  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    1/78

    Training Materials For Reference Only Slide 1

    Finding and eliminating (forever) the root

    cause of a problem.

    HBC 8D Process for Problem Solving

    Course Duration: 4.0 hours

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    2/78

    Training Materials For Reference Only Slide 2

    Course Objectives

    At Completion YOU should:

    Understand HBCs 8D process Know when to use the 8D Process

    Be able to write an 8D Summary Report

    Be comfortable using typical problem solving tools

    Know how to get additional help/training

    I hear...I forgetI see...and I rememberI do...and I understand

    Ancient Chinese Proverb

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    3/78

    Training Materials For Reference Only Slide 3

    Origin of HBCs 8D process Fit with:

    Hawker Beechcraft Performance System (HBPS) Initiatives

    Existing processes Overview of the 8 Steps

    0 - Decide to use the HBC 8D Process1 - Describe the Problem

    2 - Assemble a Team3 - Implement Interim Containment4 - Find Root Cause5 - Develop Corrective Action

    6 - Implement Permanent Fix7 - Prevent Recurrence8 - Recognize the Team

    Additional Information contacts, reference material

    Agenda

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    4/78Training Materials For Reference Only Slide 4

    Round Robin Introductions

    Your Name

    Where you work -position/responsibilities

    Personal objectives for this course

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    5/78Training Materials For Reference Only Slide 5

    Root Cause: The very basic reason why, how, & when the conditionoccurred.A Root Cause Mentality: An insatiable desire to understand why things gowrong, why people do what they do, and how things got into their presentstate. (C. Robert Nelms)

    This takes persistence

    Interim Containment Action: This is the action taken which shouldaddress and correct the actual nonconforming condition.

    Permanent Corrective Action: This should address the root cause ofa nonconformance and prevent future occurrences of the problemwhich caused the nonconformance.

    Contributing Cause: This factor contributed to the problem, but it is

    not the root cause. Keep going to get to Root Cause.

    Verification: Making sure that something is going to work prior toimplementation.

    Validation: Checking to make sure that the change is working (afterimplementation)

    Definitions

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    6/78Training Materials For Reference Only Slide 6

    A systematic approach to effectively identify the

    cause chain of a nonconformance and topermanently eliminate the source(s) of problems.

    Directed at reducing, and if possible eliminating,quality system escapes and the costs associated withpoor quality.

    Root Cause / Corrective Action (RCCA) is:

    More on Root Cause

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    7/78Training Materials For Reference Only Slide 7

    Origin of HBCs 8D Process

    8D (8 Disciplines) first standardized by the U.S.government during World War 2

    Military Standard 1520: Corrective action and disposition

    system for nonconforming material Popularized by Ford Motor Company in the 1960s and

    1970s (called Global 8D or G8D) 8D now a standard in the Auto Industry

    8D fills a void we currently have at HBC We reference root cause (internally, with our suppliers and

    customers) BUT, we dont provide a standard process to get to root cause

    HBC 8D a Structured Process (and Tool Set) for Root Cause Corrective Action

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    8/78Training Materials For Reference Only Slide 8

    HBPS Initiative Positioning

    Goal solve the problem Smooth land (drain the lake,

    remove boulders) No leaks in the boats (rental

    income while lake is here)

    Pick the best fit methodology Drain the lake (remove waste)

    use LEAN Six Sigma Remove boulders (variation

    reduction) use Lean SIX SIGMA

    Leaks (immediate problems thatmust be fixed) use HBC 8D

    Use the right tools for the job Common tools will be used by all

    methodologies

    This Analogy: Bucket can beused to empty the lake, removerubble, and bail out the boat

    In general, Lean Six Sigma projects take longer; 8D is for everyday, immediate problems.

    http://www.clipart.com/en/close-up?o=898840&a=c&q=lake&k_mode=all&s=286&e=300&show=&c=&cid=&findincat=&g=&cc=4935:17:7083:251:0:4298:6&page=20&k_exc=&pubid=&color=&b=k&date=
  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    9/78Training Materials For Reference Only Slide 9

    Time

    Planning

    0

    40

    0

    Lessons Learned

    Sporadic Spike

    (Special Cause: HBC 8D)

    Control (During Production)

    Significant Shift

    AND/ORVariation Reduction(Lean SIX SIGMA)Common cause

    (random)variation/waste

    (LEAN Six Sigma)

    Special cause(assignable) variation

    HBPS Initiative Positioning (alt. view)

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    10/78Training Materials For Reference Only Slide 10

    8D Process Fit

    Policy & Procedures 12 0008 Corrective ActionSystem

    Quality Assurance Instruction (QAI) -- QAI 03-01-015

    Corrective Action Response and Review Requirements

    Corrective Action requests resulting from: Nonconforming material

    Out of control processes Internal audits Supplier issues Customer complaints Operator self-verification process Other nonconformances in product or process

    Via: PCAS - Production Corrective Action System FCAS - Field Corrective Action System IQAG - Internal Quality Audit Group OSV - Operator Self Verification + Management Directive

    8D adds structure (defined steps, language) to what we already have.

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    11/78Training Materials For Reference Only Slide 11

    Changes being made to: WI 04-09-009 Creating and Updating

    Corrective Action Records in SAP WI 04-09-014 Responding to the Corrective

    Action in SAP

    WI 04-14-005 issuing Corrective ActionRequests for Major Noncompliances

    Documents Created in SAP: Q1 Customer Complaint Q2 Vendor Product Non-Conformance Q3 HBC Product Non-Conformance

    Q4 Vendor Product CA Q5 HBC Product CA Q6 Vendor Audit CA/PA Q7 HBC Audit CA/PA

    HBC 8D form will be attached to the

    appropriate Q1-Q7 record in SAP Reference Hard Copy of HBC 8D Formhandouts

    8D Process Fit (cont.)

    Work Instructions are being modified now to incorporate 8D.

    Wh t i 8D?

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    12/78Training Materials For Reference Only Slide 12

    What is 8D?

    1. Corporate Standard

    2. Standardized Problem Solving

    Process

    Language, Methodology

    3. Reporting Format

    8 Di i li (8D )

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    13/78Training Materials For Reference Only Slide 13

    8 Disciplines (8Ds)

    D-0 Decide to use the 8D Process existing processes

    D-1 Describe Problem

    D-2 Establish TeamD-3 Implement Interim Containment

    D-4 Find Root Cause

    D-5 Choose Corrective Action

    D-6 Implement Permanent Corrective Action

    D-7 Prevent Recurrence

    D-8 Congratulate Team

    Wh t t i 8D l i ?

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    14/78

    Training Materials For Reference Only Slide 14

    What can trigger an 8D analysis?

    When do we

    use the

    8DProcess?

    Problem with Cause Unknown

    Need to Cure - Not Mask Problem

    Justifies a Structured/Team ApproachFactors Severity, Cost, Time, etc.

    Examples:

    Whenever you open a QN, ask yourself if Root Cause/8D should be done.

    Wh i iti t 8D l i ?

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    15/78

    Training Materials For Reference Only Slide 15

    Who can initiate an 8D analysis?

    Request for an 8D analysis can be made by: Customer

    Current Sales/Support Interface

    HBC Employee Initially, by contacting QA reps

    Eventually, anyone

    Working out details defining when it makes sense

    Not all problems need an 8D level of analysis

    HBC Supply Chain

    Supplier will perform the 8D

    Management

    Anyone can use the process. Using SAP makes sure we capture/share knowledge.

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    16/78

    Training Materials For Reference Only Slide 16

    Place in 8D Process

    D-0 Decide to use the 8D Process

    D-1 DESCRIBE THE PROBLEMDESCRIBE THE PROBLEM

    Why is it important for a Problem Solving

    team to start with Describe the Problem?

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    17/78

    Training Materials For Reference Only Slide 17

    8D Step 1 Describe the Problem

    What is the problem?

    This should be a short, simple and concise definition.

    IF YOU CANNOT SAY IT

    SIMPLY, YOU DO NOTUNDERSTAND THE

    PROBLEM

    REMEMBER:

    A problem well stated is aproblem half solved!

    Information about the problem

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    18/78

    Training Materials For Reference Only Slide 18

    What is the problem?

    Where was it detected? How serious is the problem?

    How many occurrences?

    Who is affected? When did it surface?

    Remember: on the problem.

    Information about the problem

    Problem Definition/Analysis Prompts

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    19/78

    Training Materials For Reference Only Slide 19

    Problem Definition/Analysis Prompts

    Who?

    Who notified you of the problem?- Manufacturing, Engineering, SAP QN Review, QA

    Audit, etc.Who are the people involved with the problem? (for step 2 team formation)

    - Supplier, customer, material handlers, assemblers, supervisors,engineers, QA personnel, etc.

    High Level information belongs in the Problem Description, Investigate all others in Step 3 & 4.

    Problem Definition/Analysis Prompts

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    20/78

    Training Materials For Reference Only Slide 20

    Problem Definition/Analysis Prompts

    What?

    What is the part name/number/other identification?What type of product or process?

    - Detail, assembly, vendor part- Part manufacturing process, assembly process?

    What is the type of nonconformance?- Scratch, Dent, Oversize hole, Fit?

    - Lack of communication, waiting too long for info/parts?What characteristic of the part/process is having the failure

    - hole radius, linear dimension?

    - manufacture of the part, movement, inspection?What method of measurement was used to identify the failure?What are special circumstances surrounding the problem?

    - new personnel, equipment move, new tool, etc.?

    What environmental conditions existed?- extremely cold/hot, rainy, humidity, lighting, etc.?

    What is the design/nonconformance criteria in question?- Drawing, Spec, Task Planning, Policy, Process?

    What training has been done or is available?What hardware or software is associated with the issue? Have there been recent administrative, program or equipment changes?

    Problem Definition/Analysis Prompts

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    21/78

    Training Materials For Reference Only Slide 21

    When in the build process/production schedule/work shift did the problemoccur?

    - note: occurrence point and detection point may(and usually arent) at the same time

    When in the task did the problem occur? (what step?)When in the functional test did the problem occur (what step?)When in the day, week, month did it/has it occurred (patterns)?

    Problem Definition/Analysis Prompts

    When?

    Problem Definition/Analysis Prompts

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    22/78

    Training Materials For Reference Only Slide 22

    Where is the part being contained?Where is the part being used?

    Where is the geographical location of the failure?What plant/line/station cell? Is the problem in-house or external (supplier) or external (in the field)?Where are similar nonconformance records located?

    Problem Definition/Analysis Prompts

    Where?

    Problem Definition/Analysis Prompts

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    23/78

    Training Materials For Reference Only Slide 23

    Problem Definition/Analysis Prompts

    Impact?

    How many times and in what period? Cost of nonconformance in dollars? Safety impact? Cost of delay?Warranty cost? Impact to worker morale/productivity? Has this issue been fixed before? Impact on Business processes?

    - production- delivery- product use- field reliability

    Impact on Customer Satisfaction?

    Importance of Problem Description

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    24/78

    Training Materials For Reference Only Slide 24

    Importance of Problem Description

    Focuses team on same objective

    Direction set here is used throughout the HBC8D process (foundation)

    Forces all to agree on the scope and goal

    Note: Operational Definitions MUSTaccompany the Problem Description What does failure mean?

    What is bad?

    What does success look like? Ice-scrapingvideo

    Tool: Is / Is Not for Problem Definition

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    25/78

    Training Materials For Reference Only Slide 25

    Tool: Is / Is Not for Problem Definition

    Reasons to use IS - IS NOT

    Establishes points of comparison

    Leads to a more complete problem description

    Provides a Test base for Root Cause

    Gives you a fingerprint of the problemDraws better boundaries around the problem

    SCOPE whats in, whats out

    Tool: Is / Is Not for Problem Definition

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    26/78

    Training Materials For Reference Only Slide 26

    Development of IS:

    Identity - What is the problem?

    Space - Where is the problem?

    Time - When is the problem happening?(also When did it start?)

    Mass - How Big is the problem?

    Tool: Is / Is Not for Problem Definition

    Development of IS NOT

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    27/78

    Training Materials For Reference Only Slide 27

    IS IS NOT(What, Where, When, How Big) would you EXPECTEXPECT to..

    SEE, HEAR, FEEL, SMELL, OBSERVE . . .

    .....but DO NOT?DO NOT? ((close cousinsclose cousins))

    >>>>>>>>>>>>>>>>>>>>

    Development of IS NOT

    (What, Where, When, How Big) IS it?

    (What, Where, When, How Big) could it be but it IS NOT ?

    Once you have the Problem Defined, get feedback from others

    (coworkers, manager, others) who have done 8D/RCCA

    Reasons to use IS - IS NOT

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    28/78

    Training Materials For Reference Only Slide 28

    Reasons to use IS IS NOT

    Establishes points of comparison

    Leads to a more complete problem description

    Provides a Test base for Root Cause

    Gives you a fingerprint of the problem

    Draws better boundaries around the problem SCOPE whats in, whats out

    Document Your Work

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    29/78

    Training Materials For Reference Only Slide 29

    1) Open a QN in SAP2) Fill Out Section 1 of the 8D Summary Report

    - go to the Quality Forms link on the QA home page

    3) Attach the 8D Summary Report file to the QN

    Step 2 in the HBC 8D Process

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    30/78

    Training Materials For Reference Only Slide 30

    p

    D-0 Decide to use the 8D Process

    D-1 Define the Problem

    DD--2 Form the Team2 Form the Team

    8D - Step 2: Form a Team

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    31/78

    Training Materials For Reference Only Slide 31

    p

    A Team may be:

    formal (scheduled meetings, for ex.) or

    informal (consulted as needed)

    Agree on work group guidelines

    CustomerComplaint

    Advantages/Disadvantages of Teams

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    32/78

    Training Materials For Reference Only Slide 32

    Advantages/Disadvantages of Teams

    WHY DO TEAMS FAIL?

    WHAT ARE THE BENEFITS

    OF A TEAM APPROACH?

    What have been your experiences with teams??

    Major Problems with Team Problem

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    33/78

    Training Materials For Reference Only Slide 33

    Solving

    Problem incorrectly describedProblem incorrectly described ! ! !! ! ! (biggest inhibitor)(biggest inhibitor)

    Make sure Problem Description is accurate and team

    members agree Problem solving process rushed

    Poor team participation

    No logical (group) process

    Lack of technical skills

    Management impatience Permanent Corrective Action Not Implemented

    Typical Team Organization

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    34/78

    Training Materials For Reference Only Slide 34

    yp ca ea O ga a o

    Champion/Sponsor

    Leader

    Recorder rotate this role

    Team Members(SMEs - Subject Matter Experts)

    Facilitator (optional)

    Customer/Supplier

    Are we having

    fun yet?

    Recommend: 4-7 members

    (10 max.)

    10, consider subteams

    Ask the initial team: Who else needs to be involved, but isnt here?

    Step 3 in the HBC 8D Process

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    35/78

    Training Materials For Reference Only Slide 35

    D-0 Decide to use 8D Process

    D-1 Define the Problem

    D-2 Establish a Team

    DD--33 CHOOSE, IMPLEMENT AND VERIFYCHOOSE, IMPLEMENT AND VERIFY

    INTERIM CONTAINMENT ACTIONINTERIM CONTAINMENT ACTION-- basically youbasically yourere DispositioningDispositioning thethe

    QNQN

    8D Step 3: Implement Interim

    C t i t A ti

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    36/78

    Training Materials For Reference Only Slide 36

    Containment Action

    Decide whether you need to use one

    Choose the best (benefits vs. risks) Tools

    Brainstorming to generate ideas

    Pros/Cons lists; Effort (or cost or time) vs.Benefit (or risk) graphic.

    Action Plan

    Test feasibility of the containment action(Verify it will work)

    Commit to it Implement

    Validate containment action effectiveness

    ActionPlan

    ALWAYS +s and s to every decision. BALANCE (and action) are the Keys!

    L H

    L

    H

    Ideal

    Effort

    Benefit

    Purpose of Interim Containment

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    37/78

    Training Materials For Reference Only Slide 37

    p

    Used to buy time to find root cause whileprotecting your customer (external or

    downstream operation) from the problem Authorized first aid, but. . . . .

    can be costly

    attacks symptoms (not the cause)

    has a masking effect

    Purpose of this step:Enforce SCOPE and EFFECTIVENESS of customerprotection needed

    Its OK to not have containment, its NOT OK to not THINK about it.

    Int. Cont. Action vs. Typical BAND AID

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    38/78

    Training Materials For Reference Only Slide 38

    yp

    __X__ Attacks Symptoms __X__

    __X__ Added Costs __X____X__ Monitored while being used _____

    __X__ Documented &Data Collected _____

    __X__ Verified for effectiveness _______X__ Replaced by Perm. Correction _____

    InterimContainment

    Action BANDAID

    Key Points of Step 3: Interim Containment

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    39/78

    Training Materials For Reference Only Slide 40

    y p

    Act quickly (and carefully) Use the team to come up with the list of potential actions

    Minimizes risk, results in better ideas

    Pick the best overall Containment Action(s) Consider actions that may be needed to address other areas: Product in the field WIP Work In Process

    Product in transit/at the Supplier Spares

    Use Action Plan to make sure nothing falls through the cracks Examples:

    VERIFICATION and VALIDATION Airworthiness Directives Service Bulletins Kits for field

    DONT STOP HERE!!! XX

    ActionPlan

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    40/78

    Training Materials For Reference Only Slide 41

    Fill Out Section 3 of the 8D

    Summary Report

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    41/78

    Training Materials For Reference Only Slide 42

    BREAK FOR 10 MINUTES

    Where are We?

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    42/78

    Training Materials For Reference Only Slide 43

    Place in the HBC 8D Process D-0 Decide to use 8D Process

    D-1 Define the Problem

    D-2 Establish a Team

    D-3 Choose, Implement and Verify Interim Containment

    Action (I.C.A.)

    DD--44 FIND ROOT CAUSEFIND ROOT CAUSE

    Root Cause Analysis Common Tools

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    43/78

    Training Materials For Reference Only Slide 44

    Your BrainEspecially the Collective Brain of your team

    Data Thought Map Process Map

    Brainstorming 5 Whys Cause and Effect (Fishbone) Diagram

    Graphical Analysis (misc. graphs) +

    What tool to use? Problem ->Questions->Data/Tools ->More QuestionsROOT CAUSE

    Thought Map

    General Information about Step 4

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    44/78

    Training Materials For Reference Only Slide 45

    Dont try to do solutions before the analysis iscomplete.

    It is futile to continue doing things the same way while

    expecting different results. Dont fall into the trap of jumping to conclusions.

    OUR DESIRE TO ACT, OVERPOWERS OUR NEED TO UNDERSTAND(Brad Baker, CONOCO)

    This cant be a part time job. Assign aPoint Of Contact (POC) to focus on closure.

    The RCCA response ECD must be basedon a planned list of things to do (Action Item

    Lists).

    Data Collection

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    45/78

    Training Materials For Reference Only Slide 46

    Types of data to collect:

    1. Location: where problem was detected2. Personnel: who found problem

    3. Specifications: what are the requirements

    4. Environment: noise, lighting, temperature, etc5. Sequence of events

    6. Equipment

    7. Training8. Other occurrences

    9. Recent changes: personnel, process, weather

    Insufficient data can result in solving only the specific instance.

    Challenge the basis for why its beendetermined to be an isolated eventand why it couldnt potentially be a

    systemic problem

    Tools: Thought Map

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    46/78

    Training Materials For Reference Only Slide 47

    Once the problem is defined, natural tendency is to rush forward

    RESIST THE URGE!!

    Take a few minutes to plan your journey to root cause

    1) Write your Problem Statement at the top of the page

    2) Capture questions that you have Assumptions, potential causes, sources of the problem that dont belong in

    the problem statement SHOULD be captured as questions3) Answer each question with data

    4) Questions (and data) will lead to more questions

    5) Capture dead-ends as well as fruitful paths

    1) Why?

    NOTE: Review the Problem Definition (Step 1) often!

    Used: When? ________________________ Why?__________________

    Thought Map example: Drill Bit Quality

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    47/78

    Training Materials For Reference Only Slide 48

    What is the currentbit brand

    and quality used?

    Is the perceivedbit quality difference

    real or just perception?

    What specific featuresof the bit performance

    are perceived as

    the problem?

    Is it possible to

    attribute QNs and other

    sheet metal defects to

    bit quality?

    Is there a statist ically

    significant difference

    in the number of holes

    drilled before dull?

    What other factors

    contribute to manual,

    hand drilling performance?

    How much isthe difference?

    What are the bit

    performance

    indicators?

    1 - Penetration Sharpness

    2 - Straightness

    3 - CenteringWhat is considered

    the premium bit?

    1 Number of holes dril led

    2 - Straightness

    3 Centering

    4 Penetration

    5 QNs Resulting

    Precision TwistBrand

    Bruckner provides astandard, such asMichigan Twist

    LEGEND:

    Dashed LinesIndicate Links

    What is the difference

    in cost for the bits?

    Tools: Process Mapping/Value

    Stream Mapping

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    48/78

    Training Materials For Reference Only Slide 49

    Stream Mapping

    Graphical Depiction of How Its DoneTerminator (start/stop)Process Step

    Decision PointConnector (off-page)

    General Rules:

    Left to Right Yess/Nos consistent

    ?

    ??

    ?

    How would you map out the process for 8D so far?

    Used: When? ________________________ Why?__________________

    Assembly Transport InspectionOutpu

    ts

    Inputs

    Transport Storage Machine Transport

    Tools: 5 (OK, maybe just 3) Senses

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    49/78

    Training Materials For Reference Only Slide 50

    Talk to, Listen to, Observe:

    People performing the jobSuppliers

    (internal/external)

    Customers(internal/external)

    You are a root cause detective. Use all the tools you can.

    Tools: Brainstorming

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    50/78

    Training Materials For Reference Only Slide 51

    When the best solution isnt obvious, one technique forgenerating ideas (possible root causes, potential interimcorrective or permanent actions) is brainstorming.

    1. Generates a large number of ideas2. Encourage free-thinking3. Dont criticize4. Encourage everyone to participate

    5. Record all ideas. There is no bad idea.6. Let ideas incubate give it a little time

    A minimum group of atleast three people to make

    this work

    Used: When? ________________________ Why?__________________

    Tools: 5 Whys

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    51/78

    Training Materials For Reference Only Slide 52

    1. Why? There was oil on the floor.2. Why? The machine in that cell was leaking oil.

    3. Why? A pressure fitting on the machine failed.

    4. Why? Inspection of hoses and fittings is not part of the preventive

    maintenance (PM) schedule.5. Why? The PM system does not consider Equipment Manufacturers

    recommendations to develop PM schedules.

    6. Why?- Theres check to make sure this is done.

    Dont stop with Because we dont have enough people, money, time

    its a fact of life.

    Solve the problem with the people, money, time you DO HAVE.

    An employee in the plant

    slipped and fell while

    performing their regular duties.

    Peel the onion- challenge the basis for root

    cause. Most people can only support 1-2layers of questions with their basis for root

    cause or corrective action.

    Used: When? ________________________ Why?__________________

    Tools: Cause and Effect Diagram

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    52/78

    Training Materials For Reference Only Slide 53

    A Cause-and-Effect (fishbone or Ishikawa) diagram an easily applied tool used to analyze possible causes to aproblem.

    Non-conforming coating

    Manpower

    - inexperienced

    Methods

    - incorrect prep of

    metal surface

    Machinery

    - microscope

    Materials

    - poor quality of

    standards

    - microscope setting notoptimized to detect the

    smearing

    -not following the frozen

    coating parameters

    - inadequate training

    -inadequate technique

    MUST BE TESTED ANDVERIFIED!

    5 Ms and an E - addMeasures andEnvironment for 6 Bones

    Used: When? ________________________ Why?__________________

    Tools: Graphical Analysis

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    53/78

    Training Materials For Reference Only Slide 54

    Histogram Used to show patterns/distribution in ordered data

    Categories on the x-axis, # of occurrences on they axis.

    Pareto Chart (80/20 rule) Used when many problems or causes and you

    want to focus on the most significant

    Causes on x-axis, Results on the left (primary) y-axis, Cumulative % on the right (secondary) y-axis.

    Scatter Diagram

    Used to illustrate relationships between 2variables. 1 variable on each axis.

    "Correlation does not imply causality." Ex. Shark Bites and Ice Cream

    Purpose of Graphical Analysis: ________________________________

    Word of Caution: Stay on Track!

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    54/78

    Training Materials For Reference Only Slide 55

    Use Common Sense:

    1. The more significant or involvedthe problem, the more detail may

    be needed to identify the RootCause

    1. Also more advanced tools

    2. Avoid data that leads to other

    problems.1. Dont get sidetracked

    1. Review Step 1 ProblemDescription.

    2. Use the Thought Map

    Start

    GoalSide

    Issue

    Side

    Issue

    Side

    Issue

    Complex problems usually require at least a fishbone diagram of the potential

    root causes sorted from the brainstorm list

    Define the actions to validate or dismiss each one Technical problems usually require a structured FMEA

    Document Your Findings

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    55/78

    Training Materials For Reference Only Slide 56

    Fill Out Section 4 of the 8D

    Summary Report

    8D Step 5: Choose Corrective Action

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    56/78

    Training Materials For Reference Only Slide 57

    Place in the HBC 8D Process: D-0 Decide to use 8D Process

    D-1 Define the Problem

    D-2 Establish a Team

    D-3 Choose, Implement and Verify Interim Containment Action(I.C.A.)

    D-4 Find Root Cause

    DD--5 DETERMINE PERMANENT CORRECTIVE5 DETERMINE PERMANENT CORRECTIVEACTIONACTION

    Decision Making Steps(note: can also be used in Step 3)

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    57/78

    Training Materials For Reference Only Slide 58

    1. Define end result (action verb & object) Eliminating/Preventing/Reducing (verbs) Errors/Safety Incidents/QN/s (objects)

    2. List decision criteria

    GIVENSGIVENS - Mandatory WANTSWANTS - Desirable

    3. Decide relative importance ofwantswants 1-104. Identify the possible choices5. Compare possible choices against the decision criteria6. Analyze risk

    IF/THEN terms:If we choose to___________,

    Then _________ will happen.

    7. Make the final BALANCED choice and VERIFY

    NOTE: Use the Action Item Tracking Sheet toCapture and Track Actions

    ALWAYS +s and s to every decision. BALANCE (and action) are the Keys!

    ActionPlan

    Track Action Items to Completionand Summarize Results

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    58/78

    Training Materials For Reference Only Slide 59

    Use the Corrective Action Plan Worksheetin the 8D File and Summarize in Section 5

    of the 8D Summary Report

    8D - Step 6: Implement the Fix

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    59/78

    Training Materials For Reference Only Slide 60

    Place in the HBC 8D Process:D-0 Decide to use D8 Process

    D-1 Choose team members

    D-2 Define problem

    D-3 Choose Interim Corrective Action(s) & verify

    D-4 Find Root Cause

    D-5 Choose & verify Permanent Corrective Action

    DD--66 IMPLEMENT PERMANENTIMPLEMENT PERMANENT

    CORRECTIVE ACTIONCORRECTIVE ACTION

    Goals of Permanent Corrective Action

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    60/78

    Training Materials For Reference Only Slide 61

    Permanent Corrective Action MUSTMUST:Address the systemic problem (in addition to this

    specific instance)

    Eliminate the Root CausePrevent recurrenceBe implemented in a timely manner

    Include a detailed plan (especially if it will takeconsiderable time and people)Be comparable to the risk involved

    Risk to the customer, employee, organization, public, etc.

    Be verified Objectively Three knowledgeable people must agree

    Keys to Successful Corrective Action

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    61/78

    Training Materials For Reference Only Slide 62

    Persistence Natural Tendency to slack off once the Fix is determined

    and partially implemented

    Follow the Action Plan to Completion

    Involve Do-It-Level people Key to preventing recurrence

    Review Interim Containment Action(s) Remove/discontinue any not needed adds cost, time, etc.

    VERIFY IT!!!

    VALIDATE IT!!! ActionPlan

    More than Just Do It

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    62/78

    Training Materials For Reference Only Slide 63

    Why should we do planning and NEWproblem prevention when considering

    implementing a permanent corrective action

    forTHIS problem? see next slide.

    Why Planning and Problem Prevention?

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    63/78

    Training Materials For Reference Only Slide 64

    Many of our current problems are the result ofnot following through with previous plans

    Must allocate limited resources effectivelyOptimize implementation Dont waste Time/$$

    Prevent other problems from occurringWith change comes risk of creating NEW

    problems

    Control Mr. Murphy

    Summarize the Key PermanentCorrective Actions

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    64/78

    Training Materials For Reference Only Slide 65

    Fill Out Section 6 of the 8D Form

    8D - Step 7: Prevent Recurrence

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    65/78

    Training Materials For Reference Only Slide 66

    D-0 Decide to use D8 ProcessD-1 Choose team members

    D-2 Define problem

    D-3 Choose Interim Containment Action(s) & verify

    D-4 Find Root Cause

    D-5 Choose & verify permanent corrective action

    D-6 Implement Permanent Corrective Action(s)

    DD--77 PREVENT RECURRENCEPREVENT RECURRENCE

    Steps to Preventing Recurrence

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    66/78

    Training Materials For Reference Only Slide 67

    Identify what systems, practices, orprocedures allowed the problem to occur

    The whys

    Identify and implement improvements

    VALIDATE the results

    Poka yoke is the Japanese term that means fail safing or

    Tool: Mistake-Proofing

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    67/78

    Training Materials For Reference Only Slide 68

    Poka-yoke is the Japanese term that means fail-safing or

    "mistake-proofing" Examples:

    Cant start car until in park, Child-proof caps, laser beam shut-offs for machinery

    Others??

    One of the best ways to prevent problems fromoccurring/recurring

    Use mistake-proofing techniques when there are: Process steps where human intervention is required Decision points in the process Repetitive tasks where physical manipulation of objects

    is required Steps where errors are known to occur

    Opportunities for predictable errors to occur

    Mistake-Proofing Levels of Prevention

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    68/78

    Training Materials For Reference Only Slide 69

    Defect is the

    evidence of anerror

    More Proactive

    Beware of Root cause was HumanError

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    69/78

    Training Materials For Reference Only Slide 70

    HUMAN ERRORS do not make a root causeHow does HBC approach human error?

    Positive Defects can be eliminated Create a mistake-proof environmentAsk Why?

    Focus on the Process/Product NOT the Person

    Apply Mistake-Proofing device for 100% inspection

    Negative Defects are inevitable People make mistakes

    Place blame Detect at final inspection Sampling inspection Some are bound to reach the customer

    Once Root Cause is Determined,Broaden your Thinking

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    70/78

    Training Materials For Reference Only Slide 71

    How Can We Standardize Lessons Learned & SystemImprovements?

    Communication Same/similar problem other plants

    Same/similar problem different

    systems Content Quality

    Appropriate Quantity

    Effect

    Root Cause

    Potential Causes

    Current/Future Problems in other areas

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    71/78

    Training Materials For Reference Only Slide 72

    Fill Out Section 7 of the 8D Form Prevention of Recurrence

    8D - Step 8: Congratulate the Team

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    72/78

    Training Materials For Reference Only Slide 73

    D-0 Decide to use D8 ProcessD-1 Choose team members

    D-2 Define problem

    D-3 Choose I.C.A., verify

    D-4 Find Root Cause

    D-5 Choose & verify P.C.A.D-6 Implement P.C.A.(s)

    D-7 Prevent recurrence

    DD--88 CONGRATULATE THE TEAMCONGRATULATE THE TEAM

    How to Congratulate the Team

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    73/78

    Training Materials For Reference Only Slide 74

    Review significance of contribution Provide appropriate recognition for all members

    Document the efforts & results

    Celebrate successful completion

    Celebrations dont have to beelaborate/expensive

    Be creative

    How Would You Congratulate YourTeam?

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    74/78

    Training Materials For Reference Only Slide 75

    What are some things that have worked well in thepast?

    What are some things that didnt?

    5 minutes

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    75/78

    Training Materials For Reference Only Slide 76

    Fill Out Section 8 of the 8D Form

    (and attach completed file to the

    appropriate QN)

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    76/78

    Training Materials For Reference Only Slide 77

    Comments, Suggestions??

    Please fill out class/instructor

    Evaluation Forms

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    77/78

    Training Materials For Reference Only Slide 78

    Reference Material

    QA Intranet Website

  • 7/29/2019 8d Training 9-8-2008-Root Cause Analysis

    78/78

    Training Materials For Reference Only Slide 79