advance mr p
TRANSCRIPT
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 1/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Chap ter 15
Resource
Planning
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 2/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Material Requirements Planning
• Materials requirements planning (MRP) is a means fordetermining the number of parts, components, andmaterials needed to produce a product
• MRP provides time scheduling information specifying
when each of the materials, parts, and componentsshould be ordered or produced
• Dependent demand drives MRP
• It is most valuable in industries where a number ofproducts are made in batches using the sameproductive equipment.
• The theme of MRP is ―getting the right materials to theright place at the right time‖.
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 3/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Demand Patterns
| | | | | | | | | |
1 5 10
Day
2000 —
1500 —
1000 —
500 —
0
B i c y c l e s
R i m s
R i m s
2000 —
1500 —
1000 —
500 —
0| | | | | | | | | |
1 5 10
Day
Figure 15.2
(a) (b)
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 4/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Demand Patterns
| | | | | | | | | |
1 5 10
Day
2000 —
1500 —
1000 —
500 —
0
B i c y c l e s
Reorder point
Figure 15.2
R i m s
R i m s
2000
—
1500 —
1000 —
500 —
0| | | | | | | | | |
1 5 10
Day(a) (b)
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 5/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Demand Patterns
2000 —
1500 —
1000 —
500 —
0
R i m s
R i m s
2000 —
1500 —
1000 —
500 —
0| | | | | | | | | |
1 5 10
Day
| | | | | | | | | |
1 5 10
Day
Order
1000 on
day 3
B i c y c l e s
Reorder point
(a) (b)
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 6/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Demand Patterns
2000 —
1500 —
1000 —
500 —
0| | | | | | | | | |
1 5 10
Day
Order
1000 on
day 3
B i c y c l e s
Reorder point
(a) (b)
R i m s
R i m s
2000
—
1500 —
1000 —
500 —
0| | | | | | | | | |
1 5 10
Day
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 7/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Demand Patterns
(a) (b)
2000 —
1500 —
1000 —
500 —
0| | | | | | | | | |
1 5 10
Day
Order
1000 on
day 3
Order
1000 on
day 8
B i c y c l e s
Reorder point
2000 —
1500 —
1000 —
500 —
0
R i m s
R i m s
| | | | | | | | | |
1 5 10
Day
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 8/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Demand Patterns
(a) (b)
2000 —
1500 —
1000 —
500 —
0| | | | | | | | | |
1 5 10
Day
Order
1000 on
day 3
Order
1000 on
day 8
B i c y c l e s
Reorder point
2000 —
1500 —
1000 —
500 —
0
R i m s
R i m s
| | | | | | | | | |
1 5 10
Day
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 9/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Demand Patterns
2000 —
1500 —
1000 —
500 —
0
R i m s
R i m s
2000 —
1500 —
1000 —
500 —
0| | | | | | | | | |
1 5 10
Day(a) (b)
| | | | | | | | | |
1 5 10
Day
Order
1000 on
day 3
Order
1000 on
day 8
B i c y c l e s
Reorder point
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 10/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Material Requ iremen ts
Plan Inpu ts
Figure 15.4
Bills of
materials
Engineering
and process
designs
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 11/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Material Requ iremen ts
Plan Inpu ts
Bills of
materials
Engineering
and process
designs
Other
sources
of demand
Authorized
master production
schedule
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 12/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Material Requ iremen ts
Plan Inpu ts
Inventory
transactions
Inventory
records
Bills of
materials
Engineering
and process
designs
Other
sources
of demand
Authorized
master production
schedule
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 13/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Material Requ iremen ts
Plan Exp los ion
Inventory
transactions
Inventory
records
Bills of
materials
Engineering
and process
designs
MRP
explosion
Other
sources
of demand
Authorized
master production
schedule
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 14/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Material Requ iremen ts
Plan Ou tpu t
Inventory
transactions
Inventory
records
Bills of
materials
Engineering
and process
designs
Material
requirements
plan
MRP
explosion
Other
sources
of demand
Authorized
master production
schedule
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 15/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Bill of Materials (BOM)
• Indicates all the raw materials, components,subassemblies, and assemblies required toproduce an item
• A structured list of all components, parts, andmaterials of an item
• Shows way a finished product or parent item is put together from individual components
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 16/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
B il l o f Materials
Figure 15.5
Seat cushion
Seat-frame
boards
Front
legs ALadder-back
chair
Back
legs
Leg supports
Back slats
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 17/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
B il l o f Materials
Figure 15.5
Back slats Seat cushion
Seat-frame
boards
Leg supports
FrontlegsBacklegs A
Ladder-back
chairJ (4)
Seat-frame
boards
C (1)
Seat
subassembly
D (2)
Front
legs
B (1)
Ladder-back
subassembly
E (4)
Leg
supports
A
Ladder-back
chair
I (1)
Seat
cushion
H (1)
Seat
frame
G (4)
Back
slats
F (2)
Back
legs
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 18/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Master Production Schedule
• Based on actual customer orders and
predicted demand
• Indicates when each ordered item willbe produced
• Time-phased plan specifying how many
and when the firm plans to build eachend item
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 19/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Master Product ion Schedule
200
Ladder-back chair
Kitchen chair
Desk chair
1 2
April May
670
3 4 5 6 7 8
200
150
120
200
150
200
120
Aggregateproduction planfor chair family
670
Figure 15.6
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 20/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Inventory Record• Detailed information regarding the
quantity of each item, on hand, on order
committed to use in various time
periods• MRP system using inventory master file
to determine the quantity available for
use in a given period• If sufficient items are not available, the
system includes the item on the planned
order release report
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 21/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Inventory Reco rd Figure 15.11
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 22/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Inventory Reco rdItem: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
Explanation:
Gross requirements are the total demand for
the two chairs. Projected on-hand inventory
in week 1 is 37 + 230 – 150
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 23/60To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Inventory Reco rdItem: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
Explanation:
Gross requirements are the total demand for
the two chairs. Projected on-hand inventory
in week 1 is 37 + 230 – 150 = 117 units.
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 24/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Inventory Reco rd
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 25/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Inventory Reco rd
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
Projected on-hand
inventory balance
at end of week t
Inventory on
hand at end of
week t - 1
Gross
requirements
in week t
Scheduled
or planned
receipts in
week t
= + –
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 26/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Inventory Reco rd
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117 – 3 – 3 –153 –273 –273
Projected on-hand
inventory balance
at end of week t
Inventory on
hand at end of
week t - 1
Gross
requirements
in week t
Scheduled
or planned
receipts in
week t
= + –
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 27/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117 –3 – 3 –153 – 273 – 273
Planned Orders
Explanation:Without a new order in week 4,
there will be a shortage of three
units: 117 + 0 + 0 – 120 = – 3
units.
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 28/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117
Planned Orders
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 29/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117 227
230
Planned Orders
Explanation:Adding the planned receipt
brings the balance to
117 + 0 + 230 – 120 = 227 units.
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 30/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117 227
230
Planned Orders
Explanation:Adding the planned receipt
brings the balance to
117 + 0 + 230 – 120 = 227 units.
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 31/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117 227
230
230
Planned Orders
Explanation:Offsetting for a two-week lead time
puts the corresponding planned
order release back to week 2.
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 32/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117 227
230
230
Planned Orders
Explanation:Offsetting for a two-week lead time
puts the corresponding planned
order release back to week 2.
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 33/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117 227
230
230
227 77 –43
Planned Orders
Explanation:The first planned order lasts
until week 7, when projected
inventory would drop to – 43.
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 34/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117 227
230
230
227 77
230
Planned Orders
Explanation:Adding the second planned
receipt brings the balance to
77 + 0 + 230 – 120 = 187.
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 35/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117 227
230
230
227 77
230
Planned Orders
Explanation:Adding the second planned
receipt brings the balance to
77 + 0 + 230 – 120 = 187.
187
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 36/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Grossrequirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117 227
230
230
227 77
230
187
230
Planned Orders
Explanation:The corresponding planned
order release is for week 5.
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 37/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Planned Orders
Item: CDescription: Seat subassembly
Lot Size: 230 unitsLead Time: 2 weeks
Gross
requirements 150
1
230
117
0
2
0
0
3
0
120
4
0
5
0
150
6
0
120
7
0
8
0Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
00
117 117 227
230
230
227 77
230
187
230
187
Additional MRP Scheduling
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 38/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Additional MRP Scheduling
Terminology
• Gross Requirements-total requirementsfor a component or end product
•
Scheduled receipts-when a purchase orproduct order that has already been
placed will be available
• Planned order release-how many andwhen to produce to meet gross
requirements
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 39/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Lot Sizing in MRP Programs
• Lot-for-lot (L4L) (producing as much asrequired)
• Fixed order quantity (ordering same
quantity each time an order is issued)
• Periodic order quantity (allows a different
order quantity for each order issued, but
tends to issue the order at predeterminedtime intervals such as every two weeks)
• Economic order quantity (EOQ)
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 40/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Lo t-Sizing Rule Comparison
The FOQ ru le generates h igh average
invento ry because i t creates remnants.
The POQ rule reduces
average on -hand inventory
because it does a better
job o f match ing order
quant i ty to requ irements.
The L4L rule min im izes
inventory investment
bu t maxim izes the number of orders placed.
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 41/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
MRP Outpu ts
Figure 15.16
MRPexplosion
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 42/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
MRP Outpu ts
Material requirements plan
Action notices Releasing new orders
Adjusting due dates
Priority reports Dispatch lists
Supplier schedules
Capacity reports Capacity requirements planning
Finite capacity scheduling
Input-output control
MRPexplosion
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 43/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
MRP Outpu ts
Material requirements plan
Action notices Releasing new orders
Adjusting due dates
Priority reports Dispatch lists
Supplier schedules
Capacity reports Capacity requirements planning
Finite capacity scheduling
Input-output control
MRPexplosion
Routings
and time
standards
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 44/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
MRP Outpu ts
Material requirements plan
Action notices Releasing new orders
Adjusting due dates
Priority reports Dispatch lists
Supplier schedules
Capacity reports Capacity requirements planning
Finite capacity scheduling
Input-output control
MRPexplosion
Manufacturing resources plan
Performance reports
Routings
and time
standards
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 45/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
MRP Outpu ts
Material requirements plan
Action notices Releasing new orders
Adjusting due dates
Priority reports Dispatch lists
Supplier schedules
Capacity reports Capacity requirements planning
Finite capacity scheduling
Input-output control
MRPexplosion
Manufacturing resources plan
Performance reportsCost and
price data
Routings
and time
standards
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 46/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
MRP Exp losion
Item: Seat subassemblyLot size: 230 units
Lead
time: 2 weeks
Gross
requirements 150
1
230
117
2 3
120
4 5
150
6
120
7 8
Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
37
Week
117 117
0 00 0
0 0 00 00 0
227 227 77 187 187
230230
230230
Figure 15.18
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 47/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: Seat subassembly
Lot size: 230 units
Lead
time: 2 weeks
Gross
requirements150
1 2 3
120
4 5
150
6
120
7 8
Planned
receipts
Planned
order
releases
Week
0 00 0
230
230
230
230
MRP Exp losion
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 48/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: Seat subassembly
Lot size: 230 units
Lead
time: 2 weeks
Gross
requirements150
1 2 3
120
4 5
150
6
120
7 8
Planned
receipts
Planned
order
releases
Week
0 00 0
230
230
230
230
MRP Exp losion
Item: Seat frames
Lot size: 300 units
Lead
time: 1 week
Gross
requirements
1
0
2 3 4 5 6 7 8
Scheduledreceipts
Projected
on-hand
inventory
Planned
receipts
Planned
order
releases
40
Week
0 0 0300 00 0
Item: Seat cushion
Lot size: L4L
Lead
time: 1 week
Gross
requirements
1
0
2 3 4 5 6 7 8
Scheduledreceipts
Projected
on-hand
inventory
Planned
receipts
Planned
order
releases
0
Week
0 0 00 00 0
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 49/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: Seat subassembly
Lot size: 230 units
Lead
time: 2 weeks
Gross
requirements150
1 2 3
120
4 5
150
6
120
7 8
Planned
receipts
Planned
order
releases
Week
0 00 0
230
230
230
230
Item: Seat frames
Lot size: 300 units
Lead
time: 1 week
Gross
requirements0
1
0
2 3 4 5 6 7 8
Scheduledreceipts
Projected
on-hand
inventory
Planned
receipts
Planned
order
releases
40
Week
230
0 0 0300 00 0
Item: Seat cushion
Lot size: L4L
Lead
time: 1 week
Gross
requirements0
1
0
2 3 4 5 6 7 8
Scheduledreceipts
Projected
on-hand
inventory
Planned
receipts
Planned
order
releases
0
Week
230
0 0 00 00 0
Usage quantity: 1 Usage quantity: 1
MRP Exp losion
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 50/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: Seat subassembly
Lot size: 230 units
Lead
time: 2 weeks
Gross
requirements150
1 2 3
120
4 5
150
6
120
7 8
Planned
receipts
Planned
order
releases
Week
0 00 0
230
230
230
230
Item: Seat frames
Lot size: 300 units
Lead
time: 1 week
Gross
requirements0
1
0
2 3
0
4 5 6 7 8
Scheduledreceipts
Projected
on-hand
inventory
Planned
receipts
Planned
order
releases
40
Week
230 2300
0 0 0300 00 0
Item: Seat cushion
Lot size: L4L
Lead
time: 1 week
Gross
requirements0
1
0
2 3
0
4 5 6 7 8
Scheduledreceipts
Projected
on-hand
inventory
Planned
receipts
Planned
order
releases
0
Week
230 2300
0 0 00 00 0
Usage quantity: 1 Usage quantity: 1
MRP Exp losion
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 51/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: Seat subassembly
Lot size: 230 units
Lead
time: 2 weeks
Gross
requirements150
1 2 3
120
4 5
150
6
120
7 8
Planned
receipts
Planned
order
releases
Week
0 00 0
230
230
230
230
Item: Seat frames
Lot size: 300 units
Lead
time: 1 week
Gross
requirements0
1
0
40
2 3
0
4 5
0
6
0
7 8
Scheduledreceipts
Projected
on-hand
inventory
Planned
receipts
Planned
order
releases
40
Week
110 110
230 2300 0
0 0 0300 00 0
110 180 180 180 180
300
300
Item: Seat cushion
Lot size: L4L
Lead
time: 1 week
Gross
requirements0
1
0
0
2 3
0
4 5
0
6
0
7 8
Scheduledreceipts
Projected
on-hand
inventory
Planned
receipts
Planned
order
releases
0
Week
0 0
230 2300 0
0 0 00 00 0
0 0 0 0 0
230
230
230
230
MRP Exp losion
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 53/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: Seat frames
Lot size: 300 units
Lead
time: 1 week
Gross
requirements
1 2 3 4 5 6 7 8
Planned
receipts
Planned
order
releases
Week
300
300
Item: Seat cushion
Lot size: L4L
Lead
time: 1 week
Gross
requirements
1 2 3 4 5 6 7 8
Planned
receipts
Planned
order
releases
Week
230
230
230
230
0 0 0 0230 2300 00 0 0 0230 2300 0
Gross
requirements
1
0
2 3 4 5 6 7 8
Scheduled
receipts
Planned
receipts
Planned
order
releases
200
Week
0 0 00 00 0
Projected
on-hand
inventory
Item: Seat-frame boards
Lot size: 1500 units
Lead
time: 1 week
MRP Exp losion
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 54/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: Seat frames
Lot size: 300 units
Lead
time: 1 week
Gross
requirements
1 2 3 4 5 6 7 8
Planned
receipts
Planned
order
releases
Week
300
300
Item: Seat cushion
Lot size: L4L
Lead
time: 1 week
Gross
requirements
1 2 3 4 5 6 7 8
Planned
receipts
Planned
order
releases
Week
230
230
230
230
0 0 0 0230 2300 00 0 0 0230 2300 0
Gross
requirements0
1
0
2 3
1200
4 5
0
6
0
7 8
Scheduled
receipts
Planned
receipts
Planned
order
releases
200
Week
0 00 0
0 0 00 00 0
Projected
on-hand
inventory
Item: Seat-frame boards
Lot size: 1500 units
Lead
time: 1 week
Usage quantity: 4
MRP Exp losion
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 55/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Item: Seat frames
Lot size: 300 units
Lead
time: 1 week
Gross
requirements
1 2 3 4 5 6 7 8
Planned
receipts
Planned
order
releases
Week
300
300
Item: Seat cushion
Lot size: L4L
Lead
time: 1 week
Gross
requirements
1 2 3 4 5 6 7 8
Planned
receipts
Planned
order
releases
Week
230
230
230
230
0 0 0 0230 2300 00 0 0 0230 2300 0
Gross
requirements0
1
0
200
2 3
1200
4 5
0
6
0
7 8
Scheduled
receipts
Planned
receipts
Planned
order
releases
200
Week
200 200
0 00 0
0 0 00 00 0
500 500 500 500 500
1500
1500
Projected
on-hand
inventory
Item: Seat-frame boards
Lot size: 1500 units
Lead
time: 1 week
MRP Exp losion
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 56/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Solved Prob lem 1
Figure 15.21
LT = 2 LT = 3
LT = 3
A
B (3) C (1)
LT = 1
G (1)
LT = 3 LT = 6
LT = 3
LT = 1
D (1)D (1) E (2) F (1)
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 57/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Solved Prob lem 2
Figure 15.22
A
B (1) C (2)
D (1)
LT = 2
LT = 1 LT = 2
LT = 3
I nventory Record Data
ITEM
DATA CATEGORY B C D
Lot-sizing rule POQ (P =3) L4L FOQ = 500 units
Lead time 1 week 2 weeks 3 weeksScheduled receipts None 200 (week 1) None
Beginning (on-hand) 20 0 425
inventory
Table 12.1
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 58/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Solved Prob lem 2
Item: B Lot size: POQ (P = 3)Description: Lead time: 1 week
Gross
requirements 100
1
20
2 3 4 5 6 7 8
Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
20
Week
200 200
200
0 0 240 60 0
280
9 10
120 180 60
0 0
360
280 360
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 59/60
To Accompany Ritzman & Krajewski Foundations of Operations Management, © 2003 Prentice Hall, Inc. All rights reserved.
Solved Prob lem 2
Item: C Lot size: L4LDescription: Lead time: 2 weeks
Gross
requirements 200
1
200
2 3 4 5 6 7 8
Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
0
Week
0 0
400
200
0 0 0 0 0
400
9 10
240 360 120
0 0
240 360 120
400 240 360 120
8/12/2019 Advance Mr p
http://slidepdf.com/reader/full/advance-mr-p 60/60
Solved Prob lem 2
Item: D Lot size: FOQ = 500 unitsDescription: Lead time: 3 weeks
Gross
requirements 400
1
425
2 3 4 5 6 7 8
Scheduled
receipts
Projected
on-hand
inventory
Planned
receipts
Planned order
releases
425
Week
25 25
240
285 425 305
500
9 10
360 120
500
360305 305 305
500 500