a recipe for success progressive design-build restores ... · pdf filea recipe for success...
TRANSCRIPT
![Page 1: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/1.jpg)
© 2014 HDR, all rights reserved.
A Recipe For SuccessProgressive Design-Build Restores Reliability to a Critical Pump Station
Harry Shaposka, PEKarrie Buxton
Jim SalernoBrett Burgett
Rich Atoulikian, PMP, PECal Rozario, PMP
![Page 2: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/2.jpg)
Project Background
Procurement Approach
Pre-Construction Phase
Construction/ Commissioning
![Page 3: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/3.jpg)
Project Background
![Page 4: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/4.jpg)
NEORSD Plants in Cleveland AreaEasterly 85/1,600 mgdWesterly: 70/1,800 mgdSoutherly: 125/1,100 mgd
A
![Page 5: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/5.jpg)
Southerly Wastewater Treatment Center
RAS Pump Station
![Page 6: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/6.jpg)
RAS Screw Pumps
Pump No. 1 Replaced in 2012 (but not drive unit)
Replace Pumps Nos. 2-7
![Page 7: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/7.jpg)
Demolition included existing screw pumps and deflector plates,
gear reducers, motors, soft starters, bearing lubrication systems,
trough grout and support bases
Proposed new work included screw pumps, deflector plates, gear
reducers, motors, soft starters, concrete walls, trough grout, bearing
lubrication systems and support bases
![Page 8: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/8.jpg)
Proposed new work included soft starters
Proposed new work included motors, gear reducers, couplings, support
bases and lubrication systems
![Page 9: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/9.jpg)
Proposed new work includedmotors, gear reducers, couplings,
support bases and lubrication systems
Proposed new work included raise divider walls
![Page 10: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/10.jpg)
Procurement Approach
![Page 11: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/11.jpg)
District historically used Design-Bid-Build approach Ohio law changed construction process in June 2011 Equipment replacement lends itself to Design-Build Reliability concerns made schedule a critical element
o Design-Build schedule was 22 months
o Design-Bid-Build schedule was 30 months
Procurement Approach
![Page 12: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/12.jpg)
Quals-based selection, single contract Design-Builder Design–Builder starts design Construction cost estimate ‘progressively’ developed in an ‘open book’
format Owner and Design-Builder mutually agree upon a Guaranteed
Maximum Price (GMP) at about 60% Once GMP agreed upon, the Design-Builder proceeds to construction
Note: If no acceptable GMP is reached, Owner has option to bid out construction in the typical design-bid-build format
Progressive Design-Build Approach
![Page 13: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/13.jpg)
Advantages Single point of responsibility Value based selections (vs. lowest price from bids) Early budget confirmation and ongoing budget/scope management Streamlined procurement and delivery
Result: On time, on budget with Value Added
Features & Benefits
![Page 14: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/14.jpg)
NEORSD/DB Agreed Cost of Construction Estimate
Design & Preconstruction Lump Sum
General Conditions Lump Sum
DB Fee% of Construction
Design & Preconstruction Lump Sum
General Conditions Lump Sum
DB Fee% of Construction
Contract Amount/ Guaranteed Maximum Price (GMP $4.6M)
As Proposed/Bid Negotiated Contract Amount/GMP
Screw Pumps Lump Sum
General Allowance (GA) and Specific Allowance (SA)
Progressive Design-Build Project Cost Categories
![Page 15: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/15.jpg)
Proposed Project Schedule
August 8, 2012 Issued RFPSeptember 6, 2012 Proposals dueSeptember 21, 2012 Notification to selected Design-BuilderOctober 19, 2012 Notice to Proceed for pre-construction periodJune 1, 2014 Construction complete
Total Project Budget Is $4.785M
![Page 16: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/16.jpg)
Delivery (25%) Qualifications (20%) Technical Approach (45%)
Presentation and Interview (10% if required)
Proposal Selection Criteria
![Page 17: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/17.jpg)
Two Design-Build proposals submitted Kokosing/HDR team selected as best value Kokosing/HDR Pricing Information:
o $456,000-Design and Pre-construction Services
o $260,000-General Conditions
o 6.5% fee on cost of work
o 12% Business Opportunity Participation
Proposal Selection and Award
![Page 18: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/18.jpg)
Pre-construction Phase
![Page 19: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/19.jpg)
Pre-Construction Team
Design Management, Mechanical, Process, Structural
Constructability, Cost Development
Electrical and I/C
Hazardous Materials and Existing Conditions Surveys
Vibration Analysis
![Page 20: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/20.jpg)
Operations Maintenance
Construction Engineering
Developing the Best Solution Requires Collaboration
Multiple Perspectives Are Critical
![Page 21: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/21.jpg)
Screw Pumping System
![Page 22: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/22.jpg)
MSI Mobilized to Perform the Vibration/Mechanical Analysis Quickly
Goal: Understanding root cause of gear box failuresSteps:
Background review
Equipment setup &
calibration
Torque & axial thrust
measurementTesting Analysis &
reporting
•Gearbox & foundation flexibility
•Radial Proximity Probes
•Impact•Operating Deflection Shape
![Page 23: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/23.jpg)
Vendors briefed on current issues Vendors presented
o Company history
o Product overview
o Differentiators - Unique equipment features
o Recommendations for this facility, based on their industry experience
Primary benefit of workshops – O&M stakeholders engagement and input at ALL WORKSHOPS
Comprehensive Workshops Were Held with 5 Manufacturers
![Page 24: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/24.jpg)
Gear box design Drive configuration (belt vs. direct) Soft start vs. VFDs Screw flight/torque tube design Liner, stainless steel vs. grouted Bearing type System startup/operation Coatings
Key Technical Issues Discussed at Workshops
![Page 25: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/25.jpg)
Gear box service factor – Use 2.4 Improved operating efficiencies Variable frequency drives (value added)
o Energy savings
o Improved process control
o Lower starring impact loads
o But, must consider:• Upsizing for constant torque
• Gear box lube across speed range
Workshops Provided the Foundation for Solid Decision Making
![Page 26: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/26.jpg)
Stainless steel trough liners offer many benefits Closer tolerances than grout
o Higher operating efficiency
Allows faster installationo Lower construction cost
o Shorter construction schedule
Longer service life than grout
Screw pump liner use is much more prevalent in Europe than U.S.
Workshops Also Allowed Us to be Confident in the Selection of Trough Liners
![Page 27: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/27.jpg)
Completed Design for GMP Development
Selected vendor equipment data was incorporated into 3D model
![Page 28: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/28.jpg)
3D Enabled Design to be Completed in 3 Months
![Page 29: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/29.jpg)
Owner input to 60%, when GMP is developedo Workshops critical for O&M engagement
Compressed design/construction schedule Ongoing constructability reviews Regular cost updates – budget confidence Allows added value opportunity identification
In additional, annual energy savings of $55,000/year are expected
Benefits of Progressive Design-Build During Design Phase
![Page 30: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/30.jpg)
Construction/ Commissioning
![Page 31: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/31.jpg)
Project constraints to work activities o Limited access to forebays (prior to value added improvements)
o Single screw replacement at one time
o Maintain flow rates to meet plant demands even during high flow events
o By-pass pumping contingency plan
Construction Work
![Page 32: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/32.jpg)
Construction Work/Process
Prior to screw pump replacement, forebay access work Safe removal of Existing Equipment
![Page 33: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/33.jpg)
Construction Work/Process
Removal of Existing Screw Auger (approximately 26,000 lbs.)
![Page 34: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/34.jpg)
Construction Work/Process
Screw Replace: Installation of new 96” Screw auger and stainless steel trough (250 ton Grove screw auger assembly approximately 34,000 lbs)
![Page 35: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/35.jpg)
Construction Work/Process
Screw replace: Installation of
new screw auger and
stainless steel trough
![Page 36: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/36.jpg)
Construction Work/Process
Installation of new upper bearing assembly Installation of new motor and gear box
![Page 37: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/37.jpg)
Construction Work/Process
Installation of new motor and gear box pedestal
Installation of new motor base with lower bearing grease pump
![Page 38: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/38.jpg)
Construction Work/Process
Installation of new VFD Drives
Installation of new gate actuators, setting gate limits
![Page 39: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/39.jpg)
Communication is key Collaborative effort Value added design cost Effects on operation
Lessons Learned
![Page 40: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/40.jpg)
Always communicate every change in the design Be sure each group acknowledges the change Verify that any field changes can be made amendable to the given field
conditions
Lesson Learned: Communication is Key
![Page 41: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/41.jpg)
Have the right “Decisions Makers” at the table Keep the dialog open and on topic to resolve the issue Be sure each side understands what level of detail is expected at the
60% review and the acceptance of GMP for construction
Lesson Learned: Collaborative Effort
![Page 42: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/42.jpg)
Through the valued added items, it was noted that several of the items would require additional cost to the design portion of the project budget. Given the dynamic environment of the Design-Build process, it was
noted that the Owner would be wise to include a value added design budget as well as a construction contingency for all future projects.
Lesson Learned: Value Added Design Cost
![Page 43: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/43.jpg)
Overall improved reliability More efficient system Less need for personnel during operations
Lesson Learned: Effects on Operations
![Page 44: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/44.jpg)
Sound and timely decision making…leads to a Value Added Project
Example: Added safety measures in forebays for staff, VFD drives improved efficiency and finally updating existing PLC control with flow pace
Design-Build Benefits
![Page 45: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/45.jpg)
Working as a cohesive group…Designer, Builder & Owner…shorten project delivery time through ongoing engineering reviews. o Example: Initial Construction Phase schedule will be shortened by as much as four
(4) weeks from start of the project.
Design-Build Benefits
![Page 46: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/46.jpg)
Would we do it again…Yes “Design-build is working and giving the Operations and Maintenance
Staff a more reliable second stage pumping system every day.”
Brian FlanaganSoutherly Plant OperationsUnit Process Manager
Design-Build Conclusion
![Page 47: A Recipe For Success Progressive Design-Build Restores ... · PDF fileA Recipe For Success Progressive Design-Build Restores Reliability to a Critical Pump Station Harry Shaposka,](https://reader031.vdocument.in/reader031/viewer/2022030415/5aa1952f7f8b9a80378bd944/html5/thumbnails/47.jpg)
Other contributing team members:
Questions
Gary HoffmanTom VaselGeorge SchurKevin ZebrowskiPatricia MartinakPaul CrumLarry ShimerkaBrian FlanaganBrian Anielski
Kim KennedyMike PaineDino AngelopoulosJohn AwezecMike Roble
Dennis TinklerAdam PoochDave Hays