![Page 1: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/1.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Addressing Challenges Associated with Consolidation and
Decommissioning of ABSL-3 Facilities
University of Pittsburgh Department of Environmental Health & Safety
Molly S. Stitt-Fischer, PhD, CPH, SM(NRCM)
![Page 2: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/2.jpg)
University of Pittsburgh Department of Environmental Health and Safety
ABSL-3 Facility Overview
• 14 Animal Facilities
– ~330,000 square feet
• 5 ABSL-3 Facilities
– 4 separate buildings
– 15,500 square feet
![Page 3: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/3.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Why Consolidate?
• Increase efficiency of ABSL-3 program management
• Aging facilities – ~11 years old
– Latest HVAC renovation ~6 years old
– Cost/benefit analysis for consolidation vs recommissioning/renovation
• Increase efficiency for main ABSL-3 PI user group – Spaces in 3 buildings vs all spaces in 1 building on
main campus
![Page 4: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/4.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Can We Consolidate Successfully?
• Multiple logistical planning sessions with a large group of stakeholders – PI and lead research staff
• What are current laboratory usage, square footage, and equipment requirements?
– Department administration • How will costs associated with multiple relocations be
handled?
– Division of Laboratory Animal Resources
– EHS
![Page 5: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/5.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Decontamination of Facility
• Full surface disinfection by University personnel
• In house VHP vs contract decontamination services
– Rodent ABSL-3 Transgenic core facility
– NHP ABSL-3 Return to building management company for reoccupancy
– Need to fully decontaminate ductwork
![Page 6: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/6.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Rodent ABSL-3: Challenges
9th Floor of 17 Story High Rise
Animal Facility
BSL-2 Labs and Offices
ABSL-3
Surrounded by BSL-2 laboratories and common public traffic areas
![Page 7: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/7.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Rodent ABSL-3 Challenges: Timing of Gaseous Decontamination
• Samples out
• Mice out
• Full surface decontamination of ABSL-3 facility
• Immediate gaseous decontamination
![Page 8: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/8.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Rodent ABSL-3 Challenges: HVAC
+ Dedicated, separate supply and exhaust systems
+ Removal of restroom in containment
- No as built drawings
- No penthouse
- Several stories of ductwork
Animal Holding
Animal Holding
Laboratory Laboratory
Exit
Entry
![Page 9: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/9.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Rodent ABSL-3 Challenges: Impact of Location
• 9th floor of 17 story building
– Schedule gas injection after normal business hours
– Clear floor above and floor below
Animal Facility
BSL-2 Labs and Offices
ABSL-3
![Page 10: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/10.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Challenges: Impact of Location
• Communicate with all stakeholders • Department
administrators
• Building security
• Housekeeping
• Facilities management
Animal Facility
BSL-2 Labs and Offices
ABSL-3
![Page 11: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/11.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Non-Human Primate ABSL-3: Challenges
![Page 12: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/12.jpg)
University of Pittsburgh Department of Environmental Health and Safety
ABSL-2
ABSL-3
Office and Laboratory Space
Dock
Dock
NHP ABSL-3: Challenges
Stand alone building at remote campus
![Page 13: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/13.jpg)
University of Pittsburgh Department of Environmental Health and Safety
NHP ABSL-3 Challenges: Timing of Gaseous Decontamination
• Samples out
• Full surface decontamination of ABSL-3 suite
• All NHPs out of entire animal facility
• Gaseous decontamination
![Page 14: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/14.jpg)
University of Pittsburgh Department of Environmental Health and Safety
NHP ABSL-3 Challenges: HVAC - Supply shared with
other portions of NHP facility
± BTD on supply?
- No as built drawings/control sequences
– Exhaust bypass
– Fan shutdown sequences
ABSL-2
ABSL-3
Office and Laboratory Space
Dock
Dock
![Page 15: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/15.jpg)
University of Pittsburgh Department of Environmental Health and Safety
NHP ABSL-3 Challenges: Impact of Location
ABSL-2
ABSL-3
Office and Laboratory Space
Dock
Dock
• Stand alone building • No animals present so
no need for personnel
• Research operations shutdown
• Contractor access to ABSL-3
![Page 16: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/16.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Lessons Learned
• Engineering support and knowledge of all laboratory systems crucial
– Do you have as builts?
– Have you done renovations?
– If not, do you have knowledgeable engineers to help contractor trace ductwork?
![Page 17: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/17.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Lessons Learned
• Engineering support and knowledge of all laboratory systems crucial
– Do a dry run of fan shutdown/restart
– Are your control sequences accurate?
– How is airflow reported by your control system?
![Page 18: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/18.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Lessons Learned
• Engineering support and knowledge of all laboratory systems crucial
– Do you know how many circuits you have in area and where the breakers are located?
![Page 19: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/19.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Lessons Learned
• Do you know how to override your door interlocks?
– Through building management system or a manual key?
– Does anyone have possession of the key?
• Do you need to put your smoke detectors/fire alarms on standby?
– Is a permit and/or fire watch required?
![Page 20: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/20.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Lessons Learned
• Are your escorts prepared for emergencies?
• Is it possible to wait for gaseous decontamination until entire facility has been surface decontaminated?
Abort process?
![Page 21: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/21.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Lessons Learned
• Yipee! The area is decontaminated and it’s time to move equipment.
– Who is going to move your decontaminated equipment into your hot BSL-3/ABSL-3 facility?
• Hint: Not the University movers
![Page 22: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/22.jpg)
University of Pittsburgh Department of Environmental Health and Safety
Primary Lessons Learned
• Full time, dedicated engineering support crucial • Logistics meetings with all stakeholders are critical
– Specialized equipment? – Does your freezer etc fit through the door to the
anteroom?
• Once the contractor arrives you probably won’t be “hands off” during the decontamination process – Leaks? – Fan shutdown/restart – Escort? – Decontamination of equipment?
![Page 23: Addressing Challenges Associated with Consolidation and ...€¦ · University of Pittsburgh Department of Environmental Health and Safety Addressing Challenges Associated with Consolidation](https://reader031.vdocument.in/reader031/viewer/2022011914/5fb6de5f2e62301841118785/html5/thumbnails/23.jpg)
University of Pittsburgh Department of Environmental Health and Safety