a compressed air case study – illustrating the need for energy management standards in the mining...
TRANSCRIPT
A compressed air case study –illustrating the need for energy management
standards in the mining industry
UNIDO EXPERT GROUP MEETINGIndustrial Energy Efficiency and Energy Management
StandardsVienna International Centre
21-22 March 2007
PRESENTED BY DR. I.E. LANE (South Africa)
OVERVIEW
• A STORY ON MANAGEMENT COMMITMENT• HOW WE STUMBLED BEFORE WE COULD PLAN• THE BATTLE OF THE BASELINE• THE TEAM AND THE LEARNING CURVE• MODELLING AND TESTING TO FIND CREDIBLE
TARGETS• ENGAGING THE WORKFORCE• FINDING THE MONEY• IMPLEMENTING APPROPRIATE TECHNOLOGY
A STORY ON MANAGEMENT COMMITMENT
• BEFORE GOVERNMENT ENERGY ACCORD– TRAVEL 400 km, ONLY TO FIND THE GUY YOU
WERE SUPPOSED TO MEET CANNOT SEE YOU
• AFTER COMMITMENT– TRAVEL 400 km AT MORE REGULAR INTERVALS
TO FIND 10 PEOPLE FROM CROSS-FUNCTIONAL TEAM WAITING TO PRESSURIZE ESCO TO GET ON WITH IT
HOW WE STUMBLED BEFORE WE COULD OPTIMIZE
• COULD NOT FIND AIR BALANCE - AIR FLOW INSTRUMENTS TOOK MONTHS TO CALIBRATE
• COULD NOT FIND TRUSTWORTHY DRAWINGS ON AIR DISTRIBUTION – THINGS HAD CHANGED WITHOUT BEING DOCUMENTED, AND THOSE WHO KNEW HAD LEFT
• SCADA DATA HAD TO BE “CLEANED” BECAUSE INTRANET FAILED FROM TIME TO TIME
• POWER DATA COULD ONLY BE OBTAINED OFF-LINE WITH HELP FROM OUTSOURCED PROVIDER
• NO ONE KNEW WHERE TO FIND COMPRESSOR DESIGN DATA OR HANDBOOKS
• NOBODY ON SITE COULD VOUCH FOR CORRECT OPERATION OF INLET VOLUME AND PRESSURE CONTROLS
ALL THIS COULD BE AVOIDED IF ENERGY MANAGEMENT STANDARDS ARE IN PLACE AND ADHERED TO
HOW WE STUMBLED BEFORE WE COULD OPTIMIZE
• AIR DISTRIBUTION DRAWINGS INADEQUATE• POWER FLOW SCATTER PLOTS SHOW
COMPRESSOR INLET VOLUME CONTROL NOT WORKING, AND COMPRESSORS NOT BEING STARTED AND STOPPED OPTIMALLY
• PRESSURE FLOW SCATTER PLOTS INDICATE PRESSURE CONTRAINTS THAT HINDER ENERGY EFFICIENT CONTROL
• PUZZLING TEST RESULTS
Compressors scatter
0200400600800
10001200140016001800200022002400260028003000320034003600380040004200440046004800500052005400
0 5000 10000 15000 20000 25000 30000 35000 40000 45000 50000
m3/hr
kW
Decline Mark I Spud I Mark I Richard Sulzer Spud II Mark I Spud III Mark II
Specific energy scatter plotAll Compressors
0
5000
10000
15000
20000
25000
0 20000 40000 60000 80000 100000 120000 140000 160000 180000 200000
m3/hr
kW
Compressor curve
0
1
2
3
4
5
6
7
0 20000 40000 60000 80000 100000 120000 140000 160000 180000 200000
m3/hr
Bar
.
Spud Richard Decline 4
THE BATTLE OF THE BASELINE
• SIMULATION OF POWER BASED ON AIR FLOW
• EACH COMPRESSOR CONTROLLED DIFFERENTLY, DIFFERENT COMBINATIONS
Average week (9weeks - 6 March '06 - Dec '06)
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
Mon Tue Wed Thu Sat Sun
xxx.
Richard Spud III Decline 4B Spud II Spud I Sum
Average weeks
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
Mon Tue Wed Thu Sat Sun
m3/
hr
.
Richard Spud III Decline Spud II Spud I Total
THE TEAM AND THE LEARNING CURVE
• CLOSED WRONG VALVES ON FIRST TEST• MAINTENANCE PERSONNEL HAVE FALSE SENSE
THAT THEY HAVE AIR LEAKS UNDER CONTROL• VALVE THROTTLING IDEA FAILED TEST• ENGINEERS CHANGED MID-STREAM, HAD TO
START WORKFORCE ENGAGEMENT ALL OVER AGAIN
• NEW ENGINEER MORE CONSERVATIVE – WANTED TO BACK OFF ON PREVIOUS COMMITMENT
• TEAM SCEPTICAL ABOUT ABILITY TO SUSTAIN ENERGY MANAGEMENT PERFORMANCE
MODELLING AND TESTING TO FIND CREDIBLE TARGETS
• MODELLING ASSUMPTIONS ON SYSTEM CURVE PROVED WRONG ON TEST - NEED FOR STANDARDIZED MODELLING TOOLS, TEST PROCEDURES AND SYSTEM OPTIMIZATION EXPERTISE LIBRARY
• DECISION MAKERS ONLY MOVE FORWARD IF THEY CAN BELIEVE THE OPTIMIZATION SPECIALIST – NEED FOR COMPETENCE STANDARDS, ALREADY BEING DEVELOPED IN SA.
CONCLUSION – ENERGY MANAGEMENT STANDARDS WILL HELP DECISION-MAKERS TO MOVE FORWARD ON ENERGY EFFICIENCY
20,000.0
0
2000
4000
6000
8000
10000
12000
14000
16000
18000
20000
Mon Tue Wed Thu Fri Sat Sun
kW
Spud II
Richard
Declines
Spud III
M&V
-
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
Mon Tue Wed Thu Fri Sat Sun
m^3
/hr
.
Spud III Richard Declines Spud II Mobile Compressors Current Required
18,000.0
0
20000
40000
60000
80000
100000
120000
140000
160000
180000
Mon Tue Wed Thu Fri Sat Sun
m^3
/hr
.
Spud III Richard Declines Spud II Mobile Compressors Current Required
ENGAGING THE WORKFORCE• POLICY MUST MAKE PROVISION FOR CONTINUITY
OF ENERGY MANAGEMENT RESPONSIBILITY• THE ORGANIZATION MUST PROVIDE FOR THE RIGHT
DIVISION TO ACT ON THE PROBLEM – DO NOT TRY TO GET SOMEONE WHO HAS NO CONTROL OR AUTHORITY TO TAKE CORRECT ACTION
• GET THE RIGHT INFORMATION TO THE RIGHT PERSON AT THE RIGHT TIME
FINDING THE MONEY
• IDENTIFY WHO MUST BUDGET FOR CONTINUOUS IMPROVEMENT
• BUDGET HOLDER IS LINE MANAGER, NOT ENERGY MANAGER
• TAKE ADVANTAGE OF GOVERNMENT INCENTIVES (DSM FUND IN SA)
IMPLEMENT APPRORIATE TECHNOLOGY
• TECHNOLOGY DOES NOT WORK IF PEOPLE DO NOT USE IT
• WORKFORCE ENGAGEMENT HELPS DETERMINE IF THEY WILL ADOPT TECHNOLOGY
• MAKE SURE ENERGY MANAGEMENT AND OPTIMIZATION TOOLS ARE SUSTAINABLE AND EASY TO ADAPT AS FUTURE CHANGES TO PLANT TAKE PLACE
CONCLUSION
ENERGY MANAGEMENT IS MORE LIKELY TO BE SUCCESSFUL IF YOU HAVE COMPETENT PEOPLE ACTING IN RESPONSE TO APPROPRIATE STANDARDS, PROCEDURES AND OPTIMIZATION TOOLS