adopting km in a pmo

15
A case study on the adoption of knowledge management by the Corporate Projects Division of Suncorp. Presented by Cory Banks (KM Specialist) to the 2007 KM Australia Conference, 23 rd July 2007. 1

Upload: cory-banks

Post on 29-Nov-2014

4.914 views

Category:

Education


1 download

DESCRIPTION

Case study of adopting knowledge management principles and practices in a Project Management Office. Delivered at the 2007 KM Australia Conference, Sydney, July 2007.

TRANSCRIPT

Page 1: Adopting KM in a PMO

A case study on the adoption of knowledge management by the Corporate Projects Division of Suncorp. 

Presented by Cory Banks (KM Specialist) to the 2007 KM Australia Conference, 23 rd July 2007. 

1

Page 2: Adopting KM in a PMO

OPENING THOUGHT 

UK Public Footpaths 

• Public Rights of Way, Permissive Routes, Queens Highway • Countryside and Rights of Way Act 2000 • Owners cannot obstruct (fence, gate, stile) without permission and must comply with standards http://www.ramblers.org.uk/info/britain/footpathlaw.html 

What if we had “Public Footpaths” in our organisations. What if we had to maintain access to our knowledge so anyone from your organisation could travel along the footpath and discover what they need? 

2

Page 3: Adopting KM in a PMO

Agenda • Introduction • Setting the Scene • KM Program • Outcomes • Learnings • Questions 

3

Page 4: Adopting KM in a PMO

Who is Suncorp? • Top 15 ASX • Financial Services • Allfinanz model – Banking, Insurance & Investments • Headquartered in Brisbane, QLD. 17,000 staff throughout Australia & New Zealand. • Recently merged with Promina. Corporate Projects Division • Enterprise Project Management Office (PMO) • Portfolio Management Responsibility • Program & Project Management, Business Analysis, Change Management and User Acceptance Testing Capabilities. • Involved with high complexity, high risk, group wide projects. • 60­70 projects p.a. – $200­$300m • 80% Contract Delivery Staff 

4

Page 5: Adopting KM in a PMO

Investigation • Drivers – Customer Feedback – Professional Services Model • Early 2005 ­ Part of CPD Realignment Program ­ External Assessment of KM Maturity • Findings presented in July 2005 ­  Maturity level of 1 – KM by Accident • Recommended appointing a KM Specialist ­ Provided a list of 24 projects to be undertaken to improve maturity. KM Specialist • Recruitment – Meeting with MOR (General Manager). Leading the drive for KM. Came from consulting firm background and has seen and experienced the benefits. • Started Dec 2005 – Good time of year to start. Christmasslowdown and people available. • Given the Investigations Report containing a plan to deliver the 24 projects ­ Took a step back. Set about designing KM Strategy. My Thinking • Research – What have others done? ­ Models / Frameworks ­  Looking to find what was suitable for the situation. Considerations • Strategic Alignment ­ Customer Focus: Consultation, perceptions, priorities ­ People Systems, not technology ­ “Quick Wins” KM Strategy • Looking for support – Divisional Strategy, Departmental Strategy, Corporate Strategy 

• Divisional Strategy ­ Institutionalise Corporate Knowledge • Corporate Strategic Drivers ­ Execution Excellence, High Performing Teams, Group Synergies • Code of Conduct ­ Core Competencies ­ Building Capability 

• Identified Leaders Perceptions – What does KM mean to you? What are your expectations? KM Program • Balance – (Learning Before, Learning During, Learning After) • Foundation ­ Alignment with other programs ­ QuickWins 

5

Page 6: Adopting KM in a PMO

KM Program 

• Two Phases ­ Establish (foundation) and Grow • Nine Initiatives in the first 12 months • Eight Initiatives in the second 12 months 

6

Page 7: Adopting KM in a PMO

Relationship of Program Activities 

Previously mentioned balance. Balance across Learning Before, Learning During and Learning After as described by Geoff Parcell and Chris Collison in their book Learning to Fly (www.learning­to­fly.org) . 

This slide is an animated walk­thru of the cycle. 

7

Page 8: Adopting KM in a PMO

PROGRAM DELIVERY • People – Culture – Time to develop self versus time to develop others. Acceptable to ask for help, share and support others. Not a sign of weakness. • No budget. Sole resource. So what do you do? You borrow, you steal. Learn from others. • Don’t reinvent the wheel. Look for what is already there, what’s working ­ Internal and External 

• Communities ­ Networks • Procedures • Document repositories ­ Skills register • Induction/Mentoring program • PIR Process • Collaboration 

• It’s not cheating, it’s working smarter. • Rule No. 1 – Lead by example. Practice what you Preach. Show the value. Set the standard. Existing KM What did we find and reuse? • Mentoring Program • Wiki / Intranet • Memberships/Subscriptions • Explicit Resources • Communities “in the wild” What did we have to create/deliver? 

8

Page 9: Adopting KM in a PMO

• Existing Test Forum, informal Project Officers Group and sporadic PM Forum. • Working with stakeholders. Supporting ‘Owners’. Strategic Alignment. • Rebooted PM Community ­ Kicked off Change Management Community ­ Working on BA Community. • Face­to­face gatherings supported by intranet site, wiki and email list. • People reticent to ask for help. Relying on personal networks/trusted sources. • People with issues contact KM Specialist instead of community. • Core members see the value. • Leader behaviour effects participation 

9

Page 10: Adopting KM in a PMO

Headstart • Learning Before • Scalable Activity • Workshop based on Peer Assist model developed by Collison & Parcel (www.learning­to­fly.org) 

POST IMPLEMENTATION REVIEWS Previously • Occurrence determined by personal preference • 2 week to 12 month activity • External Facilitator • Survey and Interview Based • Scores produced • Blurred with Closure activities (2 similar surveys) • Report required customer approval • Findings ‘filed’ New Process • Scalable, collaborative approach – AAR. Scale E.g. SDP, APRA • Narrative Capture – Dave Snowden (Cognitive Edge) • Duration massively reduced – 2 days • Focussed on producing Improvements and Learnings • Using Learnings • Accountability • Sense of Closure  10

Page 11: Adopting KM in a PMO

• Complimenting the PM method with Knowledge Assets. 

11

Page 12: Adopting KM in a PMO

• An improvement in KM Maturity to Level 2. • Three Communities of Practice related to capability areas and another one on the way. • Embedded AAR and Headstart  activities. • Improved Induction Program – recognised as one of the most comprehensive in the organisation. • Mentoring Program recently launched • KM recognised in staff KRA’s (KPI’s) • Improved access to external knowledge sources – Corporate Executive Board, Human Systems Network • Supporting repositories due for launch in August (Lessons Learned Library & Expertise Locator ­ Sharepoint) • Other parts of the organisation asking for help 

12

Page 13: Adopting KM in a PMO

Lessons Learned •  Look at it from changing Behaviour / Culture •  There is no one way to do KM. Get across a few different ways and work out what is going to be suitable in your situation. •  Find what is already working in your environment and see what makes it tick. •  Include those you are going to effect in the design & decision making. •  People before Technology •  Don’t try to do it all at once. Pace yourself. •  Ask “Has this been done before?”. Learn from previous efforts. Practice what you preach. •  Leader Behaviour ­ People follow the Leader. •  More people offer than ask for help 

13

Page 14: Adopting KM in a PMO

Questions 

14

Page 15: Adopting KM in a PMO

15 

Thankyou for allowing me to share my knowledge. 

Best of Luck with your KM endeavours. 

Enjoy the rest of the conference. 

Cory Banks KM Specialist, Suncorp [email protected]