900-spe-5001-met&syst
TRANSCRIPT
-
7/28/2019 900-SPE-5001-MET&SYST
1/30
MULTI PURPOSE REACTOR PLANT
Discipline Code:
ELProject spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
ELECT RICAL METHODES AND SYSTEM
CLIENTS : ECOGREEN OLEOCHEMICALS
PROJECT TITLE : MULTI PURPOSE RECTOR PLANT PROJECT
CONTRACT
TITLE :
LOCATION : BATAM, INDONESIA
Rev.CONTRACTOR OWNER
DATE BY CHKD APVD DATE APVD
1 IFRA 3-Nov-10
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
2/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
2 of 30
Table of Contents
Sec Title Page
1. SCOPE...........................................................................................................................................3
2. REFERENCES..............................................................................................................................3
3. UNITS OF MEASURE AND LANGUAGE...............................................................................3
4. BASIC CONSIDERATIONS.......................................................................................................4
5. SITE CONDITIONS.....................................................................................................................4
6. HAZARDOUS AREA CLASSIFICATION...............................................................................4
7. POWER GENERATION AND DISTRIBUTION.....................................................................5
8. UTILIZATION VOLTAGE........................................................................................................6
9. DEVIATION IN SUPPLY VOLTAGE AND FREQUENCY................................................11
10. EMERGENCY POWER GENERATION AND DISTRIBUTION.....................................12
11. LOAD SHEDDING AND MOTOR RESTART SYSTEM...................................................13
12. ELECTRICAL LOAD DATA CALCULATION ...............................................................13
13. SYSTEM STUDIES..................................................................................................................13
14. LV SWITCHGEAR AND MCC..............................................................................................14
15. SYSTEM PROTECTION AND METERING.......................................................................14
16. UPS SYSTEM..........................................................................................................................15
17. LOCAL CONTROL STATION (LCS) FOR MOTOR CONTROL...................................15
18. SUBSTATIONS........................................................................................................................16
19. PAINTING................................................................................................................................17
20. PROTECTION GRADE OF ELECTRICAL EQUIPMENT..............................................17
21. NAMEPLATES.........................................................................................................................17
22. CABLING SYSTEM................................................................................................................17
23. UNDERGROUND CABLING SYSTEMS.............................................................................18
24. ABOVE GROUND CABLING SYSTEM..............................................................................21
25. CABLE AND CORE MARKER.............................................................................................25
26. TERMINATION.......................................................................................................................25
27. ELECTRICAL WIRE AND CABLES...................................................................................26
28. LIGHTING................................................................................................................................28
29. CATHODIC PROTECTION ................................................................................................30
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
3/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
3 of 30
1. SCOPE
This specification covers the minimum design requirements for electrical power supply and
distribution systems, motor control and cabling systems for Multi Purpose Reactor Plant
Project.
2. REFERENCES
The latest revision of applicable sections of the codes, standards, and specifications listed
below (including addenda, and documents incorporated by reference) shall be considered an
integral part of this specification.
IEC : International Electro-technical CommissionNFPA : National Fire Protection Associations
NEMA : National Electrical Manufacturers Associations
API : American Petroleum Institute
IP : Institute of Petroleum
BSI : British Standards Institution
Other codes and standards such as ANSI, IEEE, Indonesian code, JIS/JEM/JEC may be also
applied with approval by Owner.
The codes and standards of the countries of origin may be applied to raw materials and mass-
produced components, subject to the Vendor clearly indicating the scope of application in his
technical and commercial quotations.
3. UNITS OF MEASURE AND LANGUAGE
SI units of measure shall be used for electric system designs unless otherwise specified.
The English language shall be used for all documents.
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
4/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
4 of 30
4. BASIC CONSIDERATIONS
Consistent with reasonable economy and considering investment and operation expenditures,
the design of electrical facilities shall be based on the features and requirements of the plant
where electrical facilities are to be installed. Primary considerations are:
Safety of personnel during operation and maintenance, and adequate protection to
equipment.
Easy maintenance
Interchangeability of equipment
5. SITE CONDITIONS
Altitude : Less than 1000 m
Ambient Temperature : 680F 910F
For design of outdoor Elec. Equipment : 1040F
For design of indoor Elec. Equipment with Air Conditioning systems: 1040F
Average Relative Humidity : 90 %
Soil Temperature at 0.8m deep : 860F
Soil thermal resistivity : 2120F cm / w
Soil thermal resistivity & soil electrical resistivity shall be verified with further tests during
design stage.
6. HAZARDOUS AREA CLASSIFICATION
Plant areas shall be classified according to the API RP505. The selection of electrical
equipment and material to be installed in hazardous areas shall be in accordance with IEC
60079. Electrical equipment shall be selected according to the following Zone
Classification criteria:
Zone 1 Area
Electrical apparatus should be excluded from Zone 1 areas. Where this is not
practical, the equipment shall comply with one (1) of the following types;
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
5/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
5 of 30
- Ex(e) (Increased safety)
- Ex(p) (Pressurized enclosure)
- Ex(d)( Flame proof enclosure)
Zone 2 Area
- Ex(n) (Type N protection)
- Ex(e) (Increased safety)
- Ex(d) (Flame proof enclosure for internal sparking equipment)
Non-hazardous Area
- Standard Industrial equipment suitable for the installation
Explosion proof electrical equipment / materials suitable for Division 1 or 2 may be
also used in hazardous area. Division 1 is considered equal to Zone 1 and Division 2
is considered equal to Zone 2.
Electrical equipment and materials for hazardous areas shall be selected according to theapplicable codes and standards of the country where the equipment/materials are
manufactured.
Approved equipment must be listed or certified for use in the particular hazardous location
by an internationally recognized testing organization.
7. POWER GENERATION AND DISTRIBUTION
The power Supply shall have 0.38 kV voltage rating, 3 phases, 50 Hz and connected to
0.38 kV busbar (main substation) .
The electric power to be required for the plant operation shall be supplied from
Power distribution of 400V shall be secondary selective system with each bus tie breaker
normally open (N.O.). Power loss at one side bus shall cause an automatic transfer to
another side bus with permissive from bus fault condition. The two incoming breakers and
one tie-breaker are interlocked so that only two of the three breakers can be closed. The
returning to normal operation and manual transfer without any power interruption shall be
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
6/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
6 of 30
performed by operators. The each incoming side of secondary selective system shall be
rated for the total busbar load to cover all loads under its switchgear without incoming
power supply from another side.
Cable sizing to each motor shall be sized based on the motor full load current considering
derating factor from installation method.
The power to building loads (HVAC, Lighting) shall be controlled and distributed from
Distribution Panels properly located in each building.
8. UTILIZATION VOLTAGE
Motors above 150 kW : 6.6 kV, 3 phases, 50Hz
Motors above 0.37 kW up to 150 kW : 400 V, 3 phases, 50Hz
Motors rated 0.37 kW and below : 230 V, 1 phase, 50Hz
Welding Outlet : 380 V, 3 phases, 3 poles + earth
Space Heater/auxiliary power supply : 220 V, 1 phase, 2 wires, 50Hz
Control Supply for Switchgear, Relays, Elec. Controllers : 220 VAC
Control Supply for motors connected to LV & MV MCC : 220 VAC (from self control
transformer at each MCC unit)
SYSTEM EARTHING AND LIGHTNING PROTECTION
8.1 General
Earthing, Bonding and lightning protection facilities shall be provided to:
Protect electrical equipment from damage and to insure operation of electrical
overcurrent devices (System neutral earthing)
Protect personnel against shock from electrical enclosures or equipment (Enclosure
and equipment earthing)
Protect structures and equipment against damage from lightning (Lightning
protection)
Insure against ignition of flammable mixtures by static electricity or stray current
(Static electricity protection)
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
7/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
7 of 30
8.2 Earthing System
Earthing systems shall consist of networks installed around major process units,
buildings, structures, distribution centers, substations, etc. Networks shall consist
of earthing buses (main loops), earthing electrodes, and earthing conductors for
equipment.
Where different earthing systems, except systems for process control and computer
system, are installed close together, they shall be interconnected at convenient
points to bring all earthing to a common potential.
Earthing for lightning protection for structures/buildings which are equipped with
lightning rods shall be physically isolated from the main earthing system. Earthing
rods shall be located at the base of each protected structures/buildings.
Equipment that is located remotely from the main earthing network may be earthed
by means of individual earthing conductors and earthing electrodes.
All earthing electrodes at substations and generating stations shall be interconnected
in a loop by earthing conductors.
Earthing resistances shall not be exceed the following values:
-Total earthing resistance of loop network : 5 ohms
- An earthing electrode : 25 ohms
- An earthing electrode for lightning protection : 5 ohms
- System neutral earthing : 5 ohms
- Instrument earthing (maximum) : 5 ohms
A separate earthing system shall be provided for electronic instrument boards. It
shall be physically isolated from other earthing systems. For further details, refer to
Instrument Specification.
8.3 Methods and Materials
Earthing, Bonding and Lightning Protection Conductors
All earthing, bonding and earth return conductors shall be PVC insulated (green or
green with yellow stripe) soft-drawn stranded copper wire. Earthing buses for
earthing networks shall have 70 mm2 conductors. All lightning protectionconductors, such as down conductors and electrode conductors shall be bare hard-
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
8/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
8 of 30
drawn copper or stranded aluminum wire or bar.
All earthing conductor shall be sized as follows:
LV Switchgear and MCCs : 120 mm2
Other electrical panels : 25-35 mm2
Lighting panel board frames : 35 mm2
Welding outlet frame : 16 mm2
Motor frames : 16-70 mm2
Neutral earthing for solid earthing : 150 mm2
Neutral earthing for low resistance earthing : 70 mm2
Static electricity : 35 mm2
Bonding wire : 4-16 mm2
Fences : 16 mm2
Other equipment : 4-16 mm2
Lightning protection : 70 mm2
Note : The equipment earthing conductor shall need not be larger than the
circuit conductors supplying electrical power to the equipment.
Underground earthing conductors shall be directly buried at least 300 mm below
finished grade.
Underground earthing conductors shall be laid in cable trenches as far as routing
permits. Basically, aboveground earthing conductors shall be laid on cable tray.
Earthing conductors extending aboveground shall be protected by hard PVC
conduit at least 150 mm above and below the finished grade or concrete surface.
Earthing and Bonding Connection
All earthing or bonding conductor connections to structures and equipment shall
be made aboveground. Lug bolted connectors shall be used to allow periodical
maintenance.
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
9/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
9 of 30
Earthing lugs shall be fabricated from hot dipped galvanized steel.
All aboveground connections of earthing wires shall be made with compression
type connectors and wrapped with PVC tape.
All underground connections of earthing wires shall be made by Cadweld,
Teikaweld or C-clamp and wrapped with PVC tape.
Earthing Electrodes
Earthing electrodes shall be made by long zinc clad steel or copper clad steel
rods driven below grade.
Each earthing rod shall be installed in an earthing well which shall function as
an inspection pit for verifying earthing resistance. The loop conductor shall be
connected to the top of the earthing rod.
The earthing rod shall be connected to the loop conductor by a bolted connector.
If more than one electrode is connected to an earthing system, the electrodes
shall be spaced at least 3 m apart.
Equipment located remotely shall be furnished with a dedicated earthing rod
connected directly to the equipment. No earthing well for inspection purposes is
required.
Electrical System Earthing
Neutral earthing for each system voltage level shall be as follow:
400 V system : Solidly earthed
Enclosure and Equipment Earthing
Earthing Point of Wiring System
o The metal enclosures for wire and cable, such as conduits, cable trays, and
raceways shall be considered electrically continuous by metallic
connection, and earthed at each end by direct connection to earthing
network, bonding or metalic connection to other earthed enclosures.
Connections shall be made to the switchgear or control center earth buses
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
10/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
10 of 30
when such equipment is used.
o The metal armor of cables shall be bonded together across each splice, and
to the metal enclosures of equipment at each end of the cable utilizing
cable glands.
o The metallic shields in shielded cables shall be earthed at the supply side
only.
Earthing Point of Equipment
o The metal enclosures of all electrical equipment shall be earthed by
connecting to the earthing network using a dedicated earthing conductor
or by a earthing conductor in the multi conductor cables.
o Fences, handrails and stairways at substations shall be earthed to an
earthing network.
o Metal enclosure which may be source of static electricity shall be earthed
to an earthing network.
o Electrical equipment, even though bolted directly to an earthed metallic
structure, shall be earthed separately.
o Machinery skid base containing electrical equipment. (Two points in
diagonally opposite )
o Local control stations shall be connected to an additional earthing
conductor branched from the main earthing loop.
Lightning Protection
Lightning protection systems shall be installed basically in accordance withBS6651.
Non-steel structures higher than 20 m shall, in general, be provided with a
lightning protection system.
Tall steel structures, columns, towers, vessels etc. which require lightning
protection shall be earthed with 70 mm2 earthing wires at two points of their
base and shall be connected into the main earthing loop.
The steel structures, columns, towers, vessels, tanks etc, provided they areelectrically continuous, shall be considered protected against lightning by those
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
11/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
11 of 30
connection to the earthing network.
Static Electricity Protection
All storage tanks, columns, towers, vessels, heat exchangers and other process
equipment not mounted on an earthed steel structure shall be separately earthed.
Process equipment mounted on an earthed steel structure fixed with carbon steel
bolting shall not require additional earthing.
Buildings or structures having metallic frames or siding shall be earthed at a
minimum of two locations. These locations shall be at opposite extremities ofthe structure.
Above ground pipelines shall be connected to the earthing network only at the
boundary of plant area.
Flanged joints without insulated linings in metallic pipelines shall be
considered electrically continuous.
9. DEVIATION IN SUPPLY VOLTAGE AND FREQUENCY
Voltage and Frequency variation (during normal operation and steady state
conditions)
Voltage variation not more than +/- 10% from the rated voltage at generator
and consumer terminals
Frequency Deviation not more than +/- 10% from the rated
Maximum allowable voltage drop during normal operation and steady state
conditions
Main Feeders : 10%
Motor and plant static load cables from MCC at full loads : 20%
Lighting Circ. (from LV distribution boards to furthest lighting fixtures): 15%
Maximum allowable voltage drop during starting or reacceleration of motors:
At motor terminals: not more than 15 % (except very large motor to be connected
to the captive transformers and to be considered individually based on studies, ifapplicable.)
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
12/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
12 of 30
10. EMERGENCY POWER GENERATION AND DISTRIBUTION
Emergency power for the plant shall be provided by standby diesel driven generator
to facilitate the start up and safe and orderly shutdown of the plant in the event of
loss of main power generation. The size and number of standby generator shall be
finalized during engineering design.
The diesel generator shall supply power to essential loads such as emergency
lighting including those for control room, substation and generator shelter, UPS
including plant control system and emergency shut down system, DC power supply
units, Hazard Monitoring System, Communication systems, HVAC loads for
Control Room and Generator Operation, auxiliary loads of one main generator
Diesel Engine Generator, critical motor operated valves and essential auxiliaries of
major machinery if any, air compressor to provide instrument air to emergency
services.
The emergency generator shall be sized for the required running loads plus its 25%
spare.
The emergency generator shall be started and supply the power to the emergency
power distribution system automatically in the event of total power disturbance of
main generators (Black Start Capability). Electrical synchronizing facilities shall be
provided for emergency generator.
The load running test during commissioning test and periodical maintenance after
plant operation for Diesel Engine Generator shall be performed using plant actual
loads.
The emergency power shall be generated at the 380V low voltage level and
distributed to downstream substations as required.
The control panel of generator set shall be located inside main control building or
substation adjacent to the generator set. Only engine running status, breaker status,
neutral earthing switch status, common alarm & trip status and analogue signals of
V, A, KW, PF, Hz shall be communicated to Main Control Room by hard-wiring or
softlink / RS 485,etc and no control action can be achieved from remote location.
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
13/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
13 of 30
11. LOAD SHEDDING AND MOTOR RESTART SYSTEM
11.1 Load Shedding System
The electrical loads to be shed under emergency conditions shall be studied and
finalized during engineering stage.
11.2 Motor Re-acceleration
Automatic reacceleration and re-start scheme shall be provided for necessary
motors based on process requirement.
12. ELECTRICAL LOAD DATA CALCULATION
Maximum normal running plant load = x (%) C + y (%) I
Peak load = x (%) C + y (%) I + z (%) S
C : Continuous I : Intermittent S : Stand-by
x, y, z : Diversity Factors
Default values for initial load assessment or if the diversity factors not finalized;
x = 100 % (all driven equipment should be operating at its duty point.
But some diversity may need to be applied to non-process loads, e.g. Office and
workshop power and lighting - typically 80 %)
y = 30 %
z = 10 %
Instead of z (%)S, only one of the largest electrical stand-by units per switchgear
line-up may have to be considered when establishing the peak load.
13. SYSTEM STUDIES
The following calculations shall be performed for the design and study of electrical system
and sizing of electrical equipment;
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
14/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
14 of 30
Load Data Calculation
Short Circuit Calculation
Load Flow Calculation
Motor Starting Calculation
14. LV SWITCHGEAR AND MCC
LV switchgear 400V shall be metal clad, IP31, single bus, draw-out type, Air
Circuit Breakers. LV MCC shall be metal enclosed, IP31, with drawable motor
control or feeder unit.
Approximately 10 % of total MCC units as spare and approximately 10 % future
space shall be provided per each MCC line-up subject to manufacturers standard
practice.
transformers shall be provided.
15. SYSTEM PROTECTION AND METERING
15.1 Switchgears
Incoming of 380V switchgear
Over current relay with instantaneous unit
Earth fault relay
Feeders of 380 V Switchgear
Over current relay with instantaneous unit
Earth fault relay
Ammeter with selector switch
Multifunction relay which cover all above protections and meters requirement is
preferable (Solid State Relay).
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
15/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
15 of 30
15.2 LV MCC unit
Magnetic Trip Molded Case Circuit Breaker (sized to be tripped at approximately
10 times of motor full load current) with contactor and thermal relay for motor units
Thermal Magnetic Molded Case Circuit Breaker for feeder units.
Earth Fault Relay for motor units of at least 5.5 kW and above, and for feeder
supply units of breaker over 100 A trip rating
Single phase Ammeter for motor units of 30 kW and above
Running (red) / Stopped (green) / Fault (Amber) Lamp for MCC units
No start / stop control switch for motor units
The intelligent type solid state motor protection and control system can be also
applied for LV MCC unit with manufactures standard central unit and
maintenance facilities.
16. UPS SYSTEM
UPS systems will provide power to the DCS or PLC, Safety Instrumented System
and other critical loads. The UPS system will receive power from the emergency
supply with a bypass circuit from the emergency motor control center. UPS power
supply unit shall be provided in substation. The UPS shall be capable of operating
on small diesel engine driven generators for emergency power that may have larger
frequency variations than the larger primary power generators. UPS systems shall
be double configuration with voltage stabilizer at bypass line.
Battery back-up time for both UPS power supply unit shall be 60 minutes.
17. LOCAL CONTROL STATION (LCS) FOR MOTOR CONTROL
LCS shall be provided with start/stop control function suitable for area
classification with locking feature which is padlock able in off position.
LCS shall be hard-wired directly to the motor starter in the MCC.
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
16/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
16 of 30
Motors automatically controlled by DCS or PLC shall have Hand-off-Auto selector
switch on LCS.
For all air fin-fan motors, LCS shall be located close to air fin-fan unit.
18. SUBSTATIONS
In general, substations shall be elevated with the height from grade to the under side
of the lowest beam by min. 1500 mm for bottom entry of underground cables with
cable glands.
Substations shall be located in non-hazardous, safe areas and furnished by air
conditioning.
Personnel access doors with panic bar and equipment access double doors of
adequate size shall be provided for all substations.
The under floor space sides of each substation, not covered with firewall, shall be
fenced with proper chain link.
Substation floor shall be concrete surface and steel channel shall be installed, level
and flush with finished floor grade for mounting the electrical panels. Electrical
panels shall be tag welded or bolted to the floor steel.
In general, cables shall enter the substation from bottom side.
Suitable cable support frames made of channel, angle and unistrut below the
substation shall be provided to support cables.
All LV and control cables shall be fixed by coated stainless steel all purpose band
'Band it' or equivalent.
For cable glanding below the substation, suitable gland box below SWGR/MCC.
The box shall have removable covers of galvanized sheet on front and rear complete
with neoprene gaskets. The box shall be hot dip galvanized.
Substations shall have a separate battery room with access from outside the
substation. Provisions shall be made for sufficient diffusion and ventilation of the
gases from the battery to prevent the accumulation of an explosive mixture.
Package type substations may be provided wherever practical including small
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
17/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
17 of 30
power distribution such as tank farm, buildings, offsite users etc.
19. PAINTING
Color of Electrical Equipment (Switchgear / MCC panel, Distribution & Lighting Panels
etc.) shall be RAL7032 or equivalent.
20. PROTECTION GRADE OF ELECTRICAL EQUIPMENT
Protection grade of enclosures of outdoor Electrical Equipment ( Outdoor
Distribution & Lighting Panels etc.) shall be IP55.
Protection grade of enclosures of indoor Electrical Equipment (Substation
Switchger / MCC, UPS, Panel etc.) shall be IP31.
21. NAMEPLATES
All electrical equipment such as Switchgear/MCC, control stations, transformers,
panels, junction box etc. shall have an engraved non-corrosive nameplate.
The nameplates will be attached to the equipment with stainless steel machine
screws wherever possible, or on stainless steel mounting brackets, as required,
adjacent to the equipment.
22. CABLING SYSTEM
Electrical power and control cables for outdoor installation shall be armored cables
and shall be installed underground as direct buried cables or aboveground in cable
trays. In aboveground cabling system, the cable tray system shall be mainly used.
Non armored cables can be utilized for building loads and interconnecting cables
inside substations and control rooms.
The bolts, nuts, washers and U-bolts to be used for electrical installation shall be
made of stainless steel. The support materials for electrical installation such asangles and channels shall be hot dipped galvanized steel.
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
18/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
18 of 30
23. UNDERGROUND CABLING SYSTEMS
There are two types of underground cabling system as follows:
Direct-buried cable system
Underground conduit system
23.1 Direct-Buried Cable Systems
Direct-buried cable systems shall be either of the following two types:
Cable buried directly in a trench with exposed earth sidewalls and bottom, and
covered with red concrete slabs or tiles for protection.
Cable buried directly in a trench with reinforced concrete or brick sidewalls / covers
and an earth bottom.
23.2 Underground Conduit Systems
Underground conduit systems shall be either of the following two types:
Conduits laid underground. These are called direct-buried conduits.
Conduits laid underground and encased in concrete. These are called duct banks.
23.3 Types of Cable
The types of cable to be used shall be as specified in section 31.
23.4 Routing of Underground Cabling Systems
The route of the underground cable shall be determined by considering the
following:
The route of the cable shall avoid aboveground and underground obstructions so
that reasonable access to the cable is assured.
Wherever practical, trenches shall run in unpaved areas and shall be routed adjacent
and parallel to roadways.
A clearance of not less than 300 mm shall be maintained between the cables and
underground piping.
Cables crossing under main roads, paved heavy traffic roads, shall be run in duct
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
19/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
19 of 30
banks, or reinforced concrete culverts.
Earth wall cable trench shall be used in unpaved area. Concrete or brick wall trench
shall be used in paved area.
23.5 Design of Direct-Buried Cable Systems
Types of Underground Cable Trench
Earth Wall Trench :
The sides and bottom of earth wall cable trenches shall be exposed earth. Red
concrete slabs or tiles with a minimum thickness of 50 mm shall be laid on the
top layer of the sand fill. These slabs shall extend approximately 150 mm
beyond the cable on both sides of the trench.
Concrete or Brick Wall Trench :
Concrete or brick wall cable trenches shall consist of reinforced concrete or
brick sidewalls and covers, and a bottom of exposed earth.
The trenches and covers shall be designed to withstand the maximum loading
for the area in which they are to be installed. Trench covers shall be painted
red. The covers shall be flush with the adjacent pavement or finish grade.
Cable Depth and Separation
The minimum cover for cables installed in earth wall trenches between surface
of cables at top layer and the finished grade.
The bottom layer of cables in trenches shall be installed on a cushion of
screened sand.
Other voltage cables may be installed in the same trench up to a maximum of
four layers with 100mm vertical separation between layers.
The top layer of cables and all future cables shall be below the bottom of the
trench cover for concrete or brick wall trenches, and below the bottom of the
protective covering for earth wall trenches. The space between the top layer of
cables and the trench cover or protective covering shall be completely filled
with screened sand.
No other cables shall be installed in the same trench with the high-voltage main
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
20/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
20 of 30
distribution cables except for low-voltage interlock, relaying, and control cables
for the switchgear associated with the distribution cables. These low-voltage
cables shall be separated horizontally from the distribution cables by a masonry
barrier or screened sand.
Turns in trenches shall be constructed so that the cables can be installed with the
required bending radius.
Space for Future Cables
Trenches for direct-buried cables shall be designed with space for future cables as
listed below. The future cables include additional cables required (means design
allowance) during the detailed engineering stage of the Project.
A minimum of 10 % (with minimum 2 cables line space) of future cables shall
be estimated based on the number of cables originally installed.
The space for future cables shall be in the upper part of the trench.
23.6 Design of Underground Conduit Systems
Types of Conduit
Underground conduit to be used for duct bank shall be rigid polyvinyl chloride
(PVC) or high-density polyethylene.
Direct-Buried Conduits
The Direct-Buried Conduits consist of:
In unpaved areas
In concrete paved areas
Duct Banks
In duct banks, underground conduit runs shall be encased in concrete.
The minimum depth to the top of the concrete encasement shall be 450 mm
from finish grade.
Conduit Separation
The minimum separation between the outside surfaces of conduits shall be 25 mm
for nominal conduit sizes of 42 mm (1-1/2 inch) and smaller, and 50 mm for sizes
larger than 42 mm (1-1/2 inch).
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
21/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
21 of 30
Conduits Extended to Aboveground
Nonmetallic conduits shall not be extended aboveground except for stub-ups within
switchgear, control center and similar equipment enclosures in non hazardous
locations and except for grounding wires. Where aboveground extensions are
required, a transition to rigid metal conduit shall be made underground. Stub-up
rigid metal conduit shall be properly sealed using soft seal or equivalent after cable
installation. Non metallic conduit shall not be used in the process area and buildings
located in the process area, example: substation.
23.7 Cable Splices and Terminations
Cables shall be laid in one length wherever possible.
All splices and terminations for high voltage cables shall be made according to the
cable manufacturer's recommendations.
23.8 Cable Route Marking
A system of aboveground cable route markers shall be provided to identify
underground cables in unpaved areas as follows:
Markers shall be located at every point where the direct-buried cable or conduit
changes direction.
Markers shall be provided on both sides of the trench which are 2.0 m wide or
more. For cable trenches less than 2.0 m wide, markers shall be provided at their
center. Where cable trenches are identified by painting or equivalent, the markers
are not required. Cable marker shall be provided
24. ABOVE GROUND CABLING SYSTEM
24.1 General
Aboveground cabling and wiring systems are the following:
Cable trays
Rigid metal conduit systems
Thin-wall metallic conduit systems
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
22/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
22 of 30
Floor raceway systems
24.2 Types of Cable
The types of cables using aboveground vary depending on the services and
conditions as shown in Subsection 31.
24.3 Cable Trays
Cable tray systems shall be heavy duty, ladder type. Punched type trays and othersimilar supports may be utilized if required.
Cable tray systems shall be used in hazardous or non-hazardous, indoor or outdoor
locations. They shall be located so that they will not be damaged, such as by traffic
or during maintenance.
Trays and other fittings shall be made of hot-dipped galvanized steel.
Cable trays shall have removable covers in locations where cables are subject to
damage from falling objects, corrosive liquids or direct sunlight. In other locations,trays shall be open-topped. When removable covers are applied on cable trays in
more than one (1) layer installation, they shall be provided on top layer only.
Cable trays and ladders shall be supported properly at intervals recommended by
the manufacturer.
The arrangement of cable in or on supports shall be as follows:
Control cables shall be laid between power cables wherever possible.
MV and LV cables may be laid in the same cable trays
Trays carrying only control or instrument cables may have cables arranged in
more than two layers.
Cables shall be arranged to minimize the number of crossovers.
Tray supports shall be of heavy duty construction and galvanized or if practical,
painted.
Where there are up to three cables runs, they can be supported directly from / along
the structure by using clip or galvanized steel angle.
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
23/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
23 of 30
24.4 Rigid Metal Conduit Systems
Conduits, elbows, couplings and other associated fittings shall be hot dipped
galvanized steel.
Conduit feeding equipment that is subject to vibration shall terminate in flexible
conduits suitable for the area classification.
All conduits shall be threaded with an absolute minimum of five full threads.
Threads shall taper 3/4 inch per foot.
Breathers and drains shall be provided at high and low points of the conduit system
to prevent the accumulation of condensed water. Breathers and drains shall also be
provided in junction boxes, explosion proof panel boards and generally in
equipment enclosures subject to accumulating condensed water by its shape and
position in the conduit system
A run of conduit between outlet and outlet, fitting and fitting, or outlet and fitting
shall not contain more than the equivalent of four quarter bends (360 degrees, total).
Minimum conduit used will be 3/4 inch except for those situations of
instrumentation equipment which call for 1/2 inch conduit.
When conduit runs exceed the equivalent of a 61 m (200 feet) straight run or
contain more than the equivalent of three 90 degree bends, pull fittings must be
installed. One 90 degree bend is to be considered to be equivalent to 15.25 m (50
feet) of straight run. No single bend shall exceed 90 degrees.
Conduit and conduit fittings shall not be welded to any structure.
Conduit shall be installed a minimum of 300 mm (1 foot) from un-insulated hot
piping or hot surfaces.
Conduit connections to end devices shall be from below to prevent moisture
ingress. Side entries are acceptable, but top entries should be avoided.
24.5 Thin-Wall Metallic Conduit Systems
Thin-wall metallic conduit systems shall not be used for outdoor areas and
classified locations. (EMT shall be used for only indoor wiring system.)
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
24/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
24 of 30
24.6 Floor Raceway Systems
Acceptable floor raceway systems shall be restricted to under floor raceways and
cellular concrete floor raceways.
Floor raceway systems shall not be used for outdoor areas and classified locations.
The total cross-sectional area of all contained conductors at any cross section of a
floor raceway shall not exceed 40 % of the interior cross-sectional area of the floor
raceway.
Metal junction boxes shall be used with floor raceways and shall be electrically
continuous with the raceway. The junction boxes shall be located at floor grade and
sealed to exclude water or concrete.
Splices and taps shall be made only in header access units or junction boxes.
24.7 Routing of Aboveground Wiring Systems
Cable shall be installed according to the manufacturer's recommendation. In no
case shall manufacturer's maximum allowable pulling tension, armor compression,
etc., be exceeded during cable installation.
Wiring systems shall not be installed closer than 150 mm from surfaces with
temperatures of 1130F to 1490F and not closer than 300 mm from surfaces with
temperatures above 1490F. Where it is necessary to route a wiring system close to a
high-temperature surface, a high-reflectance thermal barrier shall be installed
between the system and the surface.
All cables shall run in one length wherever possible.
24.8 Splices and Terminations
Splices and terminations for cables operating above 600 volts shall be made
according to the cable manufacturer's recommendations by one of the following
methods:
Straight (in-line) splices
Heat shrink sleeve or similarly terminating device.
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
25/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
25 of 30
25. CABLE AND CORE MARKER
All cables except for lighting systems shall be marked with a Type 316 stainless
steel tag with embossed lettering secured with Type 316 stainless steel ties or nylon
markers enclosed in a clear heat shrink sleeve. A cable marker shall be installed on
both ends of each cable. Where cables pass through duct banks, a marker shall be
installed on both sides of each penetration in addition to being marked on both ends
of the cable.
All cores of control cables shall have wires clearly identified with permanentlyembossed type or equal heat-shrinkable wire markers at every termination point.
Where it is determined that heat-shrinkable wire markers are not practical, slip-on
permanently embossed sleeves shall be used. For internal wiring of electrical
equipment and panels, equivalent vendor standard core identification system is
acceptable. These wire numbers must correspond to the wire numbers shown on
electrical drawings. An individual wire shall have the same assigned number at
each end and at each location where it is terminated.
Cable marker shall be provided on both ends of each cable and in every 5 meterlong distance between both ends.
26. TERMINATION
Control and instrument wires shall be terminated on terminal blocks in junction box
for external cables with suitable insulated compression terminals installed with a
ratchet type crimping tool with proper dies. Ring tongue or locking fork type
terminals shall be used when terminating to screw-type terminals. Straight pin type
ferrules shall be used when terminating to screw-clamp type terminals.
A removable bottom plate or threaded hub(s) for cable gland installation of external
cables shall be provided at local panel and / or junction box for package unit.
Where control and instrument wires terminate in a device where terminal points are
not provided (such as instruments or solenoids with pigtails), terminal blocks are to
be installed if the number of terminal points exceed four within a junction box. If
four or less, terminations are to be made utilizing self-insulated crimp type butt
splice connectors.
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
26/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
26 of 30
No more than two wires shall be terminated on any one terminal point. Jumper
links or combs shall be used to connect together extra terminals to allow
termination of more than two wires to the same terminal point.
Splices at lighting fixtures and receptacles not located indoors shall be made with
self insulated crimp type butt splice connectors. These connections shall be water
proofed with rubber tape and vinyl plastic electrical tape to prevent the entrance of
moisture into the connector.
Where a lug or terminal is not provided with equipment, power wire shall be
terminated with compression ring tongue terminals. Terminals shall be installed
with a ratchet type or hydraulic crimping tool with the proper dies.
Motor terminations shall be made with ring tongue compression terminals installed
on the power wire and the motor lead. Stainless steel bolts, nuts, and lock washers
shall be used to connect the ring tongue compression terminals.
The threaded hub shall be provided at terminal box of motors for cable gland
installation of external cables. The type of thread shall be per ISO metric and size
of thread shall be designated on data sheet during design stage.
27. ELECTRICAL WIRE AND CABLES
27.1 Cable Specifications
All power and control cables (wires) shall conform to the following types:
XLPE/SWA/PVC : Cross-linked polyethylene insulated, PVC bedded,
galvanized steel wire or non-magnetic metal wire (only for
single core cable) armored and PVC outer sheathed able.
XLPE/PVC : Cross-linked polyethylene insulated and PVC outer sheathed
cable.
PVC/SWA/PVC : Polyvinyl chloride insulated, PVC bedded, galvanized steel
wire or non-magnetic metal wire (only for single core cable)
armored and PVC outer sheathed cable.
PVC/PVC : Polyvinyl chloride insulated and PVC sheathed outer cable.
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
27/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
27 of 30
PVC : Polyvinyl chloride insulated cable (wire).
All cables shall conform to IEC 60502 except for PVC insulated single core cables
(wires) which shall conform to IEC 60227.
27.2 Cable Sizing
For the sizing of power cables, the following aspects shall be considered:
Thermal short circuit capacity ( for over 3 kV cables )
Voltage drop
Current rating
Minimum conductor sizes shall be as listed below:
LV control cables : 1.5 mm2
LV power cables : 2.5 mm2
27.3 Cable Construction
The conductor shall be either compact round stranded uncoated copper wires or
solid soft annealed uncoated copper wires, as specified in IEC 60228.
Suitable fillers (as specified in IEC) shall be used in the interstices of the cable to
give the completed cable a substantially circular cross section.
The outer sheath shall be flame retardant (not applied for cable installations outside
the plant).
27.4 Color Identification of cable core and outer sheath
HV / MV cable
Three cores : Red, Yellow, Blue
One core : Vendor Standard
Outer Sheath : Red
LV Power & Control cable
One core : Black
Two cores : Red, Black
Three cores : Red, Yellow, BlueThree core + Grounding : Red, Yellow, Blue + Green
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
28/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
28 of 30
Four cores : Red, Yellow, Blue, Black
Four core + Grounding : Red, Yellow, Blue, Black + Green
Five cores and above : Black with white numbers
Outer Sheath : Black
28. LIGHTING
28.1 General
Lighting shall be provided for the following areas:
Process operating areas
Utility areas
Offsite Pump areas
Storage tank areas
Loading and unloading areas
Parking areas
Plant main roads
Buildings (Indoor & Outdoor)
Lighting shall not be provided for the following outdoor areas, unless otherwise
specified:
Waste disposal ponds
Plant perimeter and/or security fences
Access road outside battery limit
Future area
Street lighting systems shall High Pressure Sodium fixtures mounted on poles.
Outdoor general plant lighting and street lighting shall be controlled by a photo-cell
located at each substation and manual by operator.
Tank farm shall be provided with flood lighting. No lighting fixture is required on
the tank stairs and tank roof.
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
29/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
29 of 30
28.2 Types of Lighting Fixture and Receptacle
The number of different types of lighting fixture used in an area shall be restricted
as follows to simplify maintenance work:
For outdoor area lighting
Mercury vapor lamp : 70 W, 100 W, 150 W, 250 W, 400 W
Fluorescent lamp : 20 W, 40 W (20 W x 2)
For street lighting
Mercury vapor lamp : 400 W, 250 W
For emergency lighting
Fluorescent lamp : 20 W, 40 W (20 W x 2)
Incandescent lamp : 100 W
For convenience receptacle (outdoor use): 15 A, 2 poles + 1 ground
Lighting fixtures in outdoor locations shall be equipped with a gasketed glove,
reflector and guard.
Mercury vapor lamps shall be a high power factor type.
Fluorescent lamps shall have a high power factor and rapid start type ballast.
All incandescent fixtures shall be a screw-in type.
Lighting fixtures in hazardous area shall be suitable type as per applicable codes
and standards for each classified area.
28.3 Emergency Lighting
Emergency lighting shall be fluorescent type fixtures, shall be provided in outdoor
areas to permit safe movement of personnel in normal operating areas during power
outages. Approximately 10 % of the total number of lighting fixtures in the process
and important utility areas such as around stage of towers, generator and air
compressor shall be provided as emergency lighting. Emergency lighting shall not
be required at operation vessels and tanks.
Emergency lighting for buildings shall be provided in the plant control rooms,
substations, generator shelter, HVAC panel and mechanical rooms, workshops,laboratories, and escape exit light at all manned buildings.
CONFIDENTIAL
-
7/28/2019 900-SPE-5001-MET&SYST
30/30
MULTI PURPOSE REACTOR PLANT PROJECT
Discipline Code:
EL
Project spec. Title :
ELECTRICAL METHODES AND SYSTEM
Doc. No.:
900-SPE-5001
Contract Job No.:
002/SP/EP7020/08-S0Rev.A
Page:
30 of 30
Power for emergency lighting shall be supplied from distribution line backed up by
an emergency diesel generator. There shall be separate distribution panels fed from
the emergency generator.
The emergency lighting fixtures inside plant control rooms, substations and
generator shelter shall be provided with self battery pack for 30 minutes operation.
28.4 Receptacles, Welding Outlet
Convenience receptacles 15A, 230 V, two poles (phase and neutral) + Earth shall be
located so that any point in the plant areas where repairs, adjustment, or inspections
may be made can reach nearest receptacle with a 30m extension cord.
The plug for convenience receptacles shall be supplied at the rate of 1 piece per 10
receptacles.
Convenience receptacles shall be installed at 1 meter above grade or floor.
All convenience receptacles and plugs shall be suitable for the area classification.
Welding Outlets, 380V, 3 phases, 63A, 3 poles + Earth shall be provided in process
and utility areas where welding is performed on the basis of 50m extension cord.
Power supply to welding outlets shall be distributed from LV MCC in substations.
28.5 Illumination Levels
The lighting system shall be designed to provide minimum average maintained (in
service) horizontal lighting illuminance requirement as per API 540.
Lighting intensities are measured at 1 m above floor level. A maintenance factor of
0.8 is used to calculate these intensities.
29. CATHODIC PROTECTION
Design, material, installation, testing of cathodic protection system, in general shall be as per
the recommendation of National Association of Corrosion Engineers (NACE) RP-01-69, and
National Electrical Code (NEC) NFPA-70.
The detailed design of cathodic protection is covered in Specification Doc. No. 900-SPE-
5010.