a fast chopping system for high intensity linac beams f. caspers, t. kroyer cern-ab-rf e. mahner...
TRANSCRIPT
A Fast Chopping System for High A Fast Chopping System for High Intensity Linac BeamsIntensity Linac Beams
F. Caspers, T. Kroyer CERN-AB-RFE. Mahner CERN-AT-VAC
CARE’06 Frascati, November 15 – 17, 2006
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
2
Introduction CERN chopping scheme Layout Technical requirements
Evolution of the SPL chopper Modifications in 2005 Status by September 2006
Measurements & tests Electrical properties Vacuum & leak test Heat transfer test
Coverage factor Measurement Simulation
Remaining jobs
ContentsContents
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
3
Superconducting Proton Linac (SPL) Fast beam chopping at Ekin = 3 MeV ; thus is about 8%
Fast chopper required to establish desired beam pattern
SPL LayoutSPL Layout
RFQ: Radio frequency quadrupole DTL: Drift tube linac CCDTL: Coupled cavity DTL SCL: Side coupled linac = 0.65, = 1.0: superconducting cavities
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
4
8*2.84 ns ( 44 MHz)
Most demanding scheme for SPL operation: cutting out three bunches out of eight repetition rate 44 MHz bunch spacing 2.84 ns ; 10 to 90% rise and fall time required < 2 ns
CERN Chopping SchemeCERN Chopping Scheme
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
5
Chopper off
Chopper line lattice designed such as to magnify the kick from the chopper; this reduces required kick field
The chopper plates have to be installed in the quads; this saves length and reduces space-charge related emittance growth
Chopper Line (1)Chopper Line (1)
Chopper on
Kick-magnifying quad
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
6
Chopper Line (2)Chopper Line (2)
chopper beam dump
bunching cavities
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
7
The chopper plates are no longer DC-wise floating (no more triaxial mode of operation)
Now we have a coaxial instead of a triaxial chopper structure
The triaxial version was meant for simultaneous dual mode of operation, i.e. 0 to 10 MHz: electrostatic deflector, above 10 MHz travelling wave mode
Removal of isolating units both in water cooling circuits and coaxial driving lines
Modifications in 2005Modifications in 2005
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
8
Initially samples of the meander lines were produced at CERN While all parameters were basically ok (electrical, vacuum),
reproducibility of certain electrical parameters (electrical length, match) was not always perfectly satisfactory
After the accomplished proof of principle with CERN technology, a supplier that can well control all the process parameters was needed; a possible change in technology is not a problem as long as the key properties are preserved
Kyocera was eager to enter in a cooperation with CERN and willing to adapt their technology to our needs
The plate that was recently furnished compared well in all aspects with the best CERN samples and we hope that the promised good reproducibility will show up in reality
Meander linesMeander lines
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
9
Technological differences between the CERN and Kyocera meander structures:
Meander line: TechnologyMeander line: Technology
CERN Kyocera
CERN orders from Wesgo (D) ceramic plates with fixation holes and 10 to 15 m thick homogeneous MoMn layer (fired at 1400 C in hydrogen atmosphere
Kyocera produces the alumina plates in-house. Then a meander pattern is created in thick film silver paste of about 10 to 15 m thickness. This thick film silver paste has after firing a much higher resistivity than bulk silver (factor 5 to 10)
The meander structure is etched into the MoMn layer. Afterwards a 1 to 2 m thin-film layer of Ag is attached by sputtering.
Onto the Ag thick-film layer 30 to 40 m copper are deposited electrochemically
In a final step this silver-coated MoMn layer gets another 30 m silver by electrochemical deposition
Finally 1 to 2 m of Au are applied for good contacts and protection against oxidation
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
10
Metallize printing (Ag thick-film)
Firing
Cu Plating
Resistance Testing
Final inspection
Packing
Machining
Ceramic incominginspection
Au Plating
CERAMIC PLATE Process Flow CERAMIC PLATE Process Flow
RF Property Testing
Machining
Electrode for electrochemical deposition removed by grinding
Grinding Area
Courtesy: Kyocera
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
11
First meander line plate from Kyocera were received in June 2006 but it turned out that the attenuation was too high
In the second iteration the technological parameters were properly adjusted and the last sample was very satisfactory
After extensive electrical tests this single plate was installed in the chopper tank
Vacuum, leak and heat tests performed successfully
Status by September 2006Status by September 2006
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
12
Electric Measurements: Electric Measurements: Transmission AttenuationTransmission Attenuation
Measurements performed on single chopper plate with an image plane 10 mm above the line’s surface to simulate the presence of a second plate
Frequency domain transmission A DC resistance of 1.1 was
measured, which agrees very well with the low-frequency limit of the measured attenuation
3 dB bandwidth 940 MHz. If there was no phase distortion the rise time would be
All rise times quoted are 10 to 90% values ns 355.0
3
1
BWtt
Attenuation over one chopper plate
Gen
erat
or b
andw
idth
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
13
Transmission Step ResponseTransmission Step Response Response for 0 to 700 MHz low pass
step function (Kaiser Bessel weighting function with = 6)
Comparison between a measurement with and without the image plane. Due to the high electric field energy in the alumina the kick field does not change much when the symmetry is broken
Measured rise time trm = 1.771 ns, to be compared with tri = 1.407 ns of input pulse; structure rise time
This is a conservative estimate of tr since the tti is rather short and we get into the highly dispersive region of the response
ns 08.122 rirmr ttt
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
14
Phase DistortionPhase Distortion
From the measured phase without image plate the electrical delay of 16.73 ns (linear term) was removed
With image plane (realistic configuration) the electrical length was 16.83 ns, within 0.1 ns of the required value
The remaining phase is not flat as for a dispersion-free line; thus we have phase distortion
The phase distortion is due to coupling between adjacent lines in the meander structure. This coupling increases quickly with frequency like in a microstrip directional coupler
In an ordinary first-order low-pass the 45 degree points coincide with the 3 dB points. Here they are at 375 MHz, i.e. much lower than the 3 dB points
Gen
erat
or b
andw
idth
Phase without image plane
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
15
ReflectionReflection
Very good impedance match of meander line to 50 : reflection in frequency domain of the order of -30 dB below 500 MHz
These data were measured on a test jig consisting of a single plate with SMA connectors fixed on either side
Gen
erat
or B
W
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
16
Reflection Step ResponseReflection Step Response
Response for 0 to 700 MHz low pass step function
S11 very small, of the order of 0.02 which is another indication of good match
The line impedance is not perfectly constant over the meander length as can be seen from the bump at t = 10 ns.
Towards the end of the line an apparent increase in line impedance can be seen. This is an artifact caused by the lossy line; could be corrected numerically
Twice the line length of ¼17 ns
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
17
Tuning of Electrical LengthTuning of Electrical Length
It was tried to adjust the electrical delay of a chopper plate by modifying the metal ground plane
Cutting a longitudinal groove into the ground plane reduces the effective and thus increases the group velocity on the line. Since the variation in line impedance is over distances much shorter than the wavelength, the other electrical properties should not be affected much
For two 5 mm wide and 3 mm deep grooves a 5% decrease in the electrical length was found on a CERN plate
Gen
erat
or b
andw
idth
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
18
Vacuum & Leak TestingVacuum & Leak Testing Initially the obtained vacuum pressure was about
1.5e-7 mbar Leak rate smaller than 2e-10 mbar.l/s The ceramic plates were not baked before
installation and the entire tank cannot be baked due to the presence of the integrated quadrupole magnet
However, there is a rather larger thermal resistance between the ceramic plate and its aluminium support structure and the rest of the tank
Therefore an “in-situ bake-out” at about 150 degrees C was possible by passing current through the meander line with the water-cooling off
Now a vacuum pressure of about 3.5e-8 mbar is reached, which is within specs for the chopper line
water cooling
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
19
Heat Transfer Test (1)Heat Transfer Test (1)
In order to settle question about the heat contact between the ceramic plates and the water-cooled aluminium support structure a heat transfer test was carried out
The temperature of the ceramic plate was monitored in two ways, by
Observation with an infrared camera through a window at one end of the tank
measuring the resistance of the meander line, knowing that the resistivities of the Cu, Ag and Au all have about the same temperature coefficient of 4e-3 K-1
In two runs the heating with and without water cooling was measured
The vacuum pressure was monitored, as well
water-cooling off
water-cooling
on
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
20
Heat Transfer Test (2)Heat Transfer Test (2) The device under test…
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
21
Heat Transfer Test (3)Heat Transfer Test (3)
The pictures on the right show a heating cycle without water cooling (Note the change in scale for the last picture!)
Without cooling the steady state conditions were reached at a temperature difference T = 128 K. The heating power was P = 28.4 W returning a thermal resistance Rth = 4.5 K/W.
Radiative heat losses were neglected here. This can be justified by the fact that inner surface of the chopper tank has very high reflectivity, thus reducing considerably the effective power flux. The measured temperature curves follow very closely the exponential curves predicted for heat conduction, indicating that this is the main process involved.
With the cooling of the aluminium support plate switched on, the steady state T decreases to about 18.2 K for P = 20.4 W giving a Rth = 0.89 K/W
Thus more than 100 W of heat power can be dissipated for an operation temperature 100 K above the cooling water temperature
t = 0 min, T = 0 K
t = 35 min, T = 20 K
t = 500 min, T = 120 K
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
22
The chopper must be able to stand the 500 V pulses on the plates High voltage testing showed that a single chopper plate can stand
at least 2 kV to ground which is largely sufficient for the present requirements
High Voltage TestingHigh Voltage Testing
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
23
The field coverage factor is defined as the ratio of the deflecting electric field on the beam path to that for the case when a continuous metal plate replaces the meander pattern
Time domain simulations presented at EPAC02 predict a coverage factor of 0.8 in the center of the structure [1]
In the electrostatic approximation it follows from Gauss’s law that the vertical electric field integrated over any horizontal plane above the chopper plate is constant. However, in dependence of the transverse position the field strength may change.
Simulations by M. A. Clarke-Gayther predict a coverage factor of 0.78 in the center of the chopper aperture; 10 mm to the side the coverage factor decreases to about 0.73
Since the beam dump is round, the maximum kick field is needed in the center of the structure
Coverage factorCoverage factor
[1] Caspers, F; Mostacci, A; Kurennoy, S; Fast Chopper Structure for the CERN Superconducting Proton Linac, EPAC02, Paris, 2002
Time domain simulation (MAFIA)
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
24
In terms of field homogeneity the CERN structure compares favorably to the SNS meander, since the meander period to aperture ratio is considerably smaller
Field homogeneity (1)Field homogeneity (1)
+25mm
-25mm
+66mm
-66mm
SNS structure image: S.S. Kurennoy and J.F. Power, Development of a fast traveling-wave beam chopperfor the SNS project, LINAC’98, Chicago, 1998
CERN meander lineSNS meander line
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
25
An electrostatic simulation with Ansoft Maxwell was run to determine the field homogeneity of the structure in the beam aperture
Very close to the conductor surfaces the fields peak, while the smoothen out as one approaches the beam axis
Field homogeneity (2)Field homogeneity (2)
Beam goes into plane of the “paper”
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
26
Coverage Factor Measurements (1)Coverage Factor Measurements (1) Alumina plate with meander structure compared with full metal plate Metal plate made twice as wide to assure that its fringe field can be neglected Second metal plate used at the position of the beam (10 mm above ceramic
surface) as image plane In the center of the structure field measured using probe with 10 mm
diameter using a button pick-up-like set-up
Port 2
Port 1Port 3
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
27
Coverage Factor Measurement (2)Coverage Factor Measurement (2)
Button as probe at Port 3
image plane
reference line
meander line
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
28
Coverage Factor Measurement (3)Coverage Factor Measurement (3)
We have a 3-port, with ports 1 and port 2 being the input and output of the slow-wave structure and the probe at port 3 Full two-port calibration used, since for the reference measurement we have a 4 line thus strong mismatch Measured quantities
S21: Transmission along the plate with port 3 matched Reflection on ports 1 and 2 S31: Transmission from the plate to the probe with port 2 matched
These quantities were measured for the slow-wave structure (subscript DUT) and for the full metal plate as reference (index R) From these quantities the coverage factor CF in dB can be calculated from CF = S 31DUT - S21DUT/2 - (S31R - S21R); the S parameters have to be plugged in in dB This formula was derived under the assumptions
negligible losses for the reference measurement but heavy mismatch mismatch of the slow-wave structure small but certain losses
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
29
Coverage Factor Measurement (4)Coverage Factor Measurement (4) CF = 0.78 at low frequencies Ripple with ¼25 MHz due to small mismatch of slow-wave structure For high frequencies (>50 MHz) standing waves strongly impact reference measurement Mechanical uncertainty of half beam gap (chopper plate to image plane) estimated as ¼0.1 mm;
effect on results determined by introducing a 0.2 mm offset ( cyan traces) At about 1 MHz comparison with modified technique: port 2 left open in reference measurement. At
low frequency S21R is then expected to double. The corrected result is plotted at one frequency (black star)
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
30
Remaining JobsRemaining Jobs
Final assembly of both chopper tanks including outgassing, leakage and electrical tests
Power test with new pulser Test with beam
Static: A DC voltage applied at the plates, 50 termination removed Dynamic test with pulser
Whatever else you can suggest or dream up...
CARE06 Frascati, November 15-17, 2006
A Fast Chopping System for High Intensity Linac Beams
31
AcknowledgementsAcknowledgements
We would like to thank the AB-RF workshops for assembling the tank, F. Wurster and M. Nagata from Kyocera for fruitful cooperation in development and implementation of the technologies for printing the meander structure and J. Borburgh for assistance with the heat transfer measurements
Thanks to R. Garoby and T. Linnecar for support