a guide to solid wall insulation installation. surveys properties need to be fully surveyed is...
TRANSCRIPT
Surveys
• Properties need to be fully surveyed
• Is substrate suitable for mechanical fix?
• Is there sufficient overhang on cills/soffits?
• Gates/satellite dishes provision needs to be made for refix
• Windows and reveals
• Do soil pipes need to be moved?
• Access Requirements & Ties
External Wall Solutions
Installation
• 3 key stages for a typical semi
1. Boarding and beading 1-2 days
2. Base coat and Mesh 2 days
3. Top coat /finish 1days
• Usually a 3 man team
• Drying times required for stage 2 up to 48hrs
• Can only be applied if temp is 50 and rising
External Wall Solutions
Skills
• Boarding not highly skilled but important as it’s the basis
of the system
• Base coat /Top coat generally plastering or rendering
experience required
• Mainly hand application but machine application available
on most systems
External Wall Solutions
Site supervision
• Will vary from system to system but will normally take
place at the 3 critical stages
• Under CERT independent inspections will also be
required