6.3 sequence activities
TRANSCRIPT
6.3 Sequence Activities
Knowledge Area
Process
Initiating Planning ExecutingMonitoring &
ControlClosing
Time
Plan Schedule management- Define Activities Estimate Activity Resources Sequence Activities Estimate Activity Durations Develop Schedule
Control Schedule
Enter phase/Start project
Exit phase/End project
InitiatingProcesses
ClosingProcesses
PlanningProcesses
ExecutingProcesses
Monitoring &Controlling Processes
Now that we’ve identified the schedule activities, we
need to sequence them in a logical order and find out
whether dependencies exist among the activities.
The interactivity of logical relationships must be
sequenced correctly in order to facilitate the
development of a realistic, achievable project schedule
in a later process.
Consider a classic example. Let’s say
you’re going to build house.
• You must excavate before you can
build the foundations
• You must build the walls first
before you build the roof
• And so on…
During Sequence Activities, you will
use a host of inputs and tools and
techniques to produce the primary
output, project schedule network
diagrams.
Once you’ve identified the dependencies and assembled all the other inputs for the Sequence Activities process, you’ll take this information and produce a diagram or schematic display of the project activities.
The diagram or schematic display is called project schedule network diagram
Start End
Project network diagrams are schematic displays of the project’s activities and the logical relationships (dependencies) among them.
Show workflow from left to right.Not drawn to a time scale.Can vary in how detailed the diagram should be.
Network diagrams
Shows interdependencies of all activities
Show workflow so the project team will know what activities need to happen in a specific sequence
Aid in effectively planning, organizing and controlling the project
Compress the schedule (defined later) in planning and throughout the life of the project
Show project progress if used for Control Schedule and reporting
Help justify the time estimate for the project
How a network diagram helps a project?
6.3 Sequence Activities
Inputs
1.Schedule Management Plan
2.Activity list3.Activity
attributes4.Milestone list5.Project scope
statement6.Organizational
process assets
Tools & Techniques
1.Precedence Diagramming Method (PDM)
2.Dependency determination
3.Applying leads and lags
Outputs
1.Project schedule network diagrams
2.Project document updates
Inputs
1. Schedule Management Plan: Section 6.2
2. Activity list: Section 6.2
3. Activity attributes: Section 6.2
4. Milestone list: Section 6.2
5. Project scope statement
• Contains the product description that may indicate
sequencing of activities such as physical layouts,
interfaces, etc.
6. Organizational process assets
• Historical records form similar projects
Tools and Techniques
1. Dependency Determination
Dependencies are relationships between the activities in
which one activity is dependent on another to complete
an action, or perhaps an activity is dependent on
another to start an action before it can proceed.
Dependency Determination
1. Mandatory dependenciesAlso known as “hard logic” are inherent in the nature of the work being done; They often involve physical limitations.•Example: Complete the foundations before you start building the walls of a house
2. Discretionary dependenciesAlso known as “preferred” or “soft logic” are defined by the project team usually based on knowledge of:•“Best practices” within a particular area based on past experience or some unusual aspect of the project where a specific sequence is desired, even though there are other acceptable sequences.•Example: Complete Room 2 of a house before completing Room 1
3. External dependencies
•External dependencies are, well, external to the project.
This might seem obvious, but even though the dependency is
external to the project and therefore a non project activity, it
impacts project activities.
•For example, perhaps your project is researching and
marketing a new drug. The government must approve the
drug before it can be market it. This is not a project activity,
but the project cannot move forward until approval occurs.
That means government approval is an external dependency.
Dependency Determination
NOTEYou must determine all the
types of applicable
dependencies in the project in
order to sequence the
activities and subsequently
develop the project schedule
Tools and Techniques
2. Applying Leads and Lags
Activity dependencies may require a lead or a lag to
accurately define the activity logical relationship.
Lag
Inserted modification of logical dependency between
activities that allows for waiting time (delay) between
activities
• Example: In a finish to start dependency; “You must
wait 20 days after pouring concrete before you can
construct the house frame”
ConcreteConcrete
FrameFrame
ConcreteConcrete
FrameFrame
Lag = 20days
Before the Lag
After the Lag
Applying Leads and Lags
Lead
Inserted modification of a Finish to Start dependency
logical relationship that allows an acceleration of the
successor activity.
• Example: You can start the brick work on a house 10 days
before the entire wood frame is completed
Applying Leads and Lags..
Before lead
After Lead
Wood FrameWood Frame
Brick workBrick work
Wood FrameWood Frame
Brick workBrick work
Lead = 10 days
Applying Leads and Lags..
3. Precedence Diagram Method (PDM) or Activity on Node (AON):
This is a method of constructing a project network diagram that uses boxes or rectangles (nodes) to represent the activities and connects them with arrows that show the dependencies.
This is the method used by most project management software packages.
PDM/AON can be done manually or on a computer. Example:
start
A B C
D E F
Finish
Tools and Techniques
Precedence Diagram Method (PDM)
• Each activity is represented by a box.
• The activity description is written in the box.
• Each box is assigned a unique activity number.
• Activities have a precedential relationship (there are 4
types).
• Some activities may be done concurrently.
PDM/AON does not use
DUMMY arrows to connect
activities.
PDM/AON can only use one
time activity estimate (see
Estimate Activity
Durations ) to determine
project duration
Hint
Precedence relationshipsa. ) Finish-to-Start (FS):
AA
BB
In PDM diagrams, this is the most often used logical relationship.
This relationship says that the predecessor-or the “from” activity-must finish before the successor-or the “to” activity-can start.
In plain English,
Activity B cannot start until A finishes
Precedence Diagram Method (PDM)
b.) Start-to-Finish (SF)
The start-to-finish relationship says that the predecessor activity must start before the successor activity can finish.
Activity B cannot finish until A starts
This logical relationship is seldom used.
BB
AA
Precedence Diagram Method (PDM)..
c.) Finish-to-Finish (FF)
The finish-to-finish relationship says that the predecessor activity must finish before the successor activity finishes.
Activity B cannot finish until A finishes
AA
BB
Precedence Diagram Method (PDM)..
d.) Start-to-Start (SS)
I think you’re getting the hang of this. The start-to-start relationship says that the predecessor activity must start before the successive activity can start.
Activity B will start when A starts
AA
BB
Precedence Diagram Method (PDM)..
1. Project network diagrams PDM
2. Project Document Updates Activity list and Activity Attributes Updates
Keep in mind that the construction of these project schedule network diagrams might bring activities to light that were missed when defining the activity list, or it might make you break an activity down into two activities in places where you thought one activity might work.
If this is the case, you will produce both activity list updates based on this new information as well as activity attributes updates.
Risk register Chapter “ Project Risk Management”
Outputs
Project Schedule Network Diagram
Next Topic 6.4 Estimate Activity
Resources