A Recipe for Preparing a A Recipe for Preparing a Schedule that WorksSchedule that Works
Ulla MerzUlla Merzprepared for MPUGprepared for MPUG
phone: (303) 499 7301phone: (303) 499 7301
e-mail: [email protected]: [email protected]
1/14/00 © P2E, 2000
Input to the project
plan
•Requirements•Features/Functions•Budget•Time constraints
Draft schedule
•Tools & techniques•Company capabilities•Resources•Existing commitments
?=
Time
Requirements
Budget
NO
Baselined Schedule
YES
Recipe for Preparing a Schedule
1/14/00 © P2E, 2000
Creating a Schedule Using Creating a Schedule Using Divide and ConquerDivide and Conquer
Outline the work that needs to be Outline the work that needs to be done using a done using a Work Breakdown Work Breakdown Structure Structure ((WBSWBS))
Turning a WBS into a schedule byTurning a WBS into a schedule by– Defining task dependenciesDefining task dependencies– Estimating the duration of each taskEstimating the duration of each task– Assigning peopleAssigning people– Adding milestonesAdding milestones
1/14/00 © P2E, 2000
Six StepsSix Steps
Create a Work Breakdown Create a Work Breakdown StructureStructure
Define MilestonesDefine Milestones Define DependenciesDefine Dependencies Define ResourcesDefine Resources Estimate task effort/durationEstimate task effort/duration Make assignmentsMake assignments
1/14/00 © P2E, 2000
Create a Work Breakdown Create a Work Breakdown StructureStructure
Create a work Create a work breakdown structurebreakdown structure
Define milestonesDefine milestones Define dependenciesDefine dependencies Define resourcesDefine resources Estimate task Estimate task
effort/durationeffort/duration Make assignmentsMake assignments
1/14/00 © P2E, 2000
Define MilestonesDefine Milestones
Create a work Create a work breakdown structurebreakdown structure
Define milestonesDefine milestones Define dependenciesDefine dependencies Define resourcesDefine resources Estimate task Estimate task
effort/durationeffort/duration Make assignmentsMake assignments
1/14/00 © P2E, 2000
Define DependenciesDefine Dependencies
Create a work Create a work breakdown structurebreakdown structure
Define milestonesDefine milestones Define dependenciesDefine dependencies Define resourcesDefine resources Estimate task Estimate task
effort/durationeffort/duration Make assignmentsMake assignments
1/14/00 © P2E, 2000
Define ResourcesDefine Resources
Create a work Create a work breakdown structurebreakdown structure
Define milestonesDefine milestones Define dependenciesDefine dependencies Define resourcesDefine resources Estimate task Estimate task
effort/durationeffort/duration Make assignmentsMake assignments
1/14/00 © P2E, 2000
Estimate task Estimate task effort/durationeffort/duration
Create a work Create a work breakdown structurebreakdown structure
Define milestonesDefine milestones Define dependenciesDefine dependencies Define resourcesDefine resources Estimate task Estimate task
effort/durationeffort/duration Make assignmentsMake assignments
1/14/00 © P2E, 2000
Make AssignmentsMake Assignments
Create a work Create a work breakdown structurebreakdown structure
Define milestonesDefine milestones Define dependenciesDefine dependencies Define resourcesDefine resources Estimate task Estimate task
effort/durationeffort/duration Make assignmentsMake assignments
1/14/00 © P2E, 2000
D W/U
1/14/00 © P2E, 2000
Six StepsSix Steps
Create a Work Breakdown Create a Work Breakdown StructureStructure
Define MilestonesDefine Milestones Define DependenciesDefine Dependencies Define ResourcesDefine Resources Estimate task effort/durationEstimate task effort/duration Make assignmentsMake assignments
1/14/00 © P2E, 2000
Input to the project
plan
•Requirements•Features/Functions•Budget•Time constraints
Draft schedule
•Tools & techniques•Company capabilities•Resources•Existing commitments
?=
Time
Requirements
Budget
NO
Baselined Schedule
YES
Recipe for Preparing a Schedule
1/14/00 © P2E, 2000
Consider ConstraintsConsider Constraints
Resource constraints; resource Resource constraints; resource over-allocationover-allocation
Time constraints; deadlinesTime constraints; deadlines
1/14/00 © P2E, 2000
Remove Resource Over-Remove Resource Over-AllocationAllocation
Hire resourcesHire resources Replace resourcesReplace resources Delay tasksDelay tasks
1/14/00 © P2E, 2000
Resolve Time ConstraintsResolve Time Constraints
Overlap tasks Overlap tasks using lead timeusing lead time
Reassign Reassign resourcesresources
Shorten task Shorten task duration for tasks duration for tasks on the critical on the critical pathpath
1/14/00 © P2E, 2000
Baseline the ScheduleBaseline the Schedule