abbreviated resettlement plan (arp)€¦ · arp . td2 sub-project: quan ngang [lokv substation and...

67
CENTRAL POWER CORPORATION ----------- *** ------------ TRANSMISSION AND DISTRIBUTION 2 PROJECT (TD2) SUB-PROJECT QUAN NGANG 110KV SUBSTATION AND BRANCH LINE ABBREVIATED RESETTLEMENT PLAN (ARP) Da Nang city, July 2012 Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized Public Disclosure Authorized

Upload: others

Post on 27-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

=~.----.--. ====,~~~=====-----",

CENTRAL POWER CORPORATION -----------* * * ------------

TRANSMISSION AND DISTRIBUTION 2 PROJECT (TD2)

SUB-PROJECT

QUAN NGANG 110KV SUBSTATION AND BRANCH LINE

ABBREVIATED RESETTLEMENT PLAN (ARP)

Da Nang city, July 2012

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

Pub

lic D

iscl

osur

e A

utho

rized

wb406484
Typewritten Text
RP317 v19
wb406484
Typewritten Text
Page 2: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

CENTRAL PO\VER CORPORATION -----------* * * ------------

TRANSMISSION AND DISTRIBUTION 2 PROJECT (TD2)

SUB-PROJECT

QUAN NGANG lJOKV SUBSTATION AND BRANCH LINE

ABBREVIATED RESETTLEMENT PLAN (ARP)

Da Nang, ~uIY, 20 J 2 CENTRAL POWER ENGINEERING CONSULTING COMPANY LIMITED

VICE DIRECTOR

Page 3: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated
Page 4: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

,

ENVCPC TD2 • Sub·Project: Quan Ngang 110kV Substation and Branch Line

TABLE OF CONTENTS

ABBREVIATION ........................................................................................................... 2 EXECUTIVE SUMMARy ............................................................................................. 3 CHAPTER 1: INTRODUCTION ................................................................................... 4

1.1 Project ownership and organization ...................................................................... 4 1.2 Objecttives and scope of project.. .......................................................................... 4

CHAPTER 2. LEGAL FRAMEWORK ........................................................................ 6 2.1 Legal basic ............................................................................................................. 6 2.2 The cut-off date .................................................................................................... 7 2.3 Resettlement and compensation policy ................................................................. 7

CHAPTER 3. PROJECT IMPACTS .............................................................................. 9 3.1 Definition project impacts: .................................................................................... 9 3.2. Entitlement policy .............................................................................................. 10

CHAPTER 4. CONSULTATION AND PARTICIPATION OF COMMUNITY ...... 12 CHAPTER 5. INSTITUTIONAL FRAMEWORK ..................................................... 16

5.1 Institutional framework ................................................................................... 16 5.2 Detail responsibility ......................................................................................... 16

CHAPTER 6. IMPLEMENTATION ARANGEMENT ............................................... 20 6.1 Schedule for implementation ........................................................................... 20 6.2 Essential actions ............................................................................................... 20 6.3 Implementation arrangement ........................................................................... 21 6.4 Staffing for ARP implementation .................................................................... 22

CHAPTER 7. COSTS AND BUDGETS ...................................................................... 23 7.1 Bubgets ................................................................................................................ 23 7.2 Basis of calculations of compensation cost.. ...................................................... 23 7.3 Compensation unit prices ........................................................ ~ ........................... 23 7.4 Total estimated cost for ARP implementation ................................................... 23

CHAPTER 8. MONITORING AND SUPERVISION ................................................. 25

APPENDICES Appendix 1. Map of project area Appendix 2. Sample record of the questionnaire during collect information Appendix 3. Pictures and Minute of community meeting Appendix 4. Policy framework for compensation, resettlement and rehabilitation

ARP Page 1

Page 5: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC

ARP

TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line

ARP

CRC

DPC

DMS

CPEC

EVNCPC

PPC

PAP

PAH

ABBREVIATION

: Abbreviated resettlement plan

: Compensation and resettlement committee

: District People's Committee

: Detailed measurement survey

: Central Power Engineering consultant Company

: Central Power Corporartion

: Provincial People's Committee

: Project Affected People

: Project Affected Household

PMB/CREB : Central Rural Electricity Project Management Board

RP : Resettlement Plan

ROW : Right of way

RCC

VND

WB

: Resettlement & Compensation Committee

: Viet Nam Dong

: World Bank

Page 2

Page 6: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang 110kV Substation and Branch Line

EXECUTIVE SUMMARY

"Quan Ngang 1l0kV substation and branch line" sub-project belongs to Transmission and Distribution II Project (TD2) which source of capital borrowed from World Bank (WB).

This sub-project is buitl to reinforce power supply and enhance safety and confidence for 110KV network, meet the demand of electricity consumption of companies in Quan Ngang Industrial zone and neighbouring area from now to the year of 2015, prevent the overload of existingllOKV network, reduce the capacity and electricity loss.

Investor: Central Power Corporation (CPC). Management: Central Rural Electric project management board (CREB). Consulting agency: Central Power engineering consulting company limited. Quan Ngang 110kV substation is built with the capacity 2x25MV A (initial

stage lx25 MY A) and 136m connecting line.

This RP is prepared base on the Policy Framework of the Project transmission and distribution 2 was approved by Viet Nam and World Bank, the current laws of the Government's Vietnam and policy OP 4.12 on involuntary resettlement of the World Bank.

The project will affect 05 households (20 people), there is no household relocated by the project. Sub-project will permanently use 6,527m2 of land (most of them are agricultural land) and temporarily use 1,914m2 of land.

The public consultant meetings was done in May 2011 at Gio Quang commune, Gio Linh district, Quang Tri province. This RP will be done by CREB and EVNCPC.

Gio Linh district people's committee and Gio Quang commune people's committee will participate in preparation and implementation this RP. Estimated cost is 353,196,749 VND (will be updated when the sub-project implementation to ensure the principle of compensation at replacement cost). After the EVNCPC and the World Bank passed, RP will be published in local and Information Center and the World Bank Development of Vietnam in Hanoi (VDIC) (scheduled for July 2012).

ARP Page 3

Page 7: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang J JOkV Substalion and Branch Line

CHAPTER 1: INTRODUCTION

1.1 Project ownership and organization Investor: Central Power Corporation (CPC). Management: Central Rural Electric project management board (CREB). Consulting agency: Central Power engineering consulting company limited. "Quan Ngang 11 OkV Substation and Branch Line" is a sub-station of "Second Transmission and Distribution" project, WB's financial source.

1.2 Objecttives and scope of project 1.2.1 Objectives

Quan Ngang 11 Ok V Substation is placed on Gio Quang commune, Gio Linh district, Quang Tri province. This is a convenient position located on the trans-national system of road, sea, rail and on the axis of East-West economic corridor connected to Lao Bao international border gate. There is also a seaport Cfra Vi¢t, as the door to the seaports of the North Central provinces and the provinces of Southern Lao.

Quan Ngang substation is expected to supply energy for:

+ The Quan Ngang industrial zone. + In the South, South-Western ofGio Linh district and a part of northern of Dong Ha town, contacted the E4 of 11 OKV line 478 of Dong Ha. + Nothern area of Gio Linh (TBA intermediary Gio Linh). + Cua Viet tourist area.

"Quan Ngang llOkV substation and branch line" project is buitl to reinforce power supply and enhance safety and confidence for 110KV network, meet the demand of electricity consumption of companies in Quan Ngang Industrial zone and neighbouring area from now to the year of 2015, prevent the overload of existingl10KV network, reduce the capacity and electricity loss. 1.2.2 Project scale:

Quan Ngang 110kV Substation is located in the Lot signed KT/3.96 along the route RD-03 - zoning map of Quan Ngang Industrial Zone. This area has been detected mine but premises have not been cleared yet. TBA Proposed substation area: limited by the coordinates A, B, C, D as follows:

Coordinate System: HN-72. Meridian axis: 1080

Name Coordinates

X y

A 1868112.734 403220.103

B 1868070.770 403228.213

C 1868138.880 403330.179

D 1868180.845 403262.070

Land area: 6.400m2. Construction area stations: 5713.8 m2. Roads outside the station: 271.82 m2. Roads in the station: 835 m2.

ARP Page 4

Page 8: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang IIOkV Substation and Branch Line

Roads in worker's house : 79.5 m2 Area of controlling house: 413.77 m2. Worker's house construction area: 226.84 m2.

Scope of the substation scale is as follows: Type Half outside, with people frequently online

Votage level 1l0/22kV. Capacity 2x25MV A. In this project 01 machine installed capacity of lx25 MVA

- Number of 110kV line: 1l0kV Distribution system for outdoor with diagram H, includes 05 compartments, (the first stage will install 03 compartments, standby 02 compartments ):

+ 02 line blocks (used for 110kV line to I IOkV substations Dong Ha and Vinh Linh. + A block for TI substation (installing in this stage) + A block for T2 substation (period after installation) + 01 block bridge segment (this phase disconnector assembly 01 segments).

- Number of 22kV line: 22kV distribution system placed in a home with a bar chart segments, including: + 06 short lines (including a stop redundancy) MBA + 01 block. + 0 I prevents voltage transformers. + 01 to prevent self-MBA. + 01 block machine fractionation.

The 1 IOkV connecting line:

Votage level

Nuber of circuit

1l0kV

02

Start point Installing one pole between No.359 and No.360 poles of existing 11 OkV line from Dong Ha to Vinh Linh

End point

Length

Conductor

Earth wire

Insulator

Tower

Foundation

Earthing

1.2.3 Discribe route of line:

busbar 11 OkV of Quan Ngang 11 Ok V substation;

0,136 km

ACSR-185/29

GW-50 and OPGW-57

Glass or porcelain.

galvanized steel tower

reinforced concrete.

radial form with galvanized steel wire

From new pole No. 359A located between No.359 and No.360 poles of existing 110kV line from Dong Ha to Vinh Linh, distance to No.359 pole about 83m. New line across Eucalyptus/acicia planned land.

ARP Page 5

Page 9: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang IIOkV Substation and Branch Line

CHAPTER 2. LEGAL FRAMEWORK

2.1 Legal basic

"Quan Ngang 110kV Substation and Branch Line" is a sub-station of "Second Transmission and Distribution" project, WB's financial source. So, the Nam Chu Lai 110kV substation sub- project have to obey:

The Policy framework for compensation, resettlement and rehabilitation of project displaced persons of the TD2 project was approved by Vietnamese Government and cleared by WB; Current law of Vietnamese Government; Policy OP 4.12 on involuntary resettlement of World Bank.

2.1.1 World Bank's policies

According to the policy OP 4.12 of World Bank on involuntary resettlement, displaced persons (DPs) will be ensured improving or maintaining the living standards as before having the project. In order to agree with operational policy of the World Bank (OP 4.12), all of DPs that are listed will be compensated for lost properties. Only persons who settle at the site affected by the project after the statistical cut-off date are not compensated.

2.1.2 Vietnamese policies The key national laws, decrees governing land acquisition, compensation and

resettlement in Vietnam consists of the following:

ARP

The Constitution of Vietnam, 1992 confirms the right of citizens to own a house and to protect the ownership of the house.

The Land Law 2003 issued on December 10th, 2003.

- Decree 197120041ND-CP issued on December 3, 2004 on compensation, support and resettlement when land is recovered by the state.

- Decree No. 69/2009/ND-CP, effective 1st October 2009; an amendment to Decree No. 197/20041ND-CP; supplementary regulations on land use planning, land prices, land acquisition, compensation, support and resettlement.

Circular 14/2009/TT-BTNMT dated 1st October 2009 providing detailed regulations on compensation, assistances, relocation and process and procedures for land acquisition, land hand-over and land lease.

Circular 57/2010/TT-BTC issued on April 16, 2010 prescribing the estimation, use and settlement of funds for compensation, support and resettlement upon recovery by the State.

- Decree 106/20051ND-CP dated on August 17, 2005, guiding the implementation of a number of articles under the Electricity Law regarding safety protection of high-voltage power grid.

- Decree 8112009/ND-CP dated on October 12, 2009, amending or supplementing a number of articles of the government's decree No. 106/205/ND-CP of August 17, 2005 which details and guide a number of

Page 6

Page 10: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-ProJect: Quan Ngang IIOkV Substation and Branch Line

artICles of the electncity law regarding the safe protection of hIgh-voltage power grid works.

Circular 03/201O/TT-BTC issued on Jan 22, 2010 guiding some articles of decree 106/2005/ND-CP and decree Sl/2009/ND-CP

Decision No. 13/2010/QD-UBND dated July 23,2010 of Quang Tri Provincial People's Committees on "Applicable compensation unit prices for house/structure and long term trees/crops; support policies and resettlement in Quang Tri province when Government recover land".

Decision No. 27/201O/QD-DBND dated Dec 31, 2010 of Quang Tri Provincial People's Committees on "issuance of land prices in the province of Quang Tri in 2011"

2.2 The cut-off date

The cut-off date of this ARP has been fixed at the day of the inventory completion of DMS (May 30th, 2011) and had proclaimed by local authorities on first community meetings .

Encroachers who settled into the proposed affected areas after the cut-off date will not be considered as DPs therefore having no entitlement to compensation and resettlement. They will be required to demolish their structures and cut the trees or harvest the crops for land clearance to the project. In case necessary, they will be forced to remove out the proposed project area. Nevertheless, they do not have to pay any fine or sanction.

2.3 Resettlement and compensation policy

Resettlement and compensation principles of the project obey the Vietnamese laws and OP 4.12 of World Bank:

(a) Acquisition of land and other assets and resettlement of people will be minimized as much as possible.

(b) All DP's residing, working, doing business or cultivating land in right of way (ROW) of transmission line (T/L), surrounding areas of tower foundation, in the service roads under the project as of the date of the baseline surveys are entitled to be provided with rehabilitation measures sufficient to assist them to improve or at least maintain their pre-project living standards, income earning capacity and production levels. Lack of legal rights to the assets lost should not bar the DP from entitlement to such rehabilitation measures.

( c) The rehabilitation measures to be provided are:

(i) Compensation at replacement cost, without deduction for depreciation or salvage materials for houses and other structures;

(ii) Agricultural land for land of equal productive capacity acceptable to the DPs or in cash at replacement cost according to DP's choice;

ARP Page 7

Page 11: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang I 10k V Substation and Branch Line

(iii) Replacement of residential/premise land of equal size acceptable to the DP or in cash at replacement cost according to DP's choice; and

(iv) Transfer and subsistence allowances.

(d) Replacement residential and agricultural land will be as nearby as possible to the land that was lost, and acceptable to the DPs.

(e) The resettlement transition period will be minimized and the rehabilitation means will be provided to the DPs prior to the expected start-up date of works in the respective Project site.

(f) Plans for acquisition of land and other assets and provision of rehabilitation measures will be carried out in consultation with the DPs, to ensure minimal disturbance. Entitlements will be provided to DPs prior to expected start-up of works at the respective project site.

(g) The previous level of community services and resources will be maintained or improved.

(h) Financial and physical resources for resettlement and rehabilitation will be made available and as where and when required.

(i) Institutional arrangements will ensure effective and timely design, planning, consultation and implementation of DP.

(j) Effective and timely supervISIOn, monitoring and evaluation of the implementation of DP will be carried out.

Compensation for crops will be paid in cash at the market rate determined by the PPC and the amount calculated based on harvesting the largest crop of last 3 years. Price compensation applied in this ARP set by the Provincial Department of Finance and the provincial project approval based on decrees of the Government.

Because the time between preparation ARP until the project can be extended at the time of project implementation, the price applicable in this record may not be fit market value or rcplacement cost. Therefore, all the unit price will be checked at the time of the compensation and can be adjusted as needed. Price will be applied compensation councils of the project decided at the time of the project under the supervISIOn of the agencies involved (CREB, independent and internal monitoring agency)

ARP Page 8

Page 12: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-ProJecl: Quan Ngang IIOkV Substation and Branch Line

CHAPTER 3. PROJECT IMPACTS

3.1 Definition project impacts:

In the framework of the sub-project, the identified impacts include: (i) The influence on n the ROW, (ii) land revocation for the substation and the pole position, (iii) property on the revoked land. Sub-project will not affect house or buildings and other structures.

ROW is defined under Decree No.106/2005/ND-CP dated on August 17, 2005, guiding the implementation of a number of articles under the Electricity Law regarding safety protection of high-voltage power grid and Decree No.8112009/ND-CP dated on October 12, 2009, amending or supplementing a number of articles of the government's decree No. 106/2005/ND-CP. Detail as follows: - For trees located in the ROW, the distance from the highest point of the tree to the vertical height of the lowest wire is in static state for not less than 3m wire. - For trees outside the ROW, the distance from any part of the tree fell down to the parts of the line any distance not less than 1 m. - For trees that are growing in a short time may cause insecurity and the tree tops if needed cuttingor pruning branches will not be economic efficiency to cutting down and planting ban.

3.1.1 Project affected people and households:

Household People Total affected people Including: 5 20 Permanently impacted Affected permanently on crops industrial land 4 16 Affected crops 5 20 Moving houses 0 0 Temporarily impacted -Affected temporarily on crops industrial land 3 12

Note: (*) Some households may have many different effects

A total of five households affected (20 peoples), affected levels are less than 20%. Households affected only crops industrial land is mainly eucalypt trees (location substation on areas already planned, the hills are planted with eucalyptus, acacia). - The project does not have any influence on ethnic minority communities (minorities) - The project does not affect any temples or other monuments

3.1.2. Affected land:

ARP Page 9

Page 13: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TDl Sub-Project: Quan Ngang 110kV Substation and Branch Line

Affected permanent Affected temporart Number Number

Area Number of of Area Number of of No. Type of land (m2

) households People (m2) households People

I. Substation Affected permanently on crops industrial

+ land 6400 02 08 0 0 0 II. Branch line

Affected permanently on crops industrial

+ land 127 02 08 1914 3 12 Toatal 6527 1914

The area of land permanently affected by the project is 6,527 m2 and should be compensated, the land area is used for construction of sub-stations and pole position. Temporarily affected land is located in 1.914m2 due ROW. Of which: permanent effects are mainly concentrated in the corridor and station area of the hamlet Quan Ngang - Gio Quang commune.

3.1.3. Affected crops/trees:

No. Eucalyptus / Acacia (tree) Commune/district

Plan from 2-5 Plan over 5 Household People year year

I. Substation 1.890 1.087 2 II. Branch line 277 230 3

Total 2.167 1.317 5

All affected area is eucalypt/acacia woodland was planning to build industrial zone.

3.2. Entitlement policy According to survey results of CPEC and characteristics project as described above, according to the policy framework (see matrix rights), the effects are classified as follows:

Type 1: Temporary Withdrawal of productive land in ROW

Type 6: Withdrawal of land permanently for pole foundations, substation and road construction, etc ..

ARP Page 10

08 12 20

Page 14: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC

Type

1

6

ARP

TD2 Sub-Project: Quan Ngang IIOkV Substation and Branch Line

Entitlement Cash compensation for affected trees at the replacement cost plus cost for cutting trees, crops at market price. Number of crop patterns to be compensated based on the time oftemporarily acquired of land. - No compensation for land

- Rehabilitate land after the project construction. For DP losing productive land: a. Land loss less than 20% of their total landholdings - Cash compensation for the lost area if the remaining plot is still economically viable. - Cash compensation for the whole impacted plot if the remaining plot is not economically viable. - Cash compensation for properties associated with land • b. Land loss equal or more than 20% of their total landholdings: DP can opt for the followings: i)"Land for land" with the same area and productive of impacted area if the remaining plots are still economic viable and for the whole impacted plots if the remaining plots are not economic viable. ii) Cash for land at the replacement cost.

- Trees to be compensated by replacement cost. - Support recovery.

Page 11

Page 15: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang 110kV Substation and Branch Line

CHAPTER 4. CONSULTATION AND PARTICIPATION OF COMMUNITY

4.1 Procedure, order and content of public consultation

During project preparation (2011) has been carried out the following activities: - Activity 1: CPEC provides information and discuss with local authorities about the project (route direction and incidence); - Activity 2: CPEC do surveys and statistics about the impact of this project and the affected households; - Activity 3: CPEC contact the affected households;

When the investigation is completed, CPEC will co-ordinate with CREB, officials at district, commune and village (where relate to the project) to organize meetings with households that their assets affected by the project.

Content and purpose of community meeting:

+ In the meeting, CPEC staffs present the contents: A summary of the draft RP (Resettlement compensation), map field, figures, tables and other supporting documents. + CPEC staff announce the purpose of the project, present the impact of the project on land and crops, introduce the principles and compensation policies, advise people not to build houses, new structures in the corridor. The affected households are consulted about compensation policy and the compensation value. All questions asked by the affected households are answered. The interest / request of the affected households are recorded. - Consultation with those affected to minimize conflicts arising in the course of the project, avoid delays project implementation schedule. - Participants: Representatives of the people invited to attend the consultation meeting, including representatives of affected households, government representatives, the relevant agencies and sectors, non-government organizations (The Women's Association, the the War Veterans, the Farmer association ... ) and local electricity bodies.

- Activity 4: Continue to receive feedback from the affected households. - Activity 5: Promulgate information.

Investment decision, the design of total estimated cost, the design of construction

drawing will be approved only after there is appropriate adjustment of the location,

design, capacity and / or technology project to meet the requirements of environmental

protection and resettlement. In order to meet the requirements of OP4.0 1 about

information declaration, CREB will:

ARP

• Provide the Vietnamese version of the report RP, EMP and the summary of

project for the People's Committees of districts and communes in the project

area.

Page 12

Page 16: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang J JO'fV Substation and Branch Line

• Post Up the information of project on the major local newspaper several times

for a period of 2 months. EMP, RP and project summary will be posted up

within two months at the following places: (1) The People's Committee of

districts, and (2) People's Committee of communes I towns.

• The ARP in English and Vietnamese will be sent to the Vietnam Development

Information Center (VDIC) at 63 Ly Thai To - Hanoi in order that non­

governmental organizations and the public can access. ARP report in English

will be sent to the W orId Bank to be posted on the World Bank InfoShop.

4.2 Results of public consultation:

Consultation with those affected households to minimize conflicts arising in the course of the project, avoid delaying on the implementation schedule of the project. The consultative meetings with the affected households in Gio Quang commune, Gio Linh district, Quang Tri province was made in May 2011.

ARP Page 13

Page 17: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang II Ok V Substation and Branch Line

Table 4.1: Summary of the contents of the public consultation meetings

Location Number of Representatives of local authorities and households Summary of Issues discussed/raised where Participants, to participate

Consultation Date state cleary

took place how many , women

participated Nguy~n Huu Chairman of commune people's Chinh committee Nguy~n Bang - Everyone agreed to join the project and

Chairman of Fatherland Front Thao hope to soon deploy the project.

Hoang Van Nghe Representative of Farmer's

- Recommend ensure hygiene Union

Tran Thi H6ng Representative of Women's construction, not disorderly, without Union

Tran Hfru Buqc Representative of veterans' causing environmental pollution, traffic

Gio Quang organization safety, transport materials limited at nigh commune, Tran Bang Cam Land officials

- Requesting compensation implemented Gio Linh May 20, 7 man va 01 Hoang Blnh Lqi Representatives of 0 1 households distrist, 2011 woman Tran Xmln Phap are affected prior to construction to avoid future Quang Tri

complaints. province

- Unity in cash compensation and unit

prices according to current regulations.

- Agree implementation of regulations on

safety corridor grid.

- Unified electrical safety measures.

ARP Page 14

Page 18: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

/:./{VCPC TD2 Sub-Projec/.' Quan Ngang 1 lOkV Substation and Branch Line

4.3. Information promilgation

After the CPC and the World Bank passed, ARP of the project will announced in local (Gio Quang commune, Gio Linh district); at Vietnam Development Information Center (VDIC) in Hanoi and at Info shop of the World Bank in Washington. (scheduled for Aug 2012).

ARP Page 15

Page 19: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang J lOkV Substation and Branch Line

-CHAPTER 5. INSTITUTIONAL FRAMEWORK

5.1 Institutional framework - The overall responsibility for enforcement of the Policy Framework and for planning and implementing this ARP's rests with CREB, EVNCPC belongs to EVN and the People's Committee of Quang Tri province and their relevant Institutions (i.e.CRCs, provincial DOF, DOC, DOl, DONRE, etc.).

CREB and Consultant are responsible for carrying out census, socio­economic surveys and inventories and preparing ARP and for the day-to- day implementation thereof within their respective jurisdiction.

- The related District and Commune People's Committees will participate in the ARP preparation and implementation.

These administrative units will also ensure the active and effective participation of the DPs in the ARP preparation and implementation. In order to have ARP acceptable to the WB and to implement ARP smoothly, PMB is responsible for (i) hiring qualified consultants to prepare ARP; (ii) appointing qualified social safeguard staff at PMB.

5.2 Detail responsibility

Central Power Corporartion (EVNCPC)

EVNCPC is the owner of the project and is responsible for managmg and

organizing of investigation, design, budget arrangement, funding and supervision for

ARP implementation.

Central Rural Electricity Project Management Board CREB)

CREB (PMB) is responsible for the implementation of ARP' including impact survey, delivery of entitlements, carry out for the restoration program, redressal of complaints, internal monitoring. Main tasks of PMB will be:

- Establish masterplan, management and supervision of ARP implementation.

- Responsible for organizing information dissemination/disclosure, public meetings: disclosing ARP to all relevant local authorities, RCC, disseminating DMS and Entitlement forms to all DPs.

- Organizing/training for survey team to carry out the Detail Measurement Survey (DMS) and ARP implementation for all levels of People's Committees and relevant agencies.

- Supervision/monitor for compensation payment, land acquisition and land clearance.

ARP Page 16

Page 20: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang 1101fV Substation and Branch Line

~ Report the ARP implementation progress and land clearance work to WB, EVN and EVNCPC

Provincial People's Committee (PPC)

~ PPC is responsible for clearly direct! demarcate the responsibilities for their relevant institutions in implementing ARP. - Approve the compensation unit costs, allowances and establishing compensation committees at all different administrative levels and approve lands for compensation. - Redress complaints and grievances. Related Provincial Departments The Provincial DOF is responsible for studying and issuing unit prices of compensation and submitting to PPC for approval. Right from the initial stage of the ARP implementation, the DOF will closely co-ordinate with DOC, DONRE, District People's Committee and independent external monitoring agency in order to evaluate the applicable unit prices in ARP and propose to PPC for approval and ensuring the compensation unit prices to be at the replacement value at the time of compensation payment.

District People's Committee

The District People's Committee is responsible for guiding the compensation and resettlement activities in their respective district areas:

Direct the relevant institutions for carrying out impact survey; public consultation, information dissemination on the resettlement policy and ARP implementation. - Establishment of District CRe. - Responsible for settling complaints ofDPs at district levels. District Compensation

Resettlement Committee (CRC) The District CRC is principal institutions responsible for the implementation of ARP in their respective district areas. The District CRC recruit experienced personnel for gathering of base-line information and inventory. The District CRC is responsible for: - Organizing the survey team to carry out Detailed Measurement Survey (DMS) for affected houses and assets; finalizing DMS and Entitlement forms for each DP.

Checking the unit prices of compensation as applied in ARP, suggesting for the adjustment of the unit prices in conformation with market prices/replacement costs (if required).

In co-ordination with PMB, organizing the meetings with DPs, commune, disseminate the RIB, DMS and entitlement forms to DPs (if any). - Preparing the detailed implementation plan (quarterly, semi-annual, annual plans) and the together with PMB pay entitlements to DPs in a timely manner. ~ Settling the complaints and grievances of DPs, solving any difficulties during the implementation period.

ARP Page 17

Page 21: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang 110kV Substation and Branch Line

The District CRC will consist of the following representatives: - Vice Chairmen of the District People's Committee - Department of Finance - Department Natural Resources and Environment - Department of Industry - PMB - Affected commune - DPs

Commune People's Committee People's Committee of commune will be responsible for: - Contributing to census and inventory surveys.

In co-ordination with District CRC for public meetings (if any), information dissemination, compensation/allowance payment to DPs. - Transferring all feedback by DPs to District CRC and settle the complaints at the communal level.

Displaced person (DPs) DPs are ready with their necessary ARP related papers i.e. LURC, ownership of other assets.

DPs are responsible for carefully checking on their lost assets and respective entitlements and clear land in a timely manner once DPs receive full entitlements

Independent External monitoring agency

Monitor and evaluate the implementation of RP for the entire project. Independent external monitoring agency will submit independent report any routine monitoring of the implementation process of resettlement and compensation proposed solving the problem is identified for the CREB and the W orId Bank.

ARP Page 18

Page 22: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang I JOkV Substalion and Branch Line

Figure 5.1 - ARP implementation organization chart

EVN

EVNCPC

CREB

ARP

Province People's

Committee

District People's

Committee

Commune People's

Committee

DPs

District Compensation

Committee

Page 19

Page 23: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang 11 OkV Substation and Branch Line

CHAPTER 6. IMPLEMENTATION ARANGEMENT

6.1 Schedule for implementation

6.1.1 Announcement for DPs All DPs shall be thoroughly infonned about the rights and policies of ARP including eligibility, entitlement policy, modes and rates of compensation, schedules and complaint and grievances rights.

Public announcement tasks shall be implemented immediately after GOV and WB approval of project is obtained.

6.1.2 Compensation deadlines: Compensation payment for land at least five months before land clearance, compensation for trees and crops and all allowances will be paid at least 01 month before land acquisition date.

6.2 Essential actions

Action 1:

ARP

Just after the award of capital borrows convention of WB, PMB will select and contract a qualified agency for independent external monitoring.

Note: In time, district CRC are already exist and review issues of this project.

Action 2:

CRC carries out the DMS and inventory of the affected assets (on the basis of the surveys for this ARP) and together with the independent monitoring agency and other related agencies, carry out the evaluation for the applicable unit costs in ARP and propose to PPC for amendment of the applicable unit prices in ARP, if necessary, to ensure that DP is compensated at replacement costs at the time of ARP implementation.

Action 3

Immediately after the completion of the DMS and inventory survey, CRC will inspect and define the official number of DPs, impacted properties and total compensation amount for DPs.

Action 4

CRC will officially announce the policy, schedule of the ARP to DPs at public meetings including issues related to compensation, resettlement and land clearance.

Action 5

Compensation payment and assistance delivery to DPs . . Action 6

During the project implementation, CREB and Independent External Monitoring Agency will supervise/monitor all activities of ARP implementation and rehabilitation program.

Page 20

Page 24: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang 1 JOkV Substation and Branch Line

6.3 Implementation arrangement

Progress of implementation of compensation and resettlement will be built to fit

this ARP report, which will address the implementation of the clearance, cleaning and

organizing corridor construction.

The implementation must be conducted in a planned way synchronization

between the compensation and resettlement and the construction works. The payment

of compensation to be completed before construction of the work items of the project

The proposed ARP implementation schedule is as follows:

* Schedule for CREB and CRC:

1. Establishment of Project CRC Already exists

(Quan Ngang

Industrial Area

project

management board)

2. Review and approval of ARP by EVNCPC/CREB 812012

3. Review and clear of ARP by the WB 8/2012

4. Negotiation (GOV and WB) 7/2012

5. Effectiveness 8/2012

6. Commencement of public information 8/2012

7. Commencement offield works (DMS) 8/2012

8. Commencement of payment of compensation 9/2012

Implementation progress has already been discussed above between Consulting and PMB, taking into consideration the volume of the works of the project, the number of communes in each district involved, appropriate forces personnel and the ability to implement parallel activities.

All RP activities must be completed perfection before a Bank issued no objection in writing sub-projects. Any change in RP after the Bank must be through a representative office in Hanoi Bank for consideration prior to implementation.

ARP Page 21

Page 25: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang I IOkV Substation and Branch Line

6.4 Staffing for ARP implementation

6.4.1 Proposed staffing for ARP implementation Staffing for the ARP implementation is proposed in the following table.

Number of Total No. Institutions staff Working time

1 CREB 1 0.5 month

Council compensation of the Ix4

0.5 month 2

project

3 Province's CRC 1 x 1 0.5 month

4 District's CRC Ix2 0.5 month

5 CPC Ix4 1 month

6 CPEC 2 5 months

Notes: - CREB has been established - CRC of the district and province were established

ARP Page 22

Page 26: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang I JOkV Substation and Branch Line

CHAPTER 7. COSTS AND BUDGETS

7.1 Bubgets Budget for ARP implementation will be the counterpart funds: EVN/PMB. PMB will combine with CRC to pay compensation cost for all DPs based on

decision of Provincial People's Committee.

7.2 Basis of calculations of compensation cost Compensation cost estimate for temporary and permanently impacted house,

structure, agricultural land, pond, trees and crops based on: - Decree No. 1 97/20041ND-CP dated Dec. 3rd, 2004. - Decisions for unit costs of compensation of Quang Tri Provincial people's Committee.

+ Decision No. 13/201O/QD-UBND dated 23/7/2010 of Quang Tri Provincial People's Committees on "Applicable compensation unit prices for house/structure and long term trees/crops; support policies and resettlement in Quang Tri province when Government recover land"

+ Decision No. 27/2010/QD-UBND dated 31112/2010 of Quang Tri Provincial People's Committees on "issuance of land prices in the province of Quang Tri in 2011"

- The survey examines the replacement cost and market price for land, trees made by CPEC in May 2011.

7.3 Compensation unit prices

Decisions for unit costs of compensation of Quang Tri Provincial People's

Committee are applicable for this subproject.

To ensure the compensation unit price applied is replacement price, during the surveys, CPEC has made investigations unit in Quang Tri province and compare them with the unit prices approved by PPC. Price compensation applied in this report equivalent market value in the project area. It should be noted that unit prices in RP used only for estimation purposes (during the preparation of this ARP). At the time of execution RP, compensation unit price will be updated to ensure that people affected will be compensated at replacement cost for their losses. The reserve will be used for the price difference.

7.4 Total estimated cost for ARP implementation The total estimated cost for ARP implementation is 353,196,749 VND. This

cost includes the cost of compensation and the implementation costs of compensation. Calculate the cost of compensation activities is presented below.

ARP Page 23

Page 27: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang 11 Ok V Substation and Branch Line

Table 7.1. Cost of compensation

Unit Amount

No. Components Unit price Quantity (VND)

(VND) I Land 137,067,000

Plantation of industrial crops m2 21,000 6,527 137,067,000

II Trees 130,860,000 Eucalyptus

+ From 2-5 year tree 30,000 2,167 65,010,000

+ Over 5 year tree 50,000 1,317 65,850,000 Sum~ort for conversion of

III land use 32,155,200 Limited ability to use land for perennial crops m2 16,800 1,914 32,155,200 Total (1+11) 300,082,200

Table 7.2 Total cost of ARP implementation

No. Components Describing Amount (VND)

A Cost of compensation Table 7.1 300,082,200

B Cost for implementation 2%A 6,001,644

C Contingency for slippage 5% x (A+B) 15,004,110

D Contingency (*) lO% x (A+B+C) 32,108,795

Total 353,196,749

(*) According to experience , often with many changes ansmg during project implementation. So take backup rate of 10%

ARP Page 24

Page 28: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang 110kV Subslalion and Branch Line

CHAPTER 8. MONITORING AND SUPERVISION

The implementation of ARP shall be constantly supervised and monitored by CREB in coordination with local Peoples' Committee.

Internal supervision and monitoring include the following activities Monitoring the population and socio-economic surveys of DP and the

inventory of DP assets, status, occupation and living conditions and supervising the implementation of compensation, resettlement and rehabilitation for the DP in the terms agreed by the DPs.

Monitoring whether the implementation of resettlement and compensation tasks are carried out as provided in this ARP.

Monitoring the timely and sufficient deployment of resettlement and compensation funds for this ARP.

Investigate and fairly assess each case of complaint and grievance.

Internal monitoring agencies will prepare a quarterly report detailing the progress of ARP implementation. Such a report should be made available to appropriate GOV authorities, WB and external monitoring agencies.

Resettlement staff of this sub·project is responsible for updating information based on several main activities:

Table 8.1 - Some activities for monitoring and internal evaluation

. No. Actions on RP

(i) Announce to people and local government about this project

~-···-li-T-h-e-I-o-ss-e-s-i-nv-· e-n-t-o-ry~to-t-a~l ~.-.-~ ....... .

2 IInvestigate replacement cost·

Frepare document RP

Fapproved

I·EVN/CPC

I-Quang Tri's PPC

ARP Page 25

Page 29: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang 1 10k V Substalion and Branch Line

~l~-WB

~, l~diSc10se ·-·-·1-;;~j~ct areas:

-~~l~;;ovincelDistrict Electricity Company. ···.····T----····· ·········~~-·~----+---+---l--~····-····l

1- VDIC/lnfoshop . ·······-···T··-·~······

7. ICounting and detail measunng .. -..... ---~-~---~-+---r---+--------i

8. ITo calculate compensation (for companson with

iRP)

. ··~~r~~~·~~specific plans for lpensl'ltL~ ··~~~f~~-~~~rove the comp···e·····n····s··a·· .. t··i·o···n·--p-Ia-n--------t----+---'+----4

! .. ·---····-·····T-····--.. · .. ··

11.IDisclosure of compensation

···-~;]A~~~~ment and approval (i .. f .. ·-a--ny-)-------r---+---+-----l i

13. !Payment of compensation (including 11pil~tp<::

Icompared to RP - for example, the DPs, the lldget Ithe impacts ... )

. -----------+----+----r-----~ 14. mal monitoring

15 .IExternal monitoring

--l~, F~;~on implementati~,~n_p_l_an .................. ~ _____ ..!.__-..!. __ --!.. ___ __I

* The implementation of resettlement plan independent monitoring of this sub­project can be combined with other sub-projects of TD2 of the Central Power Corporation. The scope of work, method of implementation and other content will be specify the terms of reference of this work and guided by Central Power Corporation and approved by WB.

ARP Page 26

Page 30: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang 110kV Substation and Branch Line

APPENDICES Appendix 1. Map of project area Appendix 2. Sample record of the questionnaire during collect information Appendix 3. Pictures and Minute of community meeting Appendix 4. Policy framework for compensation, resettlement and rehabilitation

ARP Page 27

Page 31: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

AppndiJ: I. Map or proje(C area

'ill ~ Quo~ __ ,,,,",V __ -,_u...

W. __ u,.I_

"""" "", . """'­."~

I -- I .­.-

Page 32: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang I IOkV Substation and Branch Line

Appendix 2: Sample record of the questionnaire during collect information

QUESTIONAlRE TO SETTING RP, EMP REPORTS SUB-PROJECT: DOC SOl KY HA 11 OKV LINE NO.2

Full name: .......................................... . Address: ............................................ . Commune: .......................................... . District: ............................................. . Province: .......................................... ..

1. Household: No Name Relation A~e People Education~ Job

Male Female Adult 1 2 3 4 5 Under 16 years old 1 2 3 4 5 . Total peoples in household: .... = Adult: ......... + Under 16 years old: ...... ..

Income

* Relationship I.jpeholder: D I.Husband/WifeU 2. FatherlMother 3. ChildD 4. NephewlNiecO 5. Grandfather/Grandmoth{] 6.0therU

* Education: DBa Illiterate Readinglwritin Not yet attending scho ElementarU Primary Secondary

* Occupation: Officer Retiring Handicraft Farming Aquaculture

Trade Housewifely Learning Unemployed Other

* Monthly average income of household: ................... ...... VND/month * Affected: Perennial:

ARP Page 29

Page 33: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang 110kV Substation and Branch Line

Type ... Quantity (trees) Type Quantity (trees) Dieu Banana Coffee lackfruit tree Graphjuice Areca Eucalyptus Mango Coconut ...

Annual: Type Quantity (m2

) Type Quantity (m") Rice Manioc Maie . Vegetable Potato Peanut ... .... .. . . ...

House Level house State house Affected

Using For rent Levell Level 2 Level 3 Level 4 Temporary

Other: Type Material Affected WC Pigpen Cistern Wall Tomb Other

ARP Page 30

Page 34: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

= ..... " b • Qoooo .",_I/OIY'! __ ..,., _ J_

Appendix 3. Pictures aDd Minute of commUDlty IlltdiD&;

Page 35: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2

ARP

Sub-Project: Quan Ngang 1 JOkV Substation and Branch Line

((:N:; E.~' x.ll:JQi un) NI.:nl, .... v.rt,r r<oVrI n~~ 1~1. - Til dl;) - Upb pEinl1l: .-•• ---,.-.-,.~ 11= ~-----...

/I. " ,. .,,,. rui,on l. ,', ~p L'(~ H~ ~. ,..I..~~~ .:l .. I'i'IMt :::'..1.

HI f:.N Ul\.N THAM VAN CONG D6NG rio .h.I..: h'l:h,',I, <1'1,:", .II!J llil .... ".111'11,,·,·.·: lI.'il !~I~1J qUlitr /(J nt6J l~lIIbg: k:i.J.~"J4M.:'JJI'JN)J rr~ rliin .lVt·

• • .r rlri~rr,ji:j .(oWN oh!:)

"'),~·lilt"'H..f J' ut'!l: .... ~,),~,..,:j rrlrri1rh r~ fl'I .. • .1'1/011" , ... .:1"., ql<: ... G).J..t,JfU) ... Jm~IJ,,, .. ~" ~'fJ};,~ .....

,~'"

(1111'1;: ~'v:.""~l:",,,,(;',C.t! ........ , ............ .. - (111~! ..

- {1111.'

- {III}! ..

l "~~~i ".. ,II

l,':.. .. ",(. '",,·, •.. l"'II .. ~:. I' h:J"~.. . l·I~.! " ( r:,

Cillill;: \'1,1: ...... ,.~; ... ;tfP:n.!· ...... _ .. _ .......... . (1'11(: ~'I.,1: ••••. ,ll.7.:.,,~'llla ..... _ ............. . Cln'I(: \'I.,1:" ... f.i: ..... ~ ... e ... : ..... _ .. , ......... ..

.' • {IIII:'. CllI·''; \' I): ••... , ."."., ..................... " ............ ..

- {III~~. ('lrir(: \.1,1: ••• ".,,_ ..................................... .

... - ~1'~ t1~iA h~. :l!;in I.hnl!\.: i~"I""lh,;io); I I'll It,(: do,.t bt IIl!.lID-i ,,111. ~I:: ~1!I.1t1:.lli= .. _" ..... (h.9:~

II.Ni)l. dun I! Ih:.tm 't:il:l!

I. l\'(li \JUIlIJ: ('U(I(' 119':J1:

• !'ti1~'1 (1IIn~lllI.f .i.r: (I.~; 111l1l:~1I 1'.1, IIII~ 11"lI~I';:(~ Uinh .... i ~r.i 111JI..m.i luytm ..• )

· ('lrmh ~~.d~ ';~;n !roll 1,"li •• 11I1h l'Ir (Ri'l. chinn ~Ao:b.,~ mlil 1rtM:iT11:I. < 1I:.j'o.{] I) , (:llinh ~jxh!"'U.li wn \'.1 ":lIil..:hinll plm VI~I :'1:,1'11 11';)":1 \'~'1I r'~;'IIIYI.;11.k ~t-.":: .hi&u;!Ilt (EMDrt.

• MI,I;:' li('u 1:1111 Ri'. n.II'. fi~.1 nJ' tn-:"IIC:':'tc 1.1 I~,y 'i k,i!i~ coo 1lfl:.I,&i'I'i ~ri~" :rll1ftq ','a ~ .:J.:\n.!;. II" o,;lI~1 (',.:I.e ~~liIi F~';;'IP f:l)!~lIl:'11111~11 ~ ,:'11; ~1{111':' ~~ ';1,(1; d6i\o{r1 ngum bjtinh buxmg bbi oJlr :'111 ,,:'1 111,1' ·.+n hI,' !.;I·t,j r~lI"I: '.\·Ij ~k.J; i~ nl1.h 11 b6n,!: h$ hmt mn'l'c kh.t: 1:11 :;llIh :tl1r~ ~,j i.llt,jn

- I }i~' :. b~ill I:U:I 111:1(1'" d.in ~~: r'J:::ry~", 1.'I\I1lJ; i.li d,'i. biii t)nlbn;s~'l t.ti dinb cU'.

· Lh' ~ ~ii~!n ':u .. n~IfI;11 d:u .. Ii~·n nhl'lIIl t'l$'III'r~ dh) 1k;C ,'d~ll SJ~.

Page 32

Page 36: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

TD2 ENVCPC Sub-Project. Quan Ngang IIOkV Substation and Branch Line

•. "". ~ .... ""4,"' .... ,. ..... ,,"''' ........ ",,,, "!'" , '111:,1 ell .. " ... ~ ....... " ..... __ ............ ,,',,<IV. ~"""!' •• ,_, .. .-~ •• " •• , ••••

.. 11m .. yin clmlrrlin~ yb K6 ~ 4J~n boi bi4 dial! '~Il mi. K~ Iwych ,lllw[ .tit.. dii • • ~~ thU ... Ji lMDP (neu EO)

Of Y ki~ nguDi dAn:Qtll k.hi t)(m "'j tv rin tlunli vina,'flr,: 1r.::4':r~ ~:r.' nlllhrrs h'k: ~'1I1,: tin. ';;1,Jr

ma dv 6n .:Md ~ nwi trub:n.g sinh hoq1, * tJ.'q,l «'"~ !io.inh b.!, ~XJ. :"i:l lu}i !"i mill

I"~ ~ _Ji_~ . J r 'I '-: } •

· ··,,·~(t, ..... ;..: •. : . .In::I(4! .. ,~ •• 4.h1'#I' ~'q,.~.i.!. k' .... ·· " l'I'ir . 1,.; ............... .

i .. ~ ....... ,,, ................... - ............... ' .... ,., , '~' t * ft. j •• " , , ... " .,.. ....... ""'. • ... .. .... .. • •• •• j

• 1" , 'II' I 4 :0:" ~ 11 ........ " " ~ _ ......... ". "'" .. * ..... "', ~ ~ ... , , J I ... ill II (0" ....... ' ••• ~ .................. "- ••

bl V kl~n 11Q.!JOi &In.lilll kl'IIi Don 'Ii lU """ I2nm ,in ci,ns do!aIIS ~'thimg t;jt" .JOnr::. J.:i.:!.trl ltij·,l.: ('ColI !hi my m) gfty ff.l Wj _ on I):) mihn ~ dill ~i. nln. t"~'fI!: Itir.h. L,:iy ' .. 3 hoo m3.u phU di ..11)1 ~ didb r.':u: ,'Ii cJ.: bi!:a pb.'Jp ~n' lh;';u.

-::tl;.;:I .. ~.:5l ..• -~~ ""';~'~'£:'l"·r··J/:r:.·,!fx. :~I'~I ~ .:(~' . "";1 .IN ;( . •. '~+J ., n,.~~ ... ,(.t~ ·id-~::..~~·/!:.~~~.·J?¥·.·tf+:":· ''1NJ~~ .l'{ .. J-i .. "l-"'~'~"l' '~:~'i~' ..... ·G-t·~,. -".~-;'"~l. :eIf;.~- ... : .. . -. .•. ...... ............. ..... . ........ ..

1'."'.l"., •• ~, •• , .... ~ .. ...- ......... -... , •.• ·.,'.fa~t'.:'~; ~ •• ~ ....... ,. ... ,. •• _ •• , ....... ~.. • ••••• ,,~. ~,

• .""" , ~ ~ •• ,. i .. i~, S .. , ••. w .. ,., .. II' ". ""' ... ' •• ' ......... ,.. ~ ~ • "" ... '. ;~ if • t" , , I ~ I -j ~ •• ~,,, ... _ ...... ~ ~ ~ '" ~ • "" '" ., • " , •• •• • ••• O'

...... * ...... ,. ... " ... '~ ••• ,.;~ .. "i."' .... .,. .......... ·-· .... • ..... ••• .... ·"'1'~-1."'j;!*!.4"""'~.~ •• " .•••••• ' ,. ,.~ •• ~~,. .. "'~ •••

j ••• 0;" Oi .. _111"" "' ~ '" .... "' •• '01" ... .." ..... OR" •• , .•• t- • • j ij ~ • ,,' ., • '" w. ..... "" .......... ,. .. "',.,- ""- ... " ....... " " ) • • ~ .. , •••• ~ ~, •• - , ..

~'··~~'fl"" ••• ,. •• ', ........ ~"" ..... ,.' ... "" .... · ........ ~t.,.tf f'~.' ........ , .. ~ ..• 'w~......... ~ .~.".~~~~".~_ .. .

cl C~ t-w> bt MIl ~ ~n,J:: f ci(l hl:mliihl'.rc.rl~ bU litH- sall ~Ii;" · ~ biJ't*ts 1i~n m(ll.:

• Hlnb r.hl~f(: dt! d6i &it (dlK vQi cic [.,al'llit hi:'" d~m dung Jb. ';rl~h

• K.k hr,Tp ~n bUt billi ~L 'ri bbg ~n. bo(It: \* 'If; -c»' olli 'Ij~ n'htln@: hi)- ca) nh!'1 .;., 00,..., .rlnh ~ htmh l.i1.t\: h .. l}·~n ,J1iI h:':t;.IlI dt.!t'L. U('II kj' Ihl,l)l d10 pmptbl $it .dvnlt -<:;:1.(: tt.tb:J pblp lII1 ~ !.hal)' d'Kl 0,;:;',;: b..;:n ph/lf! ...:Ii d.;_" di diU~i·ll tlll.~' J.:hl'lns'?

ARP

Co G). KhtinS 0 ~ 1:.hfu1.g, vi s;m?

1:l5

Page 33

Page 37: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

TD2 ENVCPC Sub.Project: Quan Ngang llOkV Substation and Branch Line

c.' N~:Ii I,lln \';' (,',ng 1.1~~'UI!!: ~r(~ \·O~~. dy. ~ co~. ~ .!: t lho~l ~. oon$ tOe ~i'm lJW2u cae ttie ~I(,U Lm:: rn ll1.n d~r an I dl' ¥I~(: dDfm dpng "'" lib, ,;In pMl"U ~I,., } n.Iw!:

• \' ~~'~",L' I D'~.. Kho.l; ____ . . . I 5' d~ .. Y

fiJlra;: hi~1l I~'t~ qU) u'illit k~m ki: • .dhi b4l" ,iM pMng mJI ~ ~A l~li I ~ 1,1jnh Clr /'

f ....

s~u 1-;!'.:I"'1;I::. fhi '1.l;HI'."""

~ ~ .•• ".", ......... ~ .......... ,., ttl •• il .. "' .... "', ~ ~ ..... ~ ..... ' •• ~ '" ,i ; .• ~""' .... ,,. ...... _ ... "' ~ ~ ~. y • ~ ..

\. 1'111.1: !.h.e ;in 00 .d~nlJ i' ctJllrl :gi.a dl{ tm:

V ki~n . D~DrI K:hrkl~i f' .ij V _.-_.

" "'",~R-",,'~*,·" •• ~rr .",' .... , .. _¥ .......... ,~, "~~~.-~."' .. ~ .......... ,,.,J.* .. "._.

··,~····~·'.'i" .' ...... " ........ "" ........ , .~, .............. -.. ~.". ,~'" ..... "'., ... ", ...... .

•• ··"""i'".io, .. ~ •••• • __ 4 .. '".. !, ••• ~ •• ""' .... ""."' •• ~ ,;{_~ •••• ~"" •• "'''' ....

• 'rtl:llHl ... ~m ti,ln;ltol'JI11Y1l ~I:' .. a· hOI,l~h "l,*,rl IY mrli trulml C.;J\U) a( Thmll vii: "lIng 1,".} nhlnlg. ~ .... ;.ng lOCh. CIfC .. ~ Inlii trutmg (11iCIi I.nJXrng t:p' ~.ld. 11I,i. rt.'II~lj II\I"~ sinh [Iii'Ii, IIII~"" liN?i'rn~ '~~1 I~. IIUY.hJ thong. I/M bo:o \'a sinh :tK:1# cQllg ,It'iII l! . I

ARP Page 34

Page 38: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 .

Sub-Project: Quan Ngang J JOkV Substation and Branch Lme

i I" .............. "¥, •• ~~ ... ,..~ ..... ".,..',Jr"i,," ••• ~ ........ ,"'''' ... ''';;. ,' ... ,,.~~ .... ".~,¥

-.-.- ,,........,., .. '... ~"'''',''-,,.,-

'r~ 1It.l".du,Jc ~ ~ .quy tJW-. ~hiiju n;;li

---.-;,-_. -~-.--~. --_ .. _--t TlNln8 nlWllhu< hi~n <lOne '* '1")' dlnt>'~ hlinh 1!II1£ wI I''''," di."

"~;r'''kk..~ h··~..::1 .-\>-------- .. ' .,cu ~ .. ~ 11 \J :5110 ..... ,_-" ................. _." .• " ........... " .. "... .. ............. '"

., ~ , _K J. I ••• " ""' .. ., ~ ..... " ... " •• " ............... ~ • '" I ""': I I -.......... II' ,t .......... ,,. 1' •• 10 •• • • ,. ~ ,. • " * ~ •

i~ dl NgtIJQi d!n ,'it oCins d~trong ,,(Ina, oodl,r an d'&~ .'}'l!1;\m

I ~~b

11~~m~~ ~~~~ ~;~; ~~~ hu. I.j Ji"~ c"

t Th6ne. nh~1 LIwoK hiri!n (liiim ml qui mritlh lhi! cilnS ..:{:-rt:, I;;rilnh .,:s.!:.1 .. ·.(ri

I' f~. ~ U~u ~ns.1rJ.JdI be) qua. ~. ' . I,~ ~n <hI ~ l,lrong krll :,,;iy dUTll;! \<1 I!aUlhl .h4frn,hhh·tr&tg Irbth,t

."",,=,*- . "",,,,,.,,.,,,,, """'F'i~"'.,"'"~_,,' ___ "-,~"',h%"',''',',,_~_..-'d'''<~, ,,' ~

N~u k~ 1hl\1 t!\.IiI::I! ...... _, ....... " ............... -....... "","","""" , ............ .

..,~ "no., ~t~ I ..... , ..... ,,."" ..... ~ .'''. ~ ..... "''''' ... -- -' .. ~., • , •• ,~,,, •• , •••••• ,. ~

ARP

'.' "

Page 35

Page 39: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC TD2 Sub-Project: Quan Ngang llOkV Substation and Branch Line

I }

ARP Page 36

Page 40: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

ENVCPC IV2 Sub-Project: Quan Ngang 1 10k V Substation and Branch Line

Appendix 4. Policy framework for compensation, resettlement and rehabilitation

ARP Page 37

Page 41: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated
Page 42: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

Vietnam: Transmission and Distribution" Project

POLICY FRAMEWORK FOR COMPENSATION, RESETTLEMENT

AND REHABILITATION OF PROJECT DISPLACED PERSONS

May 2005, Corrected August 2007

Page 43: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated
Page 44: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

TABLE OF CONTENTS

Section 1:

Section 2:

Section 3:

Section 4:

Section 5:

Section 6:

Section 7:

Section 8:

Introduction

A. The Project B. Definition of Key Terms C. Policy Framework D. Principles and Objectives E. Resettlement Plan

Institutional and Legal Framework

A. Institutional Framework B. Legal Framework

Entitlement Policy

Site selection, site preparation, and relocation

People's Participation

Baseline Information

A. Inventories B. Resettlement Plans

Implementation Arrangements

A. Implementation Schedules B. Complaints and Grievances C. Supervision, Monitoring and Evaluation

Costs and Budget

A-I Second Transmission and Distribution Project

Corrected Resettlement Policy Framework August 2007

Page 45: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

A. The Project

SECTION 1 INTRODUCTION

1. The overall development objective of the VN TD 2 projects is to: • To alleviate power shortages and improve the quality of power supplies by improving

transmission and distribution network capacity; • Raise transmission and dispatch efficiency and improve power system reliability; and • Promote and support the reform and restructuring of the electricity sector.

2. The project will include three Project Components:

Component 1: Transmission and distribution expansion and reinforcement

This component will support investments at the 500 kV transmission level as well as in the 220 kV and 110 kV sub-transmission levels to alleviate power shortages and reduce equipment overloads, and improve system reliability and efficiency by upgrading and modernizing the transmission and distribution system. At the 500k V level, about 540 km transmission lines and 1500 MV A of new transformers will be built to enable the evacuation of power from the planned major generation centers at 0 Mon in the South and at Quang Ninh in the north. Substation reinforcements will be made at 500 kV and 220 kV levels to meet increased demand in Ho Chi Minh city. Additional measures will also be taken to strengthen transmission system control, protection and reactive capability so as to improve the quality and stability of the bulk power system. At the 220 kV level, the Project consists of two GIS substation constructed in Southern Vietnam. The capacity of the Binh Tan and Hiep Binh Phuoc 220 kV substations is 1000 MV A.

At the 110kV level, about 50 km of lines and 80 MVA to new transformer capacity will be built to improve network capacity, remove bottlenecks and meet growing demand from smaller load centers in Central Vietnam. Additional subcomponents may be substituted for proposed investments beyond the first year based on criteria set out in the project pre­feasibility study, and joint agreement between IDA and the Government of Vietnam.

Implementing agencies of the component are EVN Central and Southern Project Management Boards, Hochiminh City Power Company and Power Company 3 (EVN PMBs). Other implementing agencies under EVN may be added at later stages upon agreement with IDA.

Components 2 and 3: Strengthening of the NLDC and integration with Commercial Metering, Technical Assistance and Capacity Building

To implement for the first project component, land acquisition will be required. According to the project design, three (03) separate RPs will be prepared prior to the appraisal of the project. These include the RPs for the Cai Lay to Nha Be line / 0 Mon substation, and for the two GIS substations at the Binh Tan and Hiep Binh Phuoc.

A-2 Second Transmission and Distribution Project

Corrected Resettlement Policy Framework August 2007

Page 46: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

RPs of remaining project phases will be prepared later based on the proposed project implementation schedule and this Resettlement Policy Framework (one RP for each sUbcomponent).

B. Definition of Key Terms

i)Displaced Persons (DPs)

The DPs include the person or persons, household, firm, or a private or public institution to be identified by the baseline information collected for each of the Inventories and Resettlement Plans (RPs) as specified in E, Surveys and Documentation, Para. (iii), who, on account of the execution of the Project, has experienced or would experience direct economic and social impacts caused by:

(a) the involuntary taking of land, resulting in:

• relocation or loss of shelter;

• loss of assets or access to assets; or

• loss of income sources or means of livelihood, whether or not such person must move to another location; or

(b) the involuntary restriction of access to legally designated parks and protected areas, resulting in adverse impacts on the livelihood of such person.

"Displaced Persons" means, collectively, all such Displaced Persons.

ii) Compensation

Compensation includes the process of financial or material reimbursement of DPs who lost partial or the absolute value of their assets as a result of the Project. Compensation also includes the valuation and reimbursement in monetary terms or in kind of financial and physical losses as a result of impacts of the Project.

iii) Cut-off date

The cut-off-date is the last day of the survey when all DPs have been accounted for. After the cut-off date, no other DPs may be included in the inventory of DPs. The inventory lists all potential DPs, including their baseline information. People who move residences or business assets into or within the marked right of way after the cut-off date are not entitled to compensation under this policy framework.

iv) Rehabilitation

Rehabilitation means providing assistance to DPs severely affected due to the substantial or entire loss of productive assets, incomes, employment or sources of living, to supplement payment of compensation for acquired assets in order to improve, or at least achieve full restoration of incomes and living standards to the pre-project levels.

A-3 Second Transmission and Distribution Project

Corrected Resettlement Policy Framework Augyst 2007

Page 47: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

v) Replacement Cost

With regard to land and structures, "Replacement Cost" is defined as follows:

(a) For agricultural land: it is the pre-project or pre-displacement, whichever is higher, market value of land of equal productive potential or use located in the vicinity of the affected land, plus the cost of preparing the land to levels similar to those of the affected land, plus the cost of any registration and transfer taxes.

(b) For land in urban areas: it is the pre-displacement market value of land of equal size and use, with similar or improved public infrastructure facilities and services and located in the vicinity of the affected land, plus the cost of any registration and transfer taxes.

(c) For houses and other structures, it is provided by the Provincial People's Committee based on the market cost (at the time of compensation) of the materials to build a replacement structure with an area and quality similar to or better than those of the affected structure, or to repair a partially affected structure, plus the cost of transporting building materials to the construction site, plus the cost of any labor and contractors' fees, plus the cost of any registration and transfer taxes. In determining the replacement cost, depreciation of the asset and the value of salvage materials are not taken into account, nor is the value of benefits to be derived from the project deducted from the valuation of an affected asset.

(d) Crops, trees and other perennials based on current market value

1. Compensation for annual crops is equivalent to the production over the last three years multiplied by the market price for agricultural products at the time of the calculation of the compensation.

11. Compensation for trees includes total investment cost plus production cost from the time of its planting to the expropriation. In case this cost cannot be determined: the compensation will be calculated on the basis of the type, age and productive value.

Other assets (i.e .• income, cultural, aesthetic) based on replacement cost or cost of mitigating measures. For example, compensation for the removal of graves includes all expenditures for exhumation, removal and reconstruction to its original state.

vi) Resettlement

Resettlement refers to all measures tal<:en by the Project Proponent to mitigate any and all adverse social impacts of a project on the DPs, including compensation for lost assets and incomes and the provision of other entitlements, income rehabilitation assistance, and relocation, as needed.

A-4 Second Transmission and Distribution Project

COITected Resettlement Policy Framework Aug1.lst 2007

Page 48: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

vii) Righ t of Way

For this Policy Framework, Right of Way (ROW) is determined as a safety corridor along a power line or substation with width, length and height specified in the Decree 54/1 9991ND-CP dated July 8,1999 (Gov. Decree 106/2005IND-CP, Aug.l7'\ 2005 at present)on Protection of Safety for High Voltage Power System.

viii) Vulnerable Groups

Vulnerable groups include those distinct groups of people who might suffer disproportionately or face the risk of being marginalized by the effects of resettlement, and specifically include: (a) Poor and very poor communes as identified by the 1999 national survey results.

(b) Ethnic minorities (see Policy Framework and Guidelines for Ethnic Minority Development Plan).

(c) Mentally and physically handicapped people or people in poor physical health.

(d) Infants, children and women.

(e) Households without security of tenure or with tenure status.

ix) DPs Without Legal Title

DPs without legal title are occupants of land and housing without legal ownership rights and individuals or groups of people with shops conducting business in the immediate project areas without official registration and will be adversely impacted by the Project through displacement. DPs without legal title are entitled to compensation provided their assets affected by the project were documented in the pre-project census prior to the cut off date.

47.

x) Ethnic I Indigenous People

Ethniciindigenous People are defined as"persons who belong to a minority tribal group affected in part or in total (temporarily or permanently) by the Project due to acquisition of their lands, dWellings, disturbance of their place of work, and other Project-related adverse impacts.

xi) Land Use Registration Certificate (LURC)

LURC is similar to a title granted to DPs that legalize their use of the lands and/or houses they occupy.

xii) Relocation Site

The relocation site is defined as the area allocated for the resettlement of DPs living in the areas of TD2 sub-projects that are severely affected and who choose relocation over cash compensation.

A-5 Second Transmission and Distribution Project

Corrected Resettlement Policy Framework Aug1:\st 2007

Page 49: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

C. Policy Framework

This resettlement policy framework prepared based on the OP 4.12 of the World Bank on involuntary resettlement (December, 2001). The principle objective of the Policy Framework is to ensure that all displaced persons (DPs) will be compensated for their losses at replacement cost and provided with rehabilitation measures to assist them to improve, or at least maintain, their pre-project living standards and income earning capacity.

The Policy Framework lays down the principles and objectives, eligibility criteria of DP's, entitlements, legal and institutional framework, modes of compensation and rehabilitation, people participation features and grievances procedures that will guide the compensation, resettlement and rehabilitation of the DPs.

D. Principles and Objectives

The principles outlined in the World Bank's Operational Policies 4.12 (OP 4.12) have been adopted in preparing this Policy Framework. In this regard the following principles and objectives would be applied:

(a) Acquisition of land and other assets, and resettlement of people will be minimized as much as possible.

(b) All DP's residing, working, doing business or cultivating land in right of way (ROW) of transmission line (TIL), surrounding areas of tower foundation, the substation areas, in the service roads under the project as of the date of the baseline surveys are entitled to be provided with rehabilitation measures sufficient to assist them to improve or at least maintain their pre-project living standards, income earning capacity and production levels. Lack of/egal rights to the assets lost should not bar the DPs from entitlement to such rehabilitation measures.

(c) The rehabilitation measures to be provided are: (i) compensation at replacement cost, without deduction for depreciation or salvage materials for houses and other structures; (ii) agricultural land for land of equal productive capacity acceptable to the DPs or in cash at replacement cost according to DP's choice; (iii) replacement of residential/premise land of equal size acceptable to the DP or in cash at replacement cost according to DP's choice; and (iv) transfer and subsistence allowances.

(d) Replacement residential and agricultural land will be as nearby as possible to the land that was lost, and acceptable to the DPs.

(e) The resettlement transition period will be minimized and the rehabilitation means will be provided to the DP's prior to the expected start-up date of works in the respective Project site.

(f) Plans for acquisition of land and other assets and provision of rehabilitation measures will be carried out in consultation with the DPs, to ensure minimal disturbance. Entitlements will be provided to DPs prior to expected start-up of works at the respective project site.

A-6 Second Transmission and Distribution Project

Corrected Resettlement Policy Framework August 2007

Page 50: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

(g) The previous level of community services and resources will be maintained or improved.

(h) Financial and physical resources for resettlement and rehabilitation will be made available and as where and when required.

(i) Institutional arrangements will ensure effective and timely design, planning, consultation and implementation ofRPs.

G) Effective and timely supervision, monitoring and evaluation of the implementation ofRPs will be carried out.

E. Resettlement Plan (RP)

The scope and level of detail of the resettlement plan vary with the magnitude and complexity of resettlement.

Abbreviated Resettlement Plan

In case impacts on the entire displaced population are minor 1, or fewer than 200 people are affected, an Abbreviated Resettlement Plan (ARP) will be prepared by the respective Project Management Board (PMB) and consolidated by EVN for any given year, and furnished to the World Bank for its concurrence.

Each Abbreviated Resettlement Plan will cover the following minimum elements: (1) a census survey of displaced persons, and valuation of assets; (2) description of compensation and other resettlement assistance to be provided: (3) consultation with displaced persons about acceptable alternatives; (4) institutional responsibility for implementation and procedures for grievances redress;: and (5) a timetable and budget. In the case some displaced persons, lose more than 20% of their productive assets or require physical relocation, the plan also covers a socioeconomic survey and income restoration measures.

The Abbreviated Resettlement Plan will be completed by no later than tour months prior to the estimated date tor commencement of the works under the project. Each Abbreviated Resettlement Plan will be furnished to the World Bank tor consideration no later than three months prior to the actual initiation of/he works under the Project. Compensation, resettlement and rehabilitation activities will only commence after the World Bank has found acceptable the respective Abbreviated Resettlement Plan and EVN has approved it The compensation, resettlement and rehabilitation activities will be completed betore awarding the contracts of civil works under each sub-project.

Resettlement Plan

In case more than 200 people are affected by the project, a Full Resettlement Plan (FRP) will be prepared by the respective PMB in accordance with the provisions of this Policy Framework. The RP will be furnished by the EVN PMB to the World Bank for its concurrence.

I Impacts are considered "minor" if the affected people are not physically displaced and less than 20% of their productive assets are lost

A-7 Second Transmission and Distribution Project

Corrected Resettlement Policy Framework Augyst 2007

Page 51: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

Each RP will include: (1) description of the project; (2) project potential impacts; (3) objective; (4) socio-economic studies; (5) legal framework; (6) institutional framework; (7) eligibility; (8) valuation and compensation for losses; (9) resettlement measures; (10) site selection, site preparation and relocation; (11) housing, infrastructure, and social services; (12) environmental protection and management; (13) participation and consultation; (14) integration with host· popUlations; (15) grievances procedures; (16) organizational responsibilities; (17) implementation schedule; (18) cost and budget; and, (19) monitoring and evaluation.

Each RP will be completed by no later than six months prior to the estimated date {or commencement ofthe works. Each RP will be filrnished to the World Bank {or consideration by no later than three months prior to the actual initiation of the works under the Project, Rehabilitation and assistance activities will only commence after the World Bank: has found acceptable the respective RP and EVN has approved it. Rehabilitation and assistance activities will be completed before awarding contracts of civil works under each sub-project.

SECTION 2 INSTITUTIONAL AND LEGAL FRAMEWORK

A. Institutional Framework

The responsibility for preparing and implementing the Policy Framework and RPs are as follows:

(a) The overall responsibility for enforcement of the Policy Framework and for planning and implementing RPs rests with PMBs and Power Companies in charge of EVN (EVN PMB). EVN PMB is responsible for preparing Inventories and RPs and for the day-to-day implementation thereof within their respective jurisdiction. The peoples committees at the commune level will ensure the active and effective participation of the DPs in the preparation and implementation of RPs. In order to have RPs acceptable to the World Bank to implement the RP smoothly, EVN PMB is responsible for i) hiring qualified consultants to prepare RPs; ii) appointing qualified social safeguard staff at each PMB.

(b) Funds for implementing RPs will be from EVN funds, established in consultation with local governments (provincial, district and commune peoples committees) and the DPs.

B. Legal Framework

This section reviews the legal framework and policies of the Government of Vietnam and IDA policies related to land acquisition, compensation and resettlement. It then compares the two approaches. Since there are differences between the WB's policy and the Vietnamese's, the Project requires a waiver of the Vietnamese Government articles of decrees and regulations concerning compensation and resettlement. Subsequently, compensation and resettlement plans will be implemented according to the project policies.

This Resettlement Policy Framework will apply the various laws, degrees, and circular regulating use ofland in Vietnam as well as the World Bank policy.

A-8 Second Transmission and Distribution Project

Con'ected Resettlement Policy Framework August 2007

Page 52: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

1/1 The 2003 Land Law enacted by the National Assembly of Viet Nam on November 26, 2003, provides that: "the persons with land to be recovered shall be compensated with the assignment of new land of the same use purposes; if having no land for compensation, shall be compensated with the land use right value at the time of issuance of the recovery decisions. The People's Committees of the provinces and centrally-run cities shall elaborate and execute resettlement projects before the land recovery for compensations with dwelling houses, residential land for persons having residential land recovered and having to move their places of residence. The resettlement zones must have development conditions being equal to or better than the conditions in the former places of residence. In cases of having no resettlement zones, the persons having land recovered shall be compensated with money and given priority to purchase or lease dwelling houses under the State's ownership, for urban areas; be compensated with residential land, for rural areas. In case of recovering land of households and/or individuals, that are directly engaged in production, but having no land for compensation for continued production, apart from pecuniary compensations, the persons having land recovered shall be supported by the State to stabilize their lives, with training for change of their production and/or business lines, with the arrangement of new jobs." (Article 42)

-Decree 197/20041ND-CP issued by GOV on December 3, 2004, in replacement of Decree 22CP, regulates compensation, support and resettlement when land is recovered by the State. This Decree guides the implementation of compensation for land, compensation for property, support policies and resettlement relating to land acquisition.

- Circular No. 1l6/2004/TT-BTC issued on December 7, 2004 by the Ministry of Finance provides guidelines to implement the Decree 197/20041ND-CP

• Decree 60/CP issued by GOV on July 5, 1994 regulates property ownership and Land Use Rights in urban areas.

-Decrees 611CP issued by GOV on July 15, 1994 regulates dwelling house purchases, sales and business.

• Decree 88/CP issued by GOV on 17 August 1994 regulates the Management and Use of Urban Land.

• Decree 451CP issued by GOV on 3 August 1996 regulates the Amendment of Article 10 of60/CP (5/7/1994).

- Decree 188/2004IND-CP issued by GOV on November 16, 2004 sets the methodologies for defining land prices and land price frame of various categories of land. This Decree setforth the minimum and maximum prices of different types and categories of land covering the whole country. These prices have been established for the purpose of land acquisition by Government, tax value for transfer of land use rights, leasing government land and national and public purposes.

A-9 Second Transmission and Distribution Project

Corrected Resettlement Policy Framework August 2007

Page 53: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

• Circular 114/2004/TT-BTC issued by Ministry of Finance on November 26, 2004 guides the implementation of the Decree 188. This Circular elaborates in details the methodologies (i.e. direct comparison method and income method) for the land price verification of different types and categories of land in different regions/areas to ensure the replacement cost.

• Law on Taxation of Land Use Right Transfer, approved by the National Assembly, on June 22, 1994.

• Law to regulate and amend some articles of the Law on Taxation of Land Use Right on December 21, 1999.

• Decree 114/CP issued by GOV on 5/9/1994 regulates the Implementation of the Law on Taxation of Land Use Right Transfer.

• Ordinance on taxation of Land and Housing issued on October 10, 1992 by State Council of Vietnam.

• Ordinance for regulation and Amendment of Ordinance on Tax of Land and Housing (1992) issued by National Assembly on January 1, 1994.

• Decree 94/CP issued by GOV on 25/8/1994 regulates the Implementation of Ordinance for Tax of Land and Housing.

• Official letter No. 29441TC-TCT dated October 28, 1995 of Ministry of Finance regulates the tax remission of housing program.

• Law on Petition and Accusation approved by National Assembly on December 02, 1998.

• Decree 54/19991ND-CP issued by GOV on 81711999 (Gov. Decree 10612005IND-CP, Aug. 17th

, 2005 at present) defines the protection of high voltage systems.

• Decree No. 6711999IND CP, issued by GOV on 7/8/1999 regulates in detail the Law on Petition and Accusation.

World Bank Policy on Involuntary Resettlement (OP 4.12)

18.1 The primary objective of the World Bank policy is to explore all alternatives to avoid or at least minimize involuntary resettlement. Where resettlement is unavoidable, the living standards of displaced persons should be restored or improved relative to those conditions that prevailed prior to the Project. The policy applies to the taking of land and other assets when land acquisition results in the loss of shelter, the loss of all or part of productive assets, or access to them, and the loss of income sources or other means of livelihood.

18.2 Measures required to ensure that resettlement has a positive outcome include:

• Consulting with potential DPs on feasible measures for resettlement and rehabilitation;

A-lO Second Transmission and Distribution Project

Corrected Resettlement Policy Framework August 2007

Page 54: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

• Providing DPs with options for resettlement and rehabilitation; • Enabling their participation in planning and selecting these options; • Providing compensation at full replacement cost for losses; • Choosing relocation sites that provide, at a minimum, the same benefits and

services as the sites they replace; • Providing allowances, training and income support to assist in making a

smooth transition; • Identifying vulnerable groups and providing special assistance to these groups;

and, • Establishing an institutional and organizational structure that supports this

process to a successful end.

18.3 Eligibility Criteria and Compensation and or assistance:

18.3.1 The displaced or project-affected people eligible for compensation and or assistance will include: (a) those who have formal legal rights to land or other assets; (b) those who initially do not have formal legal rights to land or other assets but have a claim to legal rights based upon the laws of the country; upon the possession of documents such as land tax receipts and residence certificates; or upon the permission of local authorities to occupy or use the project affected plots; and (c) those who have no recognizable legal right or claim to the land they are occupying.

18.3.2 Persons covered under (a) and (b) are provided compensation for the land they lose, and other assistance. Persons covered under (c) are provided resettlement assistance, in lieu 0/ compensation for the land they occupy, and other assistance, as necessary, to achieve tlte objectives set Ollt in this policy, if they occupy the project area prior to a cut-off dates defined in RPs. Persons who encroach on the areas after the cut~off date defined in RPs are not entitled to compensation or any other form of resettlement assistance.

Valuation of and Compensation for Losses: T!:te methodology to be used in the valuation of losses for Bank-associated Projects is based on their replacement cost. In this Project, losses comprise land, structures and other assets. Replacement cost for land include the value of land at market price plus the cost taxes and fees to get Land Use Right Certificate (LURC). For houses and other structures, the market cost of the materials should be used to calculate the replacement cost to build a replacement structure with an area and the quality should be at least as good as those affected. For both totally and partially affected structures, compensation includes market cost of material, plus the costs of material transport, labor and contractor fees, registration and transfer taxes. Depreciation of the asset and amount saved in materials will not form a part of replacement cost.

Comparison between Government of Vietnam and World Bank Approaches

There are a number of ways in which the approaches of the Vietnam Government -either in policy or practice - are compatible with World Bank guidelines. The most important compatibilities are:

A-Ii Second Transmission and Distribution Project

Corrected Resettlement Policy Framework August 2007

Page 55: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

Vietnam has a process whereby most people without legal land rights may meet conditions of legalization and receive compensation for losses.

• Permanent residents are provided with options that include relocation to an improved site, or cash, or a combination of the two.

• Resettlement sites offer not only better improved infrastructure and services but represent a higher standard of living.

• Allowances are provided to help the DPs in the transition period and there is an institutional structure through which people are informed, can negotiate compensation, and can appeal.

• Differences between the approaches and measures that need to be addressed within the program also exist. However, in this context, procedures exist within national and City governments that allow the granting of waivers of domestic law on specific projects that . may be in conflict with that of the funding agency.

• On the issue of land tenure and the legal right to compensation, the Government and World Bank approaches are compatible. The government has its -own process in place whereby land occupied without legal documentation can be legalized; this land, however, is compensated for at a rate equal to 100% of land price minus the taxes and fee for land use right registration from 15 October 1993 (Article 6, 7, 9, 10 of Decree 38/2000 ND-CP on the payment for the Land Use Right).

c. Required Waivers

In order to meet the requirements of the World Bank OP 4.12 on Involuntary Resettlement a number of articles in various Vietnamese laws and regulations which do not ensure compensation at replacement cost or set eligibility provisions which do not extend the right to rehabilitation and or assistance to households without proper land paper, will be waived. The articles of law and regulations that will be waived are mentioned below:

Eligibility to Compensation and or assistance - Decree 197

Article 7 of Decree 197 (Cases where land is recovered without compensation) stipulates that any person whose land is recovered and who has not met one of the conditions of Article 8 of this Decree, or who has violated the plan, or who violates the protecting corridor work, or who illegally occupies land shall not receive compensation when the state recovers the land. In case of necessity, the Provincial People's Committee shall consider and decide on a case­by-case basis.

Article 18,19,20 of Decree 197:

• Houses and structures on non-eligible-for-compensation land, which have not violated announced land use plans or the right of way will be assisted at 80% of replacement cost

• Houses and structures on non-eligible-for-compensation land, which have violated announced land use plans or the right of way will not be assisted. If necessary, the PPC will consider on the case by case basis.

A-12 Second Transmission and Distribution Project

Corrected Resettlement Policy Framework August 2007

Page 56: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

Article 28, 29 of Decree 197: DPs losing more than 30% of productive land will be entitled to living stabilization and training/job creation assistance

To ensure that the objectives of this resettlement policy are met, a special decision of the Government waiving Article 7, 18, 19,20,28,29 of Decree 197 is needed to permit assistance and rehabilitation measures for illegal users ofland as proposed in the policy.

Price of Land for Calculation of Compensation

Article 9 of Decree 197: The compensation rates for land shall be determined by the PPC for the type of land which has been used for at the time of land acquisition

To ensure that the objectives of the project resettlement policy are met, unit price for land compensation established by the Project Provincial/City People's Committees will be adjusted to meet the replacement costs.

Assistance Policy for DPs who Rent State-owned dwelling houses - Decree 197

Article 21 of Decree I 97/20041ND-CP states that DPs who rent State-owned dwelling houses shall be provided with monetary supports equal to 60% of the land value and 60% of the value of currently rented houses, in cases where there are no resettlement houses to be arranged for them.

To ensure that the objectives of the policy are met, a special decision of the Government of Vietnam regarding waiver of Article 21 of Decree 197/2004IND-CP is needed to permit assistance and rehabilitation measures for DPs who share State-owned dwelling houses as proposed in this policy.

Article 2 of Decree 188/2004IND-CP states that the land price shall be defined by the provincial People's Committees andlor cities directly under the central government. To ensure that the objectives of the project resettlement policy are met, unit prices for land compensation established by the project related provincial/city People's Committees shall be adjusted to meet the replacement costs.

The Item 4, Article 2 of Decree 17/20011ND-CP dated May 04,2001 to guide on the ODA management stipulates that "in the case of the international agreements on ODA have been signed between GOV and sponsor stipUlates other contents, then that international agreements will be followed"

SECTION 3 ENTITLEMENT POLICY

DPs will be entitled to the following types of rehabilitation and assistance measures, for instance:

(a) DP's losing agriCUltural/productive land and crops:

(i) if the portion of the land to be lost represents 20% or less of the total area of the landholding, and the remaining land is still a viable economic holding, cash compensation, at full replacement cost for the acquired area may be provided to the DP.

A-I3 Second Transmission and Distribution Project

Corrected Resettlement Policy Framework August 2007

Page 57: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

(ii)if the portion of the land to be lost more than 20% of the total area of the landholding and the remaining holding is not viable then the project will acquire the entire landholding and provide "land for land" arrangements of equal productive capacity, satisfactory to the DP. However, if the DP prefers to receive cash instead of land, then cash compensation at replacement cost is applied.

(iii) DP's will be compensated for the loss of standing crops at market price, productive trees will be compensated at replacement cost.

(iv) DP's whose land is temporarily taken by the works under the project will be compensated for their loss of income, standing crops and for the cost of soil restoration and damaged infrastructure. Land will be rehabilitated after the project construction by each PC and its PMB.

(b) DP's losing residential land and house/structure

(i) The mechanism for compensating loss of residential land and structures will be: (1) the provision of replacement residential land (house site and garden) of equivalent size, satisfactory to the DP or cash compensation at replacement cost according to DPs' choice; and (2) cash compensation reflecting full replacement cost of the house/structures, without deduction for depreciation or salvage materials or compensate in kind according to DPs' options.

(ii) If residential land is only partially being affected by the project and the remaining areas are not sufficient for reorganizing DP's house then at the request of the DP, the entire residential land will be acquired at full replacement cost.

(iii) Ifhouse/other structure is only partially being affected by the project and the remaining areas are not convenient to using, the house/ structure will be acquired at full replacement cost, without depreciation.

(iv) If the lost residential land is less than the compensated land slot of standard size, the DPs are not requesteq to pay for the difference. .

(v) Tenants, who have leased a house for residential purposes will be provided with a cash grant of six months rental fee at the prevailing market rate in the area, and will be assisted in identifying alternative accommodation.

(c) OP's losing business

The mechanism for compensating loss of business will be: (1) the provision of alternative business site of equal size and accessibility to customers, satisfactory to the DP; (2) cash compensation for lost business structure reflecting full replacement cost of the structures, without depreciation; and (3) cash compensation for the loss of income during the transition period.

(d) OP's will also be provided compensation at full replacement cost, without deduction for depreciation and salvage materials for any other fixed assets affected in part or in total by the project, such as tombs and water wells, etc.

A-14 Second Transmission and Distribution Project

Corrected Resettlement Policy Framework August 2007

Page 58: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

In cases where community infrastructure such as schools, factories, water sources, roads, sewage systems is damaged, the EVN PMB will ensure that these would be restored or repaired as the case may be, at no cost to the community.

Besides the direct compensation for the losses, DPs will also be entitled to additional assistance (subsidies/allowances) as below:

a) Transportation allowance:

All DPs relocating within the province are entitled to a minimum allowance of 1 million VND and maximum of 3 million VND. All DP relocating out of the province are entitled to a minimum allowance of 3 million VND and maximum of 5 million VND. This subsidy allowance is for the transportation of their salvageable materials and living facilities.

b) Subsistence allowance for relocating:

All relocating DP shall, for a period of six months receive a cash allowance equal to 30 kg of rice of average price per month for each family member. If DPs have to be relocated to another province and the impact is severe, this subsidy period could be for one year.

c) Restoration allowance:

DPs, who are permanently affected more than 20 % of productive land or incomes, or have to relocate will be entitled to trainings or other economic restoration programs at about VND 3,000,000/HH.

d) Relocation bonus:

A bonus of maximum 5 million will be awarded to DP who dismantle their houses and vacate their premises in accordance with the resettlement schedule of will get a maximum bonus ofVND 5,OOO,OOO/HH.

By the nature of the project impacts, the potential impacted categories are classified into nine (09) categories. The entitlement matrix is attached (see Annex 1)

SECTION 4 SITE SELECTION, SITE PREPARATION, AND RELOCATION

If there are families have to be relocated because of the project impacts and resettlement sites are required. The EVN PMB will clearly describe in RP about alternative relocation sites considered and explanation of those selected, covering:

(a) institutional and technical arrangements for identifying and preparing relocation sites, for which a combination of productive potential, locational advantages, and

A-15 Second Transmission and Distribution Project

Corrected Resettlement Policy Framework August 2007

Page 59: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

other factors is at least comparable to the advantages of the old sites, with an estimate of the time needed to acquire and transfer land and ancillary resources;

(b) any measures necessary to prevent land speculation or influx of ineligible persons at the selected sites;

(c) procedures for physical relocation under the project, including timetables for site preparation and transfer; and

(d) legal arrangements for regularizing tenure and transferring titles to resettlers.

( e) housing, infrastructure, and social services. Plans to provide (or to finance resettlers' provision of) housing, infrastructure (e.g., water supply, feeder roads), and social services (e.g., schools, health services); plans to ensure comparable services to host populations; any necessary site development, engineering, and architectural designs for these facilities.

(f) a description of the boundaries of the relocation area; and an assessment of the environmental impacts of the proposed resettlement and measures to mitigate and manage these impacts (coordinated as appropriate with the environmental assessment of the main investment requiring the resettlement).

SECTION 5 PEOPLE'S PARTICIPATION

The local authorities and its relevant organizations, DPs and host communities will participate throughout the various stages of the planning and implementation ofRPs. The DPs will be fully informed of the provisions of this Policy Framework at public meetings held by the respective PMB and local authorities.

Each DP will be fully informed and consulted by the relevant District Peoples' Committee and/or Communes Peoples' Committees of their entitlements and rehabilitation choices under the respective.

SECTION 6 BASELINE INFORMATION

A. Census and Inventory

The baseline information will include the following information for each household:

(a) number of persons and names;

(b) number, type, and area of the houses lost;

(c) number and area of all the residential plots lost; A-16

Second Transmission and Distribution Project Corrected Resettlement Policy Framework August 2007

Page 60: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

(d) number, category and area of agricultural land lost;

(e) quantity and types of crops and trees lost;

(f) businesses lost including structures, land and other fixed assets;

(g) productive assets lost as a percentage of total productive assets;

(h) quantity and category of other fixed assets affected by each sub-Project; and

(i) temporary damage to productive assets.

The proposed census and inventory fonn is attached (see Annex 2)

B. Resettlement Plan

The baseline information for a RP will include: (a) an Census and Inventory (see above); and (b) a detailed socioeconomic survey of all DP's describing their age, sex, ethnicity, education, occupation, sources of income, and total household income. The proposed fonn for socio­economic is attached (see Annex 3).

The entitlements of DPs will be calculated based on the above information. The proposed entitlement form is attached (see Annex 4).

SECTION 7 IMPLEMENTATION ARRANGEMENTS

A. Implementation Schedule

A detailed implementation schedule of the various activities to be undertaken will be included in each RP. The RP implementation schedule must be developed based on the linkage to the civil work implementation schedule.

Payment olrehabilitation and furnishing olother restoration/assistance entitlements (in cash or in-kind), and relocation ifthat be the case, have to be completed prior awarding contracts for civil works.

B. Institutional Arrangement

EVN PMBs will arrange adequate and experience staff to make sure that RP will be implemented smoothly as approved schedules.

C. Complaints and Grievances

Complaints and grievances related to any aspect of RP implementation, including the determined the quantity and price of the lost assets, will be handled as follows:

First step:

A-17 Second Transmission and Distribution Project

Conected Resettlement Policy Framework August 2007

Page 61: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

If any person is aggrieved by any aspect of the resettlement and rehabilitation program, he/she can lodge an oral or written grievance with commune authorities. Commune People's Committee will resolve the issue within fifteen days from the date it receive the complaint.

Second step:

If any aggrieved person is not satisfied with the decision in stage 1, he/she can bring the complaint to the District People's Committee (DPC) or District Resettlement Committee (DRC) within fifteen days from the date of the receipt of the decision in stage 1. The District People's Committee (DRC) or District Resettlement Committee (DRC) will reach a decision on the complaint within fifteen days.

Third step:

If the DP is still not satisfied with the decision at district level, he/she can appeal to the Provincial People's Committee (PCC) or Provincial Resettlement Committee (PRC) within 15 days of receiving the decision of the DPC or DRC. The Provincial People's Committee (PRC) or Provincial Resettlement Committee (CRC) will reach a decision on the complaint within fifteen days.

Fourth step:

If the DP is not satisfied with the decision of the Provincial level, the case may be submitted for consideration by the District Court within 15 days of receiving the decision of the PPC or PRC.

DP's will be exempted from all administrative and legal fees.

D. Supervision, Monitoring and Evaluation

Implementation of RPs will be periodically supervised and monitored by the EVN PMB in a close coordination with the respective Peoples' Committees at different administrative units and independent monitoring agencies. The findings will be recorded in quarterly reports to be furnished to EVN.

Internal monitoring and supervision will:

(a) Verify that the baseline infonnation of all DP's has been carried out and that the valuation of assets lost or damaged, and the provision of compensation, resettlement and other rehabilitation entitlements has been carried out in accordance with the provisions of this Policy Framework and the respective RP.

(b) Oversee that the RPs are implemented as designed and approved.

(c) Verify that funds for implementing the RPs are provided to the respective PMBs in a timely manner and in amounts sufficient for their purposes, and that such funds are used by the respective PMB's in accordance with the provisions of the RP and policy framework. .

A-IS Second Transmission and Distribution Project

Corrected Resettlement Policy Framework August 2007

Page 62: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

Entitlement Matrix

Definition of No. Type of 1058 Application entitled DPs

I Temporary acquisition All DPs have DPs of productive land in trees, crops, with/without ROW other assets in land certificate

ROW included in the inventory or able to prove land occupancy prior to cut-off date.

2 Temporary acquisition All DPs with -do-of residential and orchards or garden land in ROW trees in ROW without house or structures in ROW

3 Temporary impact on All DPs have -do-_._-_ ..... _._ ..... _- -_ .. _. __ ...... __ .... - - -_ ... _--_ .. _-~ --

Compensation Policy

48. - Cash compensation for affected trees at the replacement cost plus cost for cutting trees, crops at market price. Number of crop patterns to be compensated based on the time oftemporarily acquired ofland. - No compensation for land - Rehabilitate land after the project construction.

- Cash compensation for affected fruit trees and trees at replacement cost. - No compensation for land - Rehabilitate land after the project construction.

Housel building: -_ ... _ ....... _ .•. _._ ....... _-

A-20

I Implementation Issues

- Trees have to be cut are regulated by Article 7 of the Government Decree 54/1999IND-CP, July 8'\ 1999 (Gov. Decree 106/2005IND-CP, Aug.l7th

, 2005 at present) on the protection of the high voltage networks. - PMBs and local authorities determine and ensure that compensation for trees will be at the replacement cost and for crops at the market price. IfDP is requested for cutting affected trees, PMBs will pay money for this work. DP has right for using salvageable trees. - Full compensation at least 01 month before land clearance. Payment to DPs will be delivered by PMBs and District Resettlement Committees (DRCs). - Affected land in ROW will be rehabilitated by contractors after the project construction and land in ROW could be used with the restricted purposes. - Finance available for compensation and well information disclosel disseminate to DPs and key stake holders.

- Trees have to be cut are regulated by Article 7 of the Government Decree 541l999IND-CP, July 8th

, 1999 (Gov. Decree l06/2005IND-CP, Aug.lt\ 2005 at present) on the protection of the high voltage networks. - PMBs and local authorities determine and ensure that compensation for trees will be at the replacement cost. If DP is requested for cutting affected trees, PMBs will pay money for this work. DP has right for using salvageable trees. I

- Full compensation to DPs at least 01 month before land clearance. Affected land in ROW will be rehabilitated by contractors after the project construction - Payment to DPs will be delivered by PMUs and DRCs - Finance available for compensation and well information

I disclosel disseminate to DPs and key stake holders.

- House and building have to be demolished or could b:: ~x~!e~~

Second Transmission and Distribution Project Outline Mid Term Review Report

Page 63: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

No. Type of loss Application Definition of entitled DPs

residential and garden houselbuilding land. Partial and trees/fruit houselbuilding within trees in ROW ROW (area in ROW less than 20% oftotal area) and the demolished area does not impact to the remaining houselbuilding. Residential land and garden land outside of ROW is sufficient for re-organizing (not less than 60 m2

).

.

4 Temporary impact on All DPs have -do-residential and or houselbuilding garden land. Impact and trees/fruit more than 20% or less trees in ROW than 20% of total houselbuilding area but the demolished area will impact to the remaining of house/structure. Land outside of ROW is sufficient for reorganizing (not less

. ... ...

Compensation Policy

49. - DP can opt for: i) Remain their houses or building in ROW with the conditions regulated by Article 8 ofthe Government Decree 54/1 999/ND-CP, July 8th

, 1999 (Gov. Decree 1 06/200S/ND-CP, Aug. 1 71h

, 200S at present) on the protection of the high voltage networks. Subsidy allowance for fireproof materials and lightning arrestors for the existing houselbuilding; or ii) Cash compensation for the directly affected rooms at the replacement cost and cost for demolishing an affected room.

SO. - No compensation for land.

51. - Rehabilitate land after the project construction by contractors.

52. Tree and fruit tree

- Compensation for affected trees and fruit trees at the replacement cost .

Allowances:

- Relocating allowance of 30 kg of rice equivalent per person per month in six months.

Housel building:

53. - DP can opt for: i) Remain their houses or building in ROW with the conditions regulated by Article 8 of the Government Decree S4/1999/ND-CP. July 8th

, 1999 (Gov. Decree 1 06l200SIND-CP, Aug. 17th

, 200S at present) on the protection of the high voltage networks. Subsidy allowance for fireproof materials and lightning arrestors for the existing houselbuilding; or ii) Cash compensation at replacement cost for full areas of impacted house/building and demolish DP's house in ROW.

,.... .

A-21

Implementation Issues

are regulated by Article 8 of the Government Decree S4/1999IND-CP, July 8th

, 1999 (Gov. Decree 106/200SIND-CP, Aug. 17th

, 200S at present) on the protection ofthe high voltage networks.

- PMBs and local authorities determine and ensure that compensation will be paid at the replacement cost, without deduction for salvageable materials.

- DPs will demolish the impacted part! room and reconstruct/or improve their houses themselves.

- Full compensation for trees and fruit trees at least 0 I month before land clearance. IfDP is requested for cutting affected trees, PC or project provinces will pay money for this work. DP has right for using salvageable trees.

- Full entitlement payment to DPs impacted on house/building at least 03 months before land clearance.

- Payment to DPs will be delivered by PMBs and DRCs

- land in ROW could be used with restricted purposes.

- Finance available for compensation and well information disclose/ disseminate to DPs and all key stake holders.

- House and building have to be demolished or could be existed are regulated by Article 8 of the Government Decree S411999IND-CP, July 8th, 1999 (Gov. Decree 106/200SIND-CP, Aug. 17th

, 200S at present) on the protection ofthe high voltage networks.

- Consultation for DP's options on remain their house in ROW or move out of ROW.

- PMBs and local authorities determine and ensure that compensation will be replacement cost at the time of payment.

- DPs will demolish the impacted areas and reconstruct/or improve their houses themselves.

- Full compensation for trees and fruit trees to DPs at least 0) month before land clearance. IfDP is requested for cutting

Second Transmission and Distribution Project Outline Mid Term Review Report

Page 64: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

No. Type of loss Application Definition of

Compensation Policy entitled DPs

than 60 m2). 54. - No compensation for land.

55. - Rehabilitate land after the project construction by contractors.

56. Tree and fruit tree - Compensation for affected trees and fruit trees at the replacement cost.

Allowances:

- Relocation allowance 000 kg of rice equivalent per person per month in six months.

5 Temporary impact on All DPs have -do- DPs can opt for one of the followings: residential and or houselbuilding i) Remain their houses or building in ROW garden land in ROW. and trees, fruit with the conditions regulated by Article 8 of Full or partial trees in ROW the Government Decree 54/1999IND-CP, houselbuilding July 8th

, 1999 (Gov. Decree I06/20051ND-impacted and land CP, Aug.l7'n, 2005 at present) on the outside of is not . protection of the high voltage networks. sufficient for Subsidy allowance for fireproof materials and reorganizing (less than lightning arrestors for the existing 60 m2) houselbuilding; or ii) Cash compensation for

the whole residential area which DP occupied (not only for the impacted areas) and properties associated with occupied land at replacement cost. Impacted land will be obtained by local authorities; or ii) "Land for land" with the same area which DP occupied and cash at replacement cost for the affected assets associated with land. Land occupied by DP will be obtained by local authorities.

- Compensation for affected trees and fruit trees at the replacement cost. Allowances:

- Relocating allowance of 30 kg of rice equivalent per person per month in six months

- Transportation allowance for relocating DP A-22

Implementation Issues

affected trees, PMB will pay money for this work. DP has right for using salvageable trees.

- Full compensation payment for impacted house and allowances to DPs at least 03 months before land clearance.

- Payment to DPs will be delivered by PMBs and DRCs

- Cleared residential could be reused with other restricted purposes.

- Finance available for compensation! rehabilitation and well information disclose! disseminate

- House and building have to be demolished or could be existed are regulated by Article 8 of the Government Decree 54/1 999IND-CP, July 8th

, 1999 (Gov. Decree 106/2005IND-CP, Aug. 17th, 2005 at present) on the protection of the high voltage networks.

- Consultation for DP's options on remain their house in ROW or move out of ROW

- PMB and local authorities determine and ensure that compensation will be at replacement cost at the time of payment.

- Replacement land, and resettlement sites development.

- DPs receive compensation will demolish the impacted house areas and reconstruct/or improve their houses themselves.

- Full compensation payment for trees and fruit trees to DPs at least 01 month before land clearance. IfDP is requested for cutting affected trees, PMBs will pay money for this work. DP has right for using salvageable trees.

- Full compensation for impacted house and allowances to DPs at least 05 months before land clearance.

- Payment to DPs will be delivered by PMBs and ORCs

- Cleared residential could be used with other restricted purposes.

- Financel land available for rehabilitation and restoration and well information disclosel disseminate to DPs and key stake

Second Transmission and Distribution Project Outline Mid Term Review Report

I I

Page 65: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

No. Type of loss Application Definition of

Compensation Policy Implementation Issues entitled DPs

according to the Compensation Decree holders. 197/2004/ND-CP - PMBs and local authorities will consult with DP who are - Rehabilitation assistance ifDPs permanently eligible to restoration programs for their options and prepare losing business or more than 25% of their proposal for restoration programs in the period of RAP incomes. implementation.

, - Incentive for relocating in a timely manner: maximum 5,000,000 VND/HH

6 Permanent acquisition All DPs -do- For DP losing productive land: - Consultation for DP's options on land compensation. of land for tower occupied land a. Land loss less than 20% of their total - PMB and local authorities determine and ensure that foundations, substation and properties landholdings compensation will be at replacement cost at the time of and access roads etc. associated with - Cash compensation for the lost area if the payment.

land remaining plot is still economically viable. - Replacement land, and resettlement sites development. permanently

- Cash compensation for the whole impacted - DPs receiving compensation will demolish the impacted areas impacted by

plot if the remaining plot is not economically and reconstruct/or improve their houses themselves. towers foundations,

viable. - Full compensation for trees and fruit trees to DPs at least 0 I

substation and - Cash compensation for properties associated month before land clearance. If DP is requested for cutting

access roads etc. , with land affected trees, PMB will pay money for this work. DP has right

b. Land loss equal or more than 20% of their for using salvageable trees.

total landholdings: - Full compensation for impacted house and allowances to DPs

DP can opt for the followings: at least 05 months before land clearance.

i)"Land for land" with the same area and - No award civil work contract before completion of

productive ofimpacted area if the remaining compensation and reorganizing houses or relocation.

plots are still economic viable and for the - Payment to DPs will be delivered by PCs and DRCs whole impacted plots if the remaining plots - Finance/land available for compensation! rehabilitation and are not economic viable. well information disclose/ disseminate. ii) Cash for land at the replacement cost. - PMBs and local authorities will consult with DP who are - Compensation for trees and affected fruit eligible to restoration for their options and prepare proposal for trees at the replacement cost. restoration programs in the period of RAP implementation.

- Rehabilitation assistance. - DPs will be granted with Land Use Right Certificate

For DP losing Residential and garden land: without payment of administrative fees.

- If remaining land is sufficient for reorganizing (not less than 60 m2): Cash compensation for lost area and assets associated with land.

- -- ---, ---, .. _-" -- -- -_ ....... _ ..... ----~-.--- .... -- - ~-----,.-~-, ....... -

A-23 Second Transmission and Distribution Project

. Outline Mid Term Review Report

Page 66: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

No. Type oflos5 Application Definition of entitled DPs

7 DP impacted on All DPs -do-business or other impacted on services business and

other services

. 8 Public Works- All impacted All impacted

Temporary institutional institutional DPs

impacts DPs shall be

(who directly approached in

manage and advance for

operate such cooperation in

impacted public impact mitigation

works systems) measures as well as measures for maintaining the normal functioning of their impacted systems by the Contractor(s)

- Permanent - do- - do-

Compensation Policy

- If remaining land is not sufficient for reorganizing:

DP can opt for i) cash compensation at replacement cost for land and assets on land, or ii) "land for land" compensation for the whole residential area which DP occupied (not only for the impacted areas) and properties associated with occupied land. For affected house and building, the same entitlement to DP of categories 3 or 4 or 5.

(a) Temporary impact on business or other services.

Compensation for income lost in the affected time

(b) Permanent impact on business or other services.

Rehabilitation assistance .

• Alternative measures to maint-ain the normal functional of the

public works (Le. roads, water supply, drainage systems, telephone lines etc.)

• Reinstatement after the project construction.

• All expenses on alternative measures to maintain the normal functioning of the impacted systems shall be born by Contractor(s).

• Alternative measures to maintain the normal - ._- .. - .. - --_ ... _- "~

A·24

--_ .. -

Implementation Issues

- Full compensation for incomes lost to DPs at least 01 month before land clearance.

- PMBs and local authorities will consult with DP who are eligible to rehabilitation for their options and prepare proposal for rehabilitation programs in the period ofRP implementation.

Contract(s) with Contractor(s) should bear one article 011 this specific responsibility of the contractor(s):

• approach the institutional DPs for cooperation;

• arrange and pay for the expenses of the alternative measures to maintain the normal functioning of the impacted systems to the satisfaction of the institutional DPs.

- do

Second Transmission and Distribution Project Outline Mid Term Review Report

!

Page 67: ABBREVIATED RESETTLEMENT PLAN (ARP)€¦ · ARP . TD2 Sub-Project: Quan Ngang [lOkV Substation and Branch Line . ARP CRC DPC DMS CPEC EVNCPC PPC PAP PAH . ABBREVIATION : Abbreviated

No. Type of loss Application Definition of

Compensation Policy Implementation Issues entitled DPs

impacts functional • complete the works for 'alter-

of the public works (Le. roads, water supply, native solutions' prior to the com-drainage systems, telephone lines etc.) mencement of the project works .

• All expenses on alternative measures to maintain the normal functioning of the impacted systems shall be born by Contractor(s).

9 Permanent impacts on All DPs DPs with house Tenants who have leased a house for PMB and local authorities will assist them in identitying rented houses impacted on lease contract residential purposes will be provided with a alternative accommodation.

their leased cash grant of six months rental fee at the houses for prevailing market rate in the area. residential

-----~rposes -_. ---.. -- ---~. ---...... -.--~- -

A-25 Second Transmission and Distribution Project

• Outline Mid Term Review Report