achieving simplicity for continuous teeroff bridges
TRANSCRIPT
Achieving Simplicity for Continuous Teeroff BridgesMichael Kakulas and Nick Keage
Reid/Tonkin Interchange
Project Overview
2
• Tonkin Hwy
− Reid/Tonkin Interchange to Maralla Road – 16km
• Reid Hwy
− Malaga Drive to Altone Road – 4km
• D&C Contract
• GNC
− BGC
− Laing O’Rourke
• AAJV – Joint Venture
− AECOM
− Arcadis
3 Northlink WA Central Section
Project Overview
• 25 bridge structures
• 15 Road bridges
− 5 continuous (up to 42m spans)
− 10 simply supported (21m to 38m spans)
• 1 Fauna bridge
• 3 Footbridges
• 6 Underpasses
• Nearly 12km of Noise and Screen Walls
• 8 Overhead gantries, 4 cantilever gantries
• Retaining walls
4 Northlink WA Central Section
Project Overview, cont.
Design Development
5
• Five of the bridges were highly skewed bridges:
− Difficult to construct pier diaphragms
− Complicated to design and difficult to construct link slabs
• Continuous design need to avoid:
6 Northlink WA Central Section
Why Continuous?
− Transverse diaphragms
− Additional formwork
7 Northlink WA Central Section
Development
HEADSTOCK
COLUMN
ORDINARY REINFORCEMENT
DECK PRECAST BEAM
INSITU DIAPHRAGM
STRANDSEND BLOCK
TEMPORARY SUPPORTS
Transverse in-situ diaphragm
COLUMN
DECK
STRANDS
VOID
8 Northlink WA Central Section
Development, cont.
SOLID END BLOCK
PRECAST BEAM
DECK
STITCH
STRANDS
9 Northlink WA Central Section
Development, cont.
ORDINARY REINFORCEMENT
SOLID END BLOCK
PRECAST BEAM
COLUMN
VOID
DECK
STITCH
STRANDS
10 Northlink WA Central Section
Development, cont.
ORDINARY REINFORCEMENT
SOLID END BLOCK
PRECAST BEAM
COLUMN
VOID
DECK
STITCH
STRANDS
11 Northlink WA Central Section
Development, cont.
ORDINARY REINFORCEMENT
SOLID END BLOCK
PRECAST BEAM
COLUMN
VOID
DECK PRECAST BEAM
STITCH
STRANDS
12 Northlink WA Central Section
Development, cont.
ORDINARY REINFORCEMENT
SOLID END BLOCK
LIFTING LOOP
COLUMN
VOID
DECK PRECAST BEAM
STITCH
STRANDS
13 Northlink WA Central Section
Development, cont.
ORDINARY REINFORCEMENT
SOLID END BLOCK
LIFTING LOOP
TEMPORARY SUPPORTS
COLUMN
VOID
14 Northlink WA Central Section
Tender Stage Details
15 Northlink WA Central Section
Tender Stage Details, cont.
• No requirement for any on site formwork
• No requirements for post tensioning
• No grouting of the stitch joint required
• No additional reinforcement in the Teeroff
16 Northlink WA Central Section
Improvements over other methods
• Shear transfer
− Bars protruding from web
− Cast-in plates
− Couplers
− Shear key
− Corbel
17 Northlink WA Central Section
Change from Tender Design
• Shear transfer
− Bars protruding from web
− Cast-in plates
− Couplers
− Shear key
− Corbel
18 Northlink WA Central Section
Change from Tender Design
• Shear transfer
− Bars protruding from web
− Cast-in plates
− Couplers
− Shear key
− Corbel
19 Northlink WA Central Section
Change from Tender Design
20 Northlink WA Central Section
Adopted Stitch Design
Detailed Design
21
Design – Strut & Tie
• ‘Indirect support’
• Strut and tie design
• Shear key monolithic with teeroff beam
• Reinforcement placed according to
strut and tie model
• Interface shear capacity across critical
shear planes
22 Northlink WA Central Section
Shear in webs ‘hung up’ by T2
ties
Shear transmitted from teeroff to stitch through
shear key
Transverse tension carried by T1 deck
reinforcement
Shear plane through corbel
and deck
Shear plane between teeroff
and deck
Shear transmitted to bearing through
C1 & C2 struts
Bearing reaction
Insufficient shear capacity
across this interface
Design – Unstressed Strand Anchorage
23 Northlink WA Central Section
• Development Length
• 150db = 2280mm (without onion anchor)
• 106db = 1610mm (with onion anchor)
• Onion anchor contributes additional
bond and mechanical resistance
• Bond resistance from the increased
surface area of the individual wires
• Mechanical resistance from the ‘virtual
work’ of the individual wires
• Onion anchor easily formed by precaster
Design – Anchorage of Positive Moment Reinforcement
24 Northlink WA Central Section
During Construction
• Clause 8.1.8.3(a) AS5100.5
• Fully tensioned strands and passive
reinforcement in teeroff web
In-Service
• Clause 8.1.8.3(c) AS5100.5
• Untensioned strands protruding from teeroff and
passive reinforcement in stitch
Strands projecting from end block
Ordinary reinforcement
Temporary prop
Anchorage reinforcement
In-situ Stitch
Design – Hog Capacity
25 Northlink WA Central Section
Precast End Block
Design – Durability
26 Northlink WA Central Section
• Stitch insulated to minimise risk of
thermal cracking
• Early age plastic settlement cracking
managed by recompacting the concrete
as cracks are observed
• Crack control reinforcement provided in
each direction
• Concrete over the stitch covered by a
waterproof membrane
• No cracking observed
Design – Reinforcement Detailing
27 Northlink WA Central Section
Design – Reinforcement Detailing
28 Northlink WA Central Section
Design – Reinforcement Detailing
29 Northlink WA Central Section
Design – Reinforcement Detailing
30 Northlink WA Central Section
Construction Sequence
1. Construct substructure
2. Erect temporary props
3. Install teeroff beams
4. Place deck and stitch reinforcement
5. Cast deck and stitch
6. Remove temporary props
7. Complete all other construction
activities
31 Northlink WA Central Section
Construction Sequence
• Staged deck pours for larger bridges
32 Northlink WA Central Section
Pour 1Pour 2 Pour 4 Pour 3 Pour 5
Span 3Span 2Span 1
Construction Sequence
33 Northlink WA Central Section
Construction Sequence
34 Northlink WA Central Section
Construction Sequence
35 Northlink WA Central Section
Bearing plate
Bearing plate
Bearing
Teeroff
Galvanised formwork
Blockout in bottom flange
Strands projecting from end block
ELEVATION
PLAN
Construction Sequence
36 Northlink WA Central Section
Stitch void
Construction Sequence
37 Northlink WA Central Section
First stage deck pour
Construction Sequence
38 Northlink WA Central Section
Curved and highly skewed bridge
Construction Sequence
39 Northlink WA Central Section
Benefits of Proposed Detail
• Reduced:
• Structural depth
• Material quantities
• Transfer strength
• Construction cost
• Eliminated:
• Link slabs
• Transverse pier diaphragms
• Tapered bearing plates
• Didn’t Require:
• Additional formwork
• Post-tensioning
• Specialised construction techniques
40 Northlink WA Central Section