a. ballarinolasa, milano,18/09/2012 high-tc superconducting link status of task 7.5 fp7 meeting at...
DESCRIPTION
A. BallarinoLASA, Milano,18/09/2012 Task 7.5: High-Tc link Deliverable of Task 5 - as described in the Eucard Grant Agreement: Superconducting link, 20 m long, containing 48 HTS cables rated at 600 A - DC.The Task includes design and assembly activities – but not the test of the final prototype The final application for LHC (P7) consists of two superconducting links, each about 500 m long, with the same configuration of the prototype CERN will test the 20 m long prototype in nominal operating conditionsTRANSCRIPT
A. Ballarino LASA, Milano,18/09/2012
High-Tc Superconducting LinkStatus of Task 7.5
FP7 Meeting at LASA-Milano
A. Ballarino, CERN
for the Task 7.5 Collaboration
CERN, Bruker, Columbus, University of Southampton
LASA, 18-09-2012
A. Ballarino LASA, Milano,18/09/2012
Outline
• Task description
• Cable concept
• Progress since last meeting (April 2012):• Cabling machines• Test station
• Status of activity vs final deliverable
• Conclusions
A. Ballarino LASA, Milano,18/09/2012
Task 7.5: High-Tc link
Deliverable of Task 5 - as described in the Eucard Grant Agreement:
Superconducting link, 20 m long, containing 48 HTS cables rated at 600 A - DC .The Task includes design and assembly activities – but not the test of the final prototype
The final application for LHC (P7) consists of two superconducting links, each about 500 m long, with the same configuration of the prototype
CERN will test the 20 m long prototype in nominal operating conditions
A. Ballarino LASA, Milano,18/09/2012
Cable concept
Elaboration of a cable concept that enables the use of pre-reacted superconductors available in the form of tape:
MgB2, YBCO and BSCCO 2223
The HTS cable design adopted for power transmission lines appeared not to be suitable for this specific application - few tapes and many cables in the same cryogenic envelope
A. Ballarino LASA, Milano,18/09/2012
+ 600 A
- 600 A
Three HTS tapes per cable interleaved with copper strips
+ 600 A
- 600 A
4 mm
1 m
m
Cable Concept
A. Ballarino LASA, Milano,18/09/2012
Cable/Link Concept (2/2)
24 × 2 × 600 A
Multi-cable assembly Link: multi-cable assembly in cryostat
~2 kg/m~ 200 mHTS/mcable
A. Ballarino LASA, Milano,18/09/2012
Prototype twisted-pair cables characterization(CERN and SOTON)
Type-5: MgB2Type-3: Y-123Type-2: Bi-2223Type-1: Bi-2223
NB The Ic in the plot refers to one single cable of the twisted pair unit
Measurement performed on twisted-pair cables made from different conductors
No cabling degradation observed (< 2 %)
Good homogeneity of Ic of cables in the same in the same twisted pair (~ 2 %)
Self-field, Length of cables = 2 m
2×4.4 kA !
A. Ballarino LASA, Milano,18/09/2012
Cabling machine (1/2)
For the controlled assembly of long cables a dedicated cabling machine hasbeen designed, assembled and fully commissioned at CERN
A. Ballarino LASA, Milano,18/09/2012
Cabling machine (2/2)
Rotating machine for the twisting of insulated cables
Design and assembly completed. To be commissioned in October 2012.
A. Ballarino LASA, Milano,18/09/2012
Test station
LHe
GHe
20 kA
L = 20 m inner = 64 mmouter = 163 mm
A. Ballarino LASA, Milano,18/09/2012
Test Station – SM 18 CERN laboratory
Refrigerator: 6 kW @ 4.5 K(18 kW for test of LHC magnets) 25 000 LHe Dewar
A. Ballarino LASA, Milano,18/09/2012
Test Station @ CERN: Conceptual DesignRT
Cryostat with current leads
Cryostat with superconducting cables
A. Ballarino LASA, Milano,18/09/2012
Test Station @ CERN: Conceptual DesignRT
LHe
4.5 K
GHe
Tv m ≤ 10 g/s 5 K ≤ Tv ≤ 70 K
Vacuum Insulation
LHe, 4.5 K GHe
Instrumentation DAQQuench Protection
A. Ballarino LASA, Milano,18/09/2012
Test Station @ CERN
A. Ballarino LASA, Milano,18/09/2012
Test Station @ CERN
A. Ballarino LASA, Milano,18/09/2012
Test station at CERN
The two cryostats are fully assembled
The cryostat with the leads has been commissioned – pressure and leak tested, cooled-down to nominal conditions, operated at some 3.5 kA and warmed up
The cryostat of the superconducting link was successfully leak tested last week, and it will be pressure tested this week
The connection of the two cryostats is planned to take place this month.
A first cool-down, with a 20 m long twisted pair YBCO cable already integrated the in cryostat of the superconducting link, is planned to take place in October 2012
A. Ballarino LASA, Milano,18/09/2012
Status of activity vs final deliverable
The 20 m long semi-flexible cryostat with a supporting system and purpose-built terminations, is available today at CERN
A 20 m long 48 HTS cable assembly can be ready by end 2012 – when also the rotating cabling machine will have been commissioned
This two components make the superconducting link which is the deliverable of the Task 7.5
In addition:
By the end of the year, the test station will have been fully commissioned and 20 m long cables will have been tested in He gas in a variable temperature range. The test of a 20 m long prototype will follow
A. Ballarino LASA, Milano,18/09/2012
Is the Task 7.5 on schedule ? Yes
Assembly of prototype link: planned to be ready by end 2012.
A. Ballarino LASA, Milano,18/09/2012
Conclusions
A new cable concept has been proposed. Validation of the proposed twisted-pair concept was done with the assembly and characterization of short prototype MgB2, YBCO and BSCCO 2223 cables
Two cabling machines have been designed and constructed for the controlled cabling of the 20 m long HTS twisted-pair cables
A new test station has been constructed at CERN for the test of the 20 m long prototype link
The task is on schedule – a full prototype is planned to be available by end 2012. The test in nominal operating conditions will follow. Single twisted-pair cables, 20 m long, will be measured this year
A. Ballarino LASA, Milano,18/09/2012
Thanks for your attention !