Release Management
-
7/27/2019 8 Release Mgt (1)
2/13
2
Goal Primary Objective
To take an holistic(Overall) view of aChange to an IT service and ensure that allaspects of a release, both technical and
non-technical are considered together
-
7/27/2019 8 Release Mgt (1)
3/13
3
Why Release Management
Managelarge or critical hardware roll-outs
Manage major software roll-outs Bundling or batching related sets of changes Controlthe release of authorised CIs into the supported
environment
Release Policy
A release policy document should be produced to clarify the
roles and responsibilities for Release Management. Theremay be one document per organisation or an umbrella set ofguidelines and specific details for each supported service
-
7/27/2019 8 Release Mgt (1)
4/13
4
Responsibilities of Release Management
Release
Policy
Release
Planning
Develop
or
purchase
software
Build /
configure
release
Fit for
purpose
testing
Release
acceptanceRoll out
planning
Communication
preparation &
training
Distribution
& installation
Configuration Management Database (CMDB)
and
Definitive Software Library (DSL)
Controlled Test Environment Live Environment
RELEASE MANAGEMENT
Development
Environment
-
7/27/2019 8 Release Mgt (1)
5/13
5
Terminology Definitive Software Library (DSL)
Definitive Software Library where ALL authorised versions of software are stored
and protected. A Physical library or storage repository where master copies ofsoftware
versions are kept. This one logical store may consist of one or more physical softwarelibraries or file stores.
Definitive Hardware Store (DHS)Definitive Hardware Store An area set aside for the secure storage of definitive
hardware spares. Types of Release
- Delta, Full and Package
Definitions
Release:a collection of authorised Changes to an IT Service
Release Unit:the portion of the IT infrastructure that isnormally released together
Roll-out:deliver, install and commission an integrated set ofnew or changed CIs across logical or physical parts of anorganisation
-
7/27/2019 8 Release Mgt (1)
6/13
6
Types of Release Delta
Only those CIs that have actually changed since last releaseare included.
FullAll components of the Release are built, tested, distributed
andimplemented together (whether they have changed or not).
PackageIndividual Releases both Full and Delta are grouped
together to
form a Package for release.
-
7/27/2019 8 Release Mgt (1)
7/13
7
Build Management
Software and Hardware components for release should beassembled in a controlled, reproducible manner.
Build Management becomes the responsibility of Releasemanagement from the controlled test environment on wards.
Back out plans should be devised and tested as part of therelease.
Change Management allows CMDB to remain accurate. Without Configuration data change impacts are not accurately
assessable.
Without Change and Configuration Management, Releases will
not be controlable.
-
7/27/2019 8 Release Mgt (1)
8/13
8
Possible Problems
Resistance from Staff to new procedures Circumvention of procedures
Unclear ownership and role acceptance Lack of understanding of release contents Reluctance to back out of a failing release.
-
7/27/2019 8 Release Mgt (1)
9/13
9
Benefits
Improved service quality from greater success rate forreleases and minimal disruption to the business
Greater ability to cope with high levels of Change Assurance that hardware and software in live use is of
known quality, reducing the chance of illegal, wrong orunauthorised software being in use
Better expectation setting for Business and Service staff
-
7/27/2019 8 Release Mgt (1)
10/13
10
Exam Tips
Release is associated with ROLLOUT Urgent Software releases do not require FULL
testing
RM
-
7/27/2019 8 Release Mgt (1)
11/13
11
Exam Questions
One of Release Managements tasks is to set up a DHS.Which statement most closely describes the DHS?
A A DHS is a number of physical locations where baselines arestored
B Before setting up a DHS a tool should first be purchased forreleasing the hardware into the environment
C A DHS is an area set aside for the secure storage of definitive
hardware spares
D A DHS is a database in which all definitive hardwareConfiguration Items are recorded
-
7/27/2019 8 Release Mgt (1)
12/13
12
Exam Question
The words Delta, Full and Package describe differenttypes of release. Which one of these following statementsis true?
A A Package release contains hardware and softwareB Urgent changes are always Delta releases
C A Delta release is only ever part of a Package release
D A Full release releases the normal release unit into the
live environment
-
7/27/2019 8 Release Mgt (1)
13/13
13
Exam Question
Students at a college can send in their course work fromtheir home PC via the telephone Network. They can thencheck their results on their PCs. A student needs anexisting set of programs that can be configured for theparticular course that the student is following. Whichprocess is responsible for the correct configuring andtransmission of the programs?
A Release Management
B Change Management
C Configuration Management
D Network Management