addendum russell creek flood mitigation€¦ · table 2-6 design flows using ar&r 2016, il-23...
TRANSCRIPT
Addendum
Russell Creek Flood Mitigation
Russell Creek Flood Mitigation - As Constructed Flood Modelling
Warrnambool City Council
November 2017
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 2
Document Status
Version Doc type Reviewed by Approved by Date issued
1 Draft Ben Hughes Ben Tate 17/03/2017
2 Draft Final Ben Tate Ben Tate 01/09/2017
3 Final Ben Tate Ben Tate 10/11/2017
Project Details
Project Name Russell Creek Flood Mitigation - As Constructed Flood Modelling
Client Warrnambool City Council
Client Project Manager Rohan McKinnon – Justin Hinch
Water Technology Project Manager Johanna Theilemann
Water Technology Project Director Ben Tate
Authors Johanna Theilemann
Document Number 2805_02R02
COPYRIGHT
Water Technology Pty Ltd has produced this document in accordance with instructions from Warrnambool City Council for
their use only. The concepts and information contained in this document are the copyright of Water Technology Pty Ltd.
Use or copying of this document in whole or in part without written permission of Water Technology Pty Ltd constitutes an
infringement of copyright.
Water Technology Pty Ltd does not warrant this document is definitive nor free from error and does not accept liability for
any loss caused, or arising from, reliance upon the information provided herein.
15 Business Park Drive
Notting Hill VIC 3168
Telephone (03) 8526 0800
Fax (03) 9558 9365
ACN 093 377 283
ABN 60 093 377 283
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 3
EXECUTIVE SUMMARY Water Technology was engaged by Warrnambool City Council to undertake “as constructed” flood modelling
of Russell Creek through North Warrnambool following the construction of structural flood mitigation works in
2016.
As part of this study the design hydrology for Russell Creek was also updated to conform with the new 2016
release of Australian Rainfall and Runoff: A guide to Flood Estimation (ARR2016). The new design peak flows
produced by this study utilise a combination of approaches suggested in ARR2016, including an ensemble
rainfall temporal pattern approach and a Monte Carlo approach to the RORB rainfall runoff modelling.
The design peak flows have reduced from previous assessments undertaken on Russell Creek. This change
can be attributed to several factors including the changed catchment delineation and routing, updated intensity
frequency duration (IFD) information from the Bureau of Meteorology, revised guidance on selection of
appropriate rainfall losses, and the newly available rainfall temporal patterns.
Location 1% AEP
Cardno Flows (2010)
(m3/s)
1% AEP
Water Technology Flows (2017)
(m3/s)
Aberline Rd 45.0 32.0
Wangoom Rd 18.6 17.3
Mortlake Rd 69.5 59.8
Merri River 76.9 64.9
Updated hydraulic modelling for a range of design events included the 4 constructed flood walls and two new
2.4 x 3.6 m box culverts under Mortlake Road. This modelling confirmed reductions in the extent, depth and
velocity of flooding during the range of design events. There were some notable instances of the flood extent
locally increasing due to the higher grid resolution of the hydraulic modelling using new topographic
information, compared to the previous modelling.
A detailed flood risk assessment of revised flood modelling was undertaken and revealed that the works have
reduced the estimated number of buildings likely to experience above floor flooding. Notably, the number of
properties likely to experience above floor flooding during the 1% AEP flood event has reduced from 146 to14
due to the construction of the flood mitigation works, as shown in the table below.
ARI (1 in X years) 1 in 200 yr 1 in 100 yr 1 in 50 yr 1 in 20 yr 1 in 10 yr 1 in 5 yr
AEP 0.5% 1% 2% 5% 10% 20%
Residential Buildings Flooded Above Floor
21 14 6 1 0 0
Commercial Buildings Flooded Above Floor
6 0 0 0 0 0
Properties Flooded Below Floor
369 205 99 69 57 36
Total Properties Flooded 396 219 105 70 57 36
The construction of the mitigation works sees a significant reduction in the population at risk from flooding
along Russell Creek under all flood events considered. Coupled with awareness programs and appropriate
land use planning this program of works will lead to a safer more resilient community.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 4
CONTENTS
EXECUTIVE SUMMARY 3
1 INTRODUCTION 7
1.1 Overview 7
1.2 Study Area 7
1.3 Available Data 8
1.4 Previous investigations 8
1.4.1 North Warrnambool Flood Study for Merri River and Russell Creek (GHD, 2003) 9
1.4.2 Cardno (2007, 2010, 2012) 9
1.4.3 Design of North Warrnambool Flood Mitigation Works (Water Technology, 2015) 10
1.4.4 Discussion 10
2 HYDROLOGY 11
2.1 Overview 11
2.2 RORB Modelling 11
2.2.1 Model Setup 11
2.2.2 Adopted Design Flood Hydrographs 23
3 RACECOURSE CATCHMENT 25
4 HYDRAULIC MODEL 26
4.1 Overview 26
4.2 Hydraulic Model Schematisation 26
4.2.1 2D Grid Size and Topography 26
4.2.2 Roughness 29
4.2.3 Hydraulic Structures 30
4.2.4 Boundary Condition – Inlet Boundaries 31
4.2.5 Boundary Condition – Outlet Boundaries 31
4.2.6 Flood Walls and Culverts – As Constructed 32
4.2.7 Hydraulic Model Calibration 33
5 DESIGN HYDRAULIC MODELLING 34
6 FLOOD DAMAGES ASSESSMENT 38
6.1 Overview 38
6.2 Current Conditions AAD 38
6.2.1 Non-economic Flood Damages 38
6.2.2 Above Floor Flooding 39
7 SENSITIVITY TESTING 41
7.1 Overview 41
7.2 Climate change scenarios 41
7.2.1 Overview 41
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 5
7.3 No Flood Walls 43
7.4 No Mortlake Rd Culverts 43
7.5 Rain on Grid 48
8 CONCLUSION 51
8.1 Overview 51
8.2 Key Outcomes 51
8.3 Recommendations 51
APPENDICES Appendix A AR&R Data hub Output
Appendix B AR&R – Regional Flood Frequency Estimation tool
Appendix C Design Flood Mapping
Appendix D Russell creek structures
LIST OF FIGURES Figure 1-1 Study area 8
Figure 2-1 Russell Creek subareas and reaches 13
Figure 2-2 Russell Creek RORB Fraction impervious map 14
Figure 2-3 Arr 2016 – Recommended Median ILs(mm) (Bk5 Ch3 Fig 5.3.18) 18
Figure 2-4 ARR 2016 – Recommended median cl (mm/hr) 19
Figure 4-1 Creek Cross-section Comparrison 27
Figure 4-2 Model boundary 28
Figure 4-3 Model Topography 28
Figure 4-4 adopted mannings ‘n’ roughness values 29
Figure 4-5 Location of Hydraulic Structures 30
Figure 4-6 Model boundaries 31
Figure 4-7 Flood Wall Locations 32
Figure 4-8 Russell Creek Flood Levee Walls 32
Figure 4-9 Mortlake road flood mitigation culverts 33
Figure 5-1 1% AEP Flood Depth (New existing conditions) 35
Figure 5-2 1% AEP FlooD Depth (New Existing Conditions) 36
Figure 5-3 Comparison of Original and new 1% AEP Flood Depth 37
Figure 6-1 Above floor flooded properties (Red Dots) 39
Figure 7-1 Climate Change rainfall intensity Increase for 1% AEP Event 42
Figure 7-2 1% AEP Flood Depth – No Flood Walls 44
Figure 7-3 1% AEP,12 Hr - Difference Plot – No Walls minus existing 45
Figure 7-4 1% AEP Flood Depth – No Mortlake Road New Culverts 46
Figure 7-5 1% AEP, 12Hr - Difference Plot - No Culverts minus existing 47
Figure 7-6 Warrnambool Pit and Pipe network 48
Figure 7-7 1% AEP Rain of Grid 49
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 6
Figure 7-8 10% AEP Rain on Grid 50
Figure 8-1 Russell Creek - RFFE 60
LIST OF TABLES Table 1-1 Design Peak Flows - North Warrnambool Flood Study for Merri River and Russell CreeK 9
Table 1-2 Cardno RORB Continuing losses 9
Table 1-3 RORB Design Flows 10
Table 2-1 Design Rainfall Depth (mm) for storm Frequency and Duration 15
Table 2-2 Regional kc and Loss Parameters 16
Table 2-3 Calculated Kc parameters 16
Table 2-4 ARR 2016 – Range of Values Used in developing ILsPrediction Equations6 18
Table 2-5 ARR 2016 – Range of Values Used in developing CL Prediction Equations6 19
Table 2-6 Design Flows Using AR&R 2016, IL-23 mm, CL-4.6 mm/hr 20
Table 2-7 Design Flows using Original Losses, IL-20 mm, CL-4.6 mm/hr 20
Table 2-8 Comparison of rainfall depths at upstream and downstream ends of Russell Creek catchment 21
Table 2-9 1% AEP Regional Peak Flow Estimate Comparison 22
Table 2-10 1% AEP Peak Flow Comparison between studies 22
Table 2-11 RORB Monte Carlo peak flow output 23
Table 2-12 Final adopted design flow input and peak flow 24
Table 3-1 1% AEP Peak Flows and Critical Duration 25
Table 3-2 10% AEP Peak Flows and Critical Duration 25
Table 4-1 Mannings ‘n’ roughness values 29
Table 4-2 Hydrualic Structures 30
Table 5-1 1% AEP Flood Level Comparison 34
Table 6-1 Depth of above floor flooding 39
Table 6-2 Damages Assesment 40
Table 7-1 Climate change rainfall intensity increase – peak flows 41
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 7
1 INTRODUCTION
1.1 Overview
Water Technology was engaged by Warrnambool City Council to update and revise the existing Russell Creek
catchment design hydrology, following the construction of key flood mitigation infrastructure. The hydrology is
a key component to the updated flood modelling. The updated catchment hydrology was used to derive design
inflows for revised hydraulic modelling.
Russell Creek is part of the greater Merri River catchment. The Merri River is gauged at Woodford, while
Russell Creek is ungauged with limited available anecdotal flood height information. Due to the lack of
calibration information, this project developed a RORB model and verified the model results to a range of
regional peak flow estimates and estimates produced during previous investigations. A key objective of the
investigation was to update and revise the flood hydrology for the Russell Creek. This included:
Redefining the catchment characteristics based on existing catchment conditions, including the impact of
urban and industrial land use areas.
Determine appropriate catchment parameters including modelled losses.
Redefine flows at 3 primary inflow locations including Wangoom Road, Aberline Road and the
Warrnambool Racecourse.
After completing the revision in hydrology, a new TUFLOW hydraulic model was created of the study area,
incorporating new Light Detection and Ranging (LiDAR) topography, and the “as constructed” flood mitigation
works.
1.2 Study Area
The study area covered the whole Russell Creek catchment as shown by the green outline in Figure 1-1. The
catchment of the Russell Creek covers an area of 37.5 km2. The area that was flood mapped covers the main
urban reaches of the Russell Creek as shown in red on Figure 1-1.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 8
FIGURE 1-1 STUDY AREA
1.3 Available Data
The investigation utilised several existing datasets available from Warrnambool City Council including:
Topography – Light Detection and Ranging (LiDAR) data
VicMap Coastal DEM 1m resolution (2007) supplied by DELWP
Corrangamite DEM 5m resolution (2008) supplied by DELWP
Warrnambool City Council DEM 1m resolution (2017)
Digital Aerial Photography (2013) supplied by DELWP
Spatial Data – VicMap (2016) supplied by DEWLP
1.4 Previous investigations
Numerous flood investigations have been undertaken on this catchment, including:
North Warrnambool Flood Study for Merri River and Russell Creek (GHD, 2003)
Russell Creek Flood Modelling (Cardno Lawson Treloar, 2007)
Design of North Warrnambool Floodplain Management Plan (Cardno, 2010)
Design of North Warrnambool Floodplain Management Plan – Phase 2 (Cardno, 2012)
Design of North Warrnambool Flood Mitigation Works (Water Technology, 2015)
A summary of each of these investigations is included in the following sections outlining key findings.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 9
1.4.1 North Warrnambool Flood Study for Merri River and Russell Creek (GHD, 2003)
GHD undertook a detailed assessment of the Merri River and Russell Creek utilising an Australian Water
Balance Model (AWBM). This investigation was the first formal analysis of flood flows in Russell Creek. At the
time, residential development was already encroaching on the Russell Creek catchment area. The study
derived peak flows for a range of design floods using AWBM, for input to HecRas and Delft FLS. GHD
calibrated the modelling to observed flood levels along Russell Creek and the Merri River. The estimated peak
flows along Russell Creek are shown in Table 1-1.
TABLE 1-1 DESIGN PEAK FLOWS - NORTH WARRNAMBOOL FLOOD STUDY FOR MERRI RIVER AND RUSSELL CREEK
Design Flood
AEP
Aberline Rd
(m3/s)
Mortlake Rd
(m3/s)
Queens Rd
(m3/s)
Merri River
(m3/s)
20% 6.94 15.05 16.20 17.36
10% 12.73 21.99 23.15 24.31
5% 15.05 25.46 27.78 27.78
2% 26.62 43.98 46.29 47.45
1% 34.72 59.03 62.5 62.5
1.4.2 Cardno (2007, 2010, 2012)
Cardno has undertaken numerous assessments of the Russell Creek floodplain, including the Russell Creek
Flood Modelling (2007), Design of North Warrnambool Floodplain Management Plan – Phase One (2010) and
Phase 2 (2012). During the 2007 study, a RORB model was developed for the Russell Creek catchment as
part of a broader Merri River catchment model, the model was validated at the Merri River at Woodford gauge
(236205) and other available historical flood data. The Russell Creek RORB model was developed based on
a catchment area of 32.7 km2. A total of 17 sub catchments were delineated in the RORB model, the modelled
fraction impervious values were as follows:
Rural land = 0.05
Existing residential areas = 0.52
Proposed residential areas and racecourse = 0.45
The study adopted a constant kc of 6.45, m of 0.8, Initial Losses (IL) of 20 mm, with Continuing Loss (CL)
varying with AEP. Table 1-2 shows the adopted CL values.
TABLE 1-2 CARDNO RORB CONTINUING LOSSES
Design AEP CL (mm/hr)
20% 1.35
10% 1.45
5% 1.79
2% 2.07
1% 2.13
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 10
The Cardno flood modelling determined higher peak flows in Warrnambool than the previous GHD
assessment. The determined peak flows across four locations are shown in Table 1-3. These flows were
modelled in the 1D/2D hydraulic modelling program SOBEK, subsequent concept flood mitigation designs
were based on this modelling. The hydrology developed as part of the Cardno investigations was rigorously
reviewed by Erwin Weinmann and Robert Keller through a peer review process at the time. The comments
made by the reviewers were actioned as part of the study delivery and have been considered as part of the
investigation.
TABLE 1-3 RORB DESIGN FLOWS
Design Flow
AEP
Flow at Aberline Rd
(m3/s)
Flow at Wangoom Road
(m3/s)
Flow at Mortlake Road
(m3/s)
Flow at Merri River Confluence
(m3/s)
20% 15.9 7.1 24.7 26.0
10% 20.4 8.9 32.6 34.5
5% 26.3 11.2 42.3 45.8
2% 36.5 15.1 56.3 61.8
1% 45.0 18.6 69.5 76.9
1.4.3 Design of North Warrnambool Flood Mitigation Works (Water Technology, 2015)
The previous Water Technology assessment assisted in the detailed design of flood mitigation structures. The
study utilised hydrology built into the existing SOBEK hydraulic model. These flow boundaries included in the
SOBEK model were based on extracted hydrographs from the Cardno Russell Creek RORB model as provided
by the Warrnambool City Council.
Water Technology did not alter the hydrographs produced by Cardno for use during the detailed design phase
of the mitigation projects, however it was noted that the hydrology was conservative and possibly
overestimated design flows. The SOBEK model only considered the two major inflows at north of Wangoom
Road and Aberline Road. The Racecourse catchment appears as a single sub-catchment draining directly to
Russell Creek and therefore was not included as an inflow boundary in the previous SOBEK modelling.
1.4.4 Discussion
Numerous assessments of Russell Creek have been undertaken in the past 15 years. These assessments all
build on our knowledge and understanding of this catchment. The previous assessments were all based on
best practice methodology at the time of their completion and in some cases, have been peer reviewed by
industry experts. These assessments are a source of comparison for the revised hydrology, which is based on
new techniques for undertaking design hydrology, emerging from the revised version of Australian Rainfall and
Runoff: A Guide to Flood Estimation (2016)1.
1 Ball J, Babister M, Nathan R, Weeks W, Weinmann E, Retallick M, Testoni I, (Editors), 2016, Australian Rainfall and Runoff: A Guide to Flood Estimation, Commonwealth of Australia.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 11
2 HYDROLOGY
2.1 Overview
A hydrologic model of the Russell Creek catchment was developed to determine design flow hydrographs at
several locations within the Russell Creek catchment to be used as inflow boundary conditions in the hydraulic
model. The rainfall-runoff program, RORB, was utilised for this study.
RORB is a non-linear rainfall runoff and streamflow routing model for calculation of flow hydrographs in
drainage and stream networks. The model requires catchments to be divided into subareas, connected by a
series of conceptual reaches and storage areas. Observed or design storm rainfall is input to the centroid of
each subarea. Specific initial and continuing losses are then deducted, and the excess runoff is routed through
the reach network.
The adopted methodology described below is based on current guidelines described in ARR20161. A Monte
Carlo approach was adopted. Monte Carlo is a probabilistic approach whereby a large number of potential
parameter combinations are modelled and probability distributions considered to determine the design flow
AEPs. In this instance 10,000 model runs were simulated, with varying initial losses and temporal patterns, to
produce a probabilistic distribution of design flows. This allowed design peak flows for the range of design
events to be determined. A Monte Carlo approach results in less uncertainty than a traditional deterministic
approach. The final parameters adopted for each design event were based on selecting a combination of
parameters from the simulations which produced the peak flow along all reaches of Russell Creek within the
study area from the Monte Carlo analysis.
The Russell Creek catchment is ungauged, therefore the adopted design flows were validated against a range
of other flow estimate methods including past studies, regional peak flow estimation equations and an existing
RORB model developed as part of previous hydrological assessments.
2.2 RORB Modelling
2.2.1 Model Setup
2.2.1.1 Sub-area and Reach Delineation
Sub-area boundaries and reaches were delineated using ArcHydro and revised as necessary to allow flows to
be extracted at the points of interest. The RORB model was constructed using MiRORB (MapInfo RORB tools),
RORB GUI and RORBWIN V6.23.
Subareas and reaches were delineated based on the provided LiDAR data. Nodes were placed at areas of
interest (to extract flow hydrographs), the centroid of each sub-area and the junction of any two reaches. Nodes
were then connected by RORB reaches, each representing the length, slope and reach type. The RORB model
had 48 sub-areas ranging in area from 9 to 210 ha. The sub-catchment delineation and reach network is shown
in Figure 2-1.
The catchment area of the RORB model is 37.5 km2, this is slightly larger than the previous RORB model. The
new model includes an area of relatively flat rural land to the south east of the creek which had previously
been unaccounted for and a small catchment north of Wangoom Road which is along the crest of the Russell
Creek and Merri River catchments which drain to Russell Creek via an excavated channel. The catchment
area was validated against council own data and local knowledge.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 12
Five different reach types are available in RORB. Reach types were selected based on aerial imagery and site
visits. The reach types were predominately “Natural” in the middle and upper catchment and “excavated and
unlined” or “lined channel or pipe” in the lower catchment.
2.2.1.2 Fraction Impervious
Fraction Impervious (FI) values were calculated using MiRORB. Default sub-area FI values were based on an
assessment of current Warrnambool City Council Planning Scheme Zones (current January 2017), and aerial
imagery. The spatial distribution of the fraction impervious data is shown in Figure 2-2. It can be seen there is
a considerable difference in fraction impervious between the lower urban areas of the catchment and the upper
agricultural areas.
The specified FI value for ‘rural areas’ was modelled at 0 (down from the 0.05 used in the previous modelling),
this is in line with industry best practice.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 13
FIGURE 2-1 RUSSELL CREEK SUBAREAS AND REACHES
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 14
FIGURE 2-2 RUSSELL CREEK RORB FRACTION IMPERVIOUS MAP
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 15
2.2.1.3 IFD
Design rainfall depths were determined using the 2016 Bureau of Meteorology online IFD tool2. The rainfall
Intensity Frequency Duration (IFD) parameters were generated for a location in the approximate centre of the
Russell Creek catchment (38.375S, 142.5E) and are shown in Table 2-1 below. There are some variations
between the rainfall depths of the new 2016 and the older IFD values. This is further discussed in the previous
Water Technology Detailed Design report. In the frequent events, the IFD rainfall depths have reduced across
the range of storm durations. For the 1% AEP event the IFD rainfall depths have increased between 4-10%
across the range of storm durations.
TABLE 2-1 DESIGN RAINFALL DEPTH (MM) FOR STORM FREQUENCY AND DURATION
EY Annual Exceedance Probability (AEP)
Duration 1EY 50% 20% 10% 5% 2% 1%
1 hour 11.6 13.5 19.8 24.4 29.3 36.1 41.6
2 hour 14.8 17.1 24.8 30.4 36.2 44.2 50.6
3 hour 17.1 19.7 28.5 34.8 41.2 50.2 57.5
6 hour 22 25.3 36.1 44 52 63.8 73.5
12 hour 28.1 32.2 45.7 55.7 66.2 82.1 95.7
24 hour 35.6 40.3 56.6 69.2 83 103.8 122
48 hour 44.3 49.3 67.7 82.8 99.9 124.1 145.2
72 hour 49.9 55.1 74.2 90.1 108.4 133 154.1
96 hour 54.4 59.7 79.2 95.2 113.5 137.6 158
120 hour 58.4 63.8 83.6 99.4 117.1 140.5 160.1
144 hour 62 67.8 87.8 103.2 119.8 142.5 161.6
168 hour 65.6 71.7 92 106.8 122.1 144.4 163
2.2.1.4 Areal Reduction Factors
Areal reduction factors were used to convert point rainfall to areal estimates and are used to account for the
variation of rainfall intensities over a large catchment. AR&R (2016) areal reduction factors were applied to the
catchment area and extracted from the AR&R data hub3. The catchment lies within the Southern Temperate
Zone of aerial reduction factors and these were applied for all design modelling.
2.2.1.5 Regional kc
kc is the primary routing parameter in RORB. As Russell Creek is an ungagged catchment with no streamflow
record, it is not possible to calibrate the RORB model against known catchment flows and rainfall records. As
such, a comparison between regional equation estimates was made against values determined by other
studies in the south-west coastal region. kc values from four nearby calibrated RORB models were compared
2 Bureau of Meterology Web Tool, http://www.bom.gov.au/water/designRainfalls/revised-ifd/?year=2016 3 AR&R 2016 Data Hub, http://data.arr-software.org/
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 16
along with the available previous Russell Creek RORB models. Models with similar catchment characteristics
were used with floodplains on or near the southern Victoria coast.
kc has been shown to be related to the average stream length from subarea centroid to catchment outlet. In
order to compare kc values adopted across catchments a ratio of average stream length and kc can be made,
as outlined in Equation 1.
𝑘𝑐 𝑅𝑢𝑠𝑠𝑒𝑙𝑙 𝐶𝑟𝑒𝑒𝑘 = 𝑘𝑐 𝐶𝑎𝑡𝑐ℎ𝑚𝑒𝑛𝑡
𝐷𝑎𝑣 𝐶𝑎𝑡𝑐ℎ𝑚𝑒𝑛𝑡
× 𝐷𝑎𝑣 𝑅𝑢𝑠𝑠𝑒𝑙𝑙 𝐶𝑟𝑒𝑒𝑘
Equation 1 kc comparison scaling
Where:
kc Russell Creek kc parameter for Russell Creek catchment
kc Catchment kc parameter for regional catchment
Dav Russell Creek Average distance from centroid of subarea to model outlet (Russell Creek)
Dav Catchment Average distance from centroid of subarea to model outlet (regional catchment)
Table 2-2 shows the adjusted kc values as well as the adopted loss values. It should be noted that the Surry River catchment results were not considered due to unique catchment characteristics as noted by the relatively high kc to Dav ratio and low losses. The new Russell Creek RORB model has a Dav of 9.29.
TABLE 2-2 REGIONAL KC AND LOSS PARAMETERS
Location kc m Dav IL CL Russell Creek
Adjusted kc
Merri River 58 0.8 64.24 20.0 2.13 8.38
Moyne River 46 0.8 31.06 15.0 1.3 13.75
Surry River 75 0.8 20.42 4 1.3 34.12*
Wattle Hill Creek 12.5 0.8 12.27 15 2 9.46
Fitzroy River/Darlot Creek 55 0.8 54.76 20 2 9.33
* To be ignored due to the skewed results from unique catchment characteristics
The adjusted kc parameters range between 8.38 to 13.75 (discounting the Surry River model as mentioned
above). The original GHD (2003) model used a kc value of 4.5. The model was revised and updated by Cardno
(2010), and used regional equations based on the calibrated Merri River model, and determined a kc of 6.45.
Several kc estimation equations are available within the RORB software, the range of equations and their
respective determined kc values are shown in Table 2-3.
TABLE 2-3 CALCULATED KC PARAMETERS
kc Equations kc
Default RORB Eqn. 13.48
Victoria data (Pearse et al, 2002) 11.62
Aust Wide Dyer (1994) (Pearce et al) 10.60
Victoria Mean Annual Rainfall > 800mm 13.14
Victoria – Mean Annual Rainfall < 800mm 5.17
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 17
A number of sensitivity tests were undertaken varying the modelled kc value within the 8.38 to 13.75 range,
and a kc of 8.38 was adopted. This is due to the close relationship between the Merri River and the Russell
Creek. Furthermore raising kc towards the higher end of the estimates resulted in dramatically lower peak
flows than all of the previous validated hydrologic assessments. Adopting a kc of 8.38 was justified given the
kc fell within the range of the various regional approximations and donor catchments, and it provided flows that
were relatively consistent with past studies. The kc value adopted for the Russell Creek model was based on
previously modelled values and scaling using the Kc:Dav ratio of the calibrated Merri River model. This Kc is
entirely reasonable, sits well within the range of acceptable Kc values, and is comparable to the previous
modelling by Cardno. This will be further validated in later sections of this report when comparing adopted and
previous design flows.
2.2.1.6 Routing Parameter - m
The RORB m value is typically set at 0.8. This value remains unchanged and is an acceptable value for the
degree of non-linearity of catchment response (Australian Rainfall and Runoff, 1987). It is rare to vary the m
value and there were no reasons to do so in this study, particularly given the lack of calibration data.
2.2.1.7 Temporal Patterns
Temporal patterns from AR&R (2016) were utilised in the analysis and extracted from the AR&R data hubError!
Bookmark not defined.. As previously described a Monte Carlo approach was adopted in RORB and the full ensemble
of temporal patterns were included within the Monte Carlo simulation. The range of temporal patterns are
included in Appendix A, with relevant ID numbers assigned as referred to in the RORB model output. The
Southern Slopes (Vic/NSW) Zone of temporal patterns was utilised.
The AR&R (2016) approach using Monte Carlo analysis with various temporal patterns allows for exhibited
variability in rainfall events of similar magnitude. The new temporal patterns are based on historical storms
using the extensive network of pluviograph data collected by the Bureau of Meteorology (BoM).
The AR&R (2016) design temporal patterns are broken into a number of AEP groupings and the subsequent
suitable AEP range for application, these include:
Very Rare – Rarest 10 within region
Rare – Suitable AEP range 3.2% AEP and rarer
Intermediate – Suitable for AEP range 3.2% - 14.4%
Frequent – Suitable for AEP range more frequent than 14.4%
Previous assessments using the earlier ARR (1987) used a single temporal pattern across all design events. The ARR (2016) approach recommends that at least 10 temporal patterns be used for each event. These 10 temporal patterns change depending on the duration and the event considered.
2.2.1.8 Design Losses
Design losses were estimated by using several methods including use of the new AR&R datahub tool3, the
guidance provided in Book 5 Chapter 3 of ARR (2016), the design loss prediction equations developed by Hill
et al (1998)4 and Hill et al (2014)5, and previous investigations. The estimated losses produced by the
recommended methods in AR&R (1987) are lower for both IL and CL, which would produce higher peak flow
4 Hill, P., Mein, R. and Siriwardena, L. (1998) How much rainfall becomes runoff? Loss modelling for flood estimation. Cooperative Research Centre for Catchment Hydrology 5 Hill, P. I., Graszkiewicz, Z., Taylor, M. and Nathan, R. J. (2014) Loss models for catchment simulation. State 4 Analysis of rural catchments. May 2014. ARR Revision project
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 18
estimates than when using losses following ARR (2016) guidance. Book 5, Chapter 3 of the new Australian
Rainfall and Runoff provides guidance on the application of losses at a regional level. Figure 2-3 shows the
mapped recommended median storm ILs in mm. The ILs map indicates that 30 mm is a recommended median
ILs in the study area. The Region 3 prediction equations shown in Table 2-4 indicate the median initial loss at
27.5 mm.
FIGURE 2-3 ARR 2016 – RECOMMENDED MEDIAN ILS(MM)6 (BK5 CH3 FIG 5.3.18)
TABLE 2-4 ARR 2016 – RANGE OF VALUES USED IN DEVELOPING ILSPREDICTION EQUATIONS6
Region N Equation Parameter Min Max Median
Region 3 11 5.5.10
SOLPAWHC 0.9 15.9 3.0
DES_RAIN_24HR 106.1 238.9 137.7
ILs 17.0 47.0 27.5
For application in the design rainfall runoff modelling the storm ILs was adjusted to be consistent with the
application of burst rainfall as no preburst rainfall was added to the IFD design rainfall depths. The ARR (2016)
6 AR&R (2016), Ball J, Babister M, Nathan R, Weeks W, Weinmann E, Retallick M, Testoni I, (Editors) Australian
Rainfall and Runoff: A Guide to Flood Estimation, © Commonwealth of Australia (Geoscience Australia), 2016.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 19
data hub provides information relating to pre-burst rainfall depths for the range of design storms. At this location
pre-burst depth ranges from between 1 to 3.8 mm for the 6 hour storm to between 0.8 and 5.4 mm for the 12
hour storm. Given that an ILs of 27.5 to 30 mm is reasonably high a preburst depth of 5 mm was subtracted
from the storm ILs giving the final burst ILb of between 22.5 to 25 mm. Sensitivity testing was performed with
an IL of 20 and 25 mm/hr. Given that the design flows were lower than those estimated from previous studies
it was felt that a degree of conservatism was required and an IL of 20 mm/hr was adopted.
The continuing loss in Figure 2-4 from Book 5 Chapter 3 of ARR (2016) provides a recommended median CL
of 6 mm/hr. The median continuing loss devised from the prediction equation for Region 3 in Table 2-5 shown
below is 3.1 mm/hr.
FIGURE 2-4 ARR 2016 – RECOMMENDED MEDIAN CL (MM/HR)
TABLE 2-5 ARR 2016 – RANGE OF VALUES USED IN DEVELOPING CL PREDICTION EQUATIONS6
Region N Equation Parameter Min Max Median
Region 3 11 5.5.11
DES_RAIN_24HR 1.6.1 128.9 137.7
S0max 17.5 62.8 42.6
CL 0.5 6 3.1
The continuing loss needs to be adjusted according to the RORB model timestep, as per the Figure 5.3.29
from Book 5 Chapter 3 of ARR (2016). A factor of 1.5 is recommended for RORB models with a 5 min timestep.
This resulted in a CL of 4.6 mm/hr to be adopted for RORB design modelling.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 20
The above losses were applied within the RORB Monte Carlo simulation. The CL was set at 4.6 mm/hr for all
scenarios, with the IL sampled using the median IL of 20 mm and the statistical distribution provided within
ARR (2016) and the RORB manual. Extensive sensitivity testing was performed, comparing flows to previous
estimates, see the following section. On balance, the above adopted loss values were felt to provide
reasonable design flow estimates.
2.2.1.9 RORB Model Losses Sensitivity Test
Table 2-6 shows design peak flows and event critical durations using a Monte Carlo simulation, for a median
IL slightly higher than the final adopted median IL shown in Table 2-7. As shown, the change in median IL
does alter the design peak flows, but they are not overly sensitive. Given that the catchment is ungauged,
either of the median IL values could be adopted, as they are both reasonable, but given that the design flows
are lower than that adopted previously, it was decided that the lower median IL value of 20 mm would be
adopted.
TABLE 2-6 DESIGN FLOWS USING AR&R 2016, IL-23 MM, CL-4.6 MM/HR
Location AR&R 2016 – VIC Losses - kc 8.38, IL 23 mm (median), CL4.6 mm/hr
20% AEP 10%AEP 5% AEP 2% AEP 1% AEP
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Aberline Rd 3.37 6hr 7.50 6hr 13.01 3hr 21.60 6hr 30.29 6hr
Wangoom Rd 1.87 6hr 4.28 6hr 7.44 3hr 12.35 3hr 16.73 3hr
Racecourse 6.70 1hr 9.31 1hr 12.85 1hr 17.79 2hr 21.67 1hr
Mortlake Rd 10.60 2hr 17.92 3hr 28.14 3hr 43.79 3hr 57.55 3hr
Merri River 12.72 2hr 20.97 3hr 31.38 3hr 47.78 3hr 62.88 12hr
TABLE 2-7 DESIGN FLOWS USING ORIGINAL LOSSES, IL-20 MM, CL-4.6 MM/HR
Location AR&R 2016 – VIC Losses - kc 8.38, IL 20 mm (median), CL4.6 mm/hr
20% AEP 10%AEP 5% AEP 2% AEP 1% AEP
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Aberline Rd 4.18 3hr 8.79 6hr 14.18 6hr 22.98 6hr 32.01 6hr
Wangoom Rd 2.27 3hr 5.02 6hr 8.31 2hr 13.22 2hr 17.34 3hr
Racecourse 6.91 1hr 10.09 1hr 13.51 1hr 18.72 2hr 22.73 2hr
Mortlake Rd 11.95 2hr 20.47 2hr 31.24 2hr 47.63 2hr 59.83 6hr
Merri River 14.19 3hr 23.03 2hr 34.35 2hr 50.94 2hr 64.94 6h
A comparison of the Cardno adopted 2.5 mm/hr continuing loss and the adopted 4.6 mm/hr was also
undertaken. The results of the assessment show an increase in peak flows across the various inflow locations
for the lower continuing loss. For the 1% AEP flood event peak flows at the Aberline Road and Wangoom
Road inflow locations reduce 15-20% with the adoption of the higher continuing loss value.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 21
2.2.1.10 Spatial Patterns
An analysis of design rainfall was made across the Russell Creek catchment to determine if a non-uniform
spatial pattern should be utilised. The AR&R (2016)6 guidelines recommend that for catchment areas of more
than 20 km2 non-uniform spatial patterns should be considered. Gridded rainfall data is not yet available on
the BoM IFD website7 however a comparison was undertaken of the variation in rainfall depths between two
points at the upper and lower ends of the catchment.
TABLE 2-8 below shows a comparison of design rainfall between the upper and lower ends of the Russell
Creek catchment for the critical duration events. The difference in rainfall is minor at generally less than 1% in
the 1 hour and less than 2.5% in the 6 and 12 hour duration events. Based on this analysis it was deemed
appropriate to adopt a uniform rainfall pattern for the design modelling.
TABLE 2-8 COMPARISON OF RAINFALL DEPTHS AT UPSTREAM AND DOWNSTREAM ENDS OF RUSSELL CREEK CATCHMENT
Duration 10% AEP event 1% AEP event
Downstream (mm)
Upstream (mm)
Difference (mm)
Downstream (mm)
Upstream (mm)
Difference (mm)
1hr 24.5 24.7 0.2 42.0 42.2 0.2
6hr 43.3 44.3 1.0 72.7 73.9 1.2
12hr 54.6 55.9 1.3 94.2 95.7 1.5
2.2.1.11 Flow Verification
A number of area based regional peak flow estimation equations were used to calculate the Russell Creek
peak flow for comparison with the new RORB outputs, as shown in Table 2-9.
These estimation methods were applied for the whole of catchment and the primary inflow locations for the
hydraulic modelling, these include Mortlake Road, Aberline Road and the Racecourse. Whilst the result below
show both RORB outputs to have higher design flows than a number of the estimation methods, it is important
to note that the confidence limits associated with these methods are general +/-30 to 50%.
The Vic Roads Rational Method does produce similar results to the new adopted flows using the AR&R (2016)
RORB approach at the Aberline and Wangoom Road inflow locations. Based on the similarity of the output
results from both RORB models and in line with current best practice recommendations to use the information
available in the AR&R data hub, the RORB model design flow produced using the AR&R (2016) losses and
data hub outputs will be adopted.
7 Bureau of Meterology (2017), www.bom.gov.au
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 22
TABLE 2-9 1% AEP REGIONAL PEAK FLOW ESTIMATE COMPARISON
Location
Catchment Area
Rational Method
(m3/s)
Vic Roads Method
(m3/s)
Hydrologic Recipes –
Rural Estimate
(m3/s)
AR&R
RFFE Tool
(m3/s)
Cardno
(2010) Output
(m3/s)
New RORB
Original Losses
(Cardno)
(m3/s)
New RORB AR&R 2016
Adopted Flow
(m3/s)
Merri River Confluence
37.5 km2 33.1 39.3 74.2 17.5 76.9 78.8 64.9
Wangoom Road
7.7 km2 11.5 19.7 22.2 NA 18.6 20.5 17.3
Aberline Road
21.5 km2 22.9 32.6 48.5 NA 45 40.4 32.0
Racecourse
2.7 km2 5.7 11.3 22.2 * NA NA 25.34 22.7
• The urban racecourse catchment used the Urban Estimate equation from the Hydrologic Recipes: Estimation Techniques in
Australian Hydrology (Grayson, 1996)
2.2.1.12 Comparison to Previous Estimates
Comparison of peak flow estimates between this study and those produced during the previous study by
Cardno (2010) are shown in Table 2-10. The variation in flows ranges between 7 - 29% in comparison to the
previous results.
There are several factors which have contributed to the variation between the old and new RORB peak flow
results. These include a change in method in accordance with AR&R (2016); specifically, a change in IFD
rainfall depths and design losses, rainfall temporal patterns, and changes in the catchment area and subarea
delineation (particularly in the Racecourse catchment). Further to this, the RORB parameter kc used in the
models is also different.
TABLE 2-10 1% AEP PEAK FLOW COMPARISON BETWEEN STUDIES
Cardno Flows (2010)
(m3/s)
Water Technology Flows (2017)
(m3/s)
Difference
Aberline Rd 45.0 32.0 - 29%
Wangoom Rd 18.6 17.3 - 7%
Mortlake Rd 69.5 59.8 - 14%
Merri River 76.9 64.9 - 15%
Water Technology acknowledge that the flows produced at Aberline road particularly, show a significant
variation to those from the previous RORB modelling. This has resulted due to that significant changes in the
model set up and how flows have been routed through the new model. The number of reaches and sub-
catchments has been increased from the previous modelling. Furthermore use of the new ARR temporal
patterns and loss parameters has also contributed to this.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 23
2.2.2 Adopted Design Flood Hydrographs
Flows on the Russell Creek were extracted from the simulated Monte Carlo analysis using the new ARR (2016)
approach described earlier. Flows were extracted at Aberline Road, Wangoom Road, Racecourse Outlet,
Mortlake Road and the confluence with the Merri River.
The flows shown in Table 2-11 were adopted for this project, with the full hydrographs extracted and modelled
in the new TUFLOW model. The Monte-Carlo assessment produces an array of results varying the temporal
pattern and loss values to produce a probabilistic distribution of design flows. Which then enables peak flows
for a range of design events to be determined using a flood frequency analysis on the simulated results. The
final adopted design peak flows for the critical storm durations are provided in Table 2-11.
The storm durations of 1, 3, 6, 12 and 24 hours were selected for modelling in the TUFLOW model. The longer
duration events were included because of the numerous structures which cross Russell Creek attenuating
volume making these events important to consider. In this case, sometimes the peak flood level is driven by
longer duration storm events, and these should be considered in the hydraulic modelling as well as the shorter
duration peak flow events. For each AEP and duration a scenario from the Monte Carlo analysis was selected
that produced peak flows as close as possible to the Monte Carlo analysis design peak flow. This scenario
was then run in the hydraulic model. Each scenario has a slightly different combination of temporal pattern,
and initial loss. The scenarios selected for each design flood AEP and duration event combination are
summarised in Table 2-12.
Whilst the 2 hour event is shown to be critical in some locations within the RORB modelling it is important to
note that the peak flows of either the 1 hour or 3 hour were within 0.5 m3/s and therefore it was decided that
in order to provide a good spread of durations whilst keeping the number of model runs to a manageable
number, it was appropriate to adopt the 1, 3, 6, 12 and 24 hour storm durations.
It is important to note that the Russell Creek model is considered uncalibrated due to the ungauged nature of
the catchment and a level of uncertainty is inherent in the catchment modelling for ungauged catchments.
TABLE 2-11 RORB MONTE CARLO PEAK FLOW OUTPUT
Location AR&R 2016 – VIC Losses - kc 8.38, IL 20mm (mean), CL24.6mm/hr
20% AEP 10%AEP 5% AEP 2% AEP 1% AEP 0.5%
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Flow
m3/s
Critical
Duration
Flow m3/s
Critical Duration
Aberline Rd
4.18 3hr 8.79 6hr 14.18 6hr 22.98 6hr 32.01 6hr 41.43 12hr
Wangoom Rd
2.27 3hr 5.02 6hr 8.31 2hr 13.22 2hr 17.34 3hr 21.82 3hr
Racecourse 6.91 1hr 10.09 1hr 13.51 1hr 18.72 2hr 22.73 2hr 27.46 1hr
Mortlake Rd
11.95 2hr 20.47 2hr 31.24 2hr 47.63 2hr 59.83 6hr 77.56 12hr
Merri River 14.19 3hr 23.03 2hr 34.35 2hr 50.94 2hr 64.94 6h 84.73 12 hr
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 24
TABLE 2-12 FINAL ADOPTED DESIGN FLOW INPUT AND PEAK FLOW
Design Event AEP
Duration Rainfall Depth (mm)
TPat IL Aberline Inflow (m3/s)
Wangoom Inflow (m3/s)
RC Inflow (m3/s)
20%
1 12.3 10 9.4 2.42 1.32 6.79
3 19.5 9 10.6 4.29 2.28 4.98
6 25.4 9 15.4 3.70 2.17 4.04
12 39.6 8 25.4 2.95 1.56 2.96
24 44.5 7 28.4 0.97 0.46 1.38
10%
1 25.7 12 17.8 6.3 3.77 10.03
3 31.7 12 12.8 8.67 4.84 7.66
6 53.4 17 32 8.86 5.09 6.36
12 61.4 20 44.2 6.31 3.44 4.5
24 71.4 19 4.2 2.77 1.44 2.09
5%
1 22.7 13 9.4 11.04 6.18 13.48
3 30.6 12 5.2 13.98 8.45 10.67
6 48 11 15.8 13.96 7.55 8.90
12 60 19 26.8 11.33 6.19 5.72
24 84.8 12 14.4 4.88 2.64 2.92
2%
1 40.9 22 23 18.43 10.33 18.72
3 45.8 22 12.6 22.03 12.59 13.21
6 78.7 24 38.2 22.8 12.87 10.92
12 77.4 22 17.2 20.78 11.61 8.95
24 91.1 25 27.8 12.73 6.52 5.12
1%
1 34.3 26 10.8 24.71 14.92 22.12
3 52.1 29 17.8 29.17 17.24 15.95
6 65.8 23 17.4 31.54 16.83 16.12
12 92.8 22 16 31.22 16.10 11.03
24 119.7 26 22.6 18.79 9.57 6.13
0.5%
1 48.5 24 23.2 30.04 17.22 27.52
3 74.9 28 39.4 37.47 21.42 20.72
6 75.4 23 18.6 41.27 21.15 19.04
12 117.8 22 32 41.04 22.69 14.72
24 130.7 30 6.8 27.22 13.37 9.33
• Rainfall depths shown correspond to the storm AEP which produced the peak flow at the respective inflow
location. This may not directly correspond with the streamflow AEP, as in many cases 1% storms do not result
in 1% floods.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 25
3 RACECOURSE CATCHMENT The racecourse catchment, south of Russell Creek has been the source of a number of drainage issues in the
past with frequent nuisance inundation over Moore Street following heavy rainfall events. Following the
expansion of the Warrnambool urban and industrial development areas to the east, additional drainage
pressure has been placed on this and neighbouring catchment areas. In addition to the existing pressure on
drainage infrastructure in this location are the issues around the functionality and capacity of the Simpson
Street drain which discharges overland flows east of the racecourse to the Hopkins River. In consideration of
future changes to natural drainage patterns in this area, assessment of retardation requirements from this
catchment are required to ensure that flooding on Russell Creek is not adversely impacted.
Based on the adopted design flows from the existing conditions of the Racecourse catchment, maximum peak
flow outputs can be set to ensure future diversion of drainage, and treatments and retardation of existing
stormwater is appropriately managed. In determining peak flow values at this location consideration must be
given to the critical duration of the peak flows in both the Racecourse catchment and the main Russell Creek
reaches downstream of the point of discharge. The Racecourse catchment is shown to have a critical duration
of 1 hour under all events, with the Mortlake Road location, immediately downstream of the point where the
Racecourse catchment discharges into the Russell Creek, having a critical duration of 6 hours during the 1%
AEP event and 2 hours in the 10% AEP event. The Mortlake Road peak flow does not change significantly
across the 2 to 6 hour duration events.
TABLE 3-1 1% AEP PEAK FLOWS AND CRITICAL DURATION
Duration 1Hr 2Hr 3Hr 6Hr 12Hr 24Hr
Racecourse 22.56 22.73 16.83 15.61 11.71 6.7
Mortlake Road 53.3 59.38 59.49 59.83 58.11 35.44
TABLE 3-2 10% AEP PEAK FLOWS AND CRITICAL DURATION
Duration 1Hr 2Hr 3Hr 6Hr 12Hr 24Hr
Racecourse 10.09 9.07 7.61 6.18 4.32 2.12
Mortlake Road 18.08 20.47 19.9 19.3 13.69 6.81
The flows generated at the Racecourse as part of the new hydrology assessment, as shown above, have been included in the revised flood mapping.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 26
4 HYDRAULIC MODEL
4.1 Overview
A new hydraulic model was constructed of Russell Creek through North Warrnambool using TUFLOW. This
allows the model to be used for a variety of purposes by a wider number of organisations. The old hydraulic
model was developed in Sobek, which is used by only a small number of consultants.
A detailed combined 1D2D hydraulic modelling approach was adopted for this study. The hydraulic modelling
approach consisted of the following components:
One dimensional (1D) hydraulic model of key waterways cross-sections, key drainage and hydraulic
structures;
Two dimensional (2D) hydraulic model of the broader floodplain; and
Linked one and two dimensional hydraulic model to accurately model the interaction between in bank
flows (1D) and overland floodplain flows (2D).
The hydraulic modelling suite, TUFLOW, was used in this study. TUFLOW is a widely used hydraulic model
that is suitable for the analysis of riverine floodplains and overland flows in urban areas. TUFLOW has four
main inputs:
Topography and drainage infrastructure data;
Inflow data (based on catchment hydrology);
Roughness; and,
Boundary conditions.
This section defines the scope of the hydraulic analysis, details the hydraulic model construction, and
discusses the hydraulic model calibration.
4.2 Hydraulic Model Schematisation
The TUFLOW model was constructed using MapInfo V11.0 and text editing software. This section details key
elements and parameters of the TUFLOW model which utilises best practice as described in AR&R (2016)
Book 6, the Melbourne Water 2D Modelling Guidelines, and elements of the TUFLOW User Manual.
The double precision version of the latest TUFLOW release was used for all simulations (TUFLOW Version:
2016-03-AD). Hydraulic model timesteps of 1s and 0.5s respectively were adopted for the 2D and 1D elements.
4.2.1 2D Grid Size and Topography
A single-domain approach was utilised to ensure the small areas of interest were modelled at an appropriate
scale, while achieving practical model run-times. A relatively fine grid size of 3 m was selected for the
Warrnambool Russell Creek area to ensure the urban area and narrow creek corridor could be accurately
represented and mapped. The 2D model extents are shown below in Figure 4-2.
The model topography adopted was based on the new Warrnambool Lidar. This data was collected on the 27th
of February 2017. The DEM grid resolution is 1m with a horizontal accuracy of 0.15 m and a vertical accuracy
of 0.1 m. The new topography was compared to existing available lidar and cross-sectional data and the main
channel of the Russell Creek immediately downstream of Wares Road to Daltons Road was checked and the
creek centreline added to ensure the lowest points in the lidar (representing the channel) was picked up in the
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 27
model. This ensured that the low flow channel of Russell Creek, where the channel is only 1-2 grid cells wide
was accurately represented.
An assessment of the topography around and within the creek was undertake as part of the model
development. Whilst we appreciate that the creek is relatively narrow in some areas 1-2 grid cells wide the use
of new accurate lidar and zlines has ensured that the creek is well represented. The lidar and the 2d model
check z file was compared at numerous locations within the model in order to ensure that the creek was well
represented. It is important to note that the capacity of the creek is exceeded early in the significant flood
events. The following cross-sections show a comparison of the 2d check z file and the Warrnambool lidar set
at three locations along the creek
FIGURE 4-1 CREEK CROSS-SECTION COMPARRISON
The adopted model topography is shown in Figure 4-3.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 28
FIGURE 4-2 MODEL BOUNDARY
FIGURE 4-3 MODEL TOPOGRAPHY
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 29
4.2.2 Roughness
The 2D model roughness values were produced based on Land Use Zones, with further refinement using
aerial photographs and site visits. The final adopted Manning’s ‘n’ roughness values are listed in Table 4-1
and shown graphically in Figure 4-4.
TABLE 4-1 MANNINGS ‘N’ ROUGHNESS VALUES
Land Use Manning’s n Roughness Coefficient
Residential zones 0.30
Agricultural / Rural / Pasture 0.04
Low Density Residential 0.15
Paved Roads 0.02
Medium Density Vegetation 0.04
Vegetated Riparian Area 0.05
Vegetated Waterway Channel 0.1
FIGURE 4-4 ADOPTED MANNINGS ‘N’ ROUGHNESS VALUES
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 30
4.2.3 Hydraulic Structures
Twenty waterway structures were included in the hydraulic model. These consisted of a range of bridges and
culvert crossings. Information relating to the size and inverts of the respective structures was obtained from
detailed plans and survey undertaken up Warrnambool City Council. A list of the locations of the included
structures is shown in Table 4-2 and the locations of these structures is shown in Figure 4-5. Information
including the type and size of these structures is included in Appendix D.
TABLE 4-2 HYDRUALIC STRUCTURES
Location
Ians Road Moonah Drive Pedestrian Crossing
Wagoom Road Oak Court Pedestrian Crossing
Aberline Road Upstream Mortlake Road Pedestrian Crossing
Whites Road (West Crossing) Mortlake Road Culverts (Original)
Whites Road (East Crossing) Mortlake Road Culverts (New)
Whites Road Pedestrian Crossing Downstream Mortlake Road Pedestrian Crossing
Wares Road Queens Street
Renior Pedestrian Crossing St Joseph’s Primary Pedestrian Crossing
Upstream Garden Street Footbridge Bromfield Street
Garden Street Daltons Road
FIGURE 4-5 LOCATION OF HYDRAULIC STRUCTURES
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 31
4.2.4 Boundary Condition – Inlet Boundaries
One of the principal considerations in constructing the model was the location of inflow boundaries to ensure
all runoff from the catchment was being adequately represented in the modelling. The model boundaries for
the Russell Creek model included the Northern and Eastern Arms of the Creek along with an inflow location
from the Warrnambool Racecourse catchment. The inflows from the northern and eastern arms of Russell
Creek are the main contributors to peak flows within the study area and were determined by the RORB model.
Additional flows from the RORB model from the local urban catchment downstream of the hydraulic model
boundaries were also included as SA boundaries within the creek.
4.2.5 Boundary Condition – Outlet Boundaries
A 2D height flowrate (HQ) boundary was used at the downstream model boundary to convey Russell Creek
flows from the model. HQ boundaries are a commonly used boundary type in TUFLOW which compute a water
level based on the flow and topography slope at the boundary.
The hydraulic model boundaries are shown in Figure 4-6.
An additional outlet boundary was included to the north-west of Wangoom Road where during initial test runs
it was established that in extreme flow events the water banking up behind Wangoom Road and spilling to the
Merri River via a low point in the topography south of Conheadys Road.
FIGURE 4-6 MODEL BOUNDARIES
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 32
4.2.6 Flood Walls and Culverts – As Constructed
The flood walls were represented in the model as z lines which used the as constructed height of the walls to
represent the structures. The walls were represented as closed structures, assuming the drop boards were in
place at the locations of the various openings within the levee. The locations of the various flood walls are
shown in Figure 4-7 below and photographs of 2 sections of the walls shown in Figure 4-8.
FIGURE 4-7 FLOOD WALL LOCATIONS
FIGURE 4-8 RUSSELL CREEK FLOOD LEVEE WALLS
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 33
FIGURE 4-9 MORTLAKE ROAD FLOOD MITIGATION CULVERTS
The mitigation works also included the construction of two 2.4 x 3.6 m box culverts at Mortlake Road, pictured
above. The previous culvert under Mortlake Road has also been upgraded, with the walkway cut out to
maximise the capacity. These new structures were included in the model as 1D structures.
4.2.7 Hydraulic Model Calibration
It is important to note that given the ungauged nature of this catchment and the scope of works for this
modelling, calibration of Russell Creek was not possible. Whilst little information is available regarding the flow
and flood extent of historical and recent flooding events it is hoped that as part of proposed future works,
additional information relating to the creek flows, height and extent coupled with accurate rainfall data will
enable accurate calibration of the developed model.
The model was run with the previous hydrology and the model was validated to the previous model results,
with particular attention paid to the headloss across the major road crossings. The head loss parameters were
chosen to produce very similar head loss across Garden Street and Mortlake Road as compared to the
previous Sobek model.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 34
5 DESIGN HYDRAULIC MODELLING Design hydraulic modelling was completed adopting the hydraulic model roughness values, hydraulic
structures and boundary conditions shown in the previous section. Modelling was completed for the full suite
of design events including the 20%, 10%, 5%, 2%, 1% and 0.5% AEP events. Storm durations including the
1, 3, 6, 12 and 24 hour were modelled for each design event. The results of the 5 duration events were
combined for each AEP design event to provide a maximum water surface elevation, depth, velocity and
hazard output.
Figure 5-1 and Figure 5-2 show the new flood depth and extents for the 1% AEP flood event. Flood depth
mapping for the range of design events are presented in Appendix C. A comparison of the original and new
flood mapping shows reductions in flood depth and extent within the Russell Creek corridor as shown in
Figure 5-3. A comparison of the modelled 1% AEP flood levels at locations along the creek corridor are shown
in Table 5-1
TABLE 5-1 1% AEP FLOOD LEVEL COMPARISON
Wangoom Rd
Aberline Rd
Whites Rd
Garden St
La Bella Crt
US Mortlake Rd
DS Mortlake Rd
Queens Road
Pre Construction – Existing Conditions – WSE (mAHD) (SOBEK)
34.34 22.27 19.14 12.7 9.9 9.469 7.91 5.37
New Existing Condition –
WSE (mAHD) (TUFLOW)
34.43 22.37 19.15 12.48 9.54 8.74 7.54 4.97
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 35
FIGURE 5-1 1% AEP FLOOD DEPTH (NEW EXISTING CONDITIONS)
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 36
FIGURE 5-2 1% AEP FLOOD DEPTH (NEW EXISTING CONDITIONS)
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 37
FIGURE 5-3 COMPARISON OF ORIGINAL AND NEW 1% AEP FLOOD DEPTH
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 38
6 FLOOD DAMAGES ASSESSMENT
6.1 Overview
A flood damage assessment for the study area was undertaken using the range of design events modelled
(20%, 10%, 5%, 2%, 1%, 0.5%, 0.2% AEP design events) for existing conditions. Existing conditions includes
the as constructed flood mitigation works. The damage assessment was used to determine the monetary flood
damage for the design floods in the North Warrnambool study area.
Water Technology has developed an industry best practice flood damage assessment methodology that has
been utilised for many studies in Victoria, The NSW Office of Environment and Heritage stage damage curves
are utilised, which represent far superior damage estimates at low depths above floor and below floor than
earlier stage damage curves used in Victoria. Recent advice from the insurance industry is that these damage
curves may still underestimate the damage, so it is likely that these damage estimates are a lower bound of
that which would be incurred during a real flood, but it is the best damage data available at present. Water
Technology utilises WaterRide to undertake the property inspections and apply the appropriate stage damage
curves.
The model results for all mapped flood events were processed to calculate the numbers and locations of
properties affected. This included properties with buildings inundated above floor, properties with buildings
inundated below floor and properties where the building was not impacted but the grounds of the property
were. In addition to the flood affected properties, lengths and damages of flood affected roads for each event
were also calculated.
The Average Annual Damage (AAD) was determined as part of the flood damage assessment. The AAD is a
measure of the flood damage per year averaged over an extended period. This is effectively a measure of the
amount of money that must be put aside each year in readiness for when a flood may happen in the future.
6.2 Current Conditions AAD
The flood damage assessment for existing conditions, with as constructed flood mitigation works, is shown
below in Table 6-2. The Average Annual Damages (AAD) for existing conditions is estimated at approximately
$69,571. The AAD determined as part of this assessment is showing results which are significantly lower than
previous assessments for the mitigation works. The previous existing conditions modelling determine a AAD
of $491,783, demonstrating a reduction in the AAD of $422,212. This significant reduction is also reflected in
the number of above floor flooded properties During the 1% AEP flood event the number of properties expected
to be flooded above floor has reduced from 146 to 14.
6.2.1 Non-economic Flood Damages
The previous discussion relating to flood damages has concentrated on monetary damages, i.e. damages that
are easily quantified. In addition to those damages, it is widely recognised that individuals and communities
also suffer significant non-monetary damage, i.e. emotional distress, health issues, etc.
The intangible non-monetary flood related damage is also likely to be high, further contributing to the flood
damages. The benefit-cost analysis presented in this report has not considered this cost. Any decisions made
that are based on the benefit cost ratios need to understand that the true cost of floods in and along the Russell
Creek is far higher than the economic damages alone. These intangible costs have the effect of increasing the
benefit-cost ratio, improving the argument for completing further flood mitigation and flood warning.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 39
6.2.2 Above Floor Flooding
The number of above floor flooded properties has significant reduced as a result of the constructed mitigation
works. Whilst 14 properties are still shown to be flooded above floor, a number of these properties are shown
to be flooded by relatively shallow depths. A breakdown of the depth of above flood flooding during the 1%
AEP flood event is shown in the table below.
TABLE 6-1 DEPTH OF ABOVE FLOOR FLOODING
Depth of Above Floor Flooding Number of Properties Impacted
< 0.1 metres 5
0.1 To 0.2 meters 5
0.2 to 0.3 meters 2
Above 0.3 meters 2
All of the properties shown to be flooded above floor following the mitigation works had previously been
identified at being at risk from above floor flooding during the 1% AEP flood events. The depth of above floor
flooding has reduced for all but 1 of the 14 properties. The average depth of above floor flooding has reduced
by 100mm. The locations of the above floor flooded properties are focused on three areas Wangoom Road,
Whites Road and within the breakout area around Moonah Drive.
FIGURE 6-1 ABOVE FLOOR FLOODED PROPERTIES (RED DOTS)
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 40
TABLE 6-2 DAMAGES ASSESMENT
ARI (1in Y years) 1 in 200 yr 1 in 100 yr 1 in 50 yr 1 in 20 yr 1 in 10 yr 1 in 5 yr
AEP 0.5% 1% 2% 5% 10% 20%
Residential Buildings Flooded Above Floor
21 14 6 1 0 0
Commercial Buildings Flooded Above Floor
6 0 0 0 0 0
Properties Flooded Below Floor
369 205 99 69 57 36
Total Properties Flooded
396 219 105 70 57 36
Direct Potential External Damage Cost
$1,070,242 $490,987 $331,469 $250,022 $168,447 $64,008
Direct Potential Residential Damage Cost
$1,263,246 $809,937 $327,627 $61,861 $0 $0
Direct Potential Commercial Damage Cost
$33,766 $0 $0 $0 $0 $0
Total Direct Potential Damage Cost
$2,367,254 $1,300,924 $659,096 $311,883 $168,447 $64,008
Total Actual Damage Cost (0.8*Potential)
$1,893,803 $1,040,739 $527,277 $249,506 $134,758 $51,206
Infrastructure Damage Cost
$326,489 $243,184 $196,212 $135,350 $113,458 $66,009
Total Cost $2,220,292 $1,283,923 $723,489 $384,856 $248,216 $117,215
Average Annual Damage (AAD)
$69,521
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 41
7 SENSITIVITY TESTING
7.1 Overview
The project brief required a number of sensitivity tests to be completed, these included:
Climate Change
Complete Blockage of new - Mortlake Road Culverts
Removal of Flood Walls
Rainfall on grid modelling to represent local stormwater drainage behind the levee
These tests were completed using both RORB and hydraulic modelling techniques.
7.2 Climate change scenarios
7.2.1 Overview
The assessment of climate change was modelled in RORB for rainfall intensity increases of 10%, 20% and
30% to provide a range of potential flows that may occur along Russell Creek due to climate change.
The latest guidance in AR&R (2016) predicts a 5% rainfall intensity increase per degree of warming. A scenario
of 2°C of warming is consistent with ‘Climate Change in Australia Projections’8 report which suggests for an
intermediate climate scenario, a temperature increase of between 1.1°C to 2.0°C is likely for the Southern
Slopes of Australia. This climate change scenario would result in a 10% increase in rainfall intensity. The
impact of climate change on flows was determined for the catchment using the existing RORB model and then
modelled in the hydraulic model. The increase in peak flow for the 1% AEP event in each climate change
sensitivity scenario is shown in Table 7-1.
TABLE 7-1 CLIMATE CHANGE RAINFALL INTENSITY INCREASE – PEAK FLOWS
% increase in rainfall intensity
Aberline Road 1% AEP peak flow (m3/s)
(critical duration)
Wangoom Road 1% AEP peak flow (m3/s) (critical duration)
Racecourse 1% AEP peak flow (m3/s)
(critical duration)
Critical Duration 6 hr 3 hr 1 hr
Existing Conditions 31.77 17.35 22.2
10 % 39.14 (23% increase) 20.69 (19% increase) 25.09 (13% increase)
20 % 46.33 (46% increase) 24.1 (39% increase) 27.98 (26% increase)
30 % 53.37 (67% increase) 27.40 (58% increase) 30.87 (39% increase)
The hydraulic model was run for all of the five storm durations (24hr,12hr, 6hr, 3hr and 1hr) for the 1% AEP
flood event with the various climate related rainfall intensity increases. The maximum envelope of the resulting
flood depths was derived and a comparison of the various flood extents is shown below.
8 CSIRO. (2005). Climate Change in Eastern Victoria - Stage 1 Report: The effect of climate change on coastal wind and weather patterns. CSIRO.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 42
FIGURE 7-1 CLIMATE CHANGE RAINFALL INTENSITY INCREASE FOR 1% AEP EVENT
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 43
7.3 No Flood Walls
An assessment of the effect of the removal or failure of the flood walls was undertaken for the 1% AEP flood
event. The flood walls were completely removed from the hydraulic model. Changes to land topography around
the walls was also smoothed.
All durations of the 1% AEP flood event were modelled and the maximum envelope of the combined extent
mapped and displayed in Figure 7-2. A comparison of the modelled extent with the current 1% AEP flood
extent and depths results indicates that’s maximum water surface elevations between Garden Street and
Mortlake Road are approximately 2-5 cm lower than the existing conditions (Figure 7-3). However, the 1%
AEP flood extent without the flood walls is greater, most notably to the south of the creek around the Garden
Street area. This can be attributed to the change in the nature of the flow through the areas which are confined
by the flood walls. In the absence of the flood walls the floodplain is broader and flood levels lower.
7.4 No Mortlake Rd Culverts
It is important to note the significant number of waterway structures along Russell Creek. These structures
effect the conveyance and storage of flows within the waterway during significant flood events. Of these
structures the Mortlake Road culverts and road embankment is the largest and most significant hydraulic
control within the Russell Creek floodplain.
An assessment of the effect of the new culverts being completely blocked/removed was undertaken to
demonstrate the efficacy of the new culverts and the sensitivity of the flood levels locally to this structure. The
scenario included the as constructed flood walls but not the 2 new box culverts. All durations of the 1% AEP
flood events were modelled and the maximum envelope of the combined extent mapped and displayed in
Figure 7-4. A comparison of the modelled (no culvert) event to the existing conditions assessment indicates
that in the absence of the culverts at Mortlake Road water levels on the upstream side of Mortlake Road are
increased in excess of 50 cm (Figure 7-5). This increase results in increased water levels up stream of the
culverts and outflanking of the levees immediately upstream and around Garden Street.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 44
FIGURE 7-2 1% AEP FLOOD DEPTH – NO FLOOD WALLS
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 45
FIGURE 7-3 1% AEP,12 HR - DIFFERENCE PLOT – NO WALLS MINUS EXISTING
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 46
FIGURE 7-4 1% AEP FLOOD DEPTH – NO MORTLAKE ROAD NEW CULVERTS
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 47
FIGURE 7-5 1% AEP, 12HR - DIFFERENCE PLOT - NO CULVERTS MINUS EXISTING
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 48
7.5 Rain on Grid
As part of the sensitivity testing some limited rain on grid modelling was completed to test the existing
stormwater network behind the flood walls. The pit and pipe information used in this assessment was supplied
by Engeny (Figure 7-6) and was not validate with any on ground checks or surveys. The 1% AEP (Figure 7-7)
and 10% AEP (Figure 7-8) flood events were run for the 30 minutes and 2 hour storm durations. This scenario
adopted zero loss and is likely to have over-estimated the volume of runoff within the urban area. The results
provide an indication of potential problem areas including low lying land north of Russell Creek where drainage
infrastructure may be undersized. Water Technology recommends that further investigation of this be
undertaken. The flood depth results shown below have been filtered to remove maximum flood depths of less
than 0.05 metres and puddles of less than 100m2.
It is important to consider that the primary driver of the rain on grid assessment was to confirm if areas behind
the flood walls could drain effectively and if additional hazard was being created by the flood walls. Having
regard to this it is noted that the land behind the Moore Street levee is low and given the orientation of local
drainage around the racecourse it is possible that water may pool behind the levee at this location. This is also
reflected at la Bella Court where water is shown to pool within the court bowl. It is important to note that the
local drainage network is not designed to cope with 1% AEP flows and that it is likely that increased water
depths would be experienced within the road network and low-lying land.
Whilst the primary focus of this report is to asses and present revised flood mapping following the construction of mitigation works on Russell Creek. The assessment focuses on riverine flooding and does not consider inundation resulting from stormwater flooding. It is possible that in some instances properties will be subject to flooding from both stormwater and riverine flooding. The risk of stormwater flooding in Warrnambool is greatest when the capacity of the stormwater drainage network is exceeded and the excess accumulates in the road networks which often then drain to low lying land, as is observed in the rain on grid stormwater mapping shown in Figure 7-8. Where our urban areas have experienced rapid growth, as has been observed in Warrnambool, these issues can be compounded due to the increased runoff from hard surfaces along with ageing and often undersized infrastructure. For these reasons it is important to have a clear understanding of the areas within the drainage network which may be undersized and at greatest risk from stormwater flooding.
FIGURE 7-6 WARRNAMBOOL PIT AND PIPE NETWORK
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 49
FIGURE 7-7 1% AEP RAIN OF GRID
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 50
FIGURE 7-8 10% AEP RAIN ON GRID
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 51
8 CONCLUSION
8.1 Overview
The North Warrnambool Flood Mitigation Study provides a comprehensive analysis and review of current flood risk in the North Warrnambool Russell Creek area following the construction of extensive flood mitigation work. This analysis has been completed based on current floodplain conditions and includes the 4 new flood levees and two new culverts at Mortlake Road. This document provides detailed mapping of the existing flood risk under a range of flood magnitudes. The study involved:
Development of detailed best practice flood hydrology in accordance with Australian Rainfall and Runoff
(2016) guidelines.
Development of a detailed hydraulic model, validated to previous modelling and used to simulate a range
of design flood events with the as constructed flood mitigation works representing the current conditions
of the Russell Creek floodplain.
Quantification of flood risk in terms of properties impacted and likely future flood damages.
Sensitivity testing for a range of various model parameters.
8.2 Key Outcomes
The project has developed revised hydrology and hydraulic models using todays best practice ARR (2016)
guidelines. The hydrology and hydraulic models can be used for future floodplain assessments of Russell
Creek.
The flood mapping has confirmed that the flood mitigation works constructed recently along Russell Creek has
greatly reduced the flood risk for the residents of North Warrnambool. The modelling has highlighted the
sensitivity of flood levels around the Garden Street area, with breakouts onto the floodplain occurring at that
location. The higher resolution modelling has shown that flood waters may outflank the levee flood wall to the
south, this was not previously shown in the coarser flood modelling.
8.3 Recommendations
Following this investigation, it is recommended that:
The revised 1% AEP flood mapping be adopted for the purposes of future planning scheme overlays and
strategic planning investigations. Furthermore, designation of the declared flood prone land in accordance
with Building Regulation 802 should also be considered.
Further investigation be undertaken into minor engineering works around the Garden Street area where
the modelling shows minor outflanking of the levee. Minor raising of the surface level will improve the
performance of the southern levee which will be outflanked in large flow events.
Undertake a more comprehensive assessment of the local drainage network capacity and function to
ensure problem drainage areas within the overland flow paths are appropriately managed. This
assessment should also include a condition assessment and comprehensive culvert blockage
assessment.
Further investigate the local impact of predicted climate variability on stormwater and catchment flooding
and where necessary investigate measures to manage the associated risks.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 52
Consider as part of long term floodplain management future upgrade works on the Garden Street
waterway crossing with the aim of improving conveyance and reducing flooding within the breakout area
north of Russell Creek.
Furthermore, given the completed modelling will superseded current best available flood mapping the
following recommendation should also be considered:
In conjunction with VICSES, the Warrnambool City Council and GHCMA should continue to
engage the community in the treatment of flood risks through regular flood awareness programs
such as the VICSES FloodSafe program. Whilst local flood guides have already been produced
for this area a revised guide would be necessary following the completion of the proposed works.
In consultation with VICSES, the Warrnambool City Council and GHCMA the Municipal Flood
Emergency plan (MFEP) should be updated to reflect the as constructed flood mitigation works
and revised flood mapping.
Warrnambool City Council and GHCMA to consider recommendations from the recent flood
warning investigation for Russell Creek along with the revised flood impacts from this
investigation, to inform further improvements to the Total Flood Warning System for Russell
Creek. This should include the installation of a gauge within Russell Creek to ensure accurate
rainfall and stream flow data can be recorded for future use and on which to base early flood
warning.
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 53
APPENDIX A AR&R DATA HUB OUTPUT
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 54
Results - ARR Data Hub
[STARTTXT]
Input Data Information
[INPUTDATA]
Latitude,-38.34035228
Longitude,142.533923
[END_INPUTDATA]
River Region
[RIVREG]
Division,South East Coast (Victoria)
RivRegNum,11.0
River Region,Hopkins River
[RIVREG_META]
Time Accessed,06 March 2017 11:37AM
Version,2016_v1
[END_RIVREG]
ARF Parameters
[LONGARF]
Zone,Southern Temperate
a,1.58E-01
b,2.76E-01
c,3.72E-01
d,3.15E-01
e,1.41E-04
f,4.10E-01
g,1.50E-01
h,1.00E-02
i,-2.70E-03
[LONGARF_META]
Time Accessed,06 March 2017 11:37AM
Version,2016_v1
[END_LONGARF]
Storm Losses
[LOSSES]
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 55
[LOSSES_META]
Time Accessed,06 March 2017 11:37AM
Version,2016_v1
[END_LOSSES]
Temporal Patterns
[TP]
CODE,SSmainland
LABEL,Southern Slopes (Vic/NSW)
[TP_META]
Time Accessed,06 March 2017 11:37AM
Version,2016_v1
[END_TP]
Areal Temporal Patterns
[ATP]
CODE,SSmainland
LABEL,Southern Slopes (Vic/NSW)
[ATP_META]
Time Accessed,06 March 2017 11:37AM
Version,2016_v1
[END_ATP]
BOM IFD Depths
[BOMIFD]
[BOMIFD_META]
[END_BOMIFD]
Median Preburst Depths and Ratios
[PREBURST]
min (h)\AEP(%),50,20,10,5,2,1,
60 (1.0),1.8 (0.135),2.7 (0.135),3.3 (0.133),3.8 (0.129),2.2 (0.061),1.0 (0.024),
90 (1.5),1.1 (0.069),1.7 (0.074),2.1 (0.075),2.5 (0.074),2.0 (0.048),1.6 (0.034),
120 (2.0),1.9 (0.11),2.0 (0.081),2.1 (0.068),2.2 (0.06),2.1 (0.047),2.1 (0.04),
180 (3.0),2.4 (0.121),2.3 (0.079),2.2 (0.062),2.1 (0.05),2.5 (0.049),2.8 (0.048),
360 (6.0),0.7 (0.028),1.0 (0.028),1.2 (0.027),1.4 (0.026),2.6 (0.041),3.6 (0.048),
720 (12.0),0.0 (0.0),0.5 (0.012),0.9 (0.016),1.3 (0.019),3.4 (0.041),5.0 (0.052),
1080 (18.0),0.0 (0.0),0.0 (0.001),0.1 (0.001),0.1 (0.001),0.7 (0.007),1.1 (0.01),
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 56
1440 (24.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
2160 (36.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
2880 (48.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
4320 (72.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
[PREBURST_META]
Time Accessed,06 March 2017 11:37AM
[END_PREBURST]
10% Preburst Depths
[PREBURST10]
min (h)\AEP(%),50,20,10,5,2,1,
60 (1.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
90 (1.5),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
120 (2.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
180 (3.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
360 (6.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
720 (12.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
1080 (18.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
1440 (24.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
2160 (36.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
2880 (48.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
4320 (72.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
[PREBURST10_META]
Time Accessed,06 March 2017 11:37AM
Version,2016_v1
[END_PREBURST10]
25% Preburst Depths
[PREBURST25]
min (h)\AEP(%),50,20,10,5,2,1,
60 (1.0),0.1 (0.005),0.0 (0.002),0.0 (0.001),0.0 (0.0),0.0 (0.001),0.0 (0.001),
90 (1.5),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
120 (2.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
180 (3.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
360 (6.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
720 (12.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
1080 (18.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
1440 (24.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 57
2160 (36.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
2880 (48.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
4320 (72.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
[PREBURST25_META]
Time Accessed,06 March 2017 11:37AM
Version,2016_v1
[END_PREBURST25]
75% Preburst Depths
[PREBURST75]
min (h)\AEP(%),50,20,10,5,2,1,
60 (1.0),7.3 (0.543),10.7 (0.536),12.9 (0.523),15.0 (0.507),13.6 (0.373),12.6 (0.299),
90 (1.5),9.8 (0.633),10.6 (0.468),11.2 (0.399),11.7 (0.349),12.7 (0.311),13.5 (0.288),
120 (2.0),9.8 (0.57),10.1 (0.406),10.4 (0.338),10.6 (0.29),13.7 (0.308),16.1 (0.315),
180 (3.0),8.4 (0.427),9.8 (0.342),10.7 (0.305),11.5 (0.277),13.4 (0.265),14.8 (0.256),
360 (6.0),4.9 (0.193),10.7 (0.295),14.5 (0.329),18.2 (0.348),20.9 (0.326),22.9 (0.31),
720 (12.0),1.5 (0.046),6.0 (0.13),8.9 (0.159),11.7 (0.177),15.8 (0.192),18.9 (0.196),
1080 (18.0),0.4 (0.011),2.9 (0.055),4.5 (0.07),6.0 (0.079),9.0 (0.095),11.3 (0.101),
1440 (24.0),0.1 (0.002),3.1 (0.054),5.0 (0.072),6.9 (0.083),8.2 (0.079),9.2 (0.075),
2160 (36.0),0.0 (0.0),0.5 (0.008),0.8 (0.011),1.2 (0.012),3.1 (0.027),4.6 (0.034),
2880 (48.0),0.0 (0.0),0.1 (0.001),0.1 (0.002),0.2 (0.002),0.9 (0.007),1.4 (0.009),
4320 (72.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),0.0 (0.0),
[PREBURST75_META]
Time Accessed,06 March 2017 11:37AM
Version,2016_v1
[END_PREBURST75]
90% Preburst Depths
[PREBURST90]
min (h)\AEP(%),50,20,10,5,2,1,
60 (1.0),15.9 (1.175),24.6 (1.236),30.4 (1.233),35.9 (1.214),29.6 (0.812),24.9 (0.591),
90 (1.5),16.0 (1.031),22.4 (0.987),26.6 (0.952),30.7 (0.918),32.8 (0.801),34.4 (0.731),
120 (2.0),21.5 (1.254),20.2 (0.809),19.3 (0.631),18.5 (0.506),32.8 (0.736),43.5 (0.853),
180 (3.0),18.4 (0.927),21.8 (0.764),24.1 (0.69),26.3 (0.635),31.9 (0.631),36.1 (0.624),
360 (6.0),16.8 (0.664),23.1 (0.637),27.2 (0.617),31.2 (0.597),34.8 (0.543),37.5 (0.508),
720 (12.0),6.4 (0.197),13.9 (0.304),18.9 (0.339),23.7 (0.357),30.8 (0.374),36.2 (0.376),
1080 (18.0),5.9 (0.16),11.5 (0.22),15.2 (0.238),18.7 (0.246),25.1 (0.265),29.9 (0.269),
1440 (24.0),7.8 (0.192),12.4 (0.218),15.4 (0.222),18.3 (0.22),20.9 (0.201),22.9 (0.187),
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 58
2160 (36.0),1.4 (0.032),5.7 (0.089),8.5 (0.109),11.2 (0.119),22.3 (0.191),30.6 (0.223),
2880 (48.0),0.9 (0.018),3.7 (0.054),5.6 (0.067),7.3 (0.073),8.8 (0.07),9.8 (0.067),
4320 (72.0),0.4 (0.007),6.4 (0.086),10.4 (0.114),14.2 (0.13),20.3 (0.151),24.8 (0.16),
[PREBURST90_META]
Time Accessed,06 March 2017 11:37AM
Version,2016_v1
[END_PREBURST90]
Interim Climate Change Factors
[CCF]
2030,0.719 (3.6%),0.739 (3.7%),0.822 (4.1%),
2040,0.925 (4.6%),0.915 (4.6%),1.119 (5.6%),
2050,1.123 (5.6%),1.085 (5.4%),1.449 (7.2%),
2060,1.271 (6.4%),1.294 (6.5%),1.865 (9.3%),
2070,1.394 (7.0%),1.526 (7.6%),2.333 (11.7%),
2080,1.477 (7.4%),1.778 (8.9%),2.776 (13.9%),
2090,1.527 (7.6%),2.009 (10.0%),3.21 (16.1%),
[CCF_META]
Time Accessed,06 March 2017 11:37AM
Version,2016_v1
Note,ARR recommends the use of RCP4.5 and RCP 8.5 values
[END_CCF]
Baseflow Factors
[BASEFLOW]
DOWNSTREAM,0.0
AREA_SQKM,1018.877
CATCH_NO,11213.0
R3RUNOFF,0.129
R1RUNOFF,0.047
[BASEFLOW_META]
Time Accessed,06 March 2017 11:37AM
Version,2016_v1
[END_BASEFLOW]
[ENDTXT]
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 59
APPENDIX B AR&R – REGIONAL FLOOD FREQUENCY ESTIMATION TOOL
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 60
AR&R (2016) has developed a new Regional Flood Frequency Estimate (RFFE) (Rahman, et al, 20159). This
method was used to compare Russell Creek flows to other regional methods. The online tool uses the
catchment centroid, catchment outlet and size to estimate peak flow outputs for a range of flood magnitudes.
The tool was developed utilising data based on gauged catchments to form region based flood relationships.
The RFFE tool has several limitations to its application and should be avoided where:
The catchment includes greater than 10% urban,
Catchment storage significantly altered the natural rainfall runoff behaviour,
Catchment where large scale clearing has taken place,
Catchments which are greatly affected by irrigation activity and or drainage.
The reliability of the tool is also considered less accurate for catchment less than 0.5 km2 and or greater than
1,000 km2 or where a catchment exhibit atypical characteristics.
Whilst several of the Russell Creek catchment characteristics suggest that the method is not suitable as a
means as providing a comparison to the RORB model, the results of the tool output are provided below in
Figure 8-1. The results yielded from this assessment show estimated peak flows significantly lower than those
produced by the RORB modelling.
FIGURE 8-1 RUSSELL CREEK - RFFE
9 AR&R (2016) - http://data.arr-software.org
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 61
APPENDIX C DESIGN FLOOD MAPPING
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 62
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 63
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 64
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 65
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 66
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 67
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 68
APPENDIX D RUSSELL CREEK STRUCTURES
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 69
Structure Name TUFLOW
Structure Type Size
Horne Road 1d_nwke 4 (3m x 1.5m)
Ians Road 1d_nwke 1 (0.6m)
Ians Road 1d_nwke 2 (0.6m)
Wangoom Road 1d_nwke 2 (0.9m x 0.9m)
Aberline Road 1d_nwke 5 (1.5m x 1.5m)
Whites Road (West Crossing) 1d_nwke 2 (1.5m)
Whites Road (East Crossing) 1d_nwke 1 (1.35m)
Whites Road Pedestrian Crossing 2d_lfcsh -
Wares Road 2d_lfcsh -
Renior Pedestrian Crossing 1d_nwke 1 (0.45m)
Upstream Garden Street Footbridge 1d_nwke 4 (0.9m)
Garden Street 1d_nwke 4 (0.9m)
Moonah Drive Pedestrian Crossing 2d_lfcsh -
Oak Court Pedestrian Crossing 2d_lfcsh -
Upstream Mortlake Road Pedestrian Crossing 2d_lfcsh -
Mortlake Road Culverts (Original) 1d_nwke
Irregular (height/flow)
Mortlake Road Culverts (New) 1d_nwke 2 (3.6m x 2.4m)
Downstream Mortlake Road Pedestrian Crossing 2d_lfcsh -
Queens Street 1d_nwke 2 (1.2m)
St Joseph’s Primary Pedestrian Crossing 2d_lfcsh -
Bromfield Street 1d_nwke 6 (0.6m)
Daltons Road 1d_nwke 1 (5.7m x 1.95m)
Warrnambool City Council | November 2017 Russell Creek Flood Mitigation - As Constructed Flood Modelling Page 70
Melbourne 15 Business Park Drive Notting Hill VIC 3168 Telephone (03) 8526 0800 Fax (03) 9558 9365
Brisbane Level 3, 43 Peel Street South Brisbane QLD 4101 Telephone (07) 3105 1460 Fax (07) 3846 5144
Wangaratta First Floor, 40 Rowan Street Wangaratta VIC 3677 Telephone (03) 5721 2650
Perth PO Box 362 Subiaco WA 6904 Telephone 0407 946 051
Geelong PO Box 436 Geelong VIC 3220 Telephone 0458 015 664
Gippsland 154 Macleod Street Bairnsdale VIC 3875 Telephone (03) 5152 5833
Wimmera PO Box 584 Stawell VIC 3380 Telephone 0438 510 240
www.watertech.com.au