A Guide to Solid Wall Insulation

INSTALLATION

Surveys

• Properties need to be fully surveyed

• Is substrate suitable for mechanical fix?

• Is there sufficient overhang on cills/soffits?

• Gates/satellite dishes provision needs to be made for refix

• Windows and reveals

• Do soil pipes need to be moved?

• Access Requirements & Ties

External Wall Solutions

Installation

• 3 key stages for a typical semi

1. Boarding and beading 1-2 days

2. Base coat and Mesh 2 days

3. Top coat /finish 1days

• Usually a 3 man team

• Drying times required for stage 2 up to 48hrs

• Can only be applied if temp is 50 and rising

External Wall Solutions

Boarding with EPS board

External Wall Solutions

Boarding with Mineral wool boards

External Wall Solutions

Base coat and mesh

External Wall Solutions

Render

External Wall Solutions

Finish coat using brick slabs

External Wall Solutions

Typical site social housing refurbishment

External Wall Solutions

External Wall Solutions

External Wall Solutions

External Wall Solutions

Skills

• Boarding not highly skilled but important as it’s the basis

of the system

• Base coat /Top coat generally plastering or rendering

experience required

• Mainly hand application but machine application available

on most systems

External Wall Solutions

Site supervision

• Will vary from system to system but will normally take

place at the 3 critical stages

• Under CERT independent inspections will also be

required

External Wall Solutions

Typical costs 3 bedroom semi

• Scaffolding costs £1000

• Material and labour £60-£85/m2

• Ancillary costs e.g. Satellite dish £100, gates £50