a portfolio approach in it

Upload: emelyn-grace-chavez-carit

Post on 14-Apr-2018

221 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 A Portfolio Approach in IT

    1/35

    Source: Applegate: Corporate

    Information Strategy and

    Management, Sixth Edition

    Emelyn Grace A. ChavezMaster of Technology

    Batangas State University

  • 7/30/2019 A Portfolio Approach in IT

    2/35

    To enable a company to track the informationnecessary to maximize the value Managing the costs and risks

    Most effectively make use of all resourcesavailable

    Balance IT services and resources with demand for ITreserves and resources

    Drive higher project success rates by tracking andreporting on progress

  • 7/30/2019 A Portfolio Approach in IT

    3/35

    IT portfolio management is the application ofsystematic management to large classes ofitems managed by enterprise Information

    Technology (IT) capabilities. Examples of IT portfolios would be planned

    initiatives, projects, and ongoing IT services(such as application support).

  • 7/30/2019 A Portfolio Approach in IT

    4/35

    Despite 40 years of accumulated experience inmanaging information technology (IT) projects, theday of the big disaster on a major IT project has not

    passed. Why? An analysis of these examples and apreponderance of research over the last 10 yearssuggest three serious deficiencies that involvegeneral and IT management:

    (1) failure to assess the implementation risk ofa project at the time it is funded,

  • 7/30/2019 A Portfolio Approach in IT

    5/35

    (2) failure to consider the aggregateimplementation risk of a portfolio of projects,

    and (3) failure to recognize that different projects

    require different managerial approaches. In this chapter we examine the sources of

    implementation risk and suggest strategiesfor managing and mitigating it.

  • 7/30/2019 A Portfolio Approach in IT

    6/35

    In discussing implementation risk, we assumethat IT managers have brought appropriatemethods and tools to bear on a project.

    Implementation risk, as we define it here, iswhat remains after the application of the propermethods and tools.

    While mismanagement is another source of risk,

    it is not included in our notion of implementationrisk because it is not inherent in the nature of aproject.

  • 7/30/2019 A Portfolio Approach in IT

    7/35

    Ignoring project risk is a profound errorwith significant consequences, such as thefollowing:

    Failure to obtain anticipated benefits due toimplementation difficulties

    Higher than expected implementation costs Longer than expected implementation time

    Resulting systems whose technical performance isbelow plans and requirements

    System incompatibility with selected hardware andsoftware

  • 7/30/2019 A Portfolio Approach in IT

    8/35

    Three important project dimensions influence inherentimplementation risk:

    Project size. The larger the project in monetary terms,

    staffing levels, duration, and number of departmentsaffected, the greater the risk. Multimillion-dollar projectsobviously carry more risk than do $50,000 efforts and tend toaffect the company more if the risk is realized. Project sizerelative to the normal size of an IT development group'sprojects is also important.

  • 7/30/2019 A Portfolio Approach in IT

    9/35

    Experience with the technology. Project riskincreases when the project team and organizationare unfamiliar with the hardware, operating

    systems, database systems, and other projecttechnologies.

  • 7/30/2019 A Portfolio Approach in IT

    10/35

    Project structure. In some projects, which weterm high structure, the nature of the task fullyand clearly defines project outputs. From the

    project s beginning throughout its duration,outputs remain fixed. Inherent stablerequirements make these projects easier tomanage.

  • 7/30/2019 A Portfolio Approach in IT

    11/35

    Project Categories and Degree of Risk

  • 7/30/2019 A Portfolio Approach in IT

    12/35

    Project Categories and Degree of Risk

  • 7/30/2019 A Portfolio Approach in IT

    13/35

    Managers should not con-sider risk unalterable;instead, its presence should encourage betterapproaches to project management. Questions 5

    and 6 in the "Structure Risk Assessment" sectionare good examples of questions that could triggerchanges.

    The higher the assessment score, the greater the

    need for very senior approval. In the company thatdeveloped this questionnaire, only the executivecommittee can approve projects with very highscores.

  • 7/30/2019 A Portfolio Approach in IT

    14/35

    Managers should ask themselves thefollowing questions: 1. Are the benefits great enough to offset the

    risks? 2. Can the affected parts of the organization

    survive if the project fails?

    3. Have the planners considered appropriatealternatives?

  • 7/30/2019 A Portfolio Approach in IT

    15/35

    In addition to determining relative risk for singleprojects, a company should develop a profile ofaggregate implementation risk for its portfolio of systemsprojects.

    Different portfolio risk profiles are appropriate todifferent companies and strategies.

    For example, in an industry where IT is strategic(such as retailing or catalog sales), managers should

    be concerned if there are no high-risk projects in theproject portfolio. Such a cautious stance may opena product or service gap through which thecompetition may seize advantage.

  • 7/30/2019 A Portfolio Approach in IT

    16/35

    A portfolio loaded with high-risk projects, however,suggests that the company may be vulnerable tooperational disruptions if projects are notcompleted as planned.

    Referring back to the strategic grid discussed inearlier chapters, for "support" companies,heavy investment in high- risk projects may notbe appropriate; they should not be taking strategicgambles in the IT arena.

    Yet even these companies should have sometechnologically challenging ventures to ensurefamiliarity with leading-edge technology andmaintain staff morale and interest.

  • 7/30/2019 A Portfolio Approach in IT

    17/35

  • 7/30/2019 A Portfolio Approach in IT

    18/35

    Conventional wisdom and much of the literatureon how to manage projects suggest that there isa single right approach to project management.

    The implication of this way of thinking is thatmanagers should apply the same tools, projectmanagement methods, and organizationallinkages to all such efforts. We disagree.

  • 7/30/2019 A Portfolio Approach in IT

    19/35

    Although there may indeed be a set of general-purpose tools that can be used in managing ITimplementation (we describe some later), the

    contribution each makes to project planning andcontrol varies widely according to the project'scharacteristics.

    Further, the means of involving the user-through

    steering committees, representation on the team,or as a team leader-should also vary by projecttype; in short, there is no universally correct wayto run all projects.

  • 7/30/2019 A Portfolio Approach in IT

    20/35

    The general methods (tools) for managing projects are of fourprincipal types:

    External integration tools include organizational and othercommunication devices that link the project team's work to

    users at both managerial and lower levels. Internal integration devices, which include various personnel

    controls, ensure that the project team operates as anintegrated unit.

    Formal planning tools help structure the sequence of tasks inadvance and estimate the time, money, and technicalresources the team will need for executing them.

  • 7/30/2019 A Portfolio Approach in IT

    21/35

    Formal results-control mechanisms help managersevaluate progress and spot potential discrepanciesso that corrective action can be taken.

    Results controls have been particularly effective inproject settings with the following characteristics: 1. There is clear knowledge in advance of the desired

    results. 2. The individuals whose actions are influenced by the

    formal mechanisms can control the desired result, at leastto some extent.

    3. Results can be measured effectively.

  • 7/30/2019 A Portfolio Approach in IT

    22/35

  • 7/30/2019 A Portfolio Approach in IT

    23/35

    When low-structure/low-technology projectsare well managed, they present low-risk profles.

    Indeed, the key to operating this kind of projectlies in effective efforts to involve the users indesign, development, and implementation

    Developing substantial user support for a system

    design and keeping the users com- mitted to thatdesign are critical

  • 7/30/2019 A Portfolio Approach in IT

    24/35

    . Such projects therefore benefit from the following: 1. A user as project leader or as the number two person on the team.

    2. A user steering committee to evaluate the design periodically.

    3. Breaking the project into a sequence of small, discrete subprojects.

    4. Formal user review and approval on all key project specifications.

    5. Distributing minutes of all key design meetings to the users.

    6. Adhering, when possible, to all key subproject time schedules.Low turnover among users is important here; a consensus reachedwith a user manager's predecessor is of dubious value.

  • 7/30/2019 A Portfolio Approach in IT

    25/35

  • 7/30/2019 A Portfolio Approach in IT

    26/35

    1. Analysis and Design

    - Traditional Process begins with a comprehensiveanalysis of requirements, followed by thedocumentation of the desired capabilities of thesystem in a form that can be used by systemdevelopers to code and implement the system.

  • 7/30/2019 A Portfolio Approach in IT

    27/35

    2. Construction

    -Traditionally, construction was a highly specializedactivity that combined high levels of technological skillwith a large dose of art, experience and logic.

    -Today, system construction involves selecting

    appropriate computer equipment and then creating,buying, and adapting the computer programs neededto meet systems requirements.

    Software Development Life Cycles

  • 7/30/2019 A Portfolio Approach in IT

    28/35

    3. Implementation-Implementing a new IT system involves extensivecoordination between the user and the technologistas the transition is made from predominantly

    technical IT-driven task of construction to user-driven on-going management of the completedsystem.

    4.Operation and Maintenance- To avoid on going problems, operation andmaintenance are planned in advance, ideally duringthe early stages of requirements definition and design.

    Software Development Life Cycles

  • 7/30/2019 A Portfolio Approach in IT

    29/35

    Five Basic Characteristics1. They are iterative2. They rely on fast cycles and require

    frequent delivery of value.3. They emphasis early delivery to end users

    of functionality.4. They require skilled project staff.5. They open resist ROI.

    Adaptive Methodologies

  • 7/30/2019 A Portfolio Approach in IT

    30/35

    Examples:1. Cisco rapid, iterative prototyping2. Tektronix 20 waves project3. Extreme programming (or XP)4. Adaptive software development

    In essence, Adaptive Approach is to createsomething that works roughly as quickly as

    possible, begin to experience unexpectedeffects as soon as possible

    Adaptive Methodologies

  • 7/30/2019 A Portfolio Approach in IT

    31/35

    Adaptive Methodologies and ChangeManagement

    -Adaptive projects achieve changemanagementin part by intensely involving user

    in evaluating the outcome of each developmentiteration and deciding on the next enhancementto be introduced into system.

    -Adaptive methods are an emerging responseto outcome uncertainty in system development.

  • 7/30/2019 A Portfolio Approach in IT

    32/35

    Adaptive Methodologies and ChangeManagement

    -The essence of sound change management isto strictly control the migration of system

    features from development, through testing intoproduction with a clear understanding of thebenefits and potential for unanticipatedproblems at each stage.

  • 7/30/2019 A Portfolio Approach in IT

    33/35

    Process Consistencyand Agility in Project Management

    Three Categories of simple management tool

    1. Flow can be simple depictions of the

    process context that are intended to givedecision makers at specific points in theprocess a sense of overall businesspractice.

    2. Completeness can be a simple lists toconvey what is needs to be done, when itneeds to be done, by whom, and whether itis complete.

  • 7/30/2019 A Portfolio Approach in IT

    34/35

    Process Consistency and Agility inProject Management

    Three Categories of simple management tool

    3. Visibility to meet the peoples need to beable to review processes while they arebeing executed to get status information.

    > In addition, another category can be added:

    >Tools to ensure that project activities areauditable.

  • 7/30/2019 A Portfolio Approach in IT

    35/35

    End