ac supply system.pdf
TRANSCRIPT
-
1
AC Supply
System
-
2
Importance of Elect System for Auxiliary
Classification of Auxiliaries
Choice of Voltage for Aux
Aux. Power supply system
Emergency AC Supply
Presentation outline
-
3
Auxiliary Power Supply System
The purpose of an Electrical system is to generate and supply electrical energy .
The system should be designed and managed to deliver power with Reliability and Economy.
As these two requirements are quite opposed a balance is required to have an optimum design of Auxiliary power
supply system
The auxiliaries have Ratings range from a few watts to few Mega Watts & Located over a large area
Work under varied Operating Conditions
-
4
Auxiliary Power Supply System
Failure of Auxiliaries can cause Outage of Power Plant
Auxiliaries need Reliable Power Supply
System designed to cater to this need
Loads segregated on the basis of
Rating (to decide Voltage)
Location (to decide the
Feeding Point)
Change-over schemes & Alternate Power Supply arrangement
to ensure Reliability
-
5
Elements of Aux. Power System
More than 95% of the auxiliaries are driven by Motors
Different Voltage levels are interconnected through
Transformers
Miscellaneous Elements
Incomers
Ties
Diesel Generators
-
6
Auxiliary Power Supply
Voltage Rating of Motors Decided based on kW Rating Rating 160kW 415V (LV), Contactor > 160kW & 200kW 415V (LV), Breaker > 200kW & 1500kW 3.3kV (MV), Breaker > 1500kW 11kV (MV), Breaker Frequent Start / Stop Operations (Coal Conveyor Motors)
MV Vacuum Contactor
List of Boards / Feeding Points arrived at based on Location of Load Centers / Systems
Quantity & Rating of Transformers calculated based on Load & Operational Requirements
Rating of Board Calculated based on the Operating Load & Transformer Rating
-
7
MV Switchgears System Parameters
Nominal System voltage 6.6kV 11kV 3.3kV
Highest System voltage 7.2 kV 12kV 3.6kV
Rated Frequency 50Hz 50Hz 50Hz
Number of phases/ poles Three Three Three
System Neutral Earthing Earthed through Resistance of 6.35 to Limit E/F Current to 300A
One minute power frequency
withstand voltage 20kV 28kV 10kV
Impulse withstand voltage 60kV (peak) 75kV (peak) 40kV (peak)
Maximum System Fault Level 40kA (rms)
Short time rating of Eqpt. 40kA (rms) for 1 second
Dynamic withstand rating 100kA (peak)
-
8
LV Switchgears System Parameters
Nominal System voltage 415V, 10%
Rated Frequency 50Hz
Number of phases Three
System Neutral Earthing Solidly Earthed
Maximum System Fault Level 45kA (rms)
Short time rating of Eqpt. 45kA (rms) for 1 second
Dynamic withstand rating 105kA (peak)
-
9
Auxiliary Power Supply System
Sizing of Unit & Station transformer
Start up source short circuit power
Feeding offsite areas loads
Rating of the Switchgear
Loads
Power Supply arrangement
6.6& 0.415kV System
11 & 3.3 & 0.415kV System
-
10
Auxiliary Power Supply
INTRODUCTION
Commonly used voltage level up to 200 MW unit size- 6.6kV, 415V
Initially same voltage level (6.6 kv, 415v) were adopted
for 500 MW unit size as well.
With 500 MW unit, quantitative and qualitative change
in auxiliaries took place.
However no significant change in SWGR available in
market.
Need for optimizing and cost effective solution
-
11
Aux. Supply system(500MW)
Grid Voltage- Normally 400kV for most of the200, 500MW units in India except few deviations
Any Intermediate Voltage Available-to provide reliable start-up power source and to meet initial
commissioning activities as well as to supply bulk
loads(CW system, make-up water etc.) away from
the main plants.Generally used Intermediate voltage
levels are 220kV, 132kV, 33kV
Nature of Auxiliaries i.e. ratings, basic characteristics and location
-
12
Auxiliary Power Supply-
500MW
Selection of voltage levels to be adopted for 500MW and above unit size.
a) 6.6 KV and 415 V system
b) 11& 3.3 kV system
-
13
HT/LT Supply System- Without
GCB
G
UAT-A Dyn1
UAT-B 16.5 KV
6.6 KV Ynd11
GT
Ynyn0
Station TRF-1
UNIT SWGR--A UNIT SWGR--B
Stn. SWGR-SA SB
UST
A
ESP TRF-A
S/Serv.
Trf.-B
UST-B ESP TRF-B
USS-A USS-B 415 V Unit EMG SWGR
X
From DG SWGR
X Blr MCC
Turb MCC
BFP ID Fan
Air Compr
Trf
X X
X
Stn Serv
Trf-A DMP Serv
Trf
1)SWYD
Serv
Trf-1
2)Ash
Handl T/F
1600KVA
6.6 KV
B.C.
N.O.
TMCC
Fdr to
Clarif
Water
SWGR
-
14
220 KV TRANSFER BUS
220 KV BUS I
220 KV BUS II
C.B.
G.T.
UAT-A
GENERATOR
UAT-B
1A 1B
ST
SA SB
Elect. Layout With GCB (220 KV BUS
SYSTEM)
ISOLATOR
GCB
-
15
Transformer feeder Details
To PMCC
MCC/PCCMedium Voltage
Magnetic Contactor
SFU CB
To ACDB
Motor Feeder
Unit Service Transformer
To PMCC
Magnetic Contactor
SFU
To ACDB
Motor Feeder
Dyn11
C.B.
415 V
6.6 KV
-
16
X X
X X
X X X X
DG-1 DG-3
DG-2
DG SWGR-1 DG SWGR-2
UNIT EMER
SWGR-1 UNIT EMER
SWGR-2
UNIT EMER
SWGR-3
UNIT EMER
SWGR-4
-
17
1A 1B 2A 2B 3A 3B 4A 4B
USS-1 USS-2 USS-3 USS-4
UES-1 UES-2 UES-3 UES-4
DG SWGR-1 DG SWGR-2
DG-3 DG-1 DG-2
EMERGENCY SWGR. SYSTEM
-
18
EMCC
(1) AOP-1 (2) Em. Lighting Trf.
(3) TVDC Reserve Supply (4) UPS Ch.
(5) Scanner Air Fan (6) BVDC Reserve Supply
(7) AC Seal Oil Pump (8) Air Heater Lub Oil Panel
(9) Jacking Oil Pump (10) Stator Water Pump-B
(11) Barring Gear (12) +26 v DC ATRS Ch. B
(13) -26V DC ATRS Ch.B (14) 26V DC FSSS Ch. B
(15) 26V DC DDC Ch. A
-
19
From Unit SWGR A Normally
(1) BFP-1C (2) BFP-1A
(3) PA Fan-1A (4) ID Fan -1A
(5) UST-1A (6) ESP T/F -1A
(7) FD Fan -1A (8) Coal Mill- 1A, C, E
(9) CEP-1A,C (10) ACW Booster Pump-1A
(11) Bus V.T.
-
20
USS A
(1) Unit Em. SWGR (2) Boiler MCC
(3) BVDC A (4) Turb. MCC A
(5) 220V Dc Ch. A (6) +24 DC ATRS Ch. A
(7) -24V DC ATRS Ch.A (8) Turb ACDB A
(9) +24 V DDCMIS Ch. B (10) Gen Control Panel
(11) Boiler ACDB A a) Grav. Feeder A,B, C,D,E,F
b) S/B MCC Feeder-1
c) INC From USS B
(12) MOT Centrifuge
-
21
USS B
(1) UPS Ch. (2) +24V FSSS Ch.
(3) TVDC (4) Boiler MCC B
(5) Turb MCC B (6) Turb ACDS B
(7) Boiler ACDB B
-
22
THANK YOU