achieving simplicity for continuous teeroff bridges

41
Achieving Simplicity for Continuous Teeroff Bridges Michael Kakulas and Nick Keage Reid/Tonkin Interchange

Upload: others

Post on 01-Nov-2021

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Achieving Simplicity for Continuous Teeroff Bridges

Achieving Simplicity for Continuous Teeroff BridgesMichael Kakulas and Nick Keage

Reid/Tonkin Interchange

Page 2: Achieving Simplicity for Continuous Teeroff Bridges

Project Overview

2

Page 3: Achieving Simplicity for Continuous Teeroff Bridges

• Tonkin Hwy

− Reid/Tonkin Interchange to Maralla Road – 16km

• Reid Hwy

− Malaga Drive to Altone Road – 4km

• D&C Contract

• GNC

− BGC

− Laing O’Rourke

• AAJV – Joint Venture

− AECOM

− Arcadis

3 Northlink WA Central Section

Project Overview

Page 4: Achieving Simplicity for Continuous Teeroff Bridges

• 25 bridge structures

• 15 Road bridges

− 5 continuous (up to 42m spans)

− 10 simply supported (21m to 38m spans)

• 1 Fauna bridge

• 3 Footbridges

• 6 Underpasses

• Nearly 12km of Noise and Screen Walls

• 8 Overhead gantries, 4 cantilever gantries

• Retaining walls

4 Northlink WA Central Section

Project Overview, cont.

Page 5: Achieving Simplicity for Continuous Teeroff Bridges

Design Development

5

Page 6: Achieving Simplicity for Continuous Teeroff Bridges

• Five of the bridges were highly skewed bridges:

− Difficult to construct pier diaphragms

− Complicated to design and difficult to construct link slabs

• Continuous design need to avoid:

6 Northlink WA Central Section

Why Continuous?

− Transverse diaphragms

− Additional formwork

Page 7: Achieving Simplicity for Continuous Teeroff Bridges

7 Northlink WA Central Section

Development

HEADSTOCK

COLUMN

ORDINARY REINFORCEMENT

DECK PRECAST BEAM

INSITU DIAPHRAGM

STRANDSEND BLOCK

TEMPORARY SUPPORTS

Transverse in-situ diaphragm

Page 8: Achieving Simplicity for Continuous Teeroff Bridges

COLUMN

DECK

STRANDS

VOID

8 Northlink WA Central Section

Development, cont.

SOLID END BLOCK

PRECAST BEAM

Page 9: Achieving Simplicity for Continuous Teeroff Bridges

DECK

STITCH

STRANDS

9 Northlink WA Central Section

Development, cont.

ORDINARY REINFORCEMENT

SOLID END BLOCK

PRECAST BEAM

COLUMN

VOID

Page 10: Achieving Simplicity for Continuous Teeroff Bridges

DECK

STITCH

STRANDS

10 Northlink WA Central Section

Development, cont.

ORDINARY REINFORCEMENT

SOLID END BLOCK

PRECAST BEAM

COLUMN

VOID

Page 11: Achieving Simplicity for Continuous Teeroff Bridges

DECK

STITCH

STRANDS

11 Northlink WA Central Section

Development, cont.

ORDINARY REINFORCEMENT

SOLID END BLOCK

PRECAST BEAM

COLUMN

VOID

Page 12: Achieving Simplicity for Continuous Teeroff Bridges

DECK PRECAST BEAM

STITCH

STRANDS

12 Northlink WA Central Section

Development, cont.

ORDINARY REINFORCEMENT

SOLID END BLOCK

LIFTING LOOP

COLUMN

VOID

Page 13: Achieving Simplicity for Continuous Teeroff Bridges

DECK PRECAST BEAM

STITCH

STRANDS

13 Northlink WA Central Section

Development, cont.

ORDINARY REINFORCEMENT

SOLID END BLOCK

LIFTING LOOP

TEMPORARY SUPPORTS

COLUMN

VOID

Page 14: Achieving Simplicity for Continuous Teeroff Bridges

14 Northlink WA Central Section

Tender Stage Details

Page 15: Achieving Simplicity for Continuous Teeroff Bridges

15 Northlink WA Central Section

Tender Stage Details, cont.

Page 16: Achieving Simplicity for Continuous Teeroff Bridges

• No requirement for any on site formwork

• No requirements for post tensioning

• No grouting of the stitch joint required

• No additional reinforcement in the Teeroff

16 Northlink WA Central Section

Improvements over other methods

Page 17: Achieving Simplicity for Continuous Teeroff Bridges

• Shear transfer

− Bars protruding from web

− Cast-in plates

− Couplers

− Shear key

− Corbel

17 Northlink WA Central Section

Change from Tender Design

Page 18: Achieving Simplicity for Continuous Teeroff Bridges

• Shear transfer

− Bars protruding from web

− Cast-in plates

− Couplers

− Shear key

− Corbel

18 Northlink WA Central Section

Change from Tender Design

Page 19: Achieving Simplicity for Continuous Teeroff Bridges

• Shear transfer

− Bars protruding from web

− Cast-in plates

− Couplers

− Shear key

− Corbel

19 Northlink WA Central Section

Change from Tender Design

Page 20: Achieving Simplicity for Continuous Teeroff Bridges

20 Northlink WA Central Section

Adopted Stitch Design

Page 21: Achieving Simplicity for Continuous Teeroff Bridges

Detailed Design

21

Page 22: Achieving Simplicity for Continuous Teeroff Bridges

Design – Strut & Tie

• ‘Indirect support’

• Strut and tie design

• Shear key monolithic with teeroff beam

• Reinforcement placed according to

strut and tie model

• Interface shear capacity across critical

shear planes

22 Northlink WA Central Section

Shear in webs ‘hung up’ by T2

ties

Shear transmitted from teeroff to stitch through

shear key

Transverse tension carried by T1 deck

reinforcement

Shear plane through corbel

and deck

Shear plane between teeroff

and deck

Shear transmitted to bearing through

C1 & C2 struts

Bearing reaction

Insufficient shear capacity

across this interface

Page 23: Achieving Simplicity for Continuous Teeroff Bridges

Design – Unstressed Strand Anchorage

23 Northlink WA Central Section

• Development Length

• 150db = 2280mm (without onion anchor)

• 106db = 1610mm (with onion anchor)

• Onion anchor contributes additional

bond and mechanical resistance

• Bond resistance from the increased

surface area of the individual wires

• Mechanical resistance from the ‘virtual

work’ of the individual wires

• Onion anchor easily formed by precaster

Page 24: Achieving Simplicity for Continuous Teeroff Bridges

Design – Anchorage of Positive Moment Reinforcement

24 Northlink WA Central Section

During Construction

• Clause 8.1.8.3(a) AS5100.5

• Fully tensioned strands and passive

reinforcement in teeroff web

In-Service

• Clause 8.1.8.3(c) AS5100.5

• Untensioned strands protruding from teeroff and

passive reinforcement in stitch

Strands projecting from end block

Ordinary reinforcement

Temporary prop

Anchorage reinforcement

Page 25: Achieving Simplicity for Continuous Teeroff Bridges

In-situ Stitch

Design – Hog Capacity

25 Northlink WA Central Section

Precast End Block

Page 26: Achieving Simplicity for Continuous Teeroff Bridges

Design – Durability

26 Northlink WA Central Section

• Stitch insulated to minimise risk of

thermal cracking

• Early age plastic settlement cracking

managed by recompacting the concrete

as cracks are observed

• Crack control reinforcement provided in

each direction

• Concrete over the stitch covered by a

waterproof membrane

• No cracking observed

Page 27: Achieving Simplicity for Continuous Teeroff Bridges

Design – Reinforcement Detailing

27 Northlink WA Central Section

Page 28: Achieving Simplicity for Continuous Teeroff Bridges

Design – Reinforcement Detailing

28 Northlink WA Central Section

Page 29: Achieving Simplicity for Continuous Teeroff Bridges

Design – Reinforcement Detailing

29 Northlink WA Central Section

Page 30: Achieving Simplicity for Continuous Teeroff Bridges

Design – Reinforcement Detailing

30 Northlink WA Central Section

Page 31: Achieving Simplicity for Continuous Teeroff Bridges

Construction Sequence

1. Construct substructure

2. Erect temporary props

3. Install teeroff beams

4. Place deck and stitch reinforcement

5. Cast deck and stitch

6. Remove temporary props

7. Complete all other construction

activities

31 Northlink WA Central Section

Page 32: Achieving Simplicity for Continuous Teeroff Bridges

Construction Sequence

• Staged deck pours for larger bridges

32 Northlink WA Central Section

Pour 1Pour 2 Pour 4 Pour 3 Pour 5

Span 3Span 2Span 1

Page 33: Achieving Simplicity for Continuous Teeroff Bridges

Construction Sequence

33 Northlink WA Central Section

Page 34: Achieving Simplicity for Continuous Teeroff Bridges

Construction Sequence

34 Northlink WA Central Section

Page 35: Achieving Simplicity for Continuous Teeroff Bridges

Construction Sequence

35 Northlink WA Central Section

Bearing plate

Bearing plate

Bearing

Teeroff

Galvanised formwork

Blockout in bottom flange

Strands projecting from end block

ELEVATION

PLAN

Page 36: Achieving Simplicity for Continuous Teeroff Bridges

Construction Sequence

36 Northlink WA Central Section

Stitch void

Page 37: Achieving Simplicity for Continuous Teeroff Bridges

Construction Sequence

37 Northlink WA Central Section

First stage deck pour

Page 38: Achieving Simplicity for Continuous Teeroff Bridges

Construction Sequence

38 Northlink WA Central Section

Curved and highly skewed bridge

Page 39: Achieving Simplicity for Continuous Teeroff Bridges

Construction Sequence

39 Northlink WA Central Section

Page 40: Achieving Simplicity for Continuous Teeroff Bridges

Benefits of Proposed Detail

• Reduced:

• Structural depth

• Material quantities

• Transfer strength

• Construction cost

• Eliminated:

• Link slabs

• Transverse pier diaphragms

• Tapered bearing plates

• Didn’t Require:

• Additional formwork

• Post-tensioning

• Specialised construction techniques

40 Northlink WA Central Section

Page 41: Achieving Simplicity for Continuous Teeroff Bridges