achieving operational efficiency with sound asset management … · 2016-07-26 · select project...

33
Achieving Operational Efficiency with Sound Asset Management Strategies Cathy Nelson – ACWD Mark Rytilahti – POWER Engineers

Upload: others

Post on 02-Apr-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Achieving Operational Efficiency with Sound Asset Management

StrategiesCathy Nelson – ACWD

Mark Rytilahti – POWER Engineers

Page 2: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

ACWD Background

• Organized in 1914• Serves Fremont, Newark, and Union City

California- Area – 104.8 square miles- Population – 343.499- Customers – 81,7009- Employees – 230 Full-time

• Supply Sources- State Water Project – 40%- San Francisco PUC (Hetch Hetchy) – 20%- Alameda Creek Watershed Runoff – 40%

Page 3: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

ACWD Background

• Production- Average Daily Production of 34.4 MGD (FY 2014-

2015)- Maximum Daily Production of 52.3 MGD (FY 2014-

2015)

• 880 Miles of Pipe• 12 Reservoirs and Tanks• Three Active Treatment Facilities

- Water Treatment Plant # 2 – 26 MGD Capacity- Newark Desalination Facility – 12.5 MGD Capacity- Blending Facility – 48 MGD Capacity

Page 4: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

ACWD Service Area

Page 5: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Software Environment

• Windows Server 2008 R2• SQL Server 2008 R2• ArcGIS 10.2.2• Cityworks 2014 SP6• infraMap 7.1.34• JD Edwards 9.1• Cayenta 7.5

Page 6: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

ACWD Organization

• Office of the General Manager• Engineering and Technology Services

- Information Technology- GIS

• Operations & Maintenance- Distribution Maintenance

• Finance• Water Resources

Page 7: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Project Goals

To address DMD unique business needs, the Asset Management System must:• Reduce or control costs• Improve or maintain service levels• Ensure accurate and timely asset and

maintenance data• Integrate cleanly and cost-effectively with

ACWD’s existing applications

Page 8: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Project GoalsReduce or Control Costs

• Tailor systems to streamline processes• Eliminate redundant data entry• Track only what matters• Support an evidence-based repair/replacement

program

Page 9: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Project GoalsImprove or Maintain Service Levels

• Design the system to allow ACWD to be proactive in:

- Maintenance - Customer response- Backlog management

• Tight integration with Cayenta

Page 10: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Project GoalsEnsure Accurate and Timely Asset and Maintenance Data

• Tight GIS integration• Leverage the existing field GIS application,

infraMAP• Capture data in the course of doing work

- Condition- As-built (new and corrections)- Relevant actuals

Page 11: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Project GoalsIntegrate With ACWD’s Existing Applications

• Eliminate redundant data entry• Leverage strengths of existing technology• Provide efficient end-to-end business

processes by integrating Cityworks with other District systems:

- Cayenta- JDE- SharePoint - DCJETS/JETS+

Page 12: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Integration Overview

Page 13: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Cayenta IntegrationC

usto

mer

Se

rvic

eTr

oubl

esho

oter

Ope

ratio

ns D

ispa

tch

Page 14: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Cayenta IntegrationService Order to Service Request

Customer Service enters service order

into CIS (Cayenta)

Service Request (SR) automatically

created in Cityworks and is immediately

available to the Trouble Truck, field

crews or office staff

Cityworks shows SR

location and provides crew with request information

and GIS asset details. Crew updates the request with resolution

Resolution details

immediately available via Cityworks to Dispatch and

other Cityworks

users

Interface updates the

CIS (Cayenta) with resolution

information and optionally

closes the service order

Page 15: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Cayenta IntegrationService Request to Service Order

Dispatch creates Service

Request in Cityworks and

it is immediately

available to the Trouble Truck, field crews or

office staff

Service Order is automatically

created in Cayenta.

Cityworks shows SR

location and provides crew with request

information and GIS asset

details. Crew updates the request with resolution

Resolution details

immediately available via Cityworks to Dispatch and

other Cityworks users

Interface updates the

CIS (Cayenta) with resolution information and

optionally closes the

service order

Page 16: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Cayenta IntegrationCayenta Meter Data In Cityworks

Page 17: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Cayenta IntegrationBarcode Scanning of Meter Number

Page 18: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

JD Edwards IntegrationACWD DMD Work Order Life Cycle

6. Assign WO and Update Status (Ready to Work or

In Progress)

8. Use JDE to Pick, Issue, and Return Parts for WO

NEW

2. Screen and Update WO (Verify WO Data, Note if

Reimbursable)

13. Complete Work and Update Status, Dates, Leak

and Meter Data in iWater

No

Customer Service Request Process

Yes

NEW

3. Emergency? Yes

5. Plan and Schedule the Work (Update Status as

Needed: RTP, RTS)

No

4. Work Needed? Yes 20. Cancel the Work Order

No

RTASSIGN

R2WORK or

WIP

11. Contractor Work (Child WO is

RTW)?

1. Create Cityworks WO; Select Template and Verify/

Select Project (JDE Job).

WIP orCOMPREVIEW

15. Pay Invoice in JDE (Distribute Lines Items to

WOs)

9. Complete Daily Paper Timesheets (Charge Time

to JDE WOs)

R2WORK or WIP

7. Interface Creates JDE WOs and Updates JDE WO

Status

12. Interface Sends WO data to/from iWater for WOs assigned to DMD

10. OPS Enters Time in JDE (Charge to WO)

16. Interface Sends Time, Inventory, Equipment, and

Service Transactions to Cityworks

17. Review, Update, and Close Completed Work

Orders in Cityworks

WIP

18. Interface Closes JDE WO (Triggers Collection of Reimbursables if Needed)

21. Interface Checks for JDE WO and

Cancels if Needed

CANCELLED

COMPCHILD or CLOSED

19. Create Cyclical, Multi-asset WOs for PM ProgramRTSCHED

23. Interface Sends Meter Readings and Serial

Numbers to Cayenta SO

22. Meter Shop: For Meter WO, Verify Reading and WO Status (Complete)

COMPREVIEW

CLOSED

24. ENGINEERING Creates JDE Jobs for Projects and Sends Project Files to DMD

25. Interface Sends Active JDE Jobs to Cityworks (Updates Project List)

14. Emails WO and Permits to Contractor and Update

WO Status

Page 19: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

JD Edwards IntegrationWork Orders

Work orders created in

Cityworks by crew leads, supervisors,

clerks

Estimated Bill of Material

automatically transferred to

JDE via Cityworks/JDE

interface. Warehouse clerk

loads material for crew

Cityworks map shows where

work is required. Field crews

have access to work order

details and GIS asset details

Crew enters resolution

information into Cityworks and material, labor, equipment info

into JDE

Cityworks populated with actual costs for the work order

Page 20: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

JD Edwards IntegrationWork Order Bill of Material

Page 21: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

JD Edwards IntegrationWork Orders/Service Orders

Meter related work orders created in

Cityworks by crew leads.

Service Request

automatically created in

Cityworks and Service Order automatically

created in Cayenta

Cityworks map shows where

work is required. Field

crews have access to work order details.

Crew completes work

and closes work order.

Cityworks Service Request

automatically closed

Cityworks/ Cayenta

interface sends meter

information to Cayenta for

manual processing.

Page 22: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Integration Approach

Page 23: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Integration Approach

• NET solution built on top of NServiceBus (Open Source). - Licensed with POWERBus360- Web services for integrating non-.NET solutions

• Cityworks adapter and standard Cityworks messages• High performance and scalability

- Async Messaging, Failover, and Performance Monitoring

• Reliable integration with automatic retries- Reliable transports (MSMQ, SQL Server transports and more).- Automatic retries and failure notifications.- Reliable persistent message storage.

• Workflow (long-running Sagas) and background task scheduling

• Centralized auditing of messages

Details

Page 24: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Integration ApproachArchitecture

Page 25: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

GIS IntegrationMap Display

Page 26: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

GIS IntegrationAGS Services

Page 27: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

GIS IntegrationAsset Data Capture

Page 28: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

GIS IntegrationLocation in Polygon

Page 29: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Key Performance Indicators

Identified 27 key performance indicators to track with the integrated system. Examples include:• Large Valves Exercised on Schedule

- % of 12-inch and Larger Valves Exercised in Last Two Years

• Water Loss Due to Leaks and Breaks- Gallons of Water Lost due to Main Breaks

• Leak Detection Program Pace- Miles of Main for which Leak Detection

Completed

Page 30: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Key Performance Indicators

• Service Restoration Time- % of Confirmed Leaks and Breaks for which

Service Restored within 6 Hours• Main Break Repair Cost

- Median Cost to Repair Emergency Main Break• On-time Construction Planning

- % of Customer Projects Started within 10 Business Days of being Ready to Assign

• Meter Mapping- % of meter locations that are field-verified

Page 31: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Status

• Soft Launch Go Live – June 3- Subset of users (12)

• Hard Launch Go Live – June 27- All Users (52)

Page 32: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Questions?

Page 33: Achieving Operational Efficiency with Sound Asset Management … · 2016-07-26 · Select Project (JDE Job). WIP or COMPREVIEW 15. Pay Invoice in JDE (Distribute Lines Items to WOs)

Contact Info

Cathy NelsonAlameda County Water [email protected]

Mark RytilahtiPOWER [email protected] Booth 224