A New Era of Transportation Improvements

Monica Backmon, Executive Director

2015 Road Show

Page 2: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

The Authority, as a regional body,

is focused on delivering real transportation

solutions and value for Northern Virginia’s

dollars.

2

Page 3: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

What is the NVTA?

We are the preeminent transportation coordination, funding and planning authority in Northern Virginia

3

Page 4: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

What is the NVTA?

• Identify regional, congestion reducing, multi-modal projects

• Work regionally to fund transportation projects

4

Page 5: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

Regional Accomplishments

Long Range Planning with updates of TransAction 2030 and 2040.

5

Page 6: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

Planning for the Future

“In the 21st century, Northern Virginia will develop and sustain a multimodal transportation system that

supports our economy and quality of life.

It will be fiscally sustainable, promote areas of concentrated growth, manage both demand and

capacity, and employ the best technology, joining rail, roadway, bus, air, water, pedestrian and bicycle

facilities into an interconnected network.”

6

Page 7: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

The Update

TransAction is the Authority’s guide to Northern Virginia’s transportation linked economic future.

The Authority is committed to:

• A multi-modal, regional approach to planning and coordination.

• Expanding outreach to Northern Virginia’s diverse communities.

• Making the connection between transportation and economic vitality.

7

Page 8: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

Approved FY 2014 Project List

33 multi-modal projects valued at over $200 million

8

Page 9: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

9

Page 10: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

10

Page 11: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

To date 78% of the regionally significant projects have been

advanced for funding

11

Page 12: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

The Two Year Planning Process for FY15-16 Has Begun

12

Page 13: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

NVTA Awarded First Credit Rating

13

Page 14: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

Inaugural Bond Sale

In December 2014 NVTA entered the Capital Bond Market for the first time with our Transportation Special Tax Revenue Bonds Series 2014 for nearly $69 million. The Bonds reflected a 2.5 times subscription rate and a low true interest cost of 3.09%.

14

Page 15: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

Financing the Future without Risk to Localities

• We support the financial policies of local governments.

• Our bonds do not jeopardize AAA bond ratings held by at least 5 out of our 9 jurisdictions.

• Best practices ensure that all projects are funded quickly without limiting future funding capacity.

15

Page 16: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

In FY2014, the NVTA received $285.6 million in revenues

NVTA Total FY2014 Revenue

Member Locality Additional Retail Sales and

Use Tax Grantors Tax (Regional

Congestion Relief Fee) Transient Occupancy Tax Total

City of Alexandria $ 14,996,328 $ 3,129,852 $ 2,827,753 $ 20,953,933

Arlington County $ 23,312,124 $ 4,313,922 $ 8,371,491 $ 35,997,537

City of Fairfax $ 7,028,117 $ 367,004 $ 205,521 $ 7,600,641

Fairfax County $ 99,716,693 $ 15,696,118 $ 9,507,033 $ 124,919,843

City of Falls Church $ 2,141,292 $ 268,842 $ 75,116 $ 2,485,250

Loudoun County $ 38,262,893 $ 8,551,256 $ 2,014,505 $ 48,828,654

City of Manassas $ 4,617,569 $ 465,593 $ 55,123 $ 5,138,285

City of Manassas Park $ 1,084,249 $ 226,746 $ - $ 1,310,996

Prince William County $ 32,212,081 $ 4,989,612 $ 1,166,332 $ 38,368,026

Total FY 2014 Revenues: $ 223,371,345 $ 38,008,947 $ 24,222,873 $ 285,603,165

16

Page 17: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

All of the NVTA member jurisdictions met the requirements to receive their 30% local

funding in FY2014 NVTA 30% Funds Distributed to Member Localities

Member Locality Additional Retail Sales and

Use Tax

Grantors Tax

(Regional Congestion Relief

Fee)

Transient Occupancy Tax Total

City of Alexandria $ 4,498,898 $ 938,956 $ 848,326 $ 6,286,180

Arlington County $ 6,993,637 $ 1,294,177 $ 2,511,447 $ 10,799,261

City of Fairfax $ 2,108,435 $ 110,101 $ 61,656 $ 2,280,192

Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110 $ 37,475,952

City of Falls Church $ 642,387 $ 80,653 $ 22,535 $ 745,575

Loudoun County $ 11,478,868 $ 2,565,377 $ 604,351 $ 14,648,596

City of Manassas $ 1,385,271 $ 139,678 $ 16,537 $ 1,541,486

City of Manassas Park $ 325,275 $ 68,024 $ 393,299

Prince William County $ 9,663,624 $ 1,496,884 $ 349,900 $ 11,510,408

Total FY 2014 30%

Revenues: $ 67,011,403 $ 11,402,684 $ 7,266,862 $ 85,680,949

17

Page 18: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

Pay-As-You-Go Projects

NVTA FY2014 “Pay-As-You-Go” Projects

Locality Project Name Funding Amount

Arlington Columbia Pike Multimodal Street Improvements $12,000,000

Blue/Silver Line Mitigation $1,000,000

Crystal City Multimodal Center $1,500,000

Fairfax Route 28 Widening 6 to 8 lanes (SB from the Dulles Toll Road to Route 50)

$20,000,000

Route 28 Widening 6 to 8 lanes (NB from McLearen Road to Dulles Toll Road) $11,100,000

Innovation Center Metrorail Station* $21,000,000

Town of Herndon Herndon Parkway Intersection Improvements at Van Buren St.

$500,000

Herndon Parkway Intersection Improvements at Sterling Road $500,000

Herndon Metrorail Intermodal Access Improvements $1,100,000

Loudoun Widening of Belmont Ridge Road, North of Dulles Greenway

$20,000,000

Route 28 Hot Spot Improvements Loudoun Segment (Sterling Boulevard and

the Dulles Toll Road)* $6,000,000

Transit Buses $880,000

Town of Leesburg Edwards Ferry Road at the Route 15 Leesburg Bypass Grade Separated

Interchange $1,000,000

Prince William Route 1 from Featherstone Road to Marys Way $3,000,000

Alexandria DASH Bus Expansion $3,250,000

Traffic Signal Upgrades/Transit Signal Priority $660,000

Shelters and Real-Time Transit Information for DASH/WMATA $450,000

Potomac Yard Metrorail Station EIS $2,000,000

Falls Church Pedestrian Access to Transit $700,000

Funding for Bus Shelters $200,000

Pedestrian Bridge at Van Buren Street $300,000

Agency

Northern Virginia Transportation Commission (NVTC) Transit Alternatives Analysis Study in the Route 7 Corridor (King Street,

Alexandria to Tysons Corner) $838,000

Potomac & Rappahannock Transportation

Commission (PRTC)

PRTC New Gainesville Service $580,000

Virginia Railway Express (VRE) VRE Gainesville-Haymarket Extension Project Development

$1,500,000

Washington Metropolitan Area Transit Authority

(WMATA)

Traction Power Upgrades on the Orange Line in Virginia $5,000,000

New Buses on Virginia Routes $7,000,000

Total FY2014 “Pay-As -You-Go” Project Amount $122,058,000

18

Page 19: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

Bond Projects NVTA FY2014 Bond Projects

Locality Project Name Funding Amount

Arlington Boundary Channel Drive Interchange

$4,335,000

Fairfax Innovation Center Metrorail Station* $20,000,000

Loudoun

Route 28 Hot Spot Improvements - Loudoun

Segment (Sterling Boulevard and the Dulles

Toll Road)* $6,400,000

Leesburg Park and Ride $1,000,000

Prince William Route 28 from Linton Hall Road to Fitzwater

Drive $28,000,000

Fairfax Chain Bridge Road Widening/ Improvements

$5,000,000

Agency

Virginia Railway Express (VRE) VRE Lorton Station second platform $7,900,000

Virginia Railway Express (VRE) VRE Alexandria station tunnel and platform

improvements $1,300,000

FY2014 Project Amount (Bond-Funded) $73,935,000

19

Page 20: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

We are Accountable

In 2014, the Authority submitted a summary report of our finances and activities to the Joint Commission on Transportation Accountability

20

Page 21: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

The Beginning of Our Six Year Program

21

Page 22: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

NVTA’s Two-Year Program (FY2015 - FY2016)

A Total of 52 Highway and Mass Transit Projects

Project Type Funding

33 Highway $423,452,810

19 Mass Transit $346,166,000

TOTAL $769,618,810

22

Page 23: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

FY2015-16 Project Schedule Date Project Activity

October 2014 NVTA approves project selection criteria

January 2015 VDOT releases draft Detailed HB 599 Rating Report

January 2015 “Strawman” Draft using approved project selection criteria and results of draft Detailed HB 599 Rating Report

January 2015 VDOT to Brief NVTA on draft Detailed Rating Report

January, 2015 VDOT releases Final HB 599 Rating Report

January/February 2015

Coordination on Draft Program with JACC, TAC, PCAC

February 2015 NVTA approves Draft NVTA FY2015-16 Program for Public Hearing

March 2015 Hold Public Hearings on Draft NVTA FY2015-16 Program

April 2015 NVTA approves FY2015-16 Program

23

Page 24: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

FY2015 – FY2016 Revenue Estimates for HB 2313 in Northern VA

Adopted

FY2014

Proposed

FY2015

Projected

FY2016

Sales 232,456,223$ 228,073,196$ 232,756,820$

TOT 24,348,642$ 25,258,011$ 25,632,398$

Grantors 34,676,790$ 36,903,666$ 37,202,478$

Total 291,481,655$ 290,234,874$ 295,591,696$

70% 204,037,159$ 203,164,412$ 206,914,187$

30% 87,444,497$ 87,070,462$ 88,677,509$

FY2015 Revenue Estimates

(Accrual Basis)

24

Page 25: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

Outreach

ENGAGING THE REGION

From April 2013 to

December 2014, the Authority held over

93 public meetings with approximately

2,890 attendees.

25

Page 26: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

More Outreach

• FY15-16 Communication Plan

• Listening Sessions

• Interactive Project Maps using Google Maps

• New E-Mail Newsletter

• More Public Engagement Opportunities to Come!

26

Page 28: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

A New Era Through Regionalism

The Authority brings Northern Virginia

jurisdictions and agencies together to

identify projects and plan transportation

solutions. • We are meeting regional priorities through the HB 599

prioritization process in addition to our own prioritization

standards.

• The law requires, and the focus is on, improvements made

throughout Northern Virginia based on regional benefits and

not just jurisdictional boundaries.

• The Authority has identified the proper mix of highway

and transit projects to represent a true mode

balance.

28

Page 30: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

How You Can Get Involved

• For more please visit: www.TheNoVaAuthority.org

• Engage with your local governments (counties,

cities and towns) and attend NVTA public meetings.

• Join our e-mail list:

[email protected]

• Like us on Facebook!

30

Page 31: A New Era of Transportation Improvements€¦ · The Update TransAction is the Authority’s guide to Northern Virginia’s ... Fairfax County $ 29,915,008 $ 4,708,834 $ 2,852,110

MONICA BACKMON, EXECUTIVE DIRECTOR

[email protected]

Thank you!

31