    SUB MANAGEMENT DEVELOPMENT THROUGH THE

    COMPETITIVENESS AND TECHNOLOGICAL INNOVATION 

    ACTION

    PLAN

    César Ricalde Bellido

    http://www.regioncusco.gob.pe/grde/subgerencia/?op=1

  • 8/18/2019 Action Plan Perú César

    2/17

    Improving the competitiveness of

    productive chains in the usco Region

    Goal of the Project

    Improve competitiveness and sustainability of production

    chains through the development, adaptation, improvement

    and technology transfer.

    Strategy.

    Through non-refundable co-financing business initiatives bytransferring infrastructure, machinery, equipment, supplies,

    materials and services for the benefit of organized economic

    operators

  • 8/18/2019 Action Plan Perú César

    3/17

    OUR VISION

    Cusco to 2021, is a Society with a strong regional identity, based on its Andean

    and Amazonian cultures of origin; manages the development of democratic,autonomous and decentralized manner, and strengthened institutions and

    interrelated organizations, favoring the social welfare as the center and end in

    harmony and dialogue with its natural surroundings.

    We have succeeded in significantly reducing poverty levels, population

    universal access to quality health services and intercultural education from the

    beginning and throughout his life, with equity, justice, and equal opportunity.

    We are articulated and integrated into the national and international

    environment competitively, allowing boost the regional economy and access

    to major markets, expanding opportunities for decent employment for all ,grounded in the capabilities of human potential to generate added value our

    tourism, agricultural resources, biodiversity and energy mining.

  • 8/18/2019 Action Plan Perú César

    4/17

    This project is articulated with the following plans::

    Bicentennial plan Perú 2021

    Regional Coordinated Development Plan to 2021

    National Competitiveness Agenda 2014 2018.

    Regional Competitiveness Plan to 2021

  • 8/18/2019 Action Plan Perú César

    5/17

    Background

    Capital Cusco

    Extension 71,987 km2

    Population 1,300,609

    GDP per capita $ 6,152

    Life expectancy 70.4

    Electricity

    coverage (%)

    78 %

    cacao

    citrus

    coffe

    avocado

    Quinoa,

    kiwicha

    corn

    Quinoa,

    kiwichacamelids

    potato

    livestockguinea

    pig

    honey

  • 8/18/2019 Action Plan Perú César

    6/17

    Limitations of productive chains

    INPUT SUPPLY AND PRODUCTION.

    Low productivity of productive chains.

    Excessive use of fertilizers and pesticides make a

    production with low nutritional value and positioning

    to specialized market niches.

    Produccion non standard and non homogeneous.

    The low quality of soil nutrient.

    GATHERING, PROCESSING AND VALUE ADDED.

    The lack of production and processing technologies.

    Poor practices in the development of derivative

    products.

    Lack of service centers for innovation and

    transformation. 

  • 8/18/2019 Action Plan Perú César

    7/17

    MARKET LINKAGE.

    Low skill and ability of producers to the

    commercial, economic and financial

    management.

    Lack of studies of local, national and

    international markets for products.

    CHAIN COMPETITIVENESS.

    Limited access to basic infrastructure and

    production support.

    Levels of formalization, association and

    organization, are underdeveloped.

    The organizational level in most (not all

    organizations) is fragmented, without

    leadership and littel order.

  • 8/18/2019 Action Plan Perú César

    8/17

    Key Tasks

    I

    Complete study of the productive chains in the region, and their

    prioritization according to their potential for a successfulmarket entry.

    II. Co-financing of business initiatives in prioritized productive

    chains.• Preparation of business plans.

    • Promote the formalization of the organizations as a condition

    for access to government aid.

    • Transfer of materials, machinery and equipment.

    • Leadership programs and development of management

    instruments in producer organizations.

    • Production with certified quality and standardization.

  • 8/18/2019 Action Plan Perú César

    9/17

    Key Tasks

    III. Preparation of operational plans for national and international

    market for the product.

    • Crop diversification with agro-ecological potential.

    • Product development with potential for sale at market

    IV. Implementation of research and innovation centers, than

    provide services to producers.

    Implementation of decentralized technological innovationcenters

  • 8/18/2019 Action Plan Perú César

    10/17

    Resources and Period of the Project

    I. Complete study of the productive chains in the region, and theirprioritization.

    BUDGET: $ 30,000.00

    NUMBER OF STAFF : 1 CONSULTING COMPANY

    PERIOD : 6 MONTHS

    II. Co-financing of business initiatives in prioritized productive chains.

    BUDGET: $ 6’000,000

    NUMBER OF STAFF : 14 OFFICIALSPERIOD : 2 YEARS.

  • 8/18/2019 Action Plan Perú César

    11/17

    Resources and Period of the Project

    III. Preparation of operational plans for national and international

    market for the product.

    BUDGET: $ 20,000.00

    NUMBER OF STAFF : 1 CONSULTING COMPANY

    PERIOD : 4 MONTHS.

    IV. Implementation of research and innovation centers, than provide

    services to producers

    BUDGET: $ 3’000,000.00

    NUMBER OF STAFF : 6 OFFICIALS

    PERIOD : 2 YEARS.

  • 8/18/2019 Action Plan Perú César

    12/17

    TASK 1 Complete study of the productive chains in the region, and their

    prioritization.

    Task Who What When How Resources

    Pick of

    information Consult

    ing

    Group

    Information

    production

    chains

    1st, 2nd, 3rd

    M.

    Interviews and

    visits to

    producers

    Microphone

    Briefing Chart

    Form.

    information

    processing

    Consult

    ing

    Group

    all information

    obtained.

    4th M. information

    technology

    PCs. Laptop.

    Printers

    prioritizingchains

    Consult

    ingGroup

    systematized

    information.

    5th M. Deciding

    Criteria

    criteria table

    final report Consult

    ing

    Group

    priority

    production

    chains

    6th M submission of

    final report

    DVD s. Paper,

    USB

  • 8/18/2019 Action Plan Perú César

    13/17

    TASK 2 Co-financing of business initiatives in prioritized productive

    chains.

    Task Who What When How Resources

    approval of

    budget regional

    Council

    Resolution of

    the regional

    council

    1st, M. Decision of the

    Assembly

    Management

    Economic

    Development

    report.

    Business

    plans

    Sub

    Managem

    ent

    EconomicDevelopm

    ent

    Preparation

    and evaluation

    of business

    plans

    2nd, M. specialized team Budget

    Resource is

    provided tobeneficiaries

    Machinery,

    equipment,supplies

    3rd 9th M. cofinancing for

    purchase.

    Beneficiaries

    counterpart

    monitoring

    and

    evaluation

    Assessment of

    compliance

    with business

    plan

    10th .. 

    24thM.

    visits to

    producers

  • 8/18/2019 Action Plan Perú César

    14/17

    TASK 3 Preparation of operational plans for national and international

    market for the product.

    Task Who What When How Resources

    Pick of

    information Consult

    ing

    group

    Information on

    market needs

    8st, 9nd, M. information

    technology

    Budget.

    information

    processing

    Consult

    ing

    Group

    all information

    obtained.

    10th M. Computer

    programs

    information

    technology

    Final report Consulting

    Group

    Consolidatedinformation

    11th

     M submission offinal report

    DVD s. Paper,USB

  • 8/18/2019 Action Plan Perú César

    15/17

    TASK 4 Implementation of research and innovation centers, that

    provide services to producers.

    Task Who What When How Resources

    Project

    formulation Project

    Office

    Record 1st, 6th M. fill out the forms

    of the ministry

    of economy

    Budet

    Project

    approval

    Ministryof

    economy

    SNIP forms 7th

    8 th

      M. Approval Form

    Project

    implementa

    tion

    Sub

    Managem

    ent

    Economic

    Developm

    ent

    Equipment

    technological

    innovation

    centers

    8th 12th 

    M.

    equipment

    acquisition

    Budget

    provide

    services to

    producers

    technological

    innovation

    centers

    12th 

    24thM

    Personal

    contract

    DVD s. Paper,

    USB

  • 8/18/2019 Action Plan Perú César

    16/17

    TASK SUB TASKS MONTH

    1 2 3 4 5 6 7 8 9 10 11 12 13

    Complete study of the productive chains in

    the region, and their prioritization

    Pick of information

    information processing

    prioritizing chains

    final report

    Co-financing of business initiatives in

    prioritized productive chains

    approval of budget

    Business plans

    Resource is provided to beneficiaries

    monitoring and evaluation

    Preparation of operational plans for

    national and international market for the

    product

    Pick of information

    information processing

    Final report

    Implementation of research andinnovation centers, that provide services

    to producers

    Project formulation

    Project approval

    Project implementation

    provide services to producers