Adeel Ahmad Jawed Mobile #: 00971-50-1223645 / 0092- 333-3207767 Email : [email protected] SYNOPSIS Total nine (9) years plus experience in engineering consultancy executing major projects in gas processing (both Onshore & Offshore) having experience in handling conceptual studies, FEED projects and detailed engineering projects. Also have around two (2) years of working experience in PMO (project management office, PMC) for SHELL (BGC) for supervising BGC projects in Iraq locating in engineering contractor’s office. Have hands on experience in all aspects of process engineering including process simulation, flow assurance, hydraulic simulation/studies, heat and material balance, preparing engineering drawings (PFD/P&ID etc.), equipment design and process data sheets, participate in safety reviews (i.e. Design Review, HAZOP, Bowtie analysis, SIL, etc.) technical document preparation etc. Skilled in industry standard softwares like HYSYS, UNISIM, PIPESIM, FLARENET, TGNET etc. well versed with international technical standards like API / ISO and company specific standards like BP, ADMA, GASCO, SHELL DEPs, etc. PROFESSIONAL EXPERIENCE SHELL / BGC (Agency WP) Abu Dhabi, U.A.E Sr. Process Engineer April 2013 – Present Joined Basrah Gas Company / Shell through WorleyParsons on April 15, 2013 as Process Engineer / Facility Engineer (PMO / PMC) Basrah Gas Company is a 25-year incorporated joint venture between Iraq’s South Gas Company, Shell and Mitsubishi Corporation. The joint venture captures associated gas that is currently being flared from three oil fields in southern Iraq – Rumaila, West Qurna and Zubair. South Gas Company, operations ia a gas project in Iraq’s history and the world’s largest flares reduction project. While in BGC worked on following activities / projects Working as Field Development Engineer: Developing plans for the full field. Supervising SHELL-BGC job(s) being done in Contractor’s office. Primarily working as in house design engineer carrying as a part of “Quick Win Team”. The team’s essential purpose is to engineer the quick projects i.e. cross-overs, compressor rehabilitation, system adequacy check, etc. While in BGC, worked as concept select engineer and PMO / PMC on following projects: Page 1 of 6

Upload: adeel-ahmed

Post on 07-Aug-2015

75 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Adeel_Ahmad_Resume

             

      

Adeel Ahmad Jawed    Mobile #: 00971-50-1223645 / 0092-333-3207767  Email     :        [email protected]  

SYNOPSIS

Total nine (9) years plus experience in engineering consultancy executing major projects in gas processing (both Onshore & Offshore) having experience in handling conceptual studies, FEED projects and detailed engineering projects. Also have around two (2) years of working experience in PMO (project management office, PMC) for SHELL (BGC) for supervising BGC projects in Iraq locating in engineering contractor’s office.

Have hands on experience in all aspects of process engineering including process simulation, flow assurance, hydraulic simulation/studies, heat and material balance, preparing engineering drawings (PFD/P&ID etc.), equipment design and process data sheets, participate in safety reviews (i.e. Design Review, HAZOP, Bowtie analysis, SIL, etc.) technical document preparation etc. Skilled in industry standard softwares like HYSYS, UNISIM, PIPESIM, FLARENET, TGNET etc. well versed with international technical standards like API / ISO and company specific standards like BP, ADMA, GASCO, SHELL DEPs, etc.

PROFESSIONAL EXPERIENCE

SHELL / BGC (Agency WP) Abu Dhabi, U.A.E Sr. Process Engineer April 2013 – Present

Joined Basrah Gas Company / Shell through WorleyParsons on April 15, 2013 as Process Engineer / Facility Engineer (PMO / PMC) Basrah Gas Company is a 25-year incorporated joint venture between Iraq’s South Gas Company, Shell and Mitsubishi Corporation. The

joint venture captures associated gas that is currently being flared from three oil fields in southern Iraq – Rumaila, West Qurna and Zubair. South Gas Company, operations ia a gas project in Iraq’s history and the world’s largest flares reduction project.

While in BGC worked on following activities / projectsWorking as Field Development Engineer:

• Developing plans for the full field.• Supervising SHELL-BGC job(s) being done in Contractor’s office.• Primarily working as in house design engineer carrying as a part of “Quick Win Team”. The team’s essential purpose is to

engineer the quick projects i.e. cross-overs, compressor rehabilitation, system adequacy check, etc.

While in BGC, worked as concept select engineer and PMO / PMC on following projects:

LP Network project that includes multiple compressor stations to capture the LP gas that is being flared at different degassing stations.

Revised the operating configuration of booster compressors at NR NGL from parallel to series to operate at low pressure. Integration of new compressors at existing compressors. Short term and long term solutions for debottlenecking of existing NGL section. As built of existing TEG dehydration units at Zubair field. Modification at NR NGL to receive liquid from Majnoon Installation of new pump at NR NGL slug catcher and adequacy check of existing condensate stripper unit along with the

debottlenecking of the system. DEM-2 analysis for the rental compressors Carried out DEM-1 gap analysis for power plant (engineered by ABB).

Beside this carried out multiple miscellaneous activities including process simulations of degasing stations / compressor stations, pipeline hydraulics, techno-commercial studies etc.

Worley Parsons Abu Dhabi, U.A.E

Page 1 of 4

Page 2: Adeel_Ahmad_Resume

Sr. Process Engineer June 2010 – Apr-2013

Joined the WorleyParsons as a Process Engineer and promoted to Sr. Process Engineer in 2011. Worked on following Pipeline/Offshore/Gas processing projects.

Umm Shaif Oil Network Expansion Project – FEED

• Abu Dhabi Marine Operating Company (ADMA-OPCO) aims to sustain Umm Shaif Field annual average production of 275 MBD for that assurance is required that Umm Shaif existing infield oil gathering network is adequate to sustain this oil production target. To achieve this, all constraints in the Umm Shaif pipeline network system are to be removed in a phased manner. ADMA OPCO selected WorleyParsons as FEED engineering contractor. The project consists of three new radials, five new infield pipelines, one manifold tower, one riser platform and modification to 8 existing wellhead towers.

Worked / took part on following activities:• Performed PIPESIM steady state simulation of complete USSC network including new pipelines / radials and existing pipelines.

Optimization and finalization of new pipelines sizes considering operating envelop from year 2016 till 2034.• Determined the topside pipe sizes of WHTs using hydraulic simulation.• Developed P&IDs and PFDs.• Performed / reviewed different calculations i.e. PSV sizing / equipment sizing / pump sizing etc.• Reports writing i.e. Process Basis of Design, Process Description, Hydraulic report etc.

ADMA OPCO 100 MBSPD Project (Detailed Engineering)• Worley Parsons is awarded a Detailed Engineering Project (the FEED of the project was also done by Worley Parsons) to modify

existing Zakum West Super Complex (ZWSC) facility to handle additional 100 MSTBPD crude from Thamama IV & Thamama • The project involves the modifications on ADMA OPCO’s (ADMA OPCO is Abu Dhabi’s major oil production company) one

of the strategic offshore platform called ZWSC (Zakhum West Super Complex).• The production of oil after completion of project will be increased from 360 thousand stock tank barrel per day to 460 thousand

stock tank barrel per day. As a senior process engineer I performed / took part in following activities:

• Performed HYSYS steady state simulation for the entire network starting from wet feed arrival upto oil storage.• Performed PIPESIM hydraulic simulation which involves 5 subsea pipelines. The HYSYS and PIPESIM simulations in this

project are iterative i.e. result from one simulation is input data for the other and vise versa.• Performed line sizing / control valve sizing / PSV sizing / equipment sizing calculations.• Prepared the data sheet of DELIQUIDISER (new online liquid separating technology) and evaluated the vendor offers.• Developed the operating and control philosophy document.• Took part and reviewed HYSYS DYNAMIC SIMULATION, which has been carried out to confirm the operating and control

philosophy.• Reports writing i.e. Design Basis, Simulation Report, Hydraulic Report etc.• Prepared PFDs and Heat and Material Balance.• Took part in P&ID preparation and optimization activity.• Assisted and reviewed the FLARENET model developed for the entire platform.• Actively took part in Outage Optimization Study. This study has been carried out to minimize the shutdown period of the Super

Complex and to carry out the modifications and commissioning in different stages.• Took part in HAZOP workshop.

ZADCO Mixed Mode Gas Project (Concept / FEED)• ZADCO has appointed WorleyParsons as an engineering contractor to carry out the FEED of a project called ZADCO Mixed

Gas Handling Project. The objective of the project was to propose the necessary modifications and investigate the changes required on ADMA OPCO’s Zakhum West Super Complex due to the changes in ZADCO gas composition.

• Performed steady state HYSYS simulation and prepared Heat and Material Balance.• Performed PIPESIM hydraulic simulation.• Performed line sizing / control valve sizing / equipment adequacy check calculations.• Prepared the data sheet of DELIQUIDISER (new online liquid separating technology).• Developed the operating and control philosophy document.• Reports writing i.e. Design Basis, Simulation Report, Hydraulic Report etc.• Prepared PFDs and Heat and Material Balance.• Prepared P&IDs.• Took part in HAZOP workshop.

Worley Parsons Abu Dhabi, U.A.E Process Engineer July 2008 – June 2010

Page 2 of 4

Page 3: Adeel_Ahmad_Resume

GASCO Hydrocarbon Acid Gas Flare Recovery Project (Concept / FEED)• GASCO (Abu Dhabi Gas Company) awarded WorleyParsons, the FEED the project called “Hydrocarbon Acid Gas Recovery

Project”. This was an environment driven project and aim was to reduce the acid gas flare venting to “Zero Flaring” as per GASCO’s environment standards. The project involves recovering the normal flaring sour gas from Acid Gas Flare by a tap off in the flare header and routing the gas back to processing units via a Gas Recovery Unit (comprises of a set of compressors, knock out drums and air coolers).

• Performed site visits and collected data to have a head start.• Performed HYSYS simulations.• Developed PFDs, P&IDs and generated Heat and Material Balance.• Extensively used FlareNet to check the back pressure on existing instruments / equipments due to additional facilities.• Establish the acid gas recovery scheme.• Carried out the gas recovery compressor selection study. Acid gas flare being operated at very low pressure therefore gas

recovery compressor selection is the most critical activity of the project.• Report writing.• Took part in HAZOP & SIL Study.

ADMA OPCO Compressor Impact Study• As a sequential of 100 MBD FEED project ADMA OPCO awarded WorleyParsons a study to check the adequacy of different

compressor stations (GG-II, GPF, GIP, CGIP), located at ZWSC platform, for the modified gas production profile resulted in 100 MBD FEED.

• Developed the adequacy checking methodology for the gas compressor units (including vessels, heat exchangers, compressors etc).

• Simulated the Gas compressor platforms (GG-II, GPF, GIP & CGIP) including Hydrocarbon dew point control unit and condensate handling system i.e. Condensate Stripper.

• Used vendor performance curves to check the adequacy of compressors.• Report writing.• Performed necessary calculations.

ADMA OPCO 100 MBSPD Project (FEED)• Worley Parsons is awarded a FEED to modify existing Zakum West Super Complex (ZWSC) facility to handle additional 100

MSTBPD crude from Thamama IV & Thamama V.• Performed simulation of ZWSC platform using HYSYS• Carried out gas / oil pipeline hydraulics using PIPESIM• Line / Relief Valve / Control Valve sizing and prepared calculation dossier• Sized the pump for new service• Report writing• Developed the PFD & P&ID• Prepared Data sheets of equipments• Took part in HAZOP & SIL study workshops• Prepared Heat & Material Balance

BANA GAS Well Head Compression (FEED)• Bahrain National Gas Company (BANAGAS) has appointed WorleyParsons (WP) to initiate a pipeline network evaluation and

compression study to identify bottlenecks and suggest additional facilities to accommodate a planned increase in throughput at the BANAGAS facilities from the current operating capacity of 300 MMSCFD to 525 MMSCFD, and design capacity of 530 MMSCFD by 2020.

• Developed PFD & P&ID• Prepared Heat & Material Balance• Developed the Relief system model using FLARENET for adequacy check.• Carried out different calculations for line sizing, control valve sizing, pump sizing etc

DOLPHIN ENERGY GAS PIPELINE (Detailed Engineering)• Dolphin Energy Ltd. is undertaking the Taweelah Fujairah Pipeline project (TFP) to deliver natural gas from its existing

Taweelah Receiving Facility (TRF) in the Emirate of Abu Dhabi to Fujairah in the Emirate of Fujairah in the UAE (United Arab Emirates). The existing TRF is operated by Dolphin Energy and has a capacity to receive 3.2 BSCFD of natural gas from Ras Laffan in Qatar through a 360 km x 48 inch subsea Export Pipeline. The TFP project intent is to provide an additional 48 inch pipeline from TRF to the FRS (Fujairah Receiving Station) in order to supply upto 1.6 BSCFD of natural gas to serve the immediate and future gas requirements.

• Carried out HYSYS Simulation and extracted Heat & Material balance• Carried out control valve and relief valve sizing calculations• Report writing• Carried out different calculations.• Prepared instruments / equipments data sheets

Presson Descon Intl. Pvt. Limited Lahore, Pakistan Process Engineer October 2007 – July 2008

Worked as a process engineer on onshore gas processing plants & supply jobs. MEHAR Field Development Project

• Performed HYSYS Simulation and extracted Heat & Material balance

Page 3 of 4

Page 4: Adeel_Ahmad_Resume

• Carried out control valve and relief valve sizing calculations• Developed PFDs & P&IDs• Prepared RFQs for the vendors• Estimated mandatory utilities i.e. Instrument air, Hot Oil, Fuel gas etc• Prepared Data sheets of equipments

Kunnar Pasakai Deep Development Project (KPD)• Revalidation of FEED documents of 300 MMSCFD KPD project owned by OGDCL• Used HYSYS to simulate the plant including Amine Sweetening, Glycol Dehydration & Condensate Stabilization Unit.• Carried out control valve and relief valve sizing calculations• Developed PFDs & P&IDs• Prepared RFQs for the vendors• Estimated mandatory utilities i.e. Instrument air, Hot Oil, Fuel gas etc• Prepared Data sheets of equipments

SINJHORO Field Development Project• Prepared HYSYS Simulation and extracted Heat & Material balance• Carried out control valve and relief valve and equipment sizing calculations• Developed PFDs & P&IDs• Prepared RFQs for the vendors• Estimated mandatory utilities i.e. Instrument air, Hot Oil, Fuel gas etc• Prepared Data sheets of equipments

Petrosin Engineering Karachi, Pakistan Junior Process Engineer December 2005 – October 2007

Worked as a junior process engineer on amine treating, glycol dehydration, HCDP unit & involved in pre-comm. & Comm. TANDO ALLAH YAR (TAY) Development Project

• Extracted Heat & Material balance• Carried out control valve and relief valve sizing calculations• Developed PFDs• Took part in preparation of P&IDs• Estimated mandatory utilities i.e. Instrument air, Hot Oil, Fuel gas etc• Prepared Data sheets of equipments

PINDORI Field Expansion Project• Prepared Data sheets of equipments. • Heat Exchanger Sizing using HTFS (TASC)• Line sizing, Control valve and Equipment Sizing• Developed As Built P&IDs• Took part in pre – commissioning • Worked as junior shift engineer during START UP and COMMISSIONING of LPG Extraction & Propane generation unit• Took part in ACCEPTANCE TEST and PERFORMANCE TEST of the plant

EDUCATION

University of Karachi, Karachi, PakistanDepartment of Chemical Engineering January 2002 - December 2005

Bachelor of Engineering in Chemical EngineeringADDITIONAL SKILLS

Engineering Software: Can use professionally, HYSYS (Got trained from ASPEN TECHNOLOGIES), PIPESIM, HTFS, HTRI, FLARENET, ASPEN ZYQAD, ASPEN SPPID, TGNET (Got training from PIPELINE STUDIO), MS Office.

Engineering Codes and Standards: A good knowledge of engineering codes and standards for Oil and Gas industry like API, NORSOK, ASME and company specific standards like DEP, BP, and TOTAL etc.

MEMBERSHIP & ASSOCIATION

Associate membership of ICHEME, Membership application is under progress.

PERSONAL DETAILS

Religion: Islam Nationality: Pakistan Address : NH-93 Labor Square Landhi Karachi, (At Present located in Abu Dhabi, UAE) Mobile #: 00971-50-1223645 Email : [email protected] Marital Status: Married Driving License: Valid UAE Driving License

Page 4 of 4