7d37bb78-ce53-15cc-7627546d83ca6ec7
DESCRIPTION
Hint for V.ETRANSCRIPT
-
The Arup Journal 3/200624
West Rail was conceived and carried through totechnical study stage as a 12-car system identicalto the operating East Rail line. This requiredplatform lengths of some 290m and overall stationlengths varying between 400m and (for Tin ShuiWai) 540m. Elevated stations generally were shorterthan those underground as they did not requirelarge plantroom spaces for tunnel ventilation.
All detailed design consultancies commenced inMarch 1998 based on the 12-car arrangement, andall teams provided KCRC with specified deliverablesthrough that year. In autumn 1998, however, KCRCas part of its review procedure questioned the basicpremise of why West Rail should replicate EastRails 12-car system where stations are largely at-grade and open-sided whereas West Rails were tobe enclosed and fully air-conditioned. This questionspurred KCRC to hold value engineering exercisesfor all parts of the project with the aim of reducingcosts and, if possible, enhancing the programme.
All consultant teams undertook a series ofintensive value engineering workshops in late 1998with KCRCs project management teams to study allfacets in particular station sizing. After KCRCsown in-house deliberations, it was decided to adopta nine-car system. This reduced platform lengths bysome 72m and thus the volumes of spaces to beconditioned. To maintain the same carrying capacitythe signalling system was improved, and headwaysreduced initially from 120 seconds to 90 seconds.
Reducing station lengths, however, increasesadjoining viaducts or tunnels (albeit these are lesscostly to construct than stations) and so did notentirely fulfil KCRCs large cost-saving agenda.As a consequence, numerous items were revisited,studied for potential savings, and recosted. As anexample, for Tsuen Wan West station a total of 68
ValueengineeringWest RailColin Wade
items were brainstormed for initial evaluation by all team members. This was post-rationalized to 42 items, and ranged from overall reassessments of basementexcavation methods, anti-flotation systems, column shapes, and floor structuresystems through to reducing screed thicknesses, moving E&M plant above ground,reducing E&M service voids, lowering concourse ceiling height, and reducingescalator design criteria. All were evaluated for cost, programme, quality, risk and,where appropriate, aesthetics.
Many were found not to offer significant advantages over and above the designas it already stood by the value engineering study stage, but some improvementswere made to the station generally, resulting in reduced length, width, and depthbelow ground. These were incorporated into the subsequent redesign which thenproceeded rapidly to tender documentation stage. Similarly, the elevated stationson the Yuen Long section were shortened and re-engineered to yield savings.
The value engineering exercise was an interesting and worthwhile undertakingfor all teams involved co-operation and empathy between KCRCs projectmanagement teams and all consultants was of paramount importance and at theend of the exercise provided a significant benefit for the project.
Together with competitive tender prices and other beneficial factors, includinglower land resumption costs, the nine-car system cost estimate for the entireproject was revised downwards from the original HK$64bn to HK$46.4bn.
1. New rolling stock on the main line near Pat Heung Maintenance Centre.
16033_Arup.qxd 1/12/06 7:54 pm Page 24