biodiversity
Dewatering and loss of
watercourse and
associated hydromorphic
grasslands
X X X
IN
Visual
No visual impacts are
expected due to
underground mining
OUT - all activities will
be underground
Archaeology & Heritage
No archaeological impacts
are expected due to no
surface works.
OUT - all activities will
be underground
Socio-economic
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
7-130
Impact Assessed Applicable Phase of the Project Scoped IN/ OUT
Constru
ction
Operati
on
Decommis
sioning
Post-
closure
Socio-economic impacts X IN
Table 7.2 Scoping Matrix - Adit 5 and Overland Conveyor
Impact Assessed Applicable Phase of the Project Interaction
Constru
ction
Operati
on
Decommis
sioning
Post-
closure
Soils, Land Use and Land Capability
Impact on soils, land use
and land capability X X X
IN
Surface Water
Impacts on surface water
quality and quantity X X X
IN
Groundwater
Mine water inflows and
decant X X X
IN
Impact of water level
drawdown on
groundwater users
X X X
IN
Impacts on water quality X X X X IN
Impact of reduced
baseflow on surface water
and wetlands
X X X
IN
Air Quality
Impacts on air quality X X X IN
Noise
Impacts on noise X X X IN
Blasting
Blasting Impacts
X
OUT – minimal blasting
is planned, only when
the continuous miner is
unable to proceed due
to hard rock.
Biodiversity
Dewatering and loss of
watercourse and
associated hydromorphic
grasslands
X X X
IN
Visual
Visual impacts X X X IN
Archaeology & Heritage
Impacts on archaeology
and heritage X
IN
Socio-economic
Socio-economic impacts X X X IN
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
7-131
Table 7.3 Scoping Matrix –Central Discard Dump
Impact Assessed Applicable Phase of the Project Scoped IN/ OUT
Constru
ction
Operati
on
Decommis
sioning
Post-
closure
Soils, Land Use and Land Capability
Impact on soils, land use
and land capability X X X
IN
Surface Water
Impacts on surface water
quality and quantity X X X X
IN
Groundwater
Impacts on groundwater
quality X X X
IN
Air Quality
Impacts on air quality X X X X IN
Noise
Impacts on noise X X X IN
Blasting
Blasting Impacts
Biodiversity
Dewatering and loss of
watercourse and
associated hydromorphic
grasslands
OUT
Visual
Visual impacts X X X X IN
Archaeology & Heritage
Impacts on archaeology
and heritage X
IN
Socio-economic
Socio-economic impacts OUT
7.3 DESCRIPTION OF POTENTIAL IMPACTS
This section contains a description of the potential environmental, socio-
economic and heritage impacts related to the expansion of underground
mining into the Maquasa West Extension area, the construction and operation
of the new main adit, the overland conveyor and the new discard dump.
These impacts have been identified through all the previous work that has
been undertaken on 133 MR including numerous specialist studies.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
7-132
Table 7.4 Impacts identified that have been Scoped IN
Aspect Project Activity
Soils, land use and land
capability
Clearance of vegetation where construction is occurring can result
in soil erosion due to exposure of open surfaces to wind and/ or
rainfall after the removal of the vegetation roots that currently bind
the soil. There will definitely be land clearance associated with the
construction phase of the main adit, the overland conveyor and the
discard dump.
Site soil compaction could be caused by heavy machinery that will
be on site for vegetation clearance and establishment of the discard
facility. Compaction of soils will tend to stabilise foundations and
decrease seepage.
A Soil Baseline Study and Impact Assessment have been
undertaken for the various components and will be included and
assessed in the EIA.
Surface Water Surface water quality in the Hlelo River and the Egude River to the
west along with their tributaries may be impacted upon. This could
occur as a result of the mobilisation of sediment following
vegetation clearance; dust created from clearance and earthworks
reaching the water resource; uncontrolled runoff from areas where
the spillage of wash water or hydrocarbons have occurred.
Surface water quantity could also be impacted as runoff
characteristics of the footprint area will be altered due to the
clearance, construction, stockpiling of overburden and soils; and
the construction of storm water management structures to separate
clean and dirty water. The compaction of surfaces would increase
the amount of runoff, while the capturing of water within the dirty
water catchment would reduce the amount of water reaching the
surface water resource.
A Surface Water Baseline Studies and Wetland Delineation as well
as Impact Assessments have been undertaken for the various
components and will be included and assessed in the EIA.
Groundwater During the construction phase of the development, minimal impact
on the groundwater system is expected.
However, the potential spillage of oils and fuels, etc. has the
potential to impact on the quality of the groundwater resource.
These impacts are considered a negligible/low impact, localised
and of short duration. However, a large hydrocarbon spill could
have a severe adverse long-term impact.
Groundwater quantity is likely to be affected by a number if the
activities, the extension of the Maquasa West Extension
underground activities in particular. In addition the construction of
the Adit 5 will impact groundwater flows and needs to be assessed.
The impacts on groundwater can have incremental impacts on the
surface water quantities as well due to baseflow reductions.
A Groundwater Baseline Study and relevant modelling as well as
an Impact Assessment will be undertaken for the various
components and will be included and assessed in the EIA.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
7-133
Aspect Project Activity
Air Quality There are likely to be some air quality impacts associated with the
clearing and construction of the surface infrastructure, including
the main adit, the overland conveyor and the discard dump. There
is also the potential for dust generation during disposal activities at
the discard dump.
An Air Quality Baseline Study and an Impact Assessment have
been undertaken for the various components and will be assessed
in the EIA.
Noise Noise impacts are expected throughout all phases of mining. There
will be additional noise impacts during construction and
decommissioning due to additional heavy machinery working on
the surface. Noise is also expected during the operational phase due
to activities at the main adit, the overland conveyor and the use of
vehicles and machinery at the discard dump.
A Noise Baseline Study and an Impact Assessment have been
undertaken for the various components and will be assessed in the
EIA.
Biodiversity Due to Kangra Coal’s 133 MR falling into the Eastern Highveld
Grassland ecosystem (listed by SANBI as Vulnerable), areas to be
cleared for construction need to be assessed.
Additionally the area is listed as an Important Bird Area and thus
also needs to have an assessment done.
Potential impacts on fauna and flora on 133 MR and surrounding
areas need to be assessed as well.
Wetland Delineation, Aquatic Ecology, Flora and Terrestrial
Ecology Baseline Studies as well as Impact Assessments have been
undertaken for the various components and will be assessed in the
EIA.
Visual There are likely to be visual impacts associated with the main adit,
the overland conveyor and the discard dump due to changes in the
landscape. Dust generation is also likely to cause poor visibility
conditions, however, this impact is expected to be limited in spatial
extent and duration.
A Visual Baseline Study and an Impact Assessment have been
undertaken for the various components and will be assessed in the
EIA.
Archaeology & Heritage Land clearance for construction of the Adit 5, overland conveyor
and the discard dump have the potential to impact on local
archaeology and heritage.
An Archaeology and Heritage Baseline Study and an Impact
Assessment have been undertaken for the various components and
will be assessed in the EIA.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
7-134
Aspect Project Activity
Socio-economic There is the potential for socio-economic impacts to surrounding
communities, both positive and negative. Some labour will be
required during the construction of the main adit and the overland
conveyor with a few jobs also being created during operations at
these sites. In general though the expectation for employment is
expected to be high and needs to be properly managed.
A Socio-economic Baseline Study and an Impact Assessment have
been undertaken and will be assessed in the EIA.
7.3.1 Cumulative Impacts
Section 2 of the NEMA requires the consideration of cumulative impacts as
part of any environmental assessment process. Furthermore this is carried
forward into Appendix 3 (j) (i) of the NEMA Regulations (2014) which
requires assessment of cumulative impacts in an EIA Report.
Cumulative impacts associated with this type of development could lead to
initial, incremental or augmentation of existing types of environmental
degradation, including impacts on the air, soil and water present within
available habitat. Pollution of these elements might not always be
immediately visible or readily quantifiable, but incremental or fractional
increases might rise to levels where biological attributes could be affected
adversely on a local or regional scale. In most cases these effects are not
bound and are dispersed, or diluted over an area that is much larger than the
actual footprint of the causal factor. Similarly, developments in
untransformed and pristine areas are usually not characterised by visibly
significant environmental degradation and these impacts are usually most
prevalent in areas where continuous and long-term impacts have been
experienced.
The nature of the development is such that pollution and degradation of the
surrounding areas are expected to some extent.
Cumulative impacts are assessed over the entire lifespan of the mining
operation and are therefore not broken down into the construction, operation
and decommission phases. These cumulative impacts will be assessed in the
EIA Phase of this Project and could include:
• Soils;
• Groundwater;
• Surface water;
• Air quality;
• Noise;
• Fauna and flora;
• Visual; and
• Socio-economic.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
8-135
8 PLAN OF STUDY FOR THE EIA
8.1 INTRODUCTION
According to Appendix 2 (i) of the NEMA Regulations (2014) a PoS needs to
be included in the Scoping Report which outlines the EIA process to be
undertaken.
A key outcome of scoping activities (described in Chapter 6) is the PoS for a
full EIA study. This Chapter provides the proposed PoS for the EIA and is
structured as follows.
• Alternatives to be considered and assessed;
• Aspects to be assessed as part of the EIA process;
• Aspects to be assessed by specialists;
• The proposed EIA methodology including assessment of duration and
significance;
• Stakeholder engagement and authority consultation;
• Steps that will be carried out to complete the EIA process;
• Structure of the EIA Report (or EIS); and
• Schedule for the EIA process.
8.2 PROJECT ALTERNATIVES CONSIDERED
The Project alternatives that have been assessed in the process of Scoping have
been addressed in Chapter 3. These included:
• MWE underground works:
• Alternative land uses;
• Alternative technology/ mining methods; and
• Alternative mineral processing methods.
• Adit 5 and overland conveyor:
• Alternative adit locations; and
• Alternative routes for the overland conveyor.
• Central Discard Dump:
• Alternative of expanding the existing Maquasa East discard dump;
and
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
8-136
• Development of a new discard dump.
For each of these components, the “No Go” option was also considered,
meaning that the proposed expansions would not be implemented. This in
turn would shorten the LoM and prevent the exploitation of important coal
resources and the retention of employment in the long term.
8.3 ASPECTS TO BE CONSIDERED IN THE EIA
Potential impacts associated with the development of the MWE underground
works, the new Adit 5 and overland conveyor and the discard dump have
been identified in Chapter 7. These impacts have been, and will be further,
assessed during the EIA phase to ensure that all potential impacts are covered
and a Consolidated EMPr for 133 MR will then be generated for the
management of all these aspects, to be implemented by Kangra Coal.
Potential impacts that have been identified in Chapter 7 include:
• Soils, land use and land capability;
• Groundwater;
• Surface water;
• Air quality;
• Noise;
• Fauna and flora;
• Visual;
• Archaeology and Heritage; and
• Socio-economic.
8.4 ASPECTS TO BE ASSESSED BY SPECIALISTS
Specialist studies have already been undertaken for the main adit, overland
conveyor and discard dump and are listed in below. For the inclusion of the
MWE underground works into the Consolidated 133MR EMPr the
groundwater information collected for the Adit 5 and overland conveyor as
well as for the discard dump and other existing information will be
remodelled and assessed to include the 209 MR underground works. The
Terms of Reference (ToR) for the groundwater study are included in Section
8.4.1. Although some of the studies were undertaken almost two years ago the
findings of these specialist studies are still applicable as there has been no
environmental change during this period.
Specialist studies undertaken for the Adit 5 and Overland Conveyor (ERM,
completed in 2014):
• Surface water and groundwater;
• Biodiversity;
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
8-137
• Heritage;
• Air quality;
• Noise;
• Soils, land use and land capability;
• Visual;
• Public participation process; and
• Socio-economic;
Specialist studies undertaken for the Central Discard Dump (GCS, completed
in 2015/2016):
• Soils, land use and land capability;
• Hydrological study;
• Wetland and aquatic assessment;
• Ecological assessment;
• Avifaunal assessment;
• Hydrogeological investigation; and
• Geotechnical assessment.
Specialist studies undertaken for the MWE (209MR) (Oryx Environmental,
completed in 2006):
• Geology;
• Climate;
• Topography, Soils, Land Use and Land Capability;
• Flora and Fauna;
• Groundwater;
• Surface Water;
• Air Quality;
• Noise and Vibrations;
• Sensitive Landscapes and Visual Aspects; and
• Socio-economic.
8.4.1 Terms of Reference (ToR) for Groundwater Study
As mentioned in the previous section, the groundwater impacts need to be
reconsidered to include the MWE (209 MR). The ToR for this Groundwater
Study are thus outlined in Table 8.1.
Table 8.1 Plan of Study for Groundwater Impact Statement Report
Specialist Plan of Study
Louis Botha
Groundwater Square
Groundwater Impact Statement Report
Project Terms of Reference include:
• Discussions on project approach;
• Site visit and discussions with relevant mine personnel;
• Collate existing data (groundwater, mine planning, aquifer
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
8-138
Specialist Plan of Study
geometry and geological);
• Perform cross-sections through mining area;
• Prepare maps;
• Identify potential groundwater-related impacts;
• Perform impact calculations and spreadsheet modelling of operational mine water balance, time for mine to flood after closure, etc.; and
• Compile impact statement on potential long-term geochemical conditions.
8.5 PROPOSED EIA METHODOLOGY
To ensure uniformity with the previously approved Kangra Coal’s
Consolidated EMPr, the assessment of potential impacts will be addressed in a
standard manner so that a wide range of impacts is comparable. The
methodology used for this impact assessment is detailed in this section.
Each impact identified will be assessed in terms of probability (likelihood of
occurring), scale (spatial scale), magnitude (severity) and duration (temporal
scale). To enable a scientific approach to the determination of the
environmental significance (importance), a numerical value will be linked to
each rating scale.
The following process will be followed:
The following criteria will be applied to the impact assessment for the
EIA/EMPr:
Occurrence
• Probability of occurrence (how likely is it that the impact may occur?); and
• Duration of occurrence (how long may the impact last?).
Severity
• Magnitude (severity) of impact (will the impact be of high, moderate or
low severity?); and
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
8-139
• Scale/extent of impact (will the impact affect the national, regional or local
environment, or only that of the site?).
Status of Impact
• +: Positive impact
• -: Negative impact
• N: Neutral (no impact)
In order to assess each of these factors for each impact, the following ranking
scales were used:
Probability:=P
5 – Definite/don’t know
4 – Highly probable
3 – Medium probability
2 – Low probability
1 – Improbable
0 – None
Duration:=D
5 – Permanent
4 - Long-term (ceases with the
operational life)
3 - Medium-term (5-15 years)
2 - Short-term (0-5 years)
1 – Immediate
Scale:=S
5 – International
4 – National
3 – Regional2 – Local
1 – Site only
0 – None
Magnitude:=M
10 - Very high/don’t know
8 – High
6 – Moderate
4 – Low
2 – Minor
Status of Impact
+: Positive
-: Negative
N: Neutral
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
8-140
Once the above factors have been ranked for each impact, the environmental
significance of each was assessed using the following formula:
SP = (magnitude + duration + scale) x probability
SIGNIFICANCE ENVIRONMENTAL SIGNIFICANCE
POINTS COLOUR CODE
High (positive) >60 H
Medium (positive) 30 to 60 M
Low (positive) <30 L
Neutral 0 N
Low (negative) >-30 L
Medium (negative) -30 to -60 M
High (negative) <-60 H
8.6 STAKEHOLDER ENGAGEMENT AND AUTHORITY CONSULTATION
Stakeholder engagement to be undertaken during the EIA phase is detailed in
Section 6.3 and includes:
• Draft EIR 30 days public commenting period;
• Comments and Responses Report;
• Notification of the DMR’s decision.
Table 8.2 lists the key commenting authorities that will be consulted
throughout the EIA process:
Table 8.2 Commenting Authorities
Organisation Name Designation
Gert Sibande District Municiplaity Mr. O.G. Xaba Director: Gert Sibande District
Mkhondo Local Municipalioty Vusiwe Dube Environmental Manager
Dr Pixley Ka Isaka Seme Local
Municipality
Ms Tebogo Mogakabe Manager: Municipal
Environmental Services at Gert
Sibande District Municipality
Mpumalanga
Department of Water & Sanitation
- Mbombela
Mr F Guma Chief Director: Mpumalanga
DARDLEA - Ermelo Mr. O.G. Xaba Director: Gert Sibande District
I&APs will be able to register and will be included on the stakeholder
database and will be given the opportunity to comment on all reports before
submission to the CA.
8.7 NEXT STEPS TO COMPLETE THE EIA
Following the scoping phase of the Project, the EIA team will:
• Update and finalise the technical project description as further engineering
details become available, working closely with project engineers to
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
8-141
confirm information such as the final layout, and construction and
operation plans;
• Conduct public participation activities and further refine the scope of the
EIA if necessary;
• Conduct any additional baseline studies through desktop research and
field studies in the Project area to complete a comprehensive description of
the environmental and social conditions;
• Develop mitigation and enhancement measures for the additional Project
components and develop an EMPr including an approach for monitoring;
• Consolidate new Project components and associated management
measures into the existing 133 MR to generate a Consolidated EMPr;
• Develop an Emergency Response and Environmental Awareness Plan
• Develop the Financial Provision for Closure;
• Develop an Environmental Rehabilitation Plan;
• Disclose the EIA and EMPr and findings to registered I&APs and the
relevant authorities; and
• Submit the Final EIA and EMPr to the DMR.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
8-142
8.8 STRUCTURE OF THE EIA REPORT
An outline of the proposed contents of the main volume of the EIA Report is
provided in Table 8.3.
Table 8.3 Proposed EIA Report Structure
Chapter Contents
Chapter 1 – Introduction Presents a brief background to the proposed Project, the Project
motivation, the project proponent and EIA team, and the
purpose and structure of the report
Chapter 2 – Project
Description
Describes the Project Area and the proposed Project components
Chapter 3 – Project
Alternatives
Discusses the Project alternatives that have been considered in
the EIA process
Chapter 4 – Legal Background Describes the legislative, policy and administrative
requirements, as well as international good practices and
standards/guidelines applicable to the proposed Project
Chapter 5 – Detailed
Environmental Description
Provides a detailed baseline assessment of the receiving physical
and biological environment in the Study Area
Chapter 6 – Public
Participation Process
Summarises engagement activities with Interested and Affected
Parties for the EIA Project
Chapter 7 – Identification and
Assessment of
Environmental Impacts and
Environmental Management
Programme
Presents the predicted impacts to the physical and biological
environment as a result of the proposed Project and associated
mitigation
Chapter 8 – Monitoring
Management Programme
Outlines procedures essential for effectively monitoring social
and environmental mitigation/management measures
Chapter 9 – Environmental
Emergency Response Plan
and Environmental
Awareness Plan
Outlines procedures for effective education of employees,
contractors and their sub-contractors on social and
environmental matters and responsibilities
Outlines procedures essential for effectively containing
emergency situations for the proposed Project
Chapter 10 – Financial
Provision
Presents a cost estimate for environmental rehabilitation and
closure of the proposed Project
Chapter 11 – Environmental
Rehabilitation Programme
Details the framework which aims to address environmental
issues related to rehabilitation, decommissioning and closure of
the proposed Project
Chapter 12 –Conclusion Summarises the key findings of the EIA Study
The content may alter slightly during the evolution of the Project or based on
the findings during the process, however, it is anticipated that the contents of
the EIA and EMPr will align broadly within the suggested framework.
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
8-143
8.9 PROVISIONAL SCHEDULE FOR THE EIA PROCESS
A provisional schedule for the EIA is provided in Table 8.4 below.
Table 8.4 Provisional EIA Schedule
Activity Timing
Start Finish
Public disclosure of Scoping Report 9 September 2016 9 October 2016
Submit the Scoping Report and PoS to DMR 14 October 2016
DMR to Accept or Reject PoS 14 October 2016 23 November 2016
Conduct the EIA November 2016 Mid December 2016
Public disclosure of Draft EIR and EMPr End November 2016 January 2017
Submission of Final EIA Report to DMR January 2017
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
9-144
9 CONCLUSIONS
This Scoping Report presents a description of the proposed Project: MWE
underground works, the Adit 5 and overland conveyor in Maquasa West
Extension and Maquasa West, and the new Central Discard Dump.
Alternatives for the Project including activity, location, process and site layout
alternatives are described in Section 3 while Section 5 provides a description
of the existing biophysical and socioeconomic environment of the Project site
which may be directly or indirectly affected by the Project. A number of key
issues/potential impacts that are expected as a result of the development of
the Project have been identified in this Report. These issues / potential
impacts will be further investigated during the EIA phase which is outlined in
the PoS (Section 8). The following aspects will be further investigated during
the EIA:
• Soils, land use and land capability;
• Groundwater;
• Surface water;
• Air quality;
• Noise;
• Fauna and flora;
• Visual;
• Archaeology and Heritage; and
• Socio-economic.
This Draft Scoping Report has been made available for a 30 day public
comment period. Comments on the Draft Scoping Report must be submitted
by 09 October 2016 to the following:
Following the comment period, the Scoping Report will be finalised,
incorporating and responding to all relevant comments. The Final Scoping
Report will be submitted to the DMR for their review and decision.
MS LISA OTTEN
ENVIRONMENTAL RESOURCES MANAGEMENT (ERM)
POSTAL ADDRESS: POSTNET SUITE 624, PRIVATE BAG X29,
GALLO MANOR, 2052
TEL: (011) 798 4300
FAX: (011) 804 2289
EMAIL: [email protected]
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
10-145
10 REFERENCES
Gert Sibande District Municipality IDP. (2012). Final IDP 2012/13 to 2016/17, Mpumalanga: District Municipality.
Department of Environmental Affairs. 2012. Highveld Priority Area Air
Quality Management Plan. Government Notice 144, Government Gazette No.
35072.
Department of Water Affairs. 2010. Operational Guideline: Integrated Water
and Waste Management Plan for the preparation of the Water Quality
Management Technical Document to support the Application for Licences for
Mining and Industries in Terms of the Requirements of the National Water
Act, 1998 (Act 36 of 1998).
Dr Pixley Ka Isaka Seme Local Municipality Final IDP. 2015/16 – 2016/17.
GCS (Pty) Ltd. 2013. Kangra Coal Pty (Ltd): Proposed Expansion of Mining
Operations: Environmental Impact Assessment and Environmental
Management Programme Report.
Geotail (Pty) Ltd. 2014. Kangra Project Design Report for New Maquasa East
Coal Discard Dump. Report no. GT-06/2014-Rev 1.
Hatch. 2011. Kusipongo Expansion Project - Concept Discard Dump Report -
Issued for Client Review.
Kangra Coal (Pty) Ltd. 2014. Social and Labour Plan for Kangra Coal
Operations, Mkhondo District- Mpumalanga
Mkhondo Local Municipality Final. IDP 2016-2017.
Okubo, S. and Yamatomi, Y. Underground Mining Methods and Equipment.
Civil Engineering Vol II.
Pistorius JCC. 2013. A Phase I Heritage Impact Assessment Study for Kangra
Coal (Pty) Ltd (Kangra Coal) Proposed New Mining Areas and Roads for the
Maquasa East and the Nooitgesien Open Cast Operations Near the Heyshope
Dam between Ermelo and Piet Retief in the Mpumalanga Province of South
Africa.
Wetland Consulting Services. 2013. Kangra Maquasa East and Maquasa West
Proposed Opencast Expansion Projects: Wetland Delineation, Ecological and
Impact Assessment Report.
Websites Accessed
ENVIRONMENTAL RESOURCES MANAGEMENT KANGRA COAL (PTY) LTD.
10-146
World coal association. (2011). Coal statistics. <http://www.worldcoal.org/
resources/coal-statistics. Accessed on 2015-03-30
US Energy Information Administration. Http://www.eia.gov/countries/
cab.cfm?fips=sf. Accessed on 2015-03-30.
Eberhard a. (2010). South African Coal: Market, Investment and Policy
challenges. <http://gsbnet.uct.ac.za/mir/admin/documents/
south%20african%20coal%20paper_15_12_2010_17821.pdf>. Accessed on
2011-03-17
NSWMINING. Http://www.nswmining.com.au/industry/mining-methods -
Accessed 4 March 2015
Wikipedia. Http://en.wikipedia.org/wiki/room_and_pillar - accessed 4
march 2015