adr digest winter 07
TRANSCRIPT
-
7/30/2019 ADR Digest Winter 07
1/8
ADR Digest 1
EVgicZgh^c6aiZgcVi^kZ9^hejiZGZhdaji^dc
Digest Winter 2007Issue 2
Contractors Beware:the new Handbookand prolongationcosts
ByJames B Longbottom BSc(Hons) LLB(Hons) FRICS
FHKIS FCIArb RPS - Managing Director, ADR Partnership Ltd
IntroductionIn December 2006, the Government o the Hong Kong
Special Administrative Region introduced its controversial
Handbook or Preparing Bills o Quantities or Civil
Engineering Works (the Handbook) which is to replace
the Standard Method o Measurement or Civil Engineering
Works, 1992 Edition (the SMM). ADR understands that the
Handbook will be issued on a trial basis on 10 new tenders
although there have been comments rom within the
industry that the trial projects chosen by Government
appear to be either small or term contracts and, thereore,
are inappropriate or any meaningul evaluation.
The HandbookThis article is the rst o two articles analysing some
o the changes in the method o measurement in the
Handbook rom those in the SMM, and concentrates on
one aspect o the new Handbook which is the paying or
prolongation costs through pre-priced measured items
in the Bills o Quantities (BQ) and the eects that the
provisions have on overhead recovery rom variations.
Prolongation CostsIn the Handbook, the measurement o extended time
based preliminaries during a period o Contract overrun
is based on the ollowing principles:
Preliminaries other than the Contractors overheads
(eg. temporary accommodation or the Engineer and
In this issue:
1 Welcome
1 Contractors Beware: the new Handbook and
prolongation costs
5 Compromise: Recovering the settlement that
shouldnt have been
Welcome
In this edition o the ADR Digest, James Longbottom takes
a look at the Hong Kong Governments new Handbook
which replaces the Standard Method o Measurement or
Civil Engineering Works. James considers one aspect o the
new Handbook which is the paying or prolongation costs
through pre-priced measured items in the Bills oQuantities and concludes that the changes are bad news
or contractors and or the industry in general.
Our guest writer in this edition o the ADR Digest is Timothy
Hill, Partner o the law rm Lovells. Tim considers a recent
English court decision on compromise settlements and
oers some practical advice or parties aced with a problem
o whether to settle a disputed claim and then look to
recover the settlement at a later date rom third parties.
In this edition, we also commence the ADR Analysis series
which will address key commercial and contractual
principles arising on construction projects. The rst in the
series considers what happens i there is delay caused to a
project by inclement weather within an extended periodater the original date or completion.
As part o our continued growth within the region we
extend a warm welcome to three new members into our
team - Derek Dixon, Travis Ling and Kaymond Lam -
see our news section or urther details.
Finally, we would like to wish you all Seasons Greetings
and a very prosperous New Year.
Patrick J ONeillDirector
7 ADR Analysis: Inclement Weather
8 ADR News
-
7/30/2019 ADR Digest Winter 07
2/8
& * . &( &, '&
Bdci]Bdci]an8dhi7FGViZ6kZgV\Z=@'#'B"^cXa#BV^ciZcVcXZEZgdY7FGViZ6kZgV\Z=@(#'B"ZmXa#BV^ciZcVcXZEZgdY
'* '. ((
)#*
)#%
(#*
(#%
'#*
'#%
*
%
%#*
%#%
=@$Bdci]
:miZcYZY
8dbeaZi^dc
9ViZ
BV^ciZcVcXZ
EZg^dY
7FGViZ
7FGViZ
6aadlVcXZ[dg8dbeZchVWaZ
:miZch^dchd[I^bZ
photographs) are measured during an extended time or
completion; and
Contractors overheads (eg. personnel, plant, temporary
accommodation, site and o-site overheads) are measured
during an extended time or completion which is due to
causes relating to the direct actions o the Employer /
Engineer (these are dened in Figure 1 and reerred to in
this article as compensable extensions o time).
In the Preace to the Handbook, Government argues that
these provisions:
... do away with the time consuming and resource
demanding Cost ascertainment exercise associated with
excusable delay by measuring and paying such Cost
through items in the Bills o Quantities.
However, a closer look at the provisions reveals that they raise
serious problems with respect to a Contractors entitlement
to the recovery o Contractors overheads arising rom
variations and prolongation.
VariationsTypically, Contractors overheads are priced in both the
Preliminaries and the items or measured works in the BQ.
However, paragraph 1.2 o the Preamble to the Handbook
deems that the Contractors overheads, including the
overheads o his subcontractors o any tier, shall be included
exclusively in the rates or Contractors overheads and not
against other items o work in the BQ.
This means that i the Contractor ollows the Handbook the
valuation o variations based on existing BQ rates or items o
measured work will no longer include or the recovery o
Contractors overheads. Moreover, Special Condition o
Contract (SCC) Clause E(3) which accompanies the Handbook
provides that:
...the provisions in General Conditions o Contract Clauses
59(4)(b) and 61... shall have no application to the rates
inserted by the Contractor against the items o work under
the sub-heading Contractors overheads in the Bills o
Quantities.
Thereore, any adjustment or increased quantities rendering
BQ rates unreasonable or inapplicable (GCC Clause 59(4)(b)) or
the valuing o new rates (GCC Clause 61) will also exclude
Contractors overheads. The upshot being that:
any additional or thickening o Contractors overheads
arising rom variations which materially aect the progress
o the Works (eg. additional supervisory sta and head
oce support) will have to be recovered as Cost pursuant to
GCC Clause 63(b) ie. a reversion back to the time consuming
and resource demanding Cost ascertainment exercise!;
where any additional or thickening o Contractorsoverheads arises rom variations which do not materially
aect the progress o the Works, the Contractor will not
have any contractual grounds or recovery and will lose
money; and
Contractors will also lose money on variations which
include price related Contractors overheads (eg. levies).
Pricing Contractors OverheadsThe guidance notes in Part III o the Handbook state that the
number o months inserted or Contractors overheads in the
Quantity column o the BQ should include or:
the original time or completion o the Works;
a reasonable allowance or compensable extensions o time
that may be granted; and
the Maintenance Period.
In other words, monthly rates priced or Contractors
overheads should be calculated as a composite average based
on the above estimated costs divided by the number o
months inserted in the Quantity column o the BQ.
The rst point to pick-up on is the inclusion o the
Maintenance Period in the overall duration or Contractors
overheads. This has the eect o articially reducing the
average BQ rate priced by the Contractor (see Figure 2).This in turn distorts and backloads the recovery o overhead
expenditure placing the Contractor in negative cash position
which the Contractor has to nance until the end o the
Maintenance Period. This is nonsensical and ADR understands
Figure 2:Example o Monthly Overhead Expenditure
GCCClause
Causes of Delay Causes Relatingto Direct Actionsof the Employer /Engineer
50(b)(i) Inclement Weather No
50(b)(ii) Tropical Cyclone No
50(b)(iia) Black Rainstorm No
50(b)(iii) Ambiguity or Discrepancy Yes
50(b)(iv) Variation Yes
50(b)(v) Substantial Increase in Quantities No
50(b)(vi) Late Possession Yes
50(b)(vii) Disturbance Yes
50(b)(viii) Suspension Order Yes
50(b)(ix) Utility Company No
50(b)(x) Nominated SubContractor No
50(b)(xi) Special Circumstances No
Figure 1:Causes o Delay Relating to the Direct Actions o the
Employer / the Engineer
2 Winter 2007
-
7/30/2019 ADR Digest Winter 07
3/8
that Government has undertaken to amend this and that the
latest drat o the Handbook actually does so. It is worth
mentioning this point, however, since the published version
available in the public domain refects the above wording.
More importantly, it shows the extent to which the new
provisions have not suciently been thought through.
Competitively Priced DelaysThe next point to pick-up on is the allowance or compensable
extensions o time. Putting aside the act that it is bizarre that
a project should include an estimate or overrunning beore it
has even got started, this provision means an increased
amount included or the allowance or compensable extensions
o time will increase the tender price. Put another way, i a
tenderer prices the allowance low, his overall tender price will
thereore be lower is this what Government wants,
competitively priced delays?
SCC Clauses E(1) to (3) which accompany the Handbook re-
dene the meaning o Cost to exclude prolongation costs andprovide that the measurement o Contractors overheads
whether or not resulting in payment, shall exonerate the
Employer rom any urther liability in respect o overheads,
whether on or o Site including head ofce overheads, cost o
fnancing and depreciation in the value o Construction Plant,
o the Contractor and any o his subcontractors o any tier
under the Contract. Thereore, the Contractor is stuck with
his pre-priced rates or valuing prolongation and there is no
mechanism or recovering any shortalls as Cost under
GCC Clause 63.
In situations where the Contractor under estimates or simply
prices his Contractors overheads competitively so that they no
longer refect his actual costs, the Employer will gain a nancialbenet or any prolongation. This contradicts the established
principle o putting the Contractor back in the position it
would have been but or the compensable delay.
Moreover, can an average cost ever airly and realistically
refect the nancial eects o a delay throughout the
construction period o a major civil engineering project?
It is a recognised principle that prolongation costs should be
ascertained during the period that the delaying eects are
elt. This is an important concept as usually a Contractors
overheads will gradually increase, peak and then decrease
during the construction period. Thereore, the nancial eects
o a delaying event are likely to be greater mid-way through
construction than towards the end o project when resources
are starting to wind down. This is why in Figure 2 the
allowance or compensable extensions o time was priced at
the peak o the curve; ie. a belts and braces approach was
taken to cover the worst eventuality. However, i the
Contractor priced the allowance at a lower point on the
expenditure prole to keep his tender price competitive, this
would result in the under recovery o prolongation costs elt
at the peak o the curve.
The Risk of Time OverrunsI the compensable extensions o time or the project
described in Figure 2 transpired and the rates or Contractors
overheads realistically represented the Contractors actual
costs, then all should be well.
However, i the project nished later than the period measuredin the BQ or compensable extensions o time, then the
Contractor would make a nancial loss (the converse would occur
i the project nished earlier than the period measured in the
BQ; ie. the Contractor would in theory make a nancial gain).
For example, in Figure 2, the period measured in the BQ or
compensable extensions o time was 3 months. However, i
the compensable delay was actually 4 months, the actual cost
o the additional month o prolongation (assuming the eects
were elt at the peak o the expenditure curve) would be HK$4
million. I this prolongation was measured using the BQ rates
(excluding the Maintenance Period), the Contractor would
recover only an additional HK$3.2 million, a shortall o
HK$0.8 million.
Further, extensions o time in Hong Kong are oten granted
retrospectively ater the Contract has nished so the
measuring and valuing o the prolongation costs using
pre-priced measured items in the BQ is likely to make little
dierence in reality, in the Contractor receiving reimbursement
o the additional expenditure any earlier.
A Possible Solution for ContractorsWhere the allowance inserted in the BQ or compensable
extensions o time is elt to be inadequate, one possible
solution could be to strategically price the Contractors
overheads using a period which realistically refects thelikelihood o prolongation. However, this solution is not
problem-ree and is raught with risks:
How does a Contractor assess whether a Contract will
ADR Digest 3
... the Contractor is stuck with
his pre-priced rates or valuing
prolongation and there is no
mechanism or recovering
any shortalls as Cost under
GCC Clause 63.
-
7/30/2019 ADR Digest Winter 07
4/8
suer compensable extensions o time? The Contractor is
required to blindly predict the timing o the eects o likely
delays which may or may not occur and their expected
duration this is a gamble which could potentially reap
nancial windalls or generate huge losses depending on
where the delays all and the pricing strategy adopted.
The Contractor may have to load disproportionate sums
o money in relation to the overall Contract Sum into the
Contractors overheads.
Any additional monies which have been strategically priced
into the Contractors overheads would have to be taken
o other rates elsewhere in the BQ. However, the BQ rates
which have been reduced in value will no longer refect
the cost o the work being perormed. This leaves the
Contractor exposed to urther risks i the quantities o
such works are subsequently increased.
ConclusionsThe methodology used or the pre-pricing o prolongation
costs in the Handbook is not avourable to Contractors.
Generally, they will be worse o that is worse o in terms
o recovery o Contractors overheads or prolongation and
variations. I the new provisions are to ... do away with the
time consuming and resource demanding Cost ascertainment
exercise associated with excusable delay ... ie. to bypass
prolongation Cost claims, then they appear ill conceived andinadequately thought through.
Surely, the position has got to refect that it is equitable or
both parties to ocus on ascertaining the actual additional
Cost incurred and or the Contractor to receive a air recovery
on the basis o this actual additional expenditure.
What is the consequence o all o the above? Well, Contractors
who have not been able to strategically price the Contractors
overheads and/or that realise that their project will not receive
commensurate nancial compensation or the delays will no
doubt pursue alternative avenues to ensure that they receive
their air entitlements and this, in our opinion, will inevitably
lead to a heightened claims environment.
In conclusion, to quote one major contractor, the new
Handbook is reducing what was already a high risk bidding
process, into a blind gamble which is beyond the control o the
Contractor.
The December 2006 version o the Handbook can be
downloaded at:
www.cedd.gov.hk/eng/downloading/index.htm
For urther inormation contact:
To quote one
major contractor,
the new Handbook is
reducing what was already
a high risk bidding process,into a blind gamble
which is beyond the control
o the Contractor.
4 Winter 2007
-
7/30/2019 ADR Digest Winter 07
5/8
Compromise: Recoveringthe settlement thatshouldnt have been
ByTimothy Hill, Partner, Lovells
From an early age children are taught that they cannot
get into trouble i they are not in the wrong, it would
thereore seem surprising i a party could ace a substantial
award o damages even i they were not in the wrong.
However, the English Technology and Construction Court has
decided just that in the case oJohn F Hunt Demolition Co Ltd
v ASME Engineering Limited [2007] EWHC 1507, (2007) 23 Con
LJ T99. When put in these terms the conclusion is surprising
but in an environment where parties are encouraged to settle
their dierences it is perhaps less remarkable.
In any complex construction project the successul completion
o the project is a team eort. It involves a complex inter-
relationship o parties with distinct obligations. Faced with
these challenges project sponsors and indeed increasingly
contractors look to package parcels o responsibility to third
parties. This can lead to diculties when problems are
encountered or projects go wrong. In a typical scenario a
project sponsor will look to its contractor to be responsible
or damage which has occurred without wishing to become
involved in an inquiry as to which o a number o sub-
contractors or suppliers was responsible or the loss.
The contractor will look to its sub-contractors or suppliers to
indemniy it against the liability or to contribute to that loss.
However, very oten the contractor will discover that the sub-contractor or supplier will deny responsibility. In an ideal world
the contractor may seek to resolve the main contract and
sub-contract disputes at the same time, but this is not always
possible. There are a number o reasons or this, or example
the breadth o the obligations owed by the contractor to
the project sponsor may be such that i the contractor
cannot avail itsel o the same type o argument as the
sub-contractor deploys, the contractor may consider the
sub-contractors arguments unsustainable or there may be
procedural or other obstacles preventing the issues being dealt
with at a common time in a common orum. In these
circumstances, a contractor is aced with a dilemma. It may
not wish to get drawn into long and costly proceedings but at
the same time it is likely to wish to ensure that it can rely
upon any settlement reached with the employer in its claim
against the sub-contractor.
The basic issue was considered in the well known decision o
Biggin & Co Ltd v Permanite Ltd [1951] 2 KB 314. In this case
Biggin supplied materials which had been sold to it by
Permanite to a third party. The materials proved to be
deective and as a result Biggin paid compensation to the
third party, it then sought to recover this compensation rom
Permanite, basing its claim upon the settlement which had
been achieved with the third party. The Court o Appeal
considered that the settlement was relevant to the
assessment o damages at the sub-contract level.
Firstly it stated that the settlement was to operate as an
upper limit on the level o damages which could be awarded.
Clearly it would be unreasonable to suggest that a contractor
who achieved a avourable settlement with a project sponsor
could seek to prot rom this by making a ull recovery against
its sub-contractor. The second more controversial conclusion
was that the settlement could be accepted by the Court as
the correct measure o damages i the settlement was a
reasonable one and somewhere around the level o damages
which would be awarded. The Court made the observation
that the party seeking to rely on the settlement could becross-examined as to its reasonableness and that in an
appropriate case the deendant might show that some vital
matter had been overlooked. This let open the prospect that
a sub-contractor could challenge a settlement both as to the
undamental question o whether liability existed and as to
the level o the settlement.
One o a number o loose ends let at the conclusion o this
case was what happened i the sub-contractor contended
that the main contractor had no liability to pay the employer.
This problem was touched upon in a decision Comyn Ching &
Co Ltd v Oriental Tube Co Ltd [1979] 17 BLR 47. Here the
supplier challenged the contractors liability to pay the
settlement sum. The case turned largely on the construction
o the relevant documents and as a result the Court did
not have to decide the question o principle. Comment was
however made that a loss could be sustained i the claim arose
ADR Digest 5
The ... more controversial
conclusion was that the
settlement could be accepted
by the Court as the correct
measure o damages i
the settlement was a
reasonable one...
-
7/30/2019 ADR Digest Winter 07
6/8
rom the reasonable settlement o a claim which had some
prospect or a signicant chance o success. Thus it could be
said that the settlement o a claim with a prospect o success
might be relied upon, but what i the contractor was plain
wrong in deciding to settle a claim?
The 8th Edition o Keating sits neatly on the ence, stating
that:
it will usually also be necessary to establish the claimants
liability to the third party and the deendants liability to the
claimant since evidence o the compromise is relevant only
to the measure o damages.
This issue however ell or consideration inJohn F Hunt
Demolition Co Ltd v ASME Engineering Limited. In the case the
deendant, ASME, was a sub-contractor engaged to undertake
welding work. Unortunately, sparks rom this work set light
to bitumen elt weather-proong on another part o the
project, which caught re. Hunt, who had engaged ASME,
received a claim rom the employer and main contractor or
approximately 250,000. The sub-contractor oered
approximately 150,000 to settle these claims, which was
accepted. Hunt then sought to recover the sum rom ASME.
For the purpose o the hearing it was accepted that a sum
in excess o 100,000 o the settlement sum could not
properly have been claimed by the employer against the
main contractor. Consequently, Hunt could not have been
responsible to pay the sum. ASME thereore resisted payment
o this sum to Hunt. ASME argued that the settlement with
The Court recognized
that the settlement o an
intrinsically weak claim in order
to avoid the uncertainties in
the expensive litigation maywell be reasonable.
the employer and main contractor was irrelevant or, at the
very least, unreasonable because Hunt had ailed to realize
and/or act upon the absence o any liability. The Court did
not accept this argument, although let a possible way out
or ASME.
The Court said that in deciding whether a settlement sum
could be recovered the starting point would be a consideration
o whether the breach o contract caused Hunt to incur theloss or damage suered as a result o its decision to
compromise the claim. I the claim was (or was reasonably
considered to be) o sucient strength reasonably to justiy a
settlement and the amount paid in settlement was
reasonable having regard to the strength o the claim, the
settlement might be relied upon to justiy the recovery o the
loss even i the claim would ater urther examination and
perhaps a trial have ailed. The Court recognized that the
settlement o an intrinsically weak claim in order to avoid the
uncertainties in the expensive litigation may well be
reasonable. It said that this conclusion was entirely consistent
with the normal rules o oreseeability and remoteness o
damage, because it considered that it was reasonably
oreseeable at the time o the contract that a party maysettle the claim brought by another aris ing out o the same
subject matter, even i on a detailed analysis, liability may be
hard or even impossible to establish.
The Court considered the question o reasonableness was a
question o act in each given set o circumstances. This nal
observation allowed the Court to avoid a nal determination
o the specic issue in the case, because o the need or a
actual inquiry as to the circumstances in which the
settlement was made.
The eect o this decision is thereore to make it clear that in
appropriate circumstances a paying party may recover the cost
o a settlement even i on urther analysis it was not liable topay the claim. I aced with a problem o whether to settle a
disputed claim it would thereore be prudent or a party to
take appropriate proessional advice and to make sure that its
reasoning in concluding that the proposed settlement oered
a commercially attractive means o settling the case is
recorded. This case may be seen as urther evidence o the
Courts willingness to oster a climate in which parties are
encouraged to arrive at a commercial resolution o their
disputes and dierences.
For urther inormation contact:
6 Winter 2007
-
7/30/2019 ADR Digest Winter 07
7/8
ADR Digest 7
ADR Analysis
Inclement Weather
Some standard orms o contract do not list inclement
weather as an excusable event (see Figure 1). Thereore, the
contractor assumes responsibility or both the nancial and
programming eects o inclement weather.
What happens then i there is delay caused by inclement
weather within an extended period ater the original date
or completion? The contractor will not have made any
allowance or such delays and the Contract Administrator
(CA) is supercially not empowered to grant extensions o
time i inclement weather is not listed as an excusable event.
The answer is simple. Delays caused by inclement weather
in an extended period should be considered as part o the
eects o the primary delaying event (ie. the excusable event)
or which extensions o time have been or should be granted.Generally, the principle is that inclement weather in an
extended period qualies or urther extensions o time i it
was incurred due to the consequential or knock-on eects o
ExcusableEvent
CompensableEvent
HKIA/HKICM/HKIS
Standard Form
of Building Contract,
Private Edition
Yessee Clause 25(b)
& (c)
No
Swire Properties Ltds
Standard Form
of Building Contract
No
No
Governments GCC
for Civil Engineering
Works
Yessee Clause 50(1)(b)(i),
(ii) & (iia)
No
KCRCs GCC forCivil Engineering
& Building Works
Nosee Clause 45.4(d)
No
Figure 1: Inclement Weather Provisions in Hong Kong Standard
Forms o Contract
an excusable event. Authority or the principle can be ound
in the Canadian case oEllis Don v The Parking Authority o
Toronto (1978).
Most standard orms o contract also provide that the CAs
assessment o an extension o time should be air and
reasonable, which should take into account all o the eects
caused by an excusable event including inclement weather.
Generally, a delay caused by inclement weather is not a
compensable event giving rise to additional payment or
recompense. However, based upon the principles established
above, the contractor may be entitled to recover the
additional costs incurred due to delays caused by inclement
weather, which costs were incurred due to the knock-on
eects o a primary excusable / compensable event.
-
7/30/2019 ADR Digest Winter 07
8/8
EVgicZgh^c6aiZgcVi^kZ9^hejiZGZhdaji^dc
8 Winter 2007
CIArb Young Members Group
Social Evening
ADR Partnership was proud to be a sponsor o the Chartered
Institute o Arbitrators Young Members Group social gathering
held at Grappas Restaurant, Central. Great company, good ood
and a plentiul supply o drink was the ideal recipe or a most
enjoyable evening.
ADR Partnership Limited
17A Seabright Plaza 9-23 Shell Street North Point Hong Kong
t: (852) 2234 5228 : (852) 2234 6228
e: [email protected] www.adrpartnership.com
ADR Partnership Limited and the contributors to ADR Digest do not accept any liability for any views, opinions or advice given in this publication.
Readers are strongly recommended to take legal and/or technical specialist advice for their own particular circumstances.
Designedby:w
ww.ichicoodesign.com
Tel:+44(0)1274560220
ADR News
Expanding the ADR Team
It has been a busy ew months or us at ADR Partnership and we
are pleased to announce that the ollowing consultants have
joined the ADR team:
Derek Dixon
FRICS
Managing Consultant
Derek is a Chartered Quantity
Surveyor with over 40 years
experience in commercial and
contractual matters. He has
acted as an expert witness in
arbitration and High Court
hearings on numerous occasions
and has extensive experience working at a senior level in the
preparation and deense o contractual claims.
Travis C K Ling
BBuild MFM MRICS AAIQS
Consultant
Travis is a Chartered Quantity
Surveyor currently studying or
a degree in Law. He has a wide
range o civil, inrastructure,
building and building services
experience having advised clientson commercial and contractual
matters on some o the largest projects in Hong Kong and Macau.
Kaymond H C Lam
BEng(Hons) LLB(Hons) MSc DIC
MHKIE MICE CEng PCLL
Consultant
Kaymond is a Chartered Engineer
with a degree in Law and has also
completed the Post Graduate
Certifcate in Laws. He has
provided a broad range o services
on various engineering projects in
Hong Kong, including providing support in both arbitration andmediation proceedings.
Further details o all our consultants and directors can be ound
on our website: www.adrpartnership.com
Chartered Institute of Arbitrators Young Members Group
Spot the Young Member!
Based in Hong Kong, ADR Partnership Limited is a dynamic practice
o construction proessionals providing specialist commercial and
contractual services to the construction industry.
I you would like to discuss any o the articles published in this Digest
or your project requirements, please contact James Longbottom,
Patrick ONeill or David Longbottom at ADR Partnership Limited on
(852) 2234 5228 or e-mail us at [email protected]