910 St. Andrews RdLocal Drainage Project (LDP)
Pre-Construction Community Meeting
WBS NO. M-000291-001A-4Hien Pham, P.E.
January 30, 2018
1 OVERVIEW OF THE PROJECT
2 PROJECT SCOPE AND PHASING
3 WHAT TO EXPECT DURING CONSTRUCTION
4 CONTACT INFORMATION
AGENDA
2
February Construction Begins
2018 May
Anticipated Completion
910 St. Andrews Rd LDP(WBS NO. M-000291-001A-4)
NOTE: EXPECTED DATES ARE ESTIMATES, MAY CHANGE DURING CONSTRUCTION
Project Map
• Replace/upsize existing inlets
910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)
Identified Improvement Needs
• Regrade roadside ditches
• Replace/upsize 24-inch to 36-inch storm sewers and culverts
910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)
What to Expect During Construction
Prepare for Construction• Residents will be notified minimum 72 hours prior to
start of construction activities• Plan for potential service impacts• Be mindful of protective barriers• Remove valuables in close proximity to the roadside
ditches
Potential Service Impacts:• Potential water service impacts, if needed• Potential parking/driveway access impacts, if needed
!
910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)
What to Expect During Construction
Parking and Driveway Access• Short-periods of limited access to your driveway• Contact us immediately if needing handicapped
access• Construction will alternate each side of the street
on different schedules
6P
910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)
What to Expect During Construction
Driveways• Driveway aprons will be reconstructed
910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)
What to Expect During Construction
Restoration• Sodding the sides of ditches will be done when construction is
complete.• City does not approve final payment to contractor until restoration is
complete.• If you have concerns:
• Document (writing, photo, etc.)• Call 3-1-1• Do not make the repairs yourself
910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)
Construction – How to Report a Problem
Contact 311• Report the project number
• Request issue be directed to Public Works Capital Projects
• Be as detailed as possible with your concern.
• Please remember to provide your contact information and address.
9
Contact us at: [email protected]
910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)
Contact Information
Contact us at pwecip@
houstontx.gov
Shawn Sidhu, Project Manager (713) 991-6685
AJ Kessinger, Project Manager (832) 395-2957
Chuck Uecker, Inspector (832) 596-4376
Reliance Construction Services, Inc. (Contractor)
Houston Public Works (Oversight)
910 St. Andrews Rd LDP(WBS NO. M-420126-0094-4)
IMPORTANT LINKS
For a complete listing of Frequently Asked Questions please visit:• https://www.publicworks.houstontx.gov/ecd/faqs.html
Today’s presentation and additional project information can be found at:
https://rebuildhouston.org/community-engagement
i
THANK YOU
Q&A to follow