acoustic installation procedure
DESCRIPTION
Installation ProcedureTRANSCRIPT
-
Fresh Air & Hot Air Attenuators
Sheet on the Louver BOX.
Fresh Air Attenuators Elements
Procedure of Isntallation of Fresh & HOT Air AttenuatorsStep 1: Suitable Size Louver Box is made with Steel Channels.and anchored to wall and ground. Steel Frame Work to House Attenuators-Louver Box.
Step 2: Tilted Horzontal Angles are welded within the Louver Box Inside Walls. At a pitch of 100 mm
Step 3: The attenuators of 100 mm thicknes are inserted in the channel slot within the Louver Box.
Step 4: The Louver element locked by welding angle on the external border of the louver Box.
Step 5: MS Sheet is reveted on the outer side of the BOX.
-
Hot Air Ducting for Radiator
Steel Frame Work
MS Sheet
Inter Connecting Canvas
Procedure Hot air Inter connection with RadiatorStep 1: Suitable Size MS steel Frames are made with the requisite opening for Radiator
Step 2: MS sheet is revetted on the steel frame.
Step 3: Radiator and the framework is connected by way of Canvas
-
Hot Air Rain Protection Louvers
Single Leaf Acoustic Hinged Doors
Rain Protection Louvers
Procedure for rain Protection Louvers Installation Steel Frame WorkStep 1: Suitable Size MS steel Frames are made fixed on One End of Hot Air Louvers
Step 2: Rain Protection Elements are revetted on these frames