6.6 changing the contract

Upload: anousack-kittilath

Post on 03-Jun-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/12/2019 6.6 Changing the Contract

    1/5

    Changing the Contract

    In PW&S standard contracts, various stipulations allow the GNWT

    to make changes to the original contract. Changes in the contractare used to formally delete, modify, of introduce new conditions to

    the original contract.

    Principles

    Although every contract change must be individually evaluated,

    the following basic principles apply:

    Legal principles dictate that changes to a contract must beconsistent with the general intent of the original contract.

    All GNWT contracts require that contract changes must be inwriting and approved by the GNWT contract authority.

    Acceptance and signature by the contractor are preferable, but

    not legally required for most PW&S contracts.

    Internal PW&S policy dictates that changes should not be usedto increase the scope of the original contract by more than

    30%. Increases beyond this magnitude should be coveredunder a separate, competitively priced contract

    Changes should be documented and processed as soon as practical,and ideally before the work affected has started.

    Reasons for Changes

    Countless reasons for changes may impact any contract. The

    reasons for changes will fall roughly into one of three possible

    categories: scope, logistics, or error. Some of the more typical

    reasons include:

    Change to the work site or the known conditions of the site

    Change to the delivery destination or the terms of delivery

  • 8/12/2019 6.6 Changing the Contract

    2/5

    Ambiguous definition of the contract scope (specifications,plans, etc.)

    Change to the magnitude, design or scope of the work

    Change in regulatory requirements

    Late or defective owner-supplied material or equipment

    Interference or lateness of another PW&S contractor involvedin the work

    Poor contract administration by the owner (late approvals,decisions, or inspections)

    When these causes are due to actions or lack of action by the

    GNWT, the contractor may receive additional reimbursement tocover damages.

    Time Extensio ns/Delays

    In addition to influencing the cost of the contract, many changes

    may also influence the time required to complete the work.

    Similarly, in some circumstances, time is the only aspect of the

    contract to be affected.

    Time extensions are normally not granted for delay caused byfactors within the contractors control and responsibility, such as

    the following:

    poor planning and organizing

    inadequate resources (labour, equipment)

    insufficient weather protection

    In situations where the contractor causes a delay, the GNWT mayassess the contractor costs incurred because of the delay.

    Time extensions may be granted when completion of the contract

    has been delayed due to circumstances beyond the contractors

  • 8/12/2019 6.6 Changing the Contract

    3/5

    control. For example:

    strike at the work site or manufacturers plant

    change in the work that affects magnitude or delivery

    delay caused directly by the GNWT (work suspensions, lateapprovals or decisions)

    delay caused by other GNWT contractors

    extraordinary weather conditions

    Format for Changes

    Two formats are used to change PW&S contracts: the Change

    Orderand theAmendment.

    Change Order

    A contract Change Orderis used to modify all PW&S standardservice, consultingandconstruction contracts. Achange orderis

    prepared on the standard PW&S form (see Section 1.7).

    The change order outlines the details of the modification to the

    contract scope, price, and completion date as appropriate. Change

    orders are normally signed for acceptance by the contractor,recommended by the consultant if applicable, and approved by the

    PW&S Contract Authority.

    Specific details on the administration of change orders in different

    contract applications may be found in thePW&S Project

    Management Manual.

    Amendments

    APurchase Ordercontract for goods may be changed by way of a

    purchase order amendment using the standardPurchase Order

    form. The original purchase order number, with the addition of the

  • 8/12/2019 6.6 Changing the Contract

    4/5

    appropriate amendment number, is used to identify the

    amendment.

    The amendment will outline the change or modifications to the

    originalPurchase Ordercontract and indicate the revised total

    contract price.

    Facsimile/Email Changes

    Contract amendments and change orders may be issued by

    facsimile transmission or electronic mail. It is good practice to

    verify receipt of the transmission. Similarly, formal acceptance of

    the change order or amendment by the contractor may be receivedby facsimile or electronic mail.

  • 8/12/2019 6.6 Changing the Contract

    5/5