adr digest winter 07

Upload: sherif-mohsen

Post on 04-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/30/2019 ADR Digest Winter 07

    1/8

    ADR Digest 1

    EVgicZgh^c6aiZgcVi^kZ9^hejiZGZhdaji^dc

    Digest Winter 2007Issue 2

    Contractors Beware:the new Handbookand prolongationcosts

    ByJames B Longbottom BSc(Hons) LLB(Hons) FRICS

    FHKIS FCIArb RPS - Managing Director, ADR Partnership Ltd

    IntroductionIn December 2006, the Government o the Hong Kong

    Special Administrative Region introduced its controversial

    Handbook or Preparing Bills o Quantities or Civil

    Engineering Works (the Handbook) which is to replace

    the Standard Method o Measurement or Civil Engineering

    Works, 1992 Edition (the SMM). ADR understands that the

    Handbook will be issued on a trial basis on 10 new tenders

    although there have been comments rom within the

    industry that the trial projects chosen by Government

    appear to be either small or term contracts and, thereore,

    are inappropriate or any meaningul evaluation.

    The HandbookThis article is the rst o two articles analysing some

    o the changes in the method o measurement in the

    Handbook rom those in the SMM, and concentrates on

    one aspect o the new Handbook which is the paying or

    prolongation costs through pre-priced measured items

    in the Bills o Quantities (BQ) and the eects that the

    provisions have on overhead recovery rom variations.

    Prolongation CostsIn the Handbook, the measurement o extended time

    based preliminaries during a period o Contract overrun

    is based on the ollowing principles:

    Preliminaries other than the Contractors overheads

    (eg. temporary accommodation or the Engineer and

    In this issue:

    1 Welcome

    1 Contractors Beware: the new Handbook and

    prolongation costs

    5 Compromise: Recovering the settlement that

    shouldnt have been

    Welcome

    In this edition o the ADR Digest, James Longbottom takes

    a look at the Hong Kong Governments new Handbook

    which replaces the Standard Method o Measurement or

    Civil Engineering Works. James considers one aspect o the

    new Handbook which is the paying or prolongation costs

    through pre-priced measured items in the Bills oQuantities and concludes that the changes are bad news

    or contractors and or the industry in general.

    Our guest writer in this edition o the ADR Digest is Timothy

    Hill, Partner o the law rm Lovells. Tim considers a recent

    English court decision on compromise settlements and

    oers some practical advice or parties aced with a problem

    o whether to settle a disputed claim and then look to

    recover the settlement at a later date rom third parties.

    In this edition, we also commence the ADR Analysis series

    which will address key commercial and contractual

    principles arising on construction projects. The rst in the

    series considers what happens i there is delay caused to a

    project by inclement weather within an extended periodater the original date or completion.

    As part o our continued growth within the region we

    extend a warm welcome to three new members into our

    team - Derek Dixon, Travis Ling and Kaymond Lam -

    see our news section or urther details.

    Finally, we would like to wish you all Seasons Greetings

    and a very prosperous New Year.

    Patrick J ONeillDirector

    7 ADR Analysis: Inclement Weather

    8 ADR News

  • 7/30/2019 ADR Digest Winter 07

    2/8

    & * . &( &, '&

    Bdci]Bdci]an8dhi7FGViZ6kZgV\Z=@'#'B"^cXa#BV^ciZcVcXZEZgdY7FGViZ6kZgV\Z=@(#'B"ZmXa#BV^ciZcVcXZEZgdY

    '* '. ((

    )#*

    )#%

    (#*

    (#%

    '#*

    '#%

    *

    %

    %#*

    %#%

    =@$Bdci]

    :miZcYZY

    8dbeaZi^dc

    9ViZ

    BV^ciZcVcXZ

    EZg^dY

    7FGViZ

    7FGViZ

    6aadlVcXZ[dg8dbeZchVWaZ

    :miZch^dchd[I^bZ

    photographs) are measured during an extended time or

    completion; and

    Contractors overheads (eg. personnel, plant, temporary

    accommodation, site and o-site overheads) are measured

    during an extended time or completion which is due to

    causes relating to the direct actions o the Employer /

    Engineer (these are dened in Figure 1 and reerred to in

    this article as compensable extensions o time).

    In the Preace to the Handbook, Government argues that

    these provisions:

    ... do away with the time consuming and resource

    demanding Cost ascertainment exercise associated with

    excusable delay by measuring and paying such Cost

    through items in the Bills o Quantities.

    However, a closer look at the provisions reveals that they raise

    serious problems with respect to a Contractors entitlement

    to the recovery o Contractors overheads arising rom

    variations and prolongation.

    VariationsTypically, Contractors overheads are priced in both the

    Preliminaries and the items or measured works in the BQ.

    However, paragraph 1.2 o the Preamble to the Handbook

    deems that the Contractors overheads, including the

    overheads o his subcontractors o any tier, shall be included

    exclusively in the rates or Contractors overheads and not

    against other items o work in the BQ.

    This means that i the Contractor ollows the Handbook the

    valuation o variations based on existing BQ rates or items o

    measured work will no longer include or the recovery o

    Contractors overheads. Moreover, Special Condition o

    Contract (SCC) Clause E(3) which accompanies the Handbook

    provides that:

    ...the provisions in General Conditions o Contract Clauses

    59(4)(b) and 61... shall have no application to the rates

    inserted by the Contractor against the items o work under

    the sub-heading Contractors overheads in the Bills o

    Quantities.

    Thereore, any adjustment or increased quantities rendering

    BQ rates unreasonable or inapplicable (GCC Clause 59(4)(b)) or

    the valuing o new rates (GCC Clause 61) will also exclude

    Contractors overheads. The upshot being that:

    any additional or thickening o Contractors overheads

    arising rom variations which materially aect the progress

    o the Works (eg. additional supervisory sta and head

    oce support) will have to be recovered as Cost pursuant to

    GCC Clause 63(b) ie. a reversion back to the time consuming

    and resource demanding Cost ascertainment exercise!;

    where any additional or thickening o Contractorsoverheads arises rom variations which do not materially

    aect the progress o the Works, the Contractor will not

    have any contractual grounds or recovery and will lose

    money; and

    Contractors will also lose money on variations which

    include price related Contractors overheads (eg. levies).

    Pricing Contractors OverheadsThe guidance notes in Part III o the Handbook state that the

    number o months inserted or Contractors overheads in the

    Quantity column o the BQ should include or:

    the original time or completion o the Works;

    a reasonable allowance or compensable extensions o time

    that may be granted; and

    the Maintenance Period.

    In other words, monthly rates priced or Contractors

    overheads should be calculated as a composite average based

    on the above estimated costs divided by the number o

    months inserted in the Quantity column o the BQ.

    The rst point to pick-up on is the inclusion o the

    Maintenance Period in the overall duration or Contractors

    overheads. This has the eect o articially reducing the

    average BQ rate priced by the Contractor (see Figure 2).This in turn distorts and backloads the recovery o overhead

    expenditure placing the Contractor in negative cash position

    which the Contractor has to nance until the end o the

    Maintenance Period. This is nonsensical and ADR understands

    Figure 2:Example o Monthly Overhead Expenditure

    GCCClause

    Causes of Delay Causes Relatingto Direct Actionsof the Employer /Engineer

    50(b)(i) Inclement Weather No

    50(b)(ii) Tropical Cyclone No

    50(b)(iia) Black Rainstorm No

    50(b)(iii) Ambiguity or Discrepancy Yes

    50(b)(iv) Variation Yes

    50(b)(v) Substantial Increase in Quantities No

    50(b)(vi) Late Possession Yes

    50(b)(vii) Disturbance Yes

    50(b)(viii) Suspension Order Yes

    50(b)(ix) Utility Company No

    50(b)(x) Nominated SubContractor No

    50(b)(xi) Special Circumstances No

    Figure 1:Causes o Delay Relating to the Direct Actions o the

    Employer / the Engineer

    2 Winter 2007

  • 7/30/2019 ADR Digest Winter 07

    3/8

    that Government has undertaken to amend this and that the

    latest drat o the Handbook actually does so. It is worth

    mentioning this point, however, since the published version

    available in the public domain refects the above wording.

    More importantly, it shows the extent to which the new

    provisions have not suciently been thought through.

    Competitively Priced DelaysThe next point to pick-up on is the allowance or compensable

    extensions o time. Putting aside the act that it is bizarre that

    a project should include an estimate or overrunning beore it

    has even got started, this provision means an increased

    amount included or the allowance or compensable extensions

    o time will increase the tender price. Put another way, i a

    tenderer prices the allowance low, his overall tender price will

    thereore be lower is this what Government wants,

    competitively priced delays?

    SCC Clauses E(1) to (3) which accompany the Handbook re-

    dene the meaning o Cost to exclude prolongation costs andprovide that the measurement o Contractors overheads

    whether or not resulting in payment, shall exonerate the

    Employer rom any urther liability in respect o overheads,

    whether on or o Site including head ofce overheads, cost o

    fnancing and depreciation in the value o Construction Plant,

    o the Contractor and any o his subcontractors o any tier

    under the Contract. Thereore, the Contractor is stuck with

    his pre-priced rates or valuing prolongation and there is no

    mechanism or recovering any shortalls as Cost under

    GCC Clause 63.

    In situations where the Contractor under estimates or simply

    prices his Contractors overheads competitively so that they no

    longer refect his actual costs, the Employer will gain a nancialbenet or any prolongation. This contradicts the established

    principle o putting the Contractor back in the position it

    would have been but or the compensable delay.

    Moreover, can an average cost ever airly and realistically

    refect the nancial eects o a delay throughout the

    construction period o a major civil engineering project?

    It is a recognised principle that prolongation costs should be

    ascertained during the period that the delaying eects are

    elt. This is an important concept as usually a Contractors

    overheads will gradually increase, peak and then decrease

    during the construction period. Thereore, the nancial eects

    o a delaying event are likely to be greater mid-way through

    construction than towards the end o project when resources

    are starting to wind down. This is why in Figure 2 the

    allowance or compensable extensions o time was priced at

    the peak o the curve; ie. a belts and braces approach was

    taken to cover the worst eventuality. However, i the

    Contractor priced the allowance at a lower point on the

    expenditure prole to keep his tender price competitive, this

    would result in the under recovery o prolongation costs elt

    at the peak o the curve.

    The Risk of Time OverrunsI the compensable extensions o time or the project

    described in Figure 2 transpired and the rates or Contractors

    overheads realistically represented the Contractors actual

    costs, then all should be well.

    However, i the project nished later than the period measuredin the BQ or compensable extensions o time, then the

    Contractor would make a nancial loss (the converse would occur

    i the project nished earlier than the period measured in the

    BQ; ie. the Contractor would in theory make a nancial gain).

    For example, in Figure 2, the period measured in the BQ or

    compensable extensions o time was 3 months. However, i

    the compensable delay was actually 4 months, the actual cost

    o the additional month o prolongation (assuming the eects

    were elt at the peak o the expenditure curve) would be HK$4

    million. I this prolongation was measured using the BQ rates

    (excluding the Maintenance Period), the Contractor would

    recover only an additional HK$3.2 million, a shortall o

    HK$0.8 million.

    Further, extensions o time in Hong Kong are oten granted

    retrospectively ater the Contract has nished so the

    measuring and valuing o the prolongation costs using

    pre-priced measured items in the BQ is likely to make little

    dierence in reality, in the Contractor receiving reimbursement

    o the additional expenditure any earlier.

    A Possible Solution for ContractorsWhere the allowance inserted in the BQ or compensable

    extensions o time is elt to be inadequate, one possible

    solution could be to strategically price the Contractors

    overheads using a period which realistically refects thelikelihood o prolongation. However, this solution is not

    problem-ree and is raught with risks:

    How does a Contractor assess whether a Contract will

    ADR Digest 3

    ... the Contractor is stuck with

    his pre-priced rates or valuing

    prolongation and there is no

    mechanism or recovering

    any shortalls as Cost under

    GCC Clause 63.

  • 7/30/2019 ADR Digest Winter 07

    4/8

    suer compensable extensions o time? The Contractor is

    required to blindly predict the timing o the eects o likely

    delays which may or may not occur and their expected

    duration this is a gamble which could potentially reap

    nancial windalls or generate huge losses depending on

    where the delays all and the pricing strategy adopted.

    The Contractor may have to load disproportionate sums

    o money in relation to the overall Contract Sum into the

    Contractors overheads.

    Any additional monies which have been strategically priced

    into the Contractors overheads would have to be taken

    o other rates elsewhere in the BQ. However, the BQ rates

    which have been reduced in value will no longer refect

    the cost o the work being perormed. This leaves the

    Contractor exposed to urther risks i the quantities o

    such works are subsequently increased.

    ConclusionsThe methodology used or the pre-pricing o prolongation

    costs in the Handbook is not avourable to Contractors.

    Generally, they will be worse o that is worse o in terms

    o recovery o Contractors overheads or prolongation and

    variations. I the new provisions are to ... do away with the

    time consuming and resource demanding Cost ascertainment

    exercise associated with excusable delay ... ie. to bypass

    prolongation Cost claims, then they appear ill conceived andinadequately thought through.

    Surely, the position has got to refect that it is equitable or

    both parties to ocus on ascertaining the actual additional

    Cost incurred and or the Contractor to receive a air recovery

    on the basis o this actual additional expenditure.

    What is the consequence o all o the above? Well, Contractors

    who have not been able to strategically price the Contractors

    overheads and/or that realise that their project will not receive

    commensurate nancial compensation or the delays will no

    doubt pursue alternative avenues to ensure that they receive

    their air entitlements and this, in our opinion, will inevitably

    lead to a heightened claims environment.

    In conclusion, to quote one major contractor, the new

    Handbook is reducing what was already a high risk bidding

    process, into a blind gamble which is beyond the control o the

    Contractor.

    The December 2006 version o the Handbook can be

    downloaded at:

    www.cedd.gov.hk/eng/downloading/index.htm

    For urther inormation contact:

    [email protected]

    To quote one

    major contractor,

    the new Handbook is

    reducing what was already

    a high risk bidding process,into a blind gamble

    which is beyond the control

    o the Contractor.

    4 Winter 2007

  • 7/30/2019 ADR Digest Winter 07

    5/8

    Compromise: Recoveringthe settlement thatshouldnt have been

    ByTimothy Hill, Partner, Lovells

    From an early age children are taught that they cannot

    get into trouble i they are not in the wrong, it would

    thereore seem surprising i a party could ace a substantial

    award o damages even i they were not in the wrong.

    However, the English Technology and Construction Court has

    decided just that in the case oJohn F Hunt Demolition Co Ltd

    v ASME Engineering Limited [2007] EWHC 1507, (2007) 23 Con

    LJ T99. When put in these terms the conclusion is surprising

    but in an environment where parties are encouraged to settle

    their dierences it is perhaps less remarkable.

    In any complex construction project the successul completion

    o the project is a team eort. It involves a complex inter-

    relationship o parties with distinct obligations. Faced with

    these challenges project sponsors and indeed increasingly

    contractors look to package parcels o responsibility to third

    parties. This can lead to diculties when problems are

    encountered or projects go wrong. In a typical scenario a

    project sponsor will look to its contractor to be responsible

    or damage which has occurred without wishing to become

    involved in an inquiry as to which o a number o sub-

    contractors or suppliers was responsible or the loss.

    The contractor will look to its sub-contractors or suppliers to

    indemniy it against the liability or to contribute to that loss.

    However, very oten the contractor will discover that the sub-contractor or supplier will deny responsibility. In an ideal world

    the contractor may seek to resolve the main contract and

    sub-contract disputes at the same time, but this is not always

    possible. There are a number o reasons or this, or example

    the breadth o the obligations owed by the contractor to

    the project sponsor may be such that i the contractor

    cannot avail itsel o the same type o argument as the

    sub-contractor deploys, the contractor may consider the

    sub-contractors arguments unsustainable or there may be

    procedural or other obstacles preventing the issues being dealt

    with at a common time in a common orum. In these

    circumstances, a contractor is aced with a dilemma. It may

    not wish to get drawn into long and costly proceedings but at

    the same time it is likely to wish to ensure that it can rely

    upon any settlement reached with the employer in its claim

    against the sub-contractor.

    The basic issue was considered in the well known decision o

    Biggin & Co Ltd v Permanite Ltd [1951] 2 KB 314. In this case

    Biggin supplied materials which had been sold to it by

    Permanite to a third party. The materials proved to be

    deective and as a result Biggin paid compensation to the

    third party, it then sought to recover this compensation rom

    Permanite, basing its claim upon the settlement which had

    been achieved with the third party. The Court o Appeal

    considered that the settlement was relevant to the

    assessment o damages at the sub-contract level.

    Firstly it stated that the settlement was to operate as an

    upper limit on the level o damages which could be awarded.

    Clearly it would be unreasonable to suggest that a contractor

    who achieved a avourable settlement with a project sponsor

    could seek to prot rom this by making a ull recovery against

    its sub-contractor. The second more controversial conclusion

    was that the settlement could be accepted by the Court as

    the correct measure o damages i the settlement was a

    reasonable one and somewhere around the level o damages

    which would be awarded. The Court made the observation

    that the party seeking to rely on the settlement could becross-examined as to its reasonableness and that in an

    appropriate case the deendant might show that some vital

    matter had been overlooked. This let open the prospect that

    a sub-contractor could challenge a settlement both as to the

    undamental question o whether liability existed and as to

    the level o the settlement.

    One o a number o loose ends let at the conclusion o this

    case was what happened i the sub-contractor contended

    that the main contractor had no liability to pay the employer.

    This problem was touched upon in a decision Comyn Ching &

    Co Ltd v Oriental Tube Co Ltd [1979] 17 BLR 47. Here the

    supplier challenged the contractors liability to pay the

    settlement sum. The case turned largely on the construction

    o the relevant documents and as a result the Court did

    not have to decide the question o principle. Comment was

    however made that a loss could be sustained i the claim arose

    ADR Digest 5

    The ... more controversial

    conclusion was that the

    settlement could be accepted

    by the Court as the correct

    measure o damages i

    the settlement was a

    reasonable one...

  • 7/30/2019 ADR Digest Winter 07

    6/8

    rom the reasonable settlement o a claim which had some

    prospect or a signicant chance o success. Thus it could be

    said that the settlement o a claim with a prospect o success

    might be relied upon, but what i the contractor was plain

    wrong in deciding to settle a claim?

    The 8th Edition o Keating sits neatly on the ence, stating

    that:

    it will usually also be necessary to establish the claimants

    liability to the third party and the deendants liability to the

    claimant since evidence o the compromise is relevant only

    to the measure o damages.

    This issue however ell or consideration inJohn F Hunt

    Demolition Co Ltd v ASME Engineering Limited. In the case the

    deendant, ASME, was a sub-contractor engaged to undertake

    welding work. Unortunately, sparks rom this work set light

    to bitumen elt weather-proong on another part o the

    project, which caught re. Hunt, who had engaged ASME,

    received a claim rom the employer and main contractor or

    approximately 250,000. The sub-contractor oered

    approximately 150,000 to settle these claims, which was

    accepted. Hunt then sought to recover the sum rom ASME.

    For the purpose o the hearing it was accepted that a sum

    in excess o 100,000 o the settlement sum could not

    properly have been claimed by the employer against the

    main contractor. Consequently, Hunt could not have been

    responsible to pay the sum. ASME thereore resisted payment

    o this sum to Hunt. ASME argued that the settlement with

    The Court recognized

    that the settlement o an

    intrinsically weak claim in order

    to avoid the uncertainties in

    the expensive litigation maywell be reasonable.

    the employer and main contractor was irrelevant or, at the

    very least, unreasonable because Hunt had ailed to realize

    and/or act upon the absence o any liability. The Court did

    not accept this argument, although let a possible way out

    or ASME.

    The Court said that in deciding whether a settlement sum

    could be recovered the starting point would be a consideration

    o whether the breach o contract caused Hunt to incur theloss or damage suered as a result o its decision to

    compromise the claim. I the claim was (or was reasonably

    considered to be) o sucient strength reasonably to justiy a

    settlement and the amount paid in settlement was

    reasonable having regard to the strength o the claim, the

    settlement might be relied upon to justiy the recovery o the

    loss even i the claim would ater urther examination and

    perhaps a trial have ailed. The Court recognized that the

    settlement o an intrinsically weak claim in order to avoid the

    uncertainties in the expensive litigation may well be

    reasonable. It said that this conclusion was entirely consistent

    with the normal rules o oreseeability and remoteness o

    damage, because it considered that it was reasonably

    oreseeable at the time o the contract that a party maysettle the claim brought by another aris ing out o the same

    subject matter, even i on a detailed analysis, liability may be

    hard or even impossible to establish.

    The Court considered the question o reasonableness was a

    question o act in each given set o circumstances. This nal

    observation allowed the Court to avoid a nal determination

    o the specic issue in the case, because o the need or a

    actual inquiry as to the circumstances in which the

    settlement was made.

    The eect o this decision is thereore to make it clear that in

    appropriate circumstances a paying party may recover the cost

    o a settlement even i on urther analysis it was not liable topay the claim. I aced with a problem o whether to settle a

    disputed claim it would thereore be prudent or a party to

    take appropriate proessional advice and to make sure that its

    reasoning in concluding that the proposed settlement oered

    a commercially attractive means o settling the case is

    recorded. This case may be seen as urther evidence o the

    Courts willingness to oster a climate in which parties are

    encouraged to arrive at a commercial resolution o their

    disputes and dierences.

    For urther inormation contact:

    [email protected]

    6 Winter 2007

  • 7/30/2019 ADR Digest Winter 07

    7/8

    ADR Digest 7

    ADR Analysis

    Inclement Weather

    Some standard orms o contract do not list inclement

    weather as an excusable event (see Figure 1). Thereore, the

    contractor assumes responsibility or both the nancial and

    programming eects o inclement weather.

    What happens then i there is delay caused by inclement

    weather within an extended period ater the original date

    or completion? The contractor will not have made any

    allowance or such delays and the Contract Administrator

    (CA) is supercially not empowered to grant extensions o

    time i inclement weather is not listed as an excusable event.

    The answer is simple. Delays caused by inclement weather

    in an extended period should be considered as part o the

    eects o the primary delaying event (ie. the excusable event)

    or which extensions o time have been or should be granted.Generally, the principle is that inclement weather in an

    extended period qualies or urther extensions o time i it

    was incurred due to the consequential or knock-on eects o

    ExcusableEvent

    CompensableEvent

    HKIA/HKICM/HKIS

    Standard Form

    of Building Contract,

    Private Edition

    Yessee Clause 25(b)

    & (c)

    No

    Swire Properties Ltds

    Standard Form

    of Building Contract

    No

    No

    Governments GCC

    for Civil Engineering

    Works

    Yessee Clause 50(1)(b)(i),

    (ii) & (iia)

    No

    KCRCs GCC forCivil Engineering

    & Building Works

    Nosee Clause 45.4(d)

    No

    Figure 1: Inclement Weather Provisions in Hong Kong Standard

    Forms o Contract

    an excusable event. Authority or the principle can be ound

    in the Canadian case oEllis Don v The Parking Authority o

    Toronto (1978).

    Most standard orms o contract also provide that the CAs

    assessment o an extension o time should be air and

    reasonable, which should take into account all o the eects

    caused by an excusable event including inclement weather.

    Generally, a delay caused by inclement weather is not a

    compensable event giving rise to additional payment or

    recompense. However, based upon the principles established

    above, the contractor may be entitled to recover the

    additional costs incurred due to delays caused by inclement

    weather, which costs were incurred due to the knock-on

    eects o a primary excusable / compensable event.

  • 7/30/2019 ADR Digest Winter 07

    8/8

    EVgicZgh^c6aiZgcVi^kZ9^hejiZGZhdaji^dc

    8 Winter 2007

    CIArb Young Members Group

    Social Evening

    ADR Partnership was proud to be a sponsor o the Chartered

    Institute o Arbitrators Young Members Group social gathering

    held at Grappas Restaurant, Central. Great company, good ood

    and a plentiul supply o drink was the ideal recipe or a most

    enjoyable evening.

    ADR Partnership Limited

    17A Seabright Plaza 9-23 Shell Street North Point Hong Kong

    t: (852) 2234 5228 : (852) 2234 6228

    e: [email protected] www.adrpartnership.com

    ADR Partnership Limited and the contributors to ADR Digest do not accept any liability for any views, opinions or advice given in this publication.

    Readers are strongly recommended to take legal and/or technical specialist advice for their own particular circumstances.

    Designedby:w

    ww.ichicoodesign.com

    Tel:+44(0)1274560220

    ADR News

    Expanding the ADR Team

    It has been a busy ew months or us at ADR Partnership and we

    are pleased to announce that the ollowing consultants have

    joined the ADR team:

    Derek Dixon

    FRICS

    Managing Consultant

    Derek is a Chartered Quantity

    Surveyor with over 40 years

    experience in commercial and

    contractual matters. He has

    acted as an expert witness in

    arbitration and High Court

    hearings on numerous occasions

    and has extensive experience working at a senior level in the

    preparation and deense o contractual claims.

    Travis C K Ling

    BBuild MFM MRICS AAIQS

    Consultant

    Travis is a Chartered Quantity

    Surveyor currently studying or

    a degree in Law. He has a wide

    range o civil, inrastructure,

    building and building services

    experience having advised clientson commercial and contractual

    matters on some o the largest projects in Hong Kong and Macau.

    Kaymond H C Lam

    BEng(Hons) LLB(Hons) MSc DIC

    MHKIE MICE CEng PCLL

    Consultant

    Kaymond is a Chartered Engineer

    with a degree in Law and has also

    completed the Post Graduate

    Certifcate in Laws. He has

    provided a broad range o services

    on various engineering projects in

    Hong Kong, including providing support in both arbitration andmediation proceedings.

    Further details o all our consultants and directors can be ound

    on our website: www.adrpartnership.com

    Chartered Institute of Arbitrators Young Members Group

    Spot the Young Member!

    Based in Hong Kong, ADR Partnership Limited is a dynamic practice

    o construction proessionals providing specialist commercial and

    contractual services to the construction industry.

    I you would like to discuss any o the articles published in this Digest

    or your project requirements, please contact James Longbottom,

    Patrick ONeill or David Longbottom at ADR Partnership Limited on

    (852) 2234 5228 or e-mail us at [email protected]