additionality and project cycle tunis, august 27-29, 2004 tims/eeaa cd4cdm- fourth regional workshop...
TRANSCRIPT
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
AdditionalityAdditionalityinin
NovaGerar Gas to Energy NovaGerar Gas to Energy Landfill Project Landfill Project
Amr Abdel-Aziz, Ph.D. Consultant
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
AdditionalityAdditionality
Emission reductions that are additional to any that would occur in the absence of the project
Most critical issue for project acceptanceProject will be refused if additionality is not
proven
DefinitionDefinition
ImportanceImportance
Year
Em
issi
on
s
Baseline
2004 2025
Project
Project AdditionalityEnvironmental Additionality
Year
Baseline
2004 2025
Project
Em
issi
on
s
•New Policies•Attractive econ.
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
AdditionalityAdditionality
Flow chart of series of questions that lead to narrowing down of potential options
Qualitative or quantitative assessment of different potential options and an indication of why the project is more likely
Qualitative or quantitative assessment of one or more barriers facing proposed project
An indication that the project type is not common practice in the proposed area of implementation
How to DemonstrateHow to Demonstrate
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
AdditionalityAdditionality
Economic Technology
In Easier TermsIn Easier Terms
Institutional
Barriers
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
NovaGerar Landfill ProjectNovaGerar Landfill Project
CH4
Excess Flared
Some Used to Generate Electricity
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
Project DesignProject Design
0
50,000
100,000
150,000
200,000
2000 2005 2010 2015 2020 2025
Year
MW
h/y
r
MWh Installed
MWh Capacity
4 MW5 MW7 MW
9 MW11 MW12 MW
Difference Flared
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
Additionality in AM003Additionality in AM0031. Continue BAU (no collection)2. LFG collection and flaring 3. High efficiency flaring and
power generation
Baseline and project are the only plausible options
Calculate a conservative IRR (excluding CERs)
IRR < Conservative acceptable IRR
Project IRR 4%
Gov. Bond Rate = 22%
Additional
Not Additional
Y
N
Not Required
Additional
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
IRR Calculations -- ElementsIRR Calculations -- ElementsCapital Costs (-ve)
– Electricity Generator (1 kW * 12 unit)– Flaring equipment – Gas plant– Assembling and testing– Connection to grid
Operating Costs (-ve)– Gas plant and flaring equip. O&M– Maintenance and supervision– Administrative expenses (PCF and EB)– Land rent
Others (-ve)– Income Tax
Revenue (+ve)– Carbon credits– Electricity sales
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
IRR Calculations -- ElementsIRR Calculations -- ElementsEquipmentFlaring Equipment ($) 314,308Gas Plant($) 301,370Assembling and Testing 34,133Connection to Grid (2 sites) 416,665Preoperational costs 150,000
1,216,4761 Mw Generating System(5*200kW) 748,509
Operational CostsGas Plant and Flaring O&M ($/yr) 126,012Engine Maintenance ($/yr) 230,544Carbon credits expenses ($/yr) 12,000Electricity Administrative expenses ($/yr) 120,000World Bank Administration costs($/yr) 20,000Land Rent ($/yr) 16,000Total /yr 524,556
TaxesIncome Tax 24.0%Additional Tax (>240,000/yr) 10.0%PIS+COFINS Tax 18.7%
52.7%Free Electricity to Municipality 10.0%
RevenueElec. Tarrif ($/MWh) 43
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
IRR Calculations – Cash FlowIRR Calculations – Cash FlowYear Capital Costs
Operational Costs Elec. Sales Net Cash Flow
0 (799,811) (174,012) 0 (1,390,488)1 0 (174,012) 0 (174,012)
2 0 (174,012) 0 (174,012)3 (3,410,701) (524,556) 670,568 (3,322,880)4 0 (524,556) 670,568 146,012 5 (794,093) (524,556) 832,211 (486,439)6 0 (524,556) 832,211 307,655 7 (1,684,907) (524,556) 1,155,495 (1,053,968)8 0 (524,556) 1,155,495 630,939 9 (1,787,518) (524,556) 1,478,779 (833,295)
10 0 (524,556) 1,478,779 954,223 11 (1,896,378) (524,556) 1,802,063 (618,870)12 0 (524,556) 1,802,063 1,277,507 13 0 (524,556) 1,802,063 1,277,507 14 (1,036,112) (524,556) 1,963,705 403,038 15 0 (524,556) 1,963,705 1,439,149 16 0 (524,556) 1,963,705 1,439,149 17 0 (524,556) 1,963,705 1,439,149 18 0 (524,556) 1,963,705 1,439,149 19 0 (524,556) 1,963,705 1,439,149 20 0 (524,556) 1,963,705 1,439,149
IRR 4% < Benchmark IRR Additional
Flaring and collection
Generators
IncrementalIncremental
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
Benchmark IRRBenchmark IRR
Government bond rate plus suitable project risk premium
Commercial lending rate
Expert views on expected IRRs for this or comparable project types
Other hurdle rates that can be applied for the country or sector
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
Application of Additionality TestApplication of Additionality TestPart 1: Has construction of the project already started
Part 2: Is Execution of Project based on direct on indirect legal obligation?
Project Economically less attractive
N
Y
NPart 3a: Financial or Economic barrier (Benchmark Approach)
Y
Project is more attractive
N
Part 4: Are many projects, based on same type of technology recently implemented without CDM (50/20 test)
Y
Project Additional
IRR 4% < acceptable IRR
No landfill in Brazil employs this technology
Additionality and Project Cycle Tunis, August 27-29, 2004
TIMS/EEAA CD4CDM- Fourth Regional Workshop (Phase II) UNEP RISOE / APEX
General Advice When Proving AdditionalityGeneral Advice When Proving Additionality
Transparent information should be provided
Documented evidence has to be available
Conservative interpretation of documented evidence as how it is used to demonstrate additionality
Conservative assumptions to be used